RFI_QA-1_Dated_21Aug18.pdf
PDF 11 KB Posted
- Attached to
- COMM Fiber Optics Cabling Survey Federal contract opportunity
- Solicitation number
- F5A3CF8219AW01
About this file
RFI Questions and Answers #1, dated 21Aug18
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| RFI_QA-2_Dated_27Aug18.pdf | ||
| Combined_Synopsis_Solicitation_-_F5A3CF8219AW01-COMM_Survey__Rev1.pdf | ||
| F5A3CF8219AW01-Sign_in_Sheet-16Aug18.pdf | ||
| F5A3CF8219AW01_COMM_Engineering_Survey_SOW_Rev1.pdf | ||
| Combined_Synopsis_Solicitation_-_F5A3CF8219AW01-COMM_Survey.pdf | ||
| F53CF8219AW01-NAS_Fort_Worth_JRB_Outside_Cable_Plant-Drawings.pdf | ||
| Confined_Space_Program_Reqrmnts.pdf | ||
| RFI_-RFC_FORM_20150420.doc | DOC document | |
| F5A3CF8219AW01_COMM_Engineering_Survey_SOW.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
F5A3CF8219AW01- COMM Fiber Optic Cabling Survey Questions/Answers #1
Dated: 21 August 2018
1. What is the performance period allowed for this project? Contractors are to give the Government an estimate time period to complete the project.
2. What is the $ magnitude of this project? (e.g. <25K, 25-100K, etc) (IF allowed to provide this info) The magnitued for this project is between 80K-180K
3. Ref para 7.2 - What are the normal operating hours of the base that we'd be allowed to work?
Hours of operation are 0700-1600
4. Are we also testing and documenting copper outside plant cable as well as fiber optic plant?
No copper will be required to be tested. Fiber only
5. In order to test existing fiber that is in use, what will be the procedures/limitations on interrupting those circuits in order to perform end to end testing? No live circuits will be tested.
Unused (dark) fiber strands only.