This document is a Construction Manager at Risk (CMAR) Agreement between the Arizona Department of Administration (ADOA), General Services Division, and Concord General Contracting, Inc. for the ARPA Arizona State Parks Water and Wastewater Upgrades project. The agreement involves six state parks: Cattail Cove, River Island, Buckskin Mountain, Lake Havasu City, Alamo Lake, and Deadhorse State Parks. The contract is funded through the American Rescue Plan Act (ARPA) and involves design, preconstruction, and construction services.

The contract covers preconstruction services with a fee of $259,292, and a construction phase CMAR fee of 5.25% of the Cost of Work. The total project budget is approximately $25 million, with work including water and wastewater system upgrades, installation of new restrooms, filtration systems, lift stations, and associated infrastructure improvements. The project will be executed in multiple phases, with Concord General Contracting responsible for providing preconstruction services, value engineering, cost estimating, and construction management. The contract includes provisions for multiple Guaranteed Maximum Price (GMP) proposals, with the first priority being the Cattail Cove State Park project, and allows for phased construction and potential cost savings sharing between the contractor and the state.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EXHIBIT A

CONSTRUCTION MANAGER AT RISK AGREEMENT State of Arizona General Services Division

1400 W Washington St., Ste. B200

Phoenix, AZ 85007

Contract No. CTR066685

Date of Agreement:

July 11, 2023

Agency Project No:

PCS-22-132

Statutory Review No: PCS-22-132 Project Name: State Parks Water & Wastewater Upgrades

Construction Manager at Risk Agreement Contract No: CTR066685 Rev 3 2-16-2023

This Agreement is made as of the date set forth in the Date of Issuance between the State of Arizona, Department of Administration, General Services Division acting by and through the State Procurement Office, and the Contractor in connection with the Project. Time is of the essence for this Agreement. Services required by this Agreement include, at no additional cost to the State, all services necessitated, in whole or in part, by errors and omissions of, or breach of this Agreement by, Contractor, its Subcontractors, or any person or entity working under Contractor for this Project.

Project Site Address: Cattail Cove, Alamo Lake, River Island, Buckskin Mountain, Lake Havasu City, and Deadhorse State Parks

Agency: Department of Administration, General Services Division Agency Address: 1400 W. Washington St., Ste. B200

Phoenix, AZ 85007

Agency’s Designated Representative:

Email:

Telephone Number:

Britt Olachea britt.olachea@azdoa.gov

(602) 552-3355

Agency Procurement Officer:

Crista Clevenger

Telephone Number:

crista.clevenger@azdoa.gov

(602) 489-9116

Design Professional Firm: Kimley-Horn Design Professional of Record

Telephone Number:

Ray Montoya ray.montoya@kimley-horn.com

(520) 730-4558

Design Professional Firm:

Design Professional of Record Email:

Telephone Number:

Design Professional Firm:

Design Professional of Record:

EPS Group Mike LoTempio mike.lotempio@epsgroupinc.com

(602) 828-9662

Entellus, Inc.

Will Janiga

Email:

Telephone Number:

Contractor Name:

Contractor Address:

Contractor Project Manager:

Telephone Number:

wjaniga@entellus.com

(480) 298-5266

Concord General Contracting 2240 W. Broadway Rd., Suite 105 Mesa, AZ 85202

Jason Beaver jbeaver@concondinc.com

(480) 258-1361 c or (480) 962-8080 o

DocuSign Envelope ID: CFC42AAC-67E3-4DE3-8FAB-8FBA151802EF mailto:ray.montoya@kimley-horn.com

1400 W Washington St., Ste. B200

Phoenix, AZ 85007

Contract No. CTR066685

Date of Agreement:

July 11, 2023

Agency Project No:

1) GENERAL DESCRIPTION OF SERVICES

a) The Contractor shall perform and provide all of the Work described in this Agreement for the Project. The executed Construction Manager at Risk Agreement, and any and all accompanying Contract Documents executed through this Agreement, shall be incorporated in the Contract for this Project.

b) Contractor has carefully examined the Site of the Project, to the extent available, and the adjacent areas, has suitably investigated the nature and location of the Work and has satisfied itself as to the general and local conditions which will be applicable, including but not limited to: (i) the Project Site and any structure(s) or other manmade features to be modified; (ii) the survey, including the location of all existing buildings, utilities, conditions, streets, equipment, components and other attributes having or likely to have an impact on the Project; (iii) Site layout and design requirements, conceptual design objectives, and budget for the Project; (iv) pertinent Project dates and programming needs, including the Project Schedule; (v) Site access and to the transportation, disposal, handling and storage of materials; (vi) the availability of labor, water, power and roads;(vii) normal weather conditions; (viii) observable physical conditions at the Site and existing Site conditions including: size, utility capacities and connection options of external utilities; (vix) the surface conditions of the ground and (x) the character and availability of the equipment and facilities which will be needed prior to and during the performance of Work.

c) Contractor shall (i) review and analyze all Project geotechnical, Hazardous Substances, structural, chemical, electrical, mechanical, and construction materials tests, investigations and recommendations; and (ii) gather any other information necessary for a thorough understanding of the Project. If the Project involves modifications to any existing structure(s) or other man-made feature(s) on the Project Site, the Contractor shall also (iii) review all As- Built and Record Drawings, plans and specifications of which Contractor has been informed by Agency about, and

(iv) thoroughly inspect the existing structure(s) and man-made feature(s) to identify existing deficiencies and ascertain the specific locations of pertinent structural components. Claims by Contractor resulting from Contractor’s failure to familiarize itself with the Site or pertinent documents shall be deemed waived.

d) General conditions are an integral part of the construction contract. They consist of items and resources needed for project completion that will not be part of the finished product that is turned over to the owner. Things like garbage removal, temporary offices and protection, and administrative time are all aspects of the project that are necessary but ultimately not seen at completion.

e) General conditions are provided by the general contractor to facilitate a completed project that will contribute to the communities in which we live, work, and go to school. Compensation is necessary for general conditions, and most commonly, their cost is included as a line item in the proposal.

2) PRECONSTRUCTION SERVICES

a) The Contractor shall commence Preconstruction Services Project Work upon receipt of a purchase order issued by the Agency authorizing services and issuance of a Notice to Proceed by the Agency Designated Representative.

b) The Contractor shall commence the Work for Agency authorized Preconstruction Services on the date specified in the Notice to Proceed.

c) Contractor shall meet with the Agency and Agency’s Design Professional to jointly participate in the final Project design and reconcile cost discrepancies at each phase of design between its estimate and Design Professionals estimate.

d) No Work may be performed under this Pre-Construction Services Contract, without prior written approval by the State. All procurement of long lead time items needed to support the construction schedule or site investigative Work necessary to complete Pre-Construction Services will be performed only after a GMP Proposal for the Work has been approved and accepted in writing by the State and all such Work will be done only under an executed Contract for Construction Services, or pursuant to a prior written direction from the State to engage in such procurement.

1400 W Washington St., Ste. B200

Phoenix, AZ 85007

Contract No. CTR066685

Date of Agreement:

July 11, 2023

Agency Project No:

e) Services which are outside the scope required under the Contract Documents will not be performed by Contractor without prior written authorization from the State. Additional services, when authorized by an executed written Change Order as per Section 1.15 Uniform Terms and Conditions and will be compensated for by a fee mutually agreed upon in such written Change Order between the State and Contractor

f) No claim for additional services, extra work done or materials furnished by Contractor will be allowed by the State except as provided herein, nor will Contractor provide any additional services, do any work, or furnish any materials(s) not covered by this Contract unless such work or material is first authorized in writing by the State. Work or material(s) furnished without such prior written authorization will be Contractors sole jeopardy, cost, and expense, and Contractor hereby agrees that without prior written authorization no claim for compensation for such services, work or materials furnished will be made, and the State will not be responsible for such costs.

g) Contractor will comply with all Special and Uniform Terms and Conditions.

3) STATEMENT OF WORK

a) The Statement of Work for Preconstruction Services shall be those tasks included in Exhibit B attached herein.

b) The Contractor Project Manager of record named in this written Agreement is the first point of contact in providing all services required by this Agreement; and shall attend design-related meetings for the duration of the Project, unless a substitution mutually acceptable to the Agency is made.

c) Notwithstanding anything to the contrary in this Agreement, all Work Product prepared or otherwise created in connection with the performance of this Agreement, including the Work, are to be and remain the property of the State.

4) COMPENSATION

a) The compensation for Preconstruction Services is $ 259,292.00 in accordance with compensation for scope of services calculated and included in Exhibit B, and listed in Exhibit C, attached herein to this Agreement.

5) CONSTRUCTION PHASE SERVICES

a) If the Agency elects to phase and/or “fast track” portions of the construction, multiple Guaranteed Maximum Price proposals (Exhibit U) with Contract Cost details for each phase of Work will be required.

b) Contractor must submit a GMP Proposal for the entire Work, and for each phase (if required) of the Work, at the times set forth in the Pre-Construction Schedule included in attached. The GMP Proposal must be presented in a format acceptable to State. State may change the schedule, format, and/or requirements for the GMP Proposal as it deems necessary during Pre-Construction, and may request resubmittal of the GMP Proposal to reflect such changes.

c) For the purposes of the GMP Proposal, the Parties agree that:

d) The CMAR Fee will be equal to 5.25 % (percent) of the Cost of Work;

e) General Conditions costs will be a fixed amount or percentage agreed to as part of the CMAR Fee

Proposal and General Conditions Worksheet.

f) The GMP Proposal must not exceed the State’s Construction Budget.

1400 W Washington St., Ste. B200

Phoenix, AZ 85007

Contract No. CTR066685

Date of Agreement:

July 11, 2023

Agency Project No:

Fees Fee Percentage

CMAR Fee-Construction Phase (CM’s Overhead & Profit) 5.25 %

General Conditions 7.29 %

g) The above amounts are to be stated in figures only and are the total amounts proposed for the entire Contract Work.

6) PAYMENTS

a) The Agency shall compensate the Construction Contractor in exchange for the Construction Contractor’s proper, timely, and complete performance of the Work in accordance with the Contract Documents and the Construction Contractor Agreement.

b) The Agency shall pay for authorized actual expenditures incurred by the Construction Contractor for Work performed in the interest of the Project as Reimbursable Expenses.

c) SCHEDULE OF VALUES

i) With each Application for Progress Payment (Exhibit H), a Schedule of Values (Exhibit R) shall be submitted with the proper breakdown of Work completed by the Contractor and Subcontractor, and for approval by Agency.

ii) The Application for Progress Payment (Exhibit H) shall a) be an accurate reflection of the progress of the Work;

b) contain line items based on the Schedule of Values (Exhibit R) with breakdown of Contractor and Subcontractor Work; c) bear the notarized signature of Contractor; d) bear the signature of the Contractor if contracted to perform Construction Phase Services; e) only be paid after approval by the Agency Designated Representative; and f) not include Subcontracted items for which Contractor does not intend to pay.

d) PAY REQUEST FOR PROJECTS UNDER STATUTORY REVIEW

i) Projects under Statutory Review, Application for Payment (Exhibit H) shall be a notarized Application and Certification for Payment and approved and stamped by the Registrant for the project.

ii) Contractor shall deliver to Agency no later than the 25th of each month for payment covering the cost of Work and fee for Work performed during the invoiced month and projected through the end of the month. Provided application timely review, Agency to make payment to Contractor not later than stated in A.R.S. § 41-2577 (Progress Payments).

iii) Retention held on each Application for Payment to be 10%

iv) Agency may withhold payment for:

(1) Defective Work not remedied

(2) Third Party claims

(3) Failure of Contractor to make payments to subcontractors or suppliers

(4) Damages to Agency caused by Contractor not covered by insurance

(5) Evidence where Contractor will not be Substantially Complete on contracted Schedule completion liquidated damages are needing to be assessed

v) With each Application for Payment submit all supporting documentation relating to payment of approved

Change Orders, substantiation for stored materials and any other pertinent items required by the Agency identified.

1400 W Washington St., Ste. B200

Phoenix, AZ 85007

Contract No. CTR066685

Date of Agreement:

July 11, 2023

Agency Project No:

7) Enumeration of Contract Documents

INCORPORATED BY REFERENCE

The following shall be incorporated by reference and shall become part of the Agreement Solicitation BPM005291 ARPA Arizona State Parks Water and Wastewater Upgrades Special Terms and Conditions of Solicitation BPM005291 ARPA Arizona State Parks Water and Wastewater Upgrades Uniform Terms and Conditions of BPM005291 ARPA Arizona State Parks Water and Wastewater Upgrades

EXHIBITS

This Agreement includes the following Exhibits attached hereto:

Exhibit A: Construction Manager at Risk Agreement Exhibit B: Statement of Work (Provided by the Contractor) Exhibit C: Fee Summary and Contractor/Subcontractor Hourly Rate Schedule (Provided by the Contractor) Exhibit D: Certificate of Insurance Exhibit E: Project Schedule and all Updates Thereto (Provided by the Contractor) Exhibit F: RESERVED – Not Used Exhibit G: Contract Amendments and Addenda Exhibit H: Application for Progress Payment for Construction Work Exhibit I: RESERVED – Not Used Exhibit J: Construction Change Order Exhibit K: Substantial Completion Certificate Exhibit L: Final Completion Certificate Exhibit M: Project Closeout Exhibit N: Payment Bond (Provided by Contractor) Exhibit O: Performance Bond (Provided by Contractor) Exhibit P: Conditional Waiver

P1: Progress Payment P2: Final Payment

Exhibit Q: Unconditional Waiver Exhibit R Schedule of Values Exhibit S: Authorized Use of Allowance Exhibit T: RESERVED – Not Used Exhibit U: Guaranteed Maximum Price Amendment

1400 W Washington St., Ste. B200

Phoenix, AZ 85007

Contract No. CTR066685

Date of Agreement:

July 11, 2023

Agency Project No:

IN WITNESS WHEREOF, STATE OF ARIZONA, DEPARTMENT OF ADMINISTRATION acting by and through the Agency procurement authority, and CONTRACTOR in connection with the Project, have executed this Agreement as of the date set forth in the date of Agreement signed by the authorized Agency Procurement Officer.

CONTRACTOR: CONCORD GENERAL CONTRACTING, INC.

By:

(Typed Name)

(Signature)

(Title)

(Date)

STATE OF ARIZONA, DEPARTMENT OF ADMINISTRATION:

By:

(Typed Name)

(Signature)

(Title)

(Date)

END OF CONSTRUCTION MANAGER AT RISK AGREEMENT

CEO

12-Jul-23 | 9:06 AM EDT

Grenee Martacho

Crista J Clevenger

12-Jul-23 | 7:49 AM PDT

Construction Procurement Manager

Arizona Department of Administration June 28, 2023

Attn: Mr. Britt Olachea, Project Manager

Ms. Crista Clevenger, Procurement Manager

1400 W Washington Street

Suite B200

RE: ARPA Parks Water & Wastewater Upgrades

Dear Mr. Olachea & Ms. Clevenger:

This letter is to propose that Concord General Contracting, Inc. will provide preconstruction and

CM@ Risk services for the ARPA Parks Water & Wastewater Upgrades construction project. Attached is a breakdown of our proposed preconstruction fees.

Preconstruction services provided in this agreement are as follows:

• Provide ongoing cost estimates based on design documents, field conditions, and owner input

• Deliverables will include full written narratives based on each component of the project on a division by division basis, On Screen Takeoff visuals of quantity takeoffs, drone photos, customized budgets based on each building and site.

• Analyze the project scope, systems and materials

• Discuss the constructability with Designers and ADOA

• Perform site investigations at each of the 6 parks to verify existing conditions

• Provide value engineering solutions that will add value to the project to include multiple manufacturers, subcontractor input to systems designs and approaches, alternate system options to save time/money, early procurement suggestions, and potentially using multiple subcontractors for main trades to capitalize on cost/manpower.

• Identify multiple recommended bid packages to capitalize on long lead or volatile materials

• Prepare subcontractor bid list and review with owner and architect

• Recommend any alternative selection methods to expedite certain trades

• Provide preconstruction schedule to meet needs of the project

• Complete GMP packages as needed to meet budget and schedule on a park by park basis

Approximate Anticipated Rough Scopes of Work

• Cattail Cove -o Lake Pump Replacement o Installation of existing new Water Filtration/Wastewater System o New Building to house equipment o New Electrical SES o Installation of owner furnished CXT Restrooms o Inspect, pressure test and camera all existing previously installed piping

• River Island – o Provide and install new Water Filtration System o Provide and install new CXT

• Buckskin – o Provide and install new Water Filtration System o Provide and install new CXT’s o Provide and install new Valves

• Lake Havasu – o Address existing grade issues o Provide and install new Lift Station o Provide and install new sewer piping

• Alamo Lake – o Install new sewer system o Install new septic system o Provide and install new CXT o Install water valves at various locations

• Deadhorse – o Install water line and valves o Provide and install new CXT o Water well replacements o Vegetation replacement o

Specifically our team individual responsibilities during the preconstruction phase will be:

• Preconstruction Director – Participate in design meetings, budget preparation, provide overall direction on GMP recommendations, assist in subcontractor team selection, and recommend systems and material options.

• Project Manager – Attend preconstruction meetings as required, complete with team evaluation of existing building systems and conditions, review and recommendations on document constructability, assist in subcontractor selection process and interviews, and participate in creation of GMP’s.

• Project Estimator – Lead all cost estimating for project from current design through GMP, provide value engineering and system recommendations, work with subcontractors on cost input during design phase, lead GMP creations, and integrate Matterport into bid packages with architect.

• Estimating Coordinator – distribute all drawings and documents related to the project, input subcontractor bid list, collect and distribute all sub proposals, assist project estimator as required

• Superintendent – perform drawing review for constructability and direction, field investigations for compliance with design and existing conditions, attend meetings as needed during design, participate in subcontractor selection process and input during the creation of the GMP.

Our fees per your request are offered below for your review:

Preconstruction Fee - $259,292 – see attached breakdown of hourly/daily rates, to be billed on a monthly basis (approximately 1.04% of rough $25 million budget)

** If time allocated by Pat Bern for days of exploration and as-built work is less than proposed we will credit back any unused dollars associated with each site.

Construction Fee - 5.25% of the GMP

Thank you for the opportunity to work again with the ADOA on this exciting project!

Sincerely, Concord General Contracting, Inc.

Grenee Martacho

CEO/Principal in Charge

Attachments

Cc: Kimberly Fiumara, Ruben Duran, Diana Reed

Arizona Department of Administration June 28, 2023

Attn: Mr. Britt Olachea, Project Manager

Ms. Crista Clevenger, Procurement Manager

1400 W Washington St.

Suite B200

RE: ARPA Parks Water & Wastewater Upgrades

Dear Mr. Olachea & Ms. Clevenger:

This letter is to propose that Concord General Contracting, Inc. will provide preconstruction and

CM@ Risk services for the ARPA Parks Water & Wastewater Upgrades construction project. Attached is a breakdown of our proposed monthly general conditions costs.

The General Conditions costs include the following items specifically related to the project:

• All labor including Project Manager, Superintendents (2), Project Engineer and Project Coordinator o Project Engineer Role – Submittals, ASI’s, RFI’s, As-Builts, Punchlist o Project Coordinator Role – Correspondence, Minutes, Subcontracts, CO’s/ACAR’s, Closeouts

• A laborer as needed for cleanup, material deliveries offloading, and subcontractor traffic control

• Project temporary utilities including toilets, cell phones, and dumpsters, we have assumed that we can use existing site power and water where needed

• Temporary fencing, signage, and safety requirements

• Office supplies, copier, and technology requirements

• Travel expenses and per diem

At the conclusion of preconstruction as well as progress continues on construction, we will evaluate as a team the percentages of staffing personnel required for the project and will adjust accordingly if determined that less time than allocated is needed.

We have completed your required form as well as included our standard GC’s sheet to cross reference if there are any questions as to inclusions.

Our fees per your request are offered below for your review:

Monthly General Conditions - $75,945 – see attached breakdown (based on 24 month duration), calculates to 7.29% of anticipated $25 million construction budget

Thank you for the opportunity to again work with ADOA on this exciting project!

Sincerely, Grenee Martacho

CEO/Principal in Charge

Attachments

Cc: Kimberly Fiumara

Dianna Reed

Ruben Duran

Date

Project Name ADOA ARPA Parks

Project Number BPM005291

Architect Multiple

Precon Duration 4 months

Description Qty Rate Total

Cattail Cove State Park - 100% 127,592$

1 Design Meeting - 4 ppl 8 $125.00 1,000$

2 Site Visits - 3 ppl 48 $400.00 19,200$

Pat Bern Quote As Built/Exploration - 8 days 8 $3,900.00 31,200$

Pat Bern Quote Existing Pipe Testing/Camera 1 $69,592.00 69,592$

Budgeting/Bidding/GMP 60 $110.00 6,600$

River Island State Park - 60% 24,270$

3 Design Meetings - 3 ppl 18 $125.00 2,250$

1 Site Visit - 3 ppl 24 $400.00 9,600$

Pat Bern Quote As Built/Exploration - 2 days 2 $4,010.00 8,020$

Budgeting/Bidding/GMP 40 $110.00 4,400$

Buckskin State Park - 60% 27,200$

2 Design Meetings - 3 ppl 12 $125.00 1,500$

1 Site Visit - 3 ppl 24 $400.00 9,600$

Pat Bern Quote As Built/Exploration - 3 days 3 $3,900.00 11,700$

Budgeting/Bidding/GMP 40 $110.00 4,400$

Lake Havasu State Park - 60% 15,930$

2 Design Meetings - 3 ppl 12 $125.00 1,500$

1 Site Visit - 3 ppl 24 $400.00 9,600$

Pat Bern Quote As Built/Exploration - 1 day 1 $1,530.00 1,530$

Budgeting/Bidding/GMP 30 $110.00 3,300$

Deadhorse State Park - 100% 16,030$

1 Design Meeting - 3 ppl 6 $125.00 750$

1 Site Visit - 3 ppl 24 $400.00 9,600$

Pat Bern Quote As Built/Exploration - 1 day 1 $1,280.00 1,280$

Budgeting/Bidding/GMP 40 $110.00 4,400$

Alamo State Park - 60% 48,270$

3 Design Meetings - 3 ppl 18 $125.00 2,250$

2 Site Visits - 3 ppl 48 $400.00 19,200$

Pat Bern Quote As Built/Exploration - 4 days 4 $5,055.00 20,220$

Budgeting/Bidding/GMP 60 $110.00 6,600$

Total Preconstruction Fee 259,292$

Enter Amount of Contract 25,000,000$

Precon Fee % 1.04%

June 28, 2023

General Conditions

ADOA - ARPA Parks TOTAL COST 6 Locations Square Feet

Duration 24 Months

Anticipated September 2023 - August 2025 104.00 Weeks 6/28/2023

Project Manager 60% 24.0 Mo $19,933 $287,040 $0 $0 $0 $287,040

Project Superintendent (1.25 FTE) 125% 104.0 Wks. $4,000 $520,000 $0 $0 $0 $520,000

Project Coordinator 50% 24.0 Mo $9,920 $119,040 $0 $0 $0 $119,040

Project Engineer/Scheduler 100% 24.0 Mo $8,500 $204,000 $0 $0 $0 $204,000

General Labor 50% 104.0 Wks. $800 $41,600 $0 $0 $0 $41,600

Mob/DeMob 2.0 LS $1,500 $1,500 $1,500 $3,000 $3,000 $3,000 $0 $9,000

Messenger Service 24.0 Mo $200 $0 $0 $0 $4,800 $4,800

Consumables & Expendables 24.0 Mo $500 $0 $12,000 $0 $0 $12,000

Small Tools & Equipment 24.0 Mo $500 $250 $0 $12,000 $6,000 $0 $18,000

Monthly Truck Charge 36.0 Mo $1,500 $0 $0 $54,000 $0 $54,000

Project Superintendent - Cell Phone 36.0 Mo $125 $0 $4,500 $4,500

Temporary Toilets/Hand Wash 6 24.0 Mo $300 $0 $0 $0 $43,200 $43,200

Travel Expense/Per Diem 36.0 Mo $5,000 $0 $0 $180,000 $0 $180,000

Temporary Storage 24.0 Mo $2,000 $0 $0 $48,000 $0 $48,000

Temporary Fencing 3,000.0 LF $5.5 $0 $0 $0 $16,500 $16,500

Temporary Signage 2.0 LS $1,000 $5,000 $2,000 $10,000 $0 $0 $12,000

Office Equipment & Supplies 24.0 Mo $1,000 $0 $24,000 $0 $0 $24,000

Technology 36.0 Mo $2,000 $0 $72,000 $0 $0 $72,000

Safety / First Aid / Fire Protection 36.0 LS $2,500 $0 $90,000 $0 $0 $90,000

Drinking Water 36.0 Mo $500 $0 $18,000 $0 $0 $18,000

Final Cleaning 6.0 Ea $2,500.00 $0.00 $0 $0 $15,000 $0 $15,000

Dumpster (6 locations) 6.0 Ea $5,000 $0 $0 $0 $30,000 $30,000

Sub -Total $1,176,680 $241,000 $310,500 $94,500 $1,822,680

GC Percentage (based on appx. $25 million) 7.29%

Monthly Cost $75,945

Sub

Contr.Total Grand Total

Sub Contr.

U.P.

Labor Total

Material

Total

Equipment

Total

$1,822,680

Description % Quanity Unit Labor U.P. Material U.P.

Equipment

U.P.

SOLICITATION NUMBER: BPM005291

DESCRIPTION CMAR FEE

General

Conditions Cost of Work Owner

Project Executive x

Project Management x

Project Engineer x

Project Coordinator / Administrative Staff x

MEP Coordinator x

Quality Assurance / Quality Control Coordinator x

PreConstruction Manager / Estimator x

Scheduler x

BIM Services x

Accounting / Purchasing x

Director of Field Ops / Superintendent x

Field Engineer N|A

Safety Specialist x

Security Services x

Testing & Inspections x

Drug Testing for General Conditions Staff x

Badging / Background Checks x

Temporary Electric (hook-up) x

Temporary Electric (consumption fees) x

Temporary Water (hook-up) x

Temporary Water (consumption fees) x

Data Hook-up x

Data Charges x

Cell Phones x

Temporary Toilets & Hand-Wash Stations x

Field Office Trailers x

Set-up Trailers (anchors, stoops, skirting, etc.) x

SOLICITATION NAME: ARPA Parks Water & Wastewater Upgrades

CMAR Fee Proposal and General Conditions Worksheet

Please identify any/all General Conditions (if any) that the Construction Contractor will utilize throughout this project. General Conditions of Contractor” means the Construction Contractor’s resources, equipment, and items used by the Construction Contractor in the Work of the Project that is used to complete the Project. This only includes Costs incurred at the jobsite for supervision and administration of the overall contract but not ascribable to any particular onsite construction activity. General

Conditions will be a pre-negiotatied percentage that is paid on actual itemized, documented Cost.

If necessary, please add any additional General Conditions to the list provided below.

In addition, please provide the percentages for General Conditions and CMAR Fee that will be used throughout the Project.

OFFICE PERSONNEL

FIELD PERSONNEL

TEMPORARY UTILITIES - ON SITE

TEMPORARY PROJECT OFFICES

Please refer to the 2nd tab of this spreadsheet for Definitions and Markup guide

TBD in GMP may be allowance

Storage Trailers (for material, equipment, supplies, tools by Self Perform) x

Office Furniture / Supplies x

Copiers x

Document Reproduction x

Computer Equipment x

Delivery / Postage Charges x

Project & Safety Signs x

Travel Expenses x

Fence & Gates x

Temporary Roadways & Parking x

Layout & Survey x

Traffic Control x

Erosion Control x

Dumpsters x

Daily Construction Cleanup x

Final Cleanup x

Fire Extinguishers x

First Aid Kits x

General Conditions Safety Equipment (i.e. Staff PPE) x

Safety Measures & Maintenance (i.e. handrail, opening protection) x

EQUIPMENT

Small Tools & Equipment x

Repairs & Maintenance x

Automobile / Truck Rental x

Fuel x

Scaffolding x

Rented equipment x

Contractor-Owned Equipment x

Crane & Operator x

Boom / Scissor Lift & Operator x

Forklift & Operator x

Repairs & Maintenance x

Fuel x

CMAR Fee Percentage 5.25%

General Conditions Percent of Work (Not to Exceed) 7.29%

GC's Percentage based on $25 Million budget

PROJECT HOISTING

TEMPORARY FACILITIES

ESTIMATE

Prepared For

ALAMO CONCORD GENERAL CONTRACTING

(480) 272-5289

Pat Bern Construction ROC 341181

2657 kiowa blvd n lake havasu city, AZ 86403 Phone: (928) 279-9938 Email: drew.patbern@gmail.com

Estimate

Date 06/29/2023

PO #

ALAMO LAKE SITE

INVESTIGATION

Description Rate Quantity Total

TOOL TRUCK PER DAY ONSITE $200.00 3.5 $700.00

INCLUDES- tools job related, traffic control needed to barricade off excavations.

MINI EXCAVATOR OPERATED PER DAY $1,080.00 3.5 $3,780.00

BOBCAT TRACK SKID STEER OPERATED PER DAY $1,080.00 3.5 $3,780.00

MOBILIZATION OF EQUIPMENT and CREW PER TRIP $1,360.00 4 $5,440.00

EQUIPMENT 1 EA DELIVERY AND 1 EACH PICK UP

TOOL TRUCK 1 EACH DELIVERY AND 1 EACH PICK UP

LABOR RATE PER EACH LABOR PER DAY $520.00 7 $3,640.00

WE HAVE 2 LABORERS FOR 5 DAYS TOTALING 10 DAYS FOR THIS PRICE

MEALS AND LODGING PER DAY $515.00 3.5 $1,802.50

2 OPERATOR

2 LABORERS

PAT BERN PROJECT MANAGER PER HR $135.00 8 $1,080.00

DocuSign Envelope ID: CFC42AAC-67E3-4DE3-8FAB-8FBA151802EF tel:(928) 279-9938 mailto:drew.patbern@gmail.com

REMOVE AND REPLACE 4" GATE VALVE PER EA $2,312.00 5 $11,560.00

INCLUDES 2 EA ROMAC COUPLING FOR EACH SIDE OF VALVE

WE ASSUME 4" UNTIL WE CAN FIELD VERIFY, PRICE SUBJECT TO CHANGE IF INCREASES OR DECREASES

Subtotal $31,782.50

Total $31,782.50

Notes:

WE ANTICIPATE TO BE THERE 1 WEEK, 5 DAYS FOR THIS SITE INVESTIGATION, IF LESS WE WILL

DISCOUNT THE DAYS NOT USED.

SCOPE -

1. POTHOLE PIPE IN SEPTIC AREA B INSPECT PIPE AND MANHOLE PRIOR TO LIFT STATION,

2. POTHOLE AREA B DUMP PIPE AND ELEVATIONS,

3. AREA C CHOLLA POTHOLE PIPES AT SEPTIC AND DUMP STATIONS, POTHOLE WATER VALVES

FOR SIZE

Exclusions:

- Transaction Privilege Tax - base bid is contingent upon receiving AZ 5005 Tax exempt form.

- Landscaping & irrigation replacement of any kind

- Relocation of any new or existing utilities due to unforeseen conflicts w/o agreement for payment

- Engineering, inspections, fees, quality control testing, surveying, permits, taxes, or outside consulting

- 3rd party consulting and inspections

- Bond costs

- Permits / fees

- BIM modeling

- Survey / staking

- Water Meters

- Manhole/valve final adjustments within proposed asphalt or concrete paving (Included if proposed paving is included in our scope of work)

- Costs associated with night work

- Roadway signs, TCP'S, Traffic devices

- Excavation of perimeter/retaining wall & waterproofing

- Slurry backfill under foundations, slabs, footings

- ABC under building slabs, other concrete flatwork and landscape

- Concrete flatwork/foundations

- Rock or hard dig excavation. Hard dig trenching is defined as material that cannot be excavated at an average of 2- CY per hour using the equivalent of a CAT 336 excavator

- Private utility locating - this is the responsibility of the utility Owner per AZ Blue Stake

- Electrical and dry utilities - power supply - connection to main - installation, conduits and trenching

- Liquidated damages

- Overtime and weekend workdays

- Dewatering

- Off site work

- Manhole Coatings

- 3D Surface Model

- tax

- import or export

- RIP RAP

- DRY WELLS

- Over Excavation. If over excavation is needed please Initial here and send specification ___________Date______ Qualifications:

- All productions are based on OSHA regulations. Client or job specific safety requirements that exceed OSHA may result in increased costs.

- Based on construction water provided onsite by others

- Price contingent on mutually agreeable contract Scope of work is inclusive of items listed below. Additional work will be tracked and submitted for payment per MAG Spec. 109

- Unit Pricing (If provided) is subject to further evaluation before it is used for contract modification request

- If existing utility lines are encountered which are not shown on the PLANS, or not located, or incorrectly located by the Utility Owner and these lines are damaged or work is required to clear these lines it shall be recognized as a change of condition and paid for as extra work associated with such change of condition

- All utilities to terminate five feet from the building except the fire line which we will install 6” above the finished floor. Domestic water, storm drain, and sanitary sewer connections from utility contractor to plumber shall be made “last-in”; meaning whichever contractor installs first they leave a cap and the last contractor to install makes the final connection.

- Materials pricing and availability is subject to change depending on market conditions

- One mobilization included unless otherwise noted

By signing this document, the customer agrees to the services and conditions outlined in this document.

ALAMO CONCORD GENERAL CONTRACTING

Prepared For

BUCKSKIN CONCORD GENERAL

CONTRACTING

(480) 272-5289

Pat Bern Construction ROC 341181

2657 kiowa blvd n lake havasu city, AZ 86403 Phone: (928) 279-9938 Email: drew.patbern@gmail.com

Estimate # 1434 Date 06/26/2023

PO # BUCKSKIN SITE INVESTIGATION

Description Rate Quantity Total

TOOL TRUCK PER DAY ONSITE $200.00 3 $600.00

INCLUDES- tools job related, traffic control needed to barricade off excavations.

MINI EXCAVATOR OPERATED PER DAY $1,080.00 3 $3,240.00

BOBCAT TRACK SKID STEER OPERATED PER DAY $1,080.00 3 $3,240.00

MOBILIZATION OF EQUIPMENT PER TRIP $340.00 2 $680.00

EQUIPMENT 1 EA DELIVERY AND 1 EACH PICK UP

TOOL TRUCK 1 EACH DELIVERY AND 1 EACH PICK UP

LABOR RATE PER EACH LABOR PER DAY $520.00 6 $3,120.00

WE HAVE 2 LABORERS FOR 2 DAYS TOTALING 4 DAYS FOR THIS PRICE

PAT BERN PROJECT MANAGER PER HR $135.00 6 $810.00

Subtotal $11,690.00

Total $11,690.00

DocuSign Envelope ID: CFC42AAC-67E3-4DE3-8FAB-8FBA151802EF

Notes:

SCOPE -

1. INVESTIGATE PIPE SIZES AND DIMENSIONS AT WATER FILTRATION SITE

2. INVESTIGATE PIPE SIZES AT EXISTING RESTROOMS AT 2 LOCATIONS

3. VERIFY UTILITIES THAT WOULD BE TERMINATED AT 3 DEMO BATHROOM LOCATIONS

4.

5.

6.

- Transaction Privilege Tax - base bid is contingent upon receiving AZ 5005 Tax exempt form.

- Landscaping & irrigation replacement of any kind

- Relocation of any new or existing utilities due to unforeseen conflicts w/o agreement for payment

- Engineering, inspections, fees, quality control testing, surveying, permits, taxes, or outside consulting

- 3rd party consulting and inspections

- Bond costs

- Permits / fees

- BIM modeling

- Survey / staking

- Water Meters

- Manhole/valve final adjustments within proposed asphalt or concrete paving (Included if proposed paving is included in our scope of work)

- Costs associated with night work

- Roadway signs, TCP'S, Traffic devices

- Excavation of perimeter/retaining wall & waterproofing

- Slurry backfill under foundations, slabs, footings

- ABC under building slabs, other concrete flatwork and landscape

- Concrete flatwork/foundations

- Rock or hard dig excavation. Hard dig trenching is defined as material that cannot be excavated at an average of 2- CY per hour using the equivalent of a CAT 336 excavator

- Private utility locating - this is the responsibility of the utility Owner per AZ Blue Stake

- Electrical and dry utilities - power supply - connection to main - installation, conduits and trenching

- Liquidated damages

- Overtime and weekend workdays

- Dewatering

- Off site work

- Manhole Coatings

- 3D Surface Model

- tax

- import or export

- RIP RAP

- DRY WELLS

- Over Excavation. If over excavation is needed please Initial here and send specification ___________Date______ Qualifications:

- All productions are based on OSHA regulations. Client or job specific safety requirements that exceed OSHA may result in increased costs.

- Based on construction water provided onsite by others

- Price contingent on mutually agreeable contract Scope of work is inclusive of items listed below. Additional work will be tracked and submitted modification request

- If existing utility lines are encountered which are not shown on the PLANS, or not located, or incorrectly located by the Utility Owner and these lines are damaged or work is required to clear these lines it shall be recognized as a change of condition and paid for as extra work associated with such change of condition

- All utilities to terminate five feet from the building except the fire line which we will install 6” above the finished floor. Domestic water, storm drain, and sanitary sewer connections from utility contractor to plumber shall be made “last-in”; meaning whichever contractor installs first they leave a cap and the last contractor to install makes the final connection.

- Materials pricing and availability is subject to change depending on market conditions document.

BUCKSKIN CONCORD GENERAL CONTRACTING

ITEM

NO. DESCRIPTION UNIT

ORIG

QTY

UNIT

PRICE AMOUNT

Mobilization EA 1

TBD

2" SCH 80 RAW LF 1380 1.5

2,070.00$ flush and pressure test

3" SCH 80 RAW LF 1860 1.5

2,790.00$ flush and pressure test

6" C900 POTABLE LF 2,820 1.5

4,230.00$ pressure test and chlorinate and bac t

8-Inch PVC C900

Pipe

LF 860 1.5

1,290.00$ pressure test and chlorinate and bac t

4" C900 POTABLE LF 2620 1.5

3,930.00$ pressure test and chlorinate and bac t

CORP STOP W/

FLUSHING

EA 4

-$ n/a

8" GATE VALVE EA 3

-$ n/a

6" GATE VALVE EA 13

-$ n/a

4" GATE VALVE EA 7

-$ n/a

6" DIP LF 108 1.5

162.00$ pressure test and chlorinate and bac t

Fire Hydrant EA 3

-$ n/a

3" Gate Valve EA 1

-$ n/a

2" Gate Valve EA 2

-$ n/a

3/4" Water Service

Connection

EA 83 10

830.00$ pressure test and chlorinate and bac t

Portable water hose bib

Ea 88

-$ n/a

Air release Valve EA 4

-$ n/a

4" Sewer Wye connection EA 83 -$ n/a

3" schedule 80 force main LF 3140 1.5 4,710.00$ flush and pressure test

20 RV_Hook up EA 91 -$ n/a

8"SDR 35 Sanitary

Sewer LF 3360 3 10,080.00$ cctv, pressuret test and mandril

48" Sanitary

Manhole EA 19 350 6,650.00$ vacuum test

2" Schedule 80 force main LF 740 1.5 1,110.00$ high psi test

4" C900 PVC treated

Effluent LF 1660 1.5 2,490.00$ high psi test

25 4" Gate Valve EA 6 -$

SUB TOTAL 40,342.00$

1 HARD ROCK DIG 1 -$ n/a

2 asbestos removal 1 -$ n/a

3 storm rv 1 1 -$ n/a

4 stomr reroute 2 1 -$ n/a

5 320 hammer 1 -$ n/a

6 18" tee 1 -$ n/a

12" Culvert 30 -$ n/a

18" Culvert 258 -$ n/a

24" Culvert 230 -$ n/a

30" Culvert 328 -$ n/a

12-Inch Slotted

Drain 72 -$ n/a

End Section for 18"

Culvert -$ n/a

End Section for 24"

Culvert 2 -$ n/a

End Section for 30"

Culvert -$ n/a

Elbow, 24" -$ n/a

Manhole 1 -$ n/a

Spillway Assembly -$ n/a

CCTV SEWER

DAY 10

$2,500.00 25,000.00$ camera existing sewer

Lift Station LS 1 750 750.00$ inspect pumps and clean control panel

SURVEY

1 3500 3,500.00$ GPS LOCATION, owner to send us control

SUB 29,250.00$

GRAND TOTAL 69,592.00$

Prepared For

DEADHORSE STATE PARK CONCORD GENERAL

CONTRACTING

(480) 272-5289

Pat Bern Construction ROC 341181

2657 kiowa blvd n lake havasu city, AZ 86403 Phone: (928) 279-9938 Email: drew.patbern@gmail.com

Estimate

Date 06/26/2023

PO #

DEADHORSE SITE

INVESTIGATION

Description Rate Quantity Total

TOOL TRUCK PER DAY ONSITE $200.00 1 $200.00

INCLUDES- tools job related, traffic control needed to barricade off excavations.

MINI EXCAVATOR OPERATED PER DAY $1,080.00 0 $0.00

BOBCAT TRACK SKID STEER OPERATED PER DAY $1,080.00 0 $0.00

MOBILIZATION OF EQUIPMENT PER TRIP $340.00 0 $0.00

EQUIPMENT 1 EA DELIVERY AND 1 EACH PICK UP

TOOL TRUCK 1 EACH DELIVERY AND 1 EACH PICK UP

PAT BERN PROJECT MANAGER PER HR $135.00 8 $1,080.00

Subtotal $1,280.00

Total $1,280.00

DocuSign Envelope ID: CFC42AAC-67E3-4DE3-8FAB-8FBA151802EF

SCOPE -

1. INVESTIGATE LOCATION AND WATER / SEWER PIPE CONNECTIONS FOR 1 RESTROOM

2. VERIFY AREA THAT NEEDS TO BE GRADED FOR 1 RESTROOM

3.

4.

5.

- Transaction Privilege Tax - base bid is contingent upon receiving AZ 5005 Tax exempt form.

- Landscaping & irrigation replacement of any kind

- Relocation of any new or existing utilities due to unforeseen conflicts w/o agreement for payment

- Engineering, inspections, fees, quality control testing, surveying, permits, taxes, or outside consulting

- 3rd party consulting and inspections

- Bond costs

- Permits / fees

- BIM modeling

- Survey / staking

- Water Meters

- Manhole/valve final adjustments within proposed asphalt or concrete paving (Included if proposed paving is included in our scope of work)

- Costs associated with night work

- Roadway signs, TCP'S, Traffic devices

- Excavation of perimeter/retaining wall & waterproofing

- Slurry backfill under foundations, slabs, footings

- ABC under building slabs, other concrete flatwork and landscape

- Concrete flatwork/foundations

- Rock or hard dig excavation. Hard dig trenching is defined as material that cannot be excavated at an average of 2- CY per hour using the equivalent of a CAT 336 excavator

- Private utility locating - this is the responsibility of the utility Owner per AZ Blue Stake

- Electrical and dry utilities - power supply - connection to main - installation, conduits and trenching

- Liquidated damages

- Overtime and weekend workdays

- Dewatering

- Off site work

- Manhole Coatings

- 3D Surface Model

- tax

- import or export

- RIP RAP

- DRY WELLS

- Over Excavation. If over excavation is needed please Initial here and send specification ___________Date______ Qualifications:

- All productions are based on OSHA regulations. Client or job specific safety requirements that exceed OSHA may result in increased costs.

- Based on construction water provided onsite by others

- Price contingent on mutually agreeable contract Scope of work is inclusive of items listed below. Additional work will be tracked and submitted modification request

- If existing utility lines are encountered which are not shown on the PLANS, or not located, or incorrectly located by the Utility Owner and these lines are damaged or work is required to clear these lines it shall be recognized as a change of condition and paid for as extra work associated with such change of condition

- All utilities to terminate five feet from the building except the fire line which we will install 6” above the finished floor. Domestic water, storm drain, and sanitary sewer connections from utility contractor to plumber shall be made “last-in”; meaning whichever contractor installs first they leave a cap and the last contractor to install makes the final connection.

- Materials pricing and availability is subject to change depending on market conditions document.

DEADHORSE STATE PARK CONCORD GENERAL

CONTRACTING

Prepared For

LHC STATE PARK CONCORD GENERAL

CONTRACTING

(480) 272-5289

Pat Bern Construction ROC 341181

2657 kiowa blvd n lake havasu city, AZ 86403 Phone: (928) 279-9938 Email: drew.patbern@gmail.com

Estimate # 1435 Date 06/26/2023

PO # LHC STATE SITE INVESTIGATION

Description Rate Quantity Total

TOOL TRUCK PER DAY ONSITE $200.00 1 $200.00

INCLUDES- tools job related, traffic control needed to barricade off excavations.

MINI EXCAVATOR OPERATED PER DAY $1,080.00 0 $0.00

BOBCAT TRACK SKID STEER OPERATED PER DAY $1,080.00 0 $0.00

MOBILIZATION OF EQUIPMENT PER TRIP $340.00 0 $0.00

EQUIPMENT 1 EA DELIVERY AND 1 EACH PICK UP

TOOL TRUCK 1 EACH DELIVERY AND 1 EACH PICK UP

LABOR RATE PER EACH LABOR PER DAY $520.00 1 $520.00

WE HAVE 2 LABORERS FOR 2 DAYS TOTALING 4 DAYS FOR THIS PRICE

PAT BERN PROJECT MANAGER PER HR $135.00 6 $810.00

Subtotal $1,530.00

Total $1,530.00

DocuSign Envelope ID: CFC42AAC-67E3-4DE3-8FAB-8FBA151802EF

SCOPE -

1. INVESTIGATE EXISTING PIPE SIZES, DEPTHS AND LOCATIONS

2.

3.

4.

5.

- Transaction Privilege Tax - base bid is contingent upon receiving AZ 5005 Tax exempt form.

- Landscaping & irrigation replacement of any kind

- Relocation of any new or existing utilities due to unforeseen conflicts w/o agreement for payment

- Engineering, inspections, fees, quality control testing, surveying, permits, taxes, or outside consulting

- 3rd party consulting and inspections

- Bond costs

- Permits / fees

- BIM modeling

- Survey / staking

- Water Meters

- Manhole/valve final adjustments within proposed asphalt or concrete paving (Included if proposed paving is included in our scope of work)

- Costs associated with night work

- Roadway signs, TCP'S, Traffic devices

- Excavation of perimeter/retaining wall & waterproofing

- Slurry backfill under foundations, slabs, footings

- ABC under building slabs, other concrete flatwork and landscape

- Concrete flatwork/foundations

- Rock or hard dig excavation. Hard dig trenching is defined as material that cannot be excavated at an average of 2- CY per hour using the equivalent of a CAT 336 excavator

- Private utility locating - this is the responsibility of the utility Owner per AZ Blue Stake

- Electrical and dry utilities - power supply - connection to main - installation, conduits and trenching

- Liquidated damages

- Overtime and weekend workdays

- Dewatering

- Off site work

- Manhole Coatings

- 3D Surface Model

- tax

- import or export

- RIP RAP

- DRY WELLS

- Over Excavation. If over excavation is needed please Initial here and send specification ___________Date______ Qualifications:

- All productions are based on OSHA regulations. Client or job specific safety requirements that exceed OSHA may result in increased costs.

- Based on construction water provided onsite by others

- Price contingent on mutually agreeable contract Scope of work is inclusive of items listed below. Additional work will be tracked and submitted modification request

- If existing utility lines are encountered which are not shown on the PLANS, or not located, or incorrectly located by the Utility Owner and these lines are damaged or work is required to clear these lines it shall be recognized as a change of condition and paid for as extra work associated with such change of condition

- All utilities to terminate five feet from the building except the fire line which we will install 6” above the finished floor. Domestic water, storm drain, and sanitary sewer connections from utility contractor to plumber shall be made “last-in”; meaning whichever contractor installs first they leave a cap and the last contractor to install makes the final connection.

- Materials pricing and availability is subject to change depending on market conditions document.

LHC STATE PARK CONCORD GENERAL

Prepared For

RIVER ISLAND CONCORD GENERAL

CONTRACTING

(480) 272-5289

Pat Bern Construction ROC 341181

2657 kiowa blvd n lake havasu city, AZ 86403 Phone: (928) 279-9938 Email: drew.patbern@gmail.com

Estimate

Date 06/26/2023

PO #

RIVER ISLAND SITE

INVESTIGATION

Description Rate Quantity Total

TOOL TRUCK PER DAY ONSITE $200.00 2 $400.00

INCLUDES- tools job related, traffic control needed to barricade off excavations.

MINI EXCAVATOR OPERATED PER DAY $1,080.00 2 $2,160.00

BOBCAT TRACK SKID STEER OPERATED PER DAY $1,080.00 2 $2,160.00

MOBILIZATION OF EQUIPMENT PER TRIP $340.00 2 $680.00

EQUIPMENT 1 EA DELIVERY AND 1 EACH PICK UP

TOOL TRUCK 1 EACH DELIVERY AND 1 EACH PICK UP

LABOR RATE PER EACH LABOR PER DAY $520.00 4 $2,080.00

WE HAVE 2 LABORERS FOR 2 DAYS TOTALING 4 DAYS FOR THIS PRICE

PAT BERN PROJECT MANAGER PER HR $135.00 4 $540.00

Subtotal $8,020.00

Total $8,020.00

DocuSign Envelope ID: CFC42AAC-67E3-4DE3-8FAB-8FBA151802EF

SCOPE -

1. INVESTIGATE PIPE SIZES AND DIMENSIONS AT WATER FILTRATION SITE

2. INVESTIGATE PIPE SIZES AT EXISTING RESTROOM

3.

4.

5.

- Transaction Privilege Tax - base bid is contingent upon receiving AZ 5005 Tax exempt form.

- Landscaping & irrigation replacement of any kind

- Relocation of any new or existing utilities due to unforeseen conflicts w/o agreement for payment

- Engineering, inspections, fees, quality control testing, surveying, permits, taxes, or outside consulting

- 3rd party consulting and inspections

- Bond costs

- Permits / fees

- BIM modeling

- Survey / staking

- Water Meters

- Manhole/valve final adjustments within proposed asphalt or concrete paving (Included if proposed paving is included in our scope of work)

- Costs associated with night work

- Roadway signs, TCP'S, Traffic devices

- Excavation of perimeter/retaining wall & waterproofing

- Slurry backfill under foundations, slabs, footings

- ABC under building slabs, other concrete flatwork and landscape

- Concrete flatwork/foundations

- Rock or hard dig excavation. Hard dig trenching is defined as material that cannot be excavated at an average of 2- CY per hour using the equivalent of a CAT 336 excavator

- Private utility locating - this is the responsibility of the utility Owner per AZ Blue Stake

- Electrical and dry utilities - power supply - connection to main - installation, conduits and trenching

- Liquidated damages

- Overtime and weekend workdays

- Dewatering

- Off site work

- Manhole Coatings

- 3D Surface Model

- tax

- import or export

- RIP RAP

- DRY WELLS

- Over Excavation. If over excavation is needed please Initial here and send specification ___________Date______ Qualifications:

- All productions are based on OSHA regulations. Client or job specific safety requirements that exceed OSHA may result in increased costs.

- Based on construction water provided onsite by others

- Price contingent on mutually agreeable contract Scope of work is inclusive of items listed below. Additional work will be tracked and submitted modification request

- If existing utility lines are encountered which are not shown on the PLANS, or not located, or incorrectly located by the Utility Owner and these lines are damaged or work is required to clear these lines it shall be recognized as a change of condition and paid for as extra work associated with such change of condition

- All utilities to terminate five feet from the building except the fire line which we will install 6” above the finished floor. Domestic water, storm drain, and sanitary sewer connections from utility contractor to plumber shall be made “last-in”; meaning whichever contractor installs first they leave a cap and the last contractor to install makes the final connection.

- Materials pricing and availability is subject to change depending on market conditions document.

RIVER ISLAND CONCORD GENERAL

Solicitation # BPM005291

ARPA Arizona State Parks Water and Wastewater Upgrades

Prepared for:

Arizona Department of Administration

April 27, 2023

Request for Qualifications Construction Manager at Risk Services

Solicitation No.

BPM005291

Description:

ARIZONA STATE PARKS WATER AND

WASTWATER UPGRADES

Arizona Department of Administration

General Services Division 1400 W Washington St., Ste. B200

ATTACHMENT 1 OFFER AND ACCEPTANCE FORM

OFFER

TO THE STATE OF ARIZONA:

The Undersigned hereby offers and agrees to furnish the…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .