encl 4_qasp - SAT CW Filtration and Upgrades.pdf
PDF 346 KB Posted
- Attached to
- Condenser Water Filtration System Upgrade Federal contract opportunity
- Solicitation number
- HC102821R0018
- Issued by
- Defense Information Systems Agency
About this file
This Quality Assurance Surveillance Plan (QASP) outlines performance monitoring for a condenser water filtration and upgrades project at a Defense Information Systems Agency data center in San Antonio, Texas. Key personnel overseeing the contract include the program manager, contracting officer, and contracting officer's representative. Performance will be evaluated on a weekly basis through 100% inspections with metrics covering on-time delivery, submittal approval rates, rework levels, and regulatory compliance. Deficiencies will be documented in corrective action reports and performance assessment reports, which may impact payment amounts. Acceptable quality is defined as 100% compliance given the sensitive computer room environment. The solicitation requests proposals for upgrading an existing condenser water filtration system at the same San Antonio facility to improve reliability, energy use, and redundancy. Enhancements include work on cooling towers, piping replacement and adjustments, water pump modifications, temporary chiller installations, and controls upgrades. Site visits for the raised floor project are scheduled for March 31, 2021 at 9:00am and 12:30pm Central Time to familiarize offerors with performance conditions. Questions are due by April 9, 2021 with responses from the Defense Information Systems Agency.
View the file
Other files for this federal contract opportunity
Show all 50
Condenser Water Filtration System Upgrade has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Encl 4, QASP
23Jun2017/v3
QUALITY ASSURANCE SURVEILLANCE PLAN (QASP)
1. Contract or Task Order Title: Condenser Water Filtration & Upgrades – DISA Data Center San Antonio
2. Purpose:
This QASP provides a systematic method to evaluate performance for the stated contract. This QASP explains the following:
What will be monitored?
How monitoring will take place.
Who will conduct the monitoring?
How monitoring efforts and results will be documented.
This QASP does not detail how the contractor accomplishes the work. Rather, the QASP is created with the premise that the contractor is responsible for management and quality control actions to meet the terms of the contract. It is the Government’s responsibility to be objective, fair, and consistent in evaluating performance. In addition, the
QASP should recognize that unforeseen and uncontrollable situations may occur.
This QASP is a “living document” and the Government may review and revise it on a regular basis. Updates shall ensure that the QASP remains a valid, useful, and enforceable document. Copies of the original QASP and revisions shall be provided to the contractor and Government officials implementing surveillance activities.
3. Roles and Responsibilities:
The following personnel shall oversee and coordinate surveillance activities.
Program/Project Manager (PM) – The PM provides program oversight and supports the COR’s performance as-sessment activities.
Contracting Officer (KO) – The KO shall ensure performance of all necessary actions for effective contracting, ensure compliance with the contract terms, and shall safeguard the interests of the United States in the contractual relationship. The KO shall also ensure that the contractor receives impartial, fair, and equitable treatment under this contract. Determine the final assessment of the contractor’s performance.
Contracting Officer’s Representative (COR) – The COR is responsible for providing continuous technical over-sight of the contractor’s performance. The COR uses the QASP to conduct the oversight/surveillance process. The
COR shall keep a Quality Assurance file that accurately documents the contractor’s actual performance. The pur-pose is to ensure that the contractor meets the performance standards contained in the contract. The COR is respon-sible for reporting early identification of performance problems to the KO. The COR is required to provide an an-nual performance assessment to the KO which will be used in documenting past performance. The QASP is the pri-mary tool for documenting contractor performance. The COR is not empowered to make any contractual commit-ments or to authorize any contractual change on the Government’s behalf.
Other Key Government Personnel – This may include performance monitors, inspectors, technical experts, work-force service division and center directorate level security personnel, requirements office, or others (i.e. users) who provide information that helps the COR monitor contractor performance.
4. Primary Method of Surveillance:
All tasks shall be evaluated with 100% inspection as the surveillance method.
100 Percent Inspection. This is usually only the most appropriate method for infrequent tasks or tasks with stringent performance requirements, e.g., where safety or health is a concern. With this method, per-formance is inspected/evaluated at each occurrence. One hundred percent inspection is too expensive to be used in most cases.
Surveillance Matrix
The Surveillance Matrix (Appendix 1) is the list of performance objectives and standards that must be performed by the contractor. This matrix details the method of surveillance the COR will use to validate and inspect these perfor-mance elements. Inspection of each element will be documented in the COR file.
Performance objectives define the desired outcomes. Performance Standards define the level of service required under the contract to successfully meet the performance objective. The inspection methodology defines how, when, and what will be assessed in measuring performance. The Government performance surveillance, using this QASP, to determine the quality of the contractor’s performance as it relates to the performance element standards. The
AQL performance Standard Table should be used to form the foundation of the COR’s inspection checklist.
5. Performance Standards:
Performance Standard Acceptable Quality Level (AQL) Method of Surveillance
6.1 - Detailed project schedule, in-vestigate existing conditions, con-duct weekly project status meetings, and prepare and submit shop draw-ings/product data
100% schedule with complete phasing plan showing no planned data center oper-ational interruptions.
100% review of schedule, meeting minutes and submit-tals
6.1-6.8 Submittals and Shop Draw-ings
100% of the documents were submitted and approved in compliance with contract requirements.
Submitted and approved docu-mentation.
6.2 Tasks Performance occurs with little to no re-
quired re-work 97% of the time.
Routine inspection during in-stallation; 100% completion inspection prior to acceptance.
6.3 Tasks Performance occurs with little to no re-
quired re-work 97% of the time.
Routine inspection during in-stallation; 100% completion inspection prior to acceptance.
6.4 Tasks Performance occurs with little to no re-
quired re-work 97% of the time.
Routine inspection during in-stallation; 100% completion inspection prior to acceptance.
6.5 Tasks Performance occurs with little to no re-
quired re-work 97% of the time.
Routine inspection during in-stallation; 100% completion inspection prior to acceptance.
6.6 Tasks Performance occurs with little to no re-
quired re-work 97% of the time.
Routine inspection during in-stallation; 100% completion inspection prior to acceptance.
6.7 Tasks Performance occurs with little to no re-
quired re-work 97% of the time.
Routine inspection during in-stallation; 100% completion inspection prior to acceptance.
6.8 Tasks Performance occurs with little to no re-
quired re-work 97% of the time.
Routine inspection during in-stallation; 100% completion inspection prior to acceptance.
6.10 Requirements Performance occurs with little to no re-
quired re-work 97% of the time.
Routine inspection during in-stallation; 100% completion inspection prior to acceptance.
6.9.1 Inventory Tasks 99% Compliance with Contract Require-
ments.
Submitted and Facility Man-ager approved documentation.
6.9.2 Testing and Testing Reports Successful Pre-functional and Functional
Testing (PFT & FT), TAB and Commis-sioning to include all testing of control se-quences and failure methods
100% review and validation.
6.9.3 As-Built Drawings 100% Compliance with Contract Require-ments.
100% inspection and valida-tion.
6.9.5 Spare Parts 100% Compliance with Contract Require-
ments.
100% inspection and valida-tion.
6.9.6 - Operations & Maintenance
(O&M) Binder
Material submissions, As-built drawings, Operation & Maintenance Manuals, re-quire only minor modifications to comply with technical requirements. Revisions that occur are minor and resolved to meet contract requirement.
100% completion inspection prior to acceptance for tech-nical compliance review by the
Government facility manage-ment personnel.
6. Documenting Performance:
Acceptable Performance.
The Government shall document positive performance. A Performance Assessment Report (PAR) template is at-tached (Appendix 2). Any report may become part of the supporting documentation for fixed price payments, award/incentive fee payments, Contractor Performance Assessment Reporting System (CPARS) entries, or other actions. Government acceptance of services permits the contractor to invoice for the service fee.
Unacceptable performance.
Unacceptable contractor performance can be identified by customer complaints (Appendix 3) or upon schedule sur-veillance evaluations. When unacceptable performance occurs, the COR shall inform the contractor. This will nor-mally be in writing unless circumstances necessitate verbal communication. The COR shall document the discus-sion and place it in the COR file and provide a copy to the KO.
When the COR determines formal written communication is required, the COR shall prepare a Corrective Action
Report (CAR). The CAR is forwarded to the KO for dissemination to the contractor. A CAR template is attached to this QASP (Appendix 4).
The contractor shall acknowledge receipt of the CAR in writing. The CAR will specify if the contractor is required to prepare a corrective action plan to document how the contractor shall correct the unacceptable performance and avoid a recurrence. The CAR will also state how long after receipt the contractor has to present this corrective ac-tion plan to the KO and COR. The Government may withhold payment for services until corrective action is taken.
The Government shall review the contractor's corrective action plan to determine acceptability. Upon Government acceptance of the corrected services the contractor will be permitted to invoice for the service fee.
Any CAR may become a part of the supporting documentation for contract payment deductions, fixed fee deduc-tions, award fee nonpayment, CPARS or other actions deemed necessary by the KO.
7. Mandatory or regulatory compliance items
The contractor will provide initial proof of compliance with regulatory and compliance items contained in the con-tract. The Contracting Officer's Representative (COR) and the Contracting Officer (KO) will evaluate the initial submission and will conduct ad hoc reviews of the contractor's compliance throughout the remainder of the contract.
The contractor will monitor compliance as required by FAR 52.222-50, Combating Trafficking in Persons, and re-port any issues to the KO.
8. Acceptable Quality Level (AQL):
The AQL for this project is 100% due to the raised floor computer room environment this project supports.
9. Evaluation Method:
There will be a 100% review of the submittals by the COR, as defined by PWS. Once the package has been ap-proved of and all comments have been addressed, the contractor can proceed onto the installation phase.
At the close-out of the project a walkthrough will be to verify that the installation was properly done and that there are no deficiencies. Any existing deficiencies shall be added to a punch list and will be addressed in a timely man-ner.
10. Performance Rating
In evaluating the quality of contractor’s performance, the following performance ratings may be used (same as
CPAR ratings).
Performance
Rating Criteria
Exceptional
Performance meets contractual requirements and exceeds many to the govern-ment’s benefits. The contractual performance of the element or sub-element being assessed was accomplished with no problems and contractor actions were highly ef-fective.
Very Good
Performance meets contractual requirements and exceeds some to the government benefits. The contractual performance was accomplished with few minor problems for which corrective actions taken by the contractor were effective.
Satisfactory
Performance meets contractual requirements. The contractual performance con-tains some minor problems for which corrective actions taken by the contractor were satisfactory.
Marginal
Performance does not meet some contractual requirements. The contractual perfor-mance reflects a serious problem for which the contractor has not yet identified cor-rective actions. The contractor’s proposed actions appear marginally effective or were not fully implemented.
Unsatisfactory
Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance contains serious problem(s) for which the contractor’s corrective actions appear or were ineffective.
Appendix 1 - Surveillance Matrix
Performance
Standards
Acceptable
Quality Levels
Methods of
Calulation Surveillance Results/Ratings
Performance is based on timely delivery of all tasks as speci-fied in PWS
Section 6.
High level of government satisfaction with the Con-tractor’s work includes the successful deliv-ery of all tech-nical tasks on schedule as specified in
PWS Section 6.
Target Criteria:
Equipment and installation work meets technical requirements
95% of the time, as specified in
PWS Section 6.
Minimum
Acceptable:
Deficient work is corrected in a timely manner.
Calculation:
The number of re-quired equipment items, 100% of the total, are satisfac-torily installed correctly and on schedule.
The Government technical person-nel (site Facility
Manager) must inspect the com-pleted work for correct equipment installation for the results to have at least a 100% com-pleteness rate.
Measurement Interval:
The Measurement Interval is at completion of each speci-fied task in the PWS Section
6.
Measurement Period:
The Measurement Period be-gins at issuance of Notice to
Proceed (NTP) and ends at fi-nal acceptance of technical compliance of the contract.
Source of Measurement Data:
Data will be collected from site Facility Manager inspec-tion of the completed work for timely and correct equip-ment installation.
Method of Surveillance:
Facility Manager on-site
100% inspection of the com-pleted work.
Timing of Measurement:
Measurements are based on inspection of completed work when notified by the Contrac-tor that task is complete.
Reporting Frequency: Re-porting to commence upon
Contract NTP and continue throughout the Period of Per-formance on a monthly schedule or as needed when
Contractor completes tasks.
Exceptional - All work completed without corrections.
Delivered ahead of schedule.
Very Good - All work completed with minor corrections.
Delivered on Sched-ule
Satisfactory - Work completed within
PWS technical re-quirements. Close monitoring by Govt required. Formally identified deficien-cies corrected within 1 week. De-livered on Schedule.
Marginal -
Project delivered in compliance but out-side the POP.
Unsatisfactory-
Contractor unable to fulfill PWS require-ments
(A rollup of assess-ment of the Surveil-lance Inspection Re-sults to develop an overall rating for this objective)
Appendix 2 – Performance Assessment Report
PERFORMANCE ASSESSMENT REPORT (PAR)
(If more space is needed, use reverse and identify by number)
1. CONTRACT/TASK ORDER
NUMBER
2. CONTRACTOR 3. TYPE OF SERVICES
4. QUALITY ASSURANCE PERSONNEL (COR) SIGNATURE AND DATE
5. COR PHONE 6. SUSPENSE DATE
I. PERFORMANCE
7. DEFICIENCY (CHECK ALL BOXES THAT
APPLY)
NEW
REPEAT
NO DEFICIENCY NOTED
8. SERVICES SUMMARY or PWS PARAGRAPH ITEM
REVIEWED
9. BRIEF DESCRIPTION OF DEFICIENCY (IF DEFICIENCY
BOX WAS CHECKED)
10. DETAILED PERFORMANCE ASSESSMENT
II. CONTRACTOR VALIDATION
11. CONTRACTOR REPRESENTATIVE CONCUR
NON-CONCUR
12. CORRECTIVE ACTION ESTIMATED COMPLETION
DATE
13. CONTRACTOR REPRESENTATIVE CORRECTIVE ACTION AND PREVENTION OF RECURRENCE OR REASON
FOR NON-CONCURRENCE OF COR CITED DEFICIENCY
III. ACTION CORRECTED
14. CONCUR NON-CONCUR COR SIGNATURE AND DATE
15. COR REMARKS (REQUIRED)
6. CONTRACTOR REPRESENTATIVE REMARKS
Appendix 3 – Customer Complaint Record
CUSTOMER COMPLAINT RECORD
DATE/TIME OF COMPLAINT
SOURCE OF COMPLAINT
ORGANIZATION
BUILDING NUM-
BER
INDIVIDUAL
PHONE NUMBER
NATURE OF COMPLAINT
CONTRACT REFERENCE
VALIDATION
DATE/TIME CONTRACTOR INFORMED OF COMPLAINT
ACTION TAKEN BY CONTRACTOR
RECEIVED/VALIDATED BY
Appendix 4 – Corrective Action Report
CORRECTIVE ACTION REPORT (CAR)
(If more space is needed, use reverse and identify by number)
1. CONTRACTOR
2. CONTRACT NUMBER
3. TYPE OF SERVICES
4. FUNCTIONAL AREA
5. SUSPENSE DATE
6. CONTROL NUMBER
7. DEFICIENCY MAJOR MINOR
FINDING:
FINDING IMPACT:
Please respond with a written corrective action plan that details the corrective action of the cited deficiency, the cause of the defi-ciency, and actions taken to prevent recurrence by Suspense Date in Block 5. If date was not entered in Block 5, the contractor is not required to provide a response.
8. QUALITY ASSURANCE PERSONNEL (COR)
TYPED NAME AND GRADE
SIGNATURE AND DATE
9. ISSUING AUTHORITY
TYPED NAME AND GRADE
SIGNATURE AND DATE
10. COR RESPONSE TO CONTRACTOR CORRECTIVE ACTION AND ACTION TAKEN TO PREVENT RECURRENCE
11. COR DETERMINATION
ACCEPTED REJECTED
12. CLOSE DATE
File details come from the government source that posted it. Updated .