Exhibit A (5) - Bldg 14 TO QASP.pdf

PDF 180 KB Posted

Attached to
Tobyhanna Multiple Award Task Order Contract (MATOC) Federal contract opportunity
Solicitation number
W25G1V-21-R-0014
Issued by
Department of the Army Materiel Command Army Contracting Command Aberdeen Proving Ground

About this file

This document contains a Quality Assurance Surveillance Plan (QASP) for the renovation of Building 14 at Tobyhanna Army Depot. The QASP establishes procedures for monitoring the renovation project and identifying any deficiencies in contractor performance against the project specifications. It defines roles for the Contracting Officer and Contracting Officer's Representative. The QASP details performance standards and ratings, corrective action and complaint reporting processes, and weekly performance assessment reporting to provide oversight of the contractor's work. It includes templates for corrective action reports, customer complaint records, and performance assessment reports to document performance issues and ensure their timely resolution.

View the file

Other files for this federal contract opportunity

Other files attached to Tobyhanna Multiple Award Task Order Contract (MATOC), newest first.
File Type Posted
Exhibit A (4) - Addendum 4 Metal Roof Panels.pdf PDF
Question-Answer Posted to SAM.gov 7-27-2021_PM.docx DOCX document
Exhibit A (4) - Addendum 3 Lift Specs.pdf PDF
Exhibit A (8) Bldg 14 TO Geotechnical Report.pdf PDF
Question-Answer Posted to SAM.gov 7-22-2021_PM.docx DOCX document
Amendment 0006.pdf PDF
Question-Answer Posted to SAM.gov 7-22-2021.docx DOCX document
Exhibit A (3) - Rev 2 Bldg 14 TO Drawings.pdf PDF
Question-Answer Posted to SAM.gov 7-20-2021.docx DOCX document
Exhibit A (4) - Rev 1 Bldg 14 TO Specs.pdf PDF
Amendment 0005 update Dwg_Spec.pdf PDF
Question-Answer Posted to SAM.gov 7-19-2021.docx DOCX document
Amendment 0004.pdf PDF
Question-Answer Posted to SAM.gov 7-15-2021.docx DOCX document
Question-Answer Posted to SAM.gov 7-14-2021.docx DOCX document
Amendment 0003.pdf PDF
Exhibit A (7) Bldg 14 TO HAZMAT Report.pdf PDF
Exhibit A (1) - Rev2 Bldg 14 TO RFP (001).pdf PDF
Exhibit A (1) - Rev1 Bldg 14 TO RFP.pdf PDF
Amendment 0002 Update Exhibit A(1) Rev1 Bldg 14 TO RFP.pdf PDF
Question-Answer Posted to SAM.gov 7-8-2021.docx DOCX document
Exhibit A (3) - Rev 1 Bldg 14 Drawings.pdf PDF
Amendment 0001 - Update Exhibit A (3) - Rev 1 Bldg 14 Drawings.pdf PDF
Bldg 14 Renovation Site Visit sign in 7-1-2021.pdf PDF
Exhibit A (2) - Bldg 14 TO SOW 20210603.pdf PDF
Exhibit A (6) - DBA PA20210098 4-9-2021.txt TXT text file
ATTACHMENT 4 Quality Control Plan Evaluation Criteria 20210603.pdf PDF
Exhibit A (1) - Bldg 14 TO RFP.pdf PDF
ATTACHMENT 2 TYAD IDG - Master Spec combo 20210603.pdf PDF
Exhibit A (3) - Bldg 14 Drawings.pdf PDF
Exhibit A (4) - Bldg 14 TO Specs.pdf PDF
ATTACHMENT 5 - Past Performance Questionnaire.pdf PDF
ATTACHMENT 3 Accident Prevention Plan Evaluation Criteria 20210603.pdf PDF
ATTACHMENT 1 MATOC SOW May 2021.pdf PDF
Solicitation W25G1V21R0014.pdf PDF
Show all 35

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Exhibit A(5) Bldg 14 TO – QASP W25G1V-21-R-0014

Quality Assurance Surveillance Plan (QASP) Building 14 Tactical Vehicle Branch Renovation Project

April 1, 2021 Version 1.0

Table of Contents:

1 Vision 2 Mission 3 Purpose 4 Authority 5 Roles and Responsibilities

5.1 Contracting Officer (KO)

5.2 Contracting Officer's Representative (COR)

6 Performance Requirements and Method of Surveillance

6.1 Contract Surveillance

6.2 Inspection Performance Rating

Appendix 2 - Corrective Action Report (CAR) Appendix 3 - Customer Complaint Record Appendix 4 - Performance Assessment Report (PAR)

Building 14 Renovation Project

1 Vision

The vision of this QASP is to provide the procedures necessary to monitor the building 14 Tactical Vehicle Branch renovations project. Additionally, this QASP shall offer the details and means to identify, record, and report deficiencies observed while comparing actual work throughout the construction process to the project specifications.

2 Mission

Tobyhanna is a recognized leader in providing world-class logistics support for Command, Control, Communications, Computers, Cyber, Intelligence, Surveillance and Reconnaissance (C5ISR) Systems across the Department of Defense. Tobyhanna's Corporate Philosophy, dedicated workforce and electronics expertise ensure the depot is the Joint C5ISR provider of choice for all branches of the Armed Forces and our industry partners. Tobyhanna's unparalleled capabilities include full-spectrum support for sustainment, overhaul and repair, fabrication and manufacturing, engineering design and development, systems integration, technology insertion, modification, and global field support to our Warfighters. To support these capabilities and its Warfighters, Tobyhanna Army Depot requires a complete renovation of building 14 Tactical Vehicle Branch to provide the necessary support.

3 Purpose This Quality Assurance Surveillance Plan (QASP) is a government-developed document used to determine if the contractor's performance meets the performance standards contained in the contract. The QASP establishes procedures on how this assessment/inspection process will be conducted. It provides the detailed process for a continuous oversight process:

- What will be monitored

- How monitoring will take place

- Who will be conduct the monitoring

- How monitoring efforts and results will be documented The contractor is responsible for implementing and delivering performance that meets contract standards using its Quality Control Plan. The QASP provides the structure for the government's surveillance of the contractor's performance to assure that it meets contract standards. It is the government's responsibility to be objective, fair and consistent in evaluating contractor performance.

The QASP is not part of the contract nor is it intended to duplicate the contractor's quality control plan. This QASP is a living document. Flexibility in the QASP is required to allow for an increase or decrease in the level of surveillance necessary based on contractor performance.

The government may provide a copy of the QASP to the contractor to facilitate open communication. In addition, the QASP should recognize that unforeseen or uncontrollable circumstances might occur that are outside the control of the contractor.

Bottom line, the QASP should ensure early identification and resolution of performance issues to minimize impact on mission performance.

4 Authority

Authority for issuance of this QASP is provided under Part 46 of the Federal Acquisition Regulation, Inspection of Services clauses, which provides for inspection, acceptance and documentation of the service called for in the contract or order. This acceptance is to be executed by the contracting officer or a duly authorized representative.

5 Roles and Responsibilities

The following personnel shall oversee and coordinate surveillance activities.

5.1 Contracting Officer (KO)

The Contracting Officer (KO) shall ensure performance of all necessary actions for effective contracting, ensure compliance with the contract terms, and shall safeguard the interests of the United States in the contractual relationship. The KO shall also ensure that the contractor receives impartial, fair, and equitable treatment under this contract. Determine and document the final assessment of the contractor's performance in the governments past performance tracking system.

Assigned KO: Robert Dombroski Organization or Agency: Tobyhanna Army Depot (TYAD) Telephone: 570-615-6442 Email: Robert.dombroski.civ@mail.mil

5.2 Contracting Officer's Representative (COR)

The Contracting Officer's Representative (COR) is responsible for providing continuous technical oversight of the contractor's performance. The COR uses the QASP to conduct the oversight/surveillance process. The COR shall keep a Quality Assurance file that accurately documents the contractor's actual performance. The purpose is to ensure that the contractor meets the performance standards contained in the contract. The COR is responsible for reporting early identification of performance problems to the KO. The COR is required to provide an annual performance assessment to the KO which will be used in documenting past performance. The QASP is the primary tool for documenting contractor performance. The COR is not empowered to make any contractual commitments or to authorize any contractual change on the Government's behalf.

Assigned COR: Daniel Stapleton Organization or Agency: Tobyhanna Army Depot (TYAD) Telephone: 570-615-7546 Email: daniel.stapleton1.civ@mail.mil

6 Performance Requirements and Method of Surveillance This section describes the special requirements for this effort. The following sub-sections provide details of various considerations on this effort.

6.1 Contract Surveillance

The goal of the QASP is to ensure that contractor performance is effectively monitored and documented. The COR's contribution is their professional, non-adversarial relationships with the KO, Project Manager and the contractor, which enables positive, open and timely communications. The foundation of this relationship is built upon objective, fair, and consistent

COR evaluations of contractor performance against contract requirements. The COR uses the methods contained in this QASP to ensure the contractor is in compliance with contract requirements. The COR function is responsible for a wide range of surveillance requirements that effectively measure and evaluate the contractor's performance. Additionally, this QASP is based on the premise that the contractor, not the government, is responsible for management and QC/QA actions to successfully meet the terms of the contract.

6.2 Inspection Performance Rating

The goal of the inspection performance rating is to provide quality assurance to ensure the material is installed per the scope of work and specifications. Inspections will be on a pass/fail basis and will reference the manufacturer’s installation and/or specification requirements for backup. Performance objectives define the desired outcomes.

Performance Standards define the level of service required under the contract to successfully meet the performance objective. The inspection methodology defines how, when, and what will be assessed in measuring performance. The Government performs surveillance, using this QASP, to determine the quality of the contractor's performance as it relates to the performance element standards. The Performance Rating Standards should be used to form the foundation of the COR's inspection checklist.

In evaluating the quality of contractor’s performance, the following performance ratings may be used.

Performance Rating

Criteria

Excellent / Outstanding

Performance meets contractual requirements and exceeds many to the Government’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor was highly effective.

Very Good Performance meets contractual requirements and exceeds some to the Government’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor was effective.

Satisfactory Performance meets contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.

Marginal Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor’s proposed actions appear only marginally effective or were not fully implemented.

Unsatisfactory Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains a serious problem(s) for which the contractor’s corrective actions appear or were ineffective.

6.3 Reporting Measures:

The COR shall utilize a Corrective Action Report (CAR) (Appendix 2) when a discrepancy is observed during the construction process. The COR submit the CAR to the contractor, KO, and customer.

If a customer has a complaint during the construction process, they shall fill out the Customer Complaint Record and submit it to the project’s COR who will then forward it onto the contractor and KO.

Additionally, the COR shall conduct daily site visits to the construction area and conduct a weekly Performance Assessment Report to provide feedback to the contractor, customer, and KO on the project’s development.

W25G1V21R0014 Exhibit A – Bldg 14 Task Order

Appendix 2 - Corrective Action Report (CAR)

CORRECTIVE ACTION REPORT (CAR)

(If more space is needed, use reverse and identify by number)

1. CONTRACTOR 2. CONTRACT NUMBER 3. TYPE OF SERVICES

4. FUNCTIONAL AREA 5. SUSPENSE

DATE

6. CONTROL

NUMBER

7. DEFICIENCY MAJOR MINOR

FINDING:

FINDING IMPACT:

Please respond with a written corrective action plan that details the corrective action of the cited deficiency, the cause of the deficiency, and actions taken to prevent recurrence by Suspense Date in Block 5. If date was not entered in Block 5, the contractor is not required to provide a response.

8. QUALITY ASSURANCE PERSONNEL (COR)

TYPED NAME AND GRADE SIGNATURE AND DATE

9. ISSUING AUTHORITY

TYPED NAME AND GRADE SIGNATURE AND DATE

10. COR RESPONSE TO CONTRACTOR CORRECTIVE ACTION AND ACTION TAKEN TO PREVENT

RECURRENCE

11. COR DETERMINATION

ACCEPTED REJECTED

12. CLOSE DATE

Appendix 3 - Customer Complaint Record

CUSTOMER COMPLAINT RECORD

DATE/TIME OF

COMPLAINT

SOURCE OF COMPLAINT

ORGANIZATION BUILDING

NUMBER

INDIVIDUAL PHONE

NUMBER

NATURE OF COMPLAINT

CONTRACT REFERENCE

VALIDATION

DATE/TIME CONTRACTOR INFORMED OF COMPLAINT

ACTION TAKEN BY CONTRACTOR

Appendix 4 - Performance Assessment Report (PAR)

PERFORMANCE ASSESSMENT REPORT (PAR)

(If more space is needed, use reverse and identify by number)

1. CONTRACT/TASK

ORDER NUMBER

2. CONTRACTOR 3. TYPE OF SERVICES

4. QUALITY ASSURANCE PERSONNEL (COR)

SIGNATURE AND DATE

5. COR

PHONE

6. SUSPENSE

DATE

I. PERFORMANCE

7. DEFICIENCY (CHECK ALL

BOXES THAT APPLY)

NEW

REPEAT

NO DEFICIENCY NOTED

8. SERVICES SUMMARY or PWS PARAGRAPH

ITEM REVIEWED

9. BRIEF DESCRIPTION OF DEFICIENCY (IF

DEFICIENCY BOX WAS CHECKED)

10. DETAILED PERFORMANCE ASSESSMENT

II. CONTRACTOR VALIDATION

11. CONTRACTOR REPRESENTATIVE

CONCUR NON-CONCUR

12. CORRECTIVE ACTION ESTIMATED

COMPLETION DATE

13. CONTRACTOR REPRESENTATIVE CORRECTIVE ACTION AND PREVENTION OF

RECURRENCE OR REASON FOR NON-CONCURRENCE OF COR CITED DEFICIENCY

III. ACTION CORRECTED

14. CONCUR NON-CONCUR COR SIGNATURE AND DATE

15. COR REMARKS (REQUIRED)

RECEIVED/VALIDATED BY

6. CONTRACTOR REPRESENTATIVE REMARKS