Report_SWPPP_GRSM_1A29_(draft).pdf

PDF 7 MB Posted

Attached to
Great Smoky Mountains National Park Projects Federal contract opportunity
Solicitation number
DTFH71-17-B-00007
Issued by
Department of Transportation Federal Highway Administration

About this file

Report_SWPPP_GRSM 1A29 (draft)

View the file

Other files for this federal contract opportunity

Show all 19

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Stormwater Pollution Prevention Plan (SWPPP) NP-GRSM 1A29, September 19, 2016 i

Stormwater Pollution Prevention Plan for:

Newfound Gap Road Improvements

Project Number PRA-GRSM 1A28 Renumbered as NP-GRSM 1A29 Great Smoky Mountains National Park, Sevier County, Tennessee

Nearest City: Gatlinburg, Tennessee

Operator(s):

*COMPANY THAT SIGNS SECTION 8

To Be Determined

SWPPP Contact(s):

Federal Highway Administration

Mr. Kevin Rose 21400 Ridgetop Circle

Sterling, VA 20166 571-434-1541

Kevin.Rose@dot.gov

SWPPP Preparation Date:

4/1/14

Updated 9/19/16

Estimated Project Dates:

Begin: November 3, 2014 End: November 3, 2016

Estimated Project Duration: 2.0 Years ii

Contents

SECTION 1: SITE EVALUATION, ASSESSMENT, AND PLANNING

1.1 Project/Site Information

1.2 Contact Information/Responsible Parties

1.3 Nature and Sequence of Construction Activity

1.4 Soils, Slopes, Vegetation, and Current Drainage Patterns

1.5 Construction Site Estimates

1.6 Receiving Waters

1.7 Site Features and Sensitive Areas to be Protected

1.8 Potential Sources of Pollution

1.9 Endangered Species Certification

1.10 Historic Preservation

1.11 Applicable Federal, Tribal, State or Local Programs

1.12 Maps

SECTION 2: EROSION AND SEDIMENT CONTROL BMPS

2.1 Minimize Disturbed Area and Protect Natural Features and Soil

2.2 Phase Construction Activity

2.3 Control Stormwater Flowing onto and through the Project

2.4 Stabilize Soils

2.5 Protect Slopes

2.6 Protect Storm Drain Inlets

2.7 Establish Perimeter Controls and Sediment Barriers

2.8 Retain Sediment On-Site

2.9 Establish Stabilized Construction Exits

2.10 Additional BMPs

SECTION 3: GOOD HOUSEKEEPING BMPS

3.1 Material Handling and Waste Management

3.2 Establish Proper Building Material Staging Areas

3.3 Designate Washout Areas

3.4 Establish Proper Equipment/Vehicle Fueling and Maintenance Practices

3.5 Control Equipment/Vehicle Washing

3.6 Spill Prevention and Control Plan

3.7 Any Additional BMPs

3.8 Allowable Non-Stormwater Discharge Management

SECTION 4: SELECTING POST-CONSTRUCTION BMPs

SECTION 5: INSPECTIONS

5.1 Inspections

5.2 Delegation of Authority

5.3 Corrective Action Log

SECTION 6: RECORDKEEPING AND TRAINING

6.1 Recordkeeping

6.2 Log of Changes to the SWPPP

6.3 Training

SECTION 7: FINAL STABILIZATION

iii

SECTION 8: CERTIFICATION AND NOTIFICATION

SWPPP APPENDICES

Appendix A – General Location Map Appendix B – Soil Resource Report and Map Appendix C – Construction General Permit Appendix D – NOI and Acknowledgement Letter from EPA/State Appendix E – Inspection Reports Appendix F – Corrective Action Log (or in Part 5.3) Appendix G – SWPPP Amendment Log (or in Part 6.2) Appendix H – Subcontractor Certifications/Agreements Appendix I – Grading and Stabilization Activities Log (or in Part 6.1) Appendix J – Training Log Appendix K – Delegation of Authority Appendix L – Additional Information (i.e., Endangered Species and Historic Preservation Documentation)

SECTION 1: SITE EVALUATION, ASSESSMENT, AND PLANNING

1.1 Project/Site Information

Project/Site Name: Newfound Gap Road Improvements, Project Number PRA-GRSM 1A28 Project Street/Location: Newfound Gap Road, Great Smoky Mountains National Park Nearest City: Gatlinburg State: TN ZIP Code: 37738 County or Similar Subdivision: Sevier County

Latitude/Longitude (Use one of three possible formats, and specify method) Latitude: Longitude:

1. _ _ º _ _ ' _ _'' N (degrees, minutes, seconds) 1. _ _ º _ _ ' _ _'' W (degrees, minutes, seconds)

2. _ _ º _ _ . _ _' N (degrees, minutes, decimal) 2. _ _ º _ _ . _ _' W (degrees, minutes, decimal)

3. 35.7064 º N (decimal) 3. 83.5216 º W (decimal)

Method for determining latitude/longitude:

USGS topographic map (specify scale: 1:24,000 ) EPA Web site GPS Other (please specify):

Is the project located in Indian country? Yes No If yes, name of Reservation, or if not part of a Reservation, indicate "not applicable."

Not applicable

Is this project considered a federal facility? Yes No

NPDES project or permit tracking number*:

*(This is the unique identifying number assigned to your project by your permitting authority after you have applied for coverage under the appropriate National Pollutant Discharge Elimination System (NPDES) construction general permit.)

Instructions:

― In this section, you can gather some basic site information that will be helpful to you later when you file for permit coverage.

― For more information, see Developing Your Stormwater Pollution Prevention Plan: A SWPPP Guide for

Construction Sites (also known as the SWPPP Guide), Chapter 2 ― Detailed information on determining your site’s latitude and longitude can be found at www.epa.gov/npdes/stormwater/latlong http://www.epa.gov/npdes/stormwater/latlong

1.2 Contact Information/Responsible Parties

Operator(s):

Insert Company or Organization Name: To Be Determined Insert Name:

Insert Address:

Insert City, State, Zip Code:

Insert Telephone Number:

Insert Fax/Email:

Insert area of control (if more than one operator at site):

Repeat as necessary

Project Manager(s) or Site Supervisor(s):

SWPPP Contact(s):

Federal Highway Administration Mr. Kevin Rose 21400 Ridgetop Circle Sterling, VA 20166 kevin.rose@dot.gov

― List the operator(s), project managers, stormwater contact(s), and person or organization that prepared the

SWPPP. Indicate respective responsibilities, where appropriate.

― Also, list subcontractors expected to work on-site. Notify subcontractors of stormwater requirements applicable to their work.

― See SWPPP Guide, Chapter 2.B.

This SWPPP was Prepared by:

Lisa Landers Federal Highway Administration Eastern Federal Lands Highway Division 21400 Ridgetop Circle Sterling, VA 20166

(571) 434-1592 Lisa.Landers@dot.gov

Subcontractor(s):

Emergency 24-Hour Contact:

1.3 Nature and Sequence of Construction Activity

Describe the general scope of the work for the project, major phases of construction, etc:

The purpose of this project is to rehabilitate Newfound Gap Road from TN milepost 0.0 to TN milepost 6.3 in the great Smoky Mountains National Park. The rehabilitation includes removal of the deteriorated pavement surface from the existing two-lane roadway; placement of a new asphalt overlay, including reconstruction of structurally deficient pavement sections; paving pullouts. The road surface and pullouts will be replaced with a new asphalt surface. Work within the culverts will be limited to the repair or replacement of the existing structure. Various existing gravel pullouts will be stabilized and paved which will require minor grading. A portion of the roadway near the Carlos Campbell Overlook has subsided over the years. Two permanent ground anchor walls (PGA Walls) will be constructed at the toe of the slope to stop further subsidence.

The purpose of this project is to rehabilitate schedule C of the project (renumbered as NP- GRSM 1A29) Newfound Gap Road from TN milepost 0.0 to TN milepost 1.8 in the Great Smoky Mountains National Park. Work between TN milepost 1.8 and TN milepost 6.3 has been completed. The rehabilitation includes full depth pavement reconstruction, final asphalt course, box culvert repair, repointing/repair of existing stone masonry, resetting stone curb, repair of drainage structures, pullout construction, shoulder stabilization, pavement markings, signing, installation of steel backed timber guardrail and traffic control.

Instructions:

― Briefly describe the nature of the construction activity and approximate time frames (one or more paragraphs, depending on the nature and complexity of the project).

― For more information, see SWPPP Guide, Chapter 3.A.

An Environmental Assessment for this project was completed in March of 2010 and a Finding of No Significant Impact was signed on June 22, 2010. Potential impacts endangered or threatened species within the project corridor were found to be negligible to minor. A full list of endangered or threatened species can be found in the environmental assessment.

What is the function of the construction activity?

Residential Commercial Industrial Road Construction Linear Utility Other (please specify): See above

Estimated Project Duration: 24 months

1.4 Soils, Slopes, Vegetation, and Current Drainage Patterns

Soil type(s):

A USDA soil survey for the project corridor is included in Appendix A.

Slopes (describe current slopes and note any changes due to grading or fill activities):

The project traverses steeply sloping terrain over the entire length. The natural slope inclinations along the right-of-way vary from 2 horizontal to 1 vertcal (2H:1V) to 1H:1V. The proposed grading will generally follow the slopes of the existing roadway shoulders.

Drainage Patterns (describe current drainage patterns and note any changes dues to grading or fill activities):

The existing drainage patterns generally sheet flow off of the pavement, across the shoulder, down the fill slope or roadside ditch and to the receiving waterways. The drainage patterns will not be significantly altered due to the proposed grading. Channelized flow from curb and gutter sections will be directed through paved water ways to rip rap pads to dissipate the concentrated flow.

Instructions:

― Describe the existing soil conditions at the construction site including soil types, slopes and slope lengths, drainage patterns, and other topographic features that might affect erosion and sediment control.

― Also, note any historic site contamination evident from existing site features and known past usage of the site.

― This information should also be included on your site maps (See SWPPP Guide, Chapter 3.C.).

Vegetation:

The project corridor is a maintained roadway. The existing vegetation along the roadway shoulders is grasses and low shrubbery. Dense forests exist outside of the roadway prism. It is anticipated that the proposed grading and land disturbance will be within the existing maintained roadway prism.

1.5 Construction Site Estimates

The following are estimates of the construction site.

Total project area: 29.2* acres Construction site area to be disturbed : 2.1 acres Percentage impervious area before construction: % Runoff coefficient before construction:

Percentage impervious area after construction: % Runoff coefficient after construction

*Total project area consists of the existing roadway prism, pavement and maintained shoulders for the entire GRSM 1A28 project.

The increase in impervious area is negligible. The proposed paved pullouts will fall within the same general footprint as an existing compacted gravel pullout.

― Estimate the area to be disturbed by excavation, grading, or other construction activities, including dedicated off-site borrow and fill areas.

― Calculate the percentage of impervious surface area before and after construction ― Calculate the runoff coefficients before and after construction.

― For more information, see SWPPP Guide, Chapter 3.A and Appendix C.

1.6 Receiving Waters

Description of receiving waters:

The receiving waters of this project are named and un-named tributaries to West Prong Little Pigeon River to the Pigeon River to French Broad River, a tributary to the Tennessee River.

Description of storm sewer systems:

The existing storm system consists of cross pipes/culverts and very few catch basins with a single pipe system. A majority of the storm system is conveyed with roadside ditches and waterways.

Description of impaired waters or waters subject to TMDLs:

Other:

1.7 Site Features and Sensitive Areas to be Protected

― Describe unique site features including streams, stream buffers, wetlands, specimen trees, natural vegetation, steep slopes, or highly erodible soils that are to be preserved.

― Describe measures to protect these features.

― Include these features and areas on your site maps.

― For more information, see SWPPP Guide, Chapter 3.A and 3.B.

― List the waterbody(s) that would receive stormwater from your site, including streams, rivers, lakes, coastal waters, and wetlands. Describe each as clearly as possible, such as Mill Creek, a tributary to the Potomac River, and so on.

― Indicate the location of all waters, including wetlands, on the site map.

― Note any stream crossings, if applicable.

― List the storm sewer system or drainage system that stormwater from your site could discharge to and the waterbody(s) that it ultimately discharges to.

― If any of the waterbodies above are impaired and/or subject to Total Maximum Daily Loads (TMDLs), please list the pollutants causing the impairment and any specific requirements in the TMDL(s) that are applicable to construction sites. Your SWPPP should specifically include measures to prevent the discharge of these pollutants.

― For more information, see SWPPP Guide, Chapter 3.A and 3.B.

― Also, for more information and a list of TMDL contacts and links by state, visit www.epa.gov/npdes/stormwater/tmdl.

http://www.epa.gov/npdes/stormwater/tmdl

1.8 Potential Sources of Pollution

Potential sources of sediment to stormwater runoff:

Land grading operations.

Potential pollutants and sources, other than sediment, to stormwater runoff:

Normal pollutants contained within a typical construction site. It will be the responsibility of the contractor to contain any pollutants.

Trade Name Material Stormwater Pollutants Location

Description of unique features that are to be preserved:

Steep Slopes outside of roadway prism, blue line streams.

Describe measures to protect these features:

The contractor will be required to install and maintain the appropriate erosion control measures throughout all phases of the project to minimize the risk of sediment leaving the construction area. Furthermore, the work around the blue line streams will be limited to the maintenance activities for the existing culvert crossings.

― Identify and list all potential sources of sediment, which may reasonably be expected to affect the quality of stormwater discharges from the construction site.

― Identify and list all potential sources of pollution, other than sediment, which may reasonably be expected to affect the quality of stormwater discharges from the construction site.

1.9 Endangered Species Certification

Are endangered or threatened species and critical habitats on or near the project area?

Yes No

Describe how this determination was made:

See Environmental Assessment dated March 2010.

If yes, describe the species and/or critical habitat:

See Environmental Assessment dated March 2010.

If yes, describe or refer to documentation that determines the likelihood of an impact on identified species and/or habitat and the steps taken to address that impact. (Note, if species are on or near your project site, EPA strongly recommends that the site operator work closely with the appropriate field office of the U.S. Fish and Wildlife Service or National Marine Fisheries Service. For concerns related to state or tribal listing of species, please contact a state or tribal official.)

See Environmental Assessment dated March 2010.

― Before beginning construction, determine whether endangered or threatened species or their critical habitats are on or near your site.

― Adapt this section as needed for state or tribal endangered species requirements and, if applicable, document any measures deemed necessary to protect endangered or threatened species or their critical habitats.

― For more information on this topic, see SWPPP Guide, Chapter 3.B.

― Additional information on Endangered Species Act (ESA) provisions is at www.epa.gov/npdes/stormwater/esa http://www.epa.gov/npdes/stormwater/esa

1.10 Historic Preservation

Are there any historic sites on or near the construction site?

Yes No

Describe how this determination was made:

See Environmental Assessment dated March 2010.

If yes, describe or refer to documentation that determines the likelihood of an impact on this historic site and the steps taken to address that impact.

See Environmental Assessment dated March 2010.

1.11 Applicable Federal, Tribal, State or Local Programs

Not Applicable

― Note other applicable federal, tribal, state or local soil and erosion control and stormwater management requirements that apply to your construction site.

― Before you begin construction, you should review federal and any applicable state, local, or tribal historic preservation laws and determine if there are historic sites on or near your project. If so, you might need to make adjustments to your construction plans or to your stormwater controls to ensure that these historic sites are not damaged.

― For more information, see SWPPP Guide, Chapter 3.B or contact your state or tribal historic preservation officer.

1.12 Maps

Include the site maps with the SWPPP.

Map Listing:

Figure 1 – Overall Site Map with Beginning and End of Project, Receiving Water, and Noted Disturbed Areas Figure 2- List of Disturbed areas Maps 3.1-3.10 – Figures Detailing Stormwater Flow Direction, Grading, and BMPs at Disturbed areas

Instructions:

― Attach site maps. For most projects, a series of site maps is recommended. The first should show the undeveloped site and its current features. An additional map or maps should be created to show the developed site or for more complicated sites show the major phases of development.

These maps should include the following:

― Direction(s) of stormwater flow and approximate slopes before and after major grading activities;

― Areas and timing of soil disturbance;

― Areas that will not be disturbed;

― Natural features to be preserved;

― Locations of major structural and non-structural BMPs identified in the SWPPP;

― Locations and timing of stabilization measures;

― Locations of off-site material, waste, borrow, or equipment storage areas;

― Locations of all waters of the United States, including wetlands;

― Locations where stormwater discharges to a surface water;

― Locations of storm drain inlets; and ― Areas where final stabilization has been accomplished.

― For more information, see SWPPP Guide, Chapter 3.C.

SECTION 2: EROSION AND SEDIMENT CONTROL BMPS

― Describe the BMPs that will be implemented to control pollutants in stormwater discharges. For each major activity identified, do the following Clearly describe appropriate control measures.

Describe the general sequence during the construction process in which the measures will be implemented.

Describe the maintenance and inspection procedures that will be used for that specific BMP.

Include protocols, thresholds, and schedules for cleaning, repairing, or replacing damaged or failing

BMPs.

Identify staff responsible for maintaining BMPs.

(If your SWPPP is shared by multiple operators, indicate the operator responsible for each BMP.)

― Categorize each BMP under one of the following 10 areas of BMP activity as described below:

2.1 Minimize disturbed area and protect natural features and soil

2.2 Phase Construction Activity

2.3 Control Stormwater flowing onto and through the project

2.4 Stabilize Soils

2.5 Protect Slopes

2.6 Protect Storm Drain Inlets

2.7 Establish Perimeter Controls and Sediment Barriers

2.8 Retain Sediment On-Site and Control Dewatering Practices

2.9 Establish Stabilized Construction Exits

2.10 Any Additional BMPs

― Note the location of each BMP on your site map(s).

― For any structural BMPs, you should provide design specifications and details and refer to them. Attach them as appendices to the SWPPP or within the text of the SWPPP.

― For more information, see SWPPP Guide, Chapter 4.

― Consult your state’s design manual or one of those listed in Appendix D of the SWPPP Guide.

― For more information or ideas on BMPs, see EPA’s National Menu of BMPs http://www.epa.gov/npdes/stormwater/menuofbmps

2.1 Minimize Disturbed Area and Protect Natural Features and

Soil

See attached Erosion Control Narrative

2.2 Phase Construction Activity

• Phase I

• Phase II

― Describe the intended construction sequencing and timing of major activities, including any opportunities for phasing grading and stabilization activities to minimize the overall amount of disturbed soil that will be subject to potential erosion at one time. Also, describe opportunities for timing grading and stabilization so that all or a majority of the soil disturbance occurs during a time of year with less erosion potential (i.e., during the dry or less windy season). (For more information, see SWPPP Guide, Chapter 4, ESC Principle 2.) It might be useful to develop a separate, detailed site map for each phase of construction.

― Also, see EPA’s Construction Sequencing BMP Fact Sheet at http://www.epa.gov/npdes/stormwater/menuofbmps/construction/cons_seq)

Instructions:

― Describe the areas that will be disturbed with each phase of construction and the methods (e.g., signs, fences) that you will use to protect those areas that should not be disturbed. Describe natural features identified earlier and how each will be protected during construction activity. Also describe how topsoil will be preserved. Include these areas and associated BMPs on your site map(s) also. (For more information, see SWPPP Guide, Chapter 4, ESC Principle 1.)

― Also, see EPA’s Preserving Natural Vegetation BMP Fact Sheet at www.epa.gov/npdes/stormwater/menuofbmps/construction/perserve_veg http://www.epa.gov/npdes/stormwater/menuofbmps/construction/cons_seq http://www.epa.gov/npdes/stormwater/menuofbmps/construction/perserve_veg

2.3 Control Stormwater Flowing onto and through the Project

BMP Description: Not Applicable Installation Schedule:

Maintenance and Inspection:

Responsible Staff:

BMP Description:

Installation Schedule:

Repeat as needed

2.4 Stabilize Soils

BMP Description: Temporary Seeding Permanent Temporary

Installation Schedule: TBD Maintenance and Inspection:

TBD

Responsible Staff: TBD

― Describe controls (e.g., interim seeding with native vegetation, hydroseeding) to stabilize exposed soils where construction activities have temporarily or permanently ceased. Also describe measures to control dust generation. Avoid using impervious surfaces for stabilization whenever possible. (For more information, see SWPPP Guide, Chapter 4, ESC Principle 4.)

― Also, see EPA’s Seeding BMP Fact Sheet at www.epa.gov/npdes/stormwater/menuofbmps/construction/seeding

― Describe structural practices (e.g., diversions, berms, ditches, storage basins) including design specifications and details used to divert flows from exposed soils, retain or detain flows, or otherwise limit runoff and the discharge of pollutants from exposed areas of the site. (For more information, see SWPPP Guide, Chapter 4, ESC Principle 3.)

http://www.epa.gov/npdes/stormwater/menuofbmps/construction/seeding

BMP Description: Establish Turf

Installation Schedule: TBD Maintenance and Inspection:

TBD

Responsible Staff: TBD

BMP Description: Rolled Erosion Control Product, Type 2.A & Type 5.A

Permanent Temporary Installation Schedule: TBD Maintenance and Inspection:

TBD

Responsible Staff: TBD

BMP Description: Bonded Fiber Matrix

Permanent Temporary Installation Schedule: TBD Maintenance and Inspection:

2.5 Protect Slopes

BMP Description: Temporary Seeding

Installation Schedule: TBD Maintenance and Inspection:

TBD

Responsible Staff: TBD

Instructions:

― Describe controls (e.g., erosion control blankets, tackifiers) including design specifications and details that will be implemented to protect all slopes. (For more information, see SWPPP Guide, Chapter 4, ESC Principle 5.)

― Also, see EPA’s Geotextiles BMP Fact Sheet at www.epa.gov/npdes/stormwater/menuofbmps/construction/geotextiles http://www.epa.gov/npdes/stormwater/menuofbmps/construction/geotextiles

BMP Description: Establish Turf

Installation Schedule: TBD Maintenance and Inspection:

TBD

Responsible Staff: TBD

BMP Description: Rolled Erosion Control Product, Type 2.A & Type 5.A

Permanent Temporary Installation Schedule: TBD Maintenance and Inspection:

TBD

Responsible Staff: TBD

BMP Description: Bonded Fiber Matrix

Permanent Temporary Installation Schedule: TBD Maintenance and Inspection:

2.6 Protect Storm Drain Inlets

― Describe controls (e.g., inserts, rock-filled bags, or block and gravel) including design specifications and details that will be implemented to protect all inlets receiving stormwater from the project during the entire project. (For more information, see SWPPP Guide, Chapter 4, ESC Principle 6.)

― Also, see EPA’s Storm Drain Inlet Protection BMP Fact Sheet at www.epa.gov/npdes/stormwater/menuofbmps/construction/storm_drain http://www.epa.gov/npdes/stormwater/menuofbmps/construction/storm_drain

BMP Description: Storm Drain Inlet Protection (Type C) Installation Schedule: TBD Maintenance and Inspection:

TBD

Responsible Staff: TBD

BMP Description:

Installation Schedule:

2.7 Establish Perimeter Controls and Sediment Barriers

BMP Description: Silt Fence Installation Schedule: TBD Maintenance and Inspection:

TBD

Responsible Staff: TBD

BMP Description:

Installation Schedule:

― Describe structural practices (e.g., silt fences or fiber rolls) including design specifications and details to filter and trap sediment before it leaves the construction site. (For more information, see SWPPP Guide, Chapter 4, ESC Principle 7.)

― Also see, EPA’s Silt Fence BMP Fact Sheet at www.epa.gov/npdes/stormwater/menuofbmps/construction/silt_fences, or Fiber Rolls BMP Fact Sheet at www.epa.gov/npdes/stormwater/menuofbmps/construction/fiber_rolls http://www.epa.gov/npdes/stormwater/menuofbmps/construction/fiber_rolls

2.8 Retain Sediment On-Site

Installation Schedule:

2.9 Establish Stabilized Construction Exits

BMP Description: NA

― Describe location(s) of vehicle entrance(s) and exit(s), procedures to remove accumulated sediment off-site (e.g., vehicle tracking), and stabilization practices (e.g., stone pads or wash racks or both) to minimize off-site vehicle tracking of sediments and discharges to stormwater. (For more information, see SWPPP Guide, Chapter 4, ESC Principle 9.)

― Also, see EPA’s Construction Entrances BMP Fact Sheet at www.epa.gov/npdes/stormwater/menuofbmps/construction/cons_entrance

― Describe sediment control practices (e.g., sediment trap or sediment basin), including design specifications and details (volume, dimensions, outlet structure) that will be implemented at the construction site to retain sediments on-site. (For more information, see SWPPP Guide, Chapter 4, ESC Principle 8.)

― Also, see EPA’s Sediment Basin BMP Fact Sheet at www.epa.gov/npdes/stormwater/menuofbmps/construction/sediment_basins http://www.epa.gov/npdes/stormwater/menuofbmps/construction/cons_entrance http://www.epa.gov/npdes/stormwater/menuofbmps/construction/sediment_basins

Installation Schedule:

2.10 Additional BMPs

Installation Schedule:

― Describe additional BMPs that do not fit into the above categories.

SECTION 3: GOOD HOUSEKEEPING BMPS

The items contained in Section 3 will be the responsibility of the contractor.

3.1 Material Handling and Waste Management

― Describe measures (e.g., trash disposal, sanitary wastes, recycling, and proper material handling) to prevent the discharge of solid materials to receiving waters, except as authorized by a permit issued under section 404 of the CWA (For more information, see SWPPP Guide, Chapter 5, P2 Principle 1.)

― Also, see EPA’s General Construction Site Waste Management BMP Fact Sheet at www.epa.gov/npdes/stormwater/menuofbmps/construction/cons_wasteman

― Describe the key good housekeeping and pollution prevention (P2) BMPs that will be implemented to control pollutants in stormwater.

― Categorize each good housekeeping and pollution prevention (P2) BMP under one of the following seven categories:

3.1 Material Handling and Waste Management

3.2 Establish Proper Building Material Staging Areas

3.3 Designate Washout Areas

3.4 Establish Proper Equipment/Vehicle Fueling and Maintenance Practices

3.5 Allowable Non-Stormwater Discharges and Control Equipment/Vehicle Washing

3.6 Spill Prevention and Control Plan

3.7 Any Additional BMPs

― For more information, see SWPPP Guide, Chapter 5.

― Consult your state’s design manual or resources in Appendix D of the SWPPP Guide.

― For more information or ideas on BMPs, see EPA’s National Menu of BMPs http://www.epa.gov/npdes/stormwater/menuofbmps/construction/cons_wasteman

Installation Schedule:

3.2 Establish Proper Building Material Staging Areas

Installation Schedule:

3.3 Designate Washout Areas

― Describe location(s) and controls to eliminate the potential for discharges from washout areas for concrete mixers, paint, stucco, and so on. (For more information, see SWPPP Guide, Chapter 5, P2 Principle 3.)

― Also, see EPA’s Concrete Washout BMP Fact Sheet at www.epa.gov/npdes/stormwater/menuofbmps/construction/concrete_wash

― Describe construction materials expected to be stored on-site and procedures for storage of materials to minimize exposure of the materials to stormwater. (For more information, see SWPPP Guide, Chapter 5, P2 Principle 2.)

http://www.epa.gov/npdes/stormwater/menuofbmps/construction/concrete_wash

Installation Schedule:

Installation Schedule:

3.4 Establish Proper Equipment/Vehicle Fueling and

Maintenance Practices

Installation Schedule:

― Describe equipment/vehicle fueling and maintenance practices that will be implemented to control pollutants to stormwater (e.g., secondary containment, drip pans, and spill kits) (For more information, see SWPPP Guide, Chapter 5, P2 Principle 4.)

― Also, see EPA’s Vehicle Maintenance and Washing Areas BMP Fact Sheet at www.epa.gov/npdes/stormwater/menuofbmps/construction/vehicile_maintain http://www.epa.gov/npdes/stormwater/menuofbmps/construction/vehicile_maintain

3.5 Control Equipment/Vehicle Washing

Installation Schedule:

3.6 Spill Prevention and Control Plan

INSERT TEXT HERE or REFERENCE ATTACHMENT

― Describe the spill prevention and control plan to include ways to reduce the chance of spills, stop the source of spills, contain and clean up spills, dispose of materials contaminated by spills, and train personnel responsible for spill prevention and control. (For more information, see SWPPP Guide, Chapter 5, P2 Principle 6.)

― Also, see EPA’s Spill Prevention and Control Plan BMP Fact sheet at www.epa.gov/npdes/stormwater/menuofbmps/construction/spill_control

― Describe equipment/vehicle washing practices that will be implemented to control pollutants to stormwater.

(For more information, see SWPPP Guide, Chapter 5, P2 Principle 5.)

― Also, see EPA’s Vehicle Maintenance and Washing Areas BMP Fact Sheet at www.epa.gov/npdes/stormwater/menuofbmps/construction/vehicile_maintain http://www.epa.gov/npdes/stormwater/menuofbmps/construction/spill_control http://www.epa.gov/npdes/stormwater/menuofbmps/construction/vehicile_maintain

3.7 Any Additional BMPs

Installation Schedule:

― Describe any additional BMPs that do not fit into the above categories. Indicate the problem they are intended to address.

3.8 Allowable Non-Stormwater Discharge Management

List allowable non-stormwater discharges and the measures used to eliminate or reduce them and to prevent them from becoming contaminated:

― Identify all allowable sources of non-stormwater discharges that are not identified. The allowable non-stormwater discharges identified might include the following (see your permit for an exact list):

Waters used to wash vehicles where detergents are not used Water used to control dust Potable water including uncontaminated water line flushings Routine external building wash down that does not use detergents Pavement wash waters where spills or leaks of toxic or hazardous materials have not occurred

(unless all spilled material has been removed) and where detergents are not used Uncontaminated air conditioning or compressor condensate Uncontaminated ground water or spring water Foundation or footing drains where flows are not contaminated with process materials such as solvents Uncontaminated excavation dewatering Landscape irrigation

― Identify measures used to eliminate or reduce these discharges and the BMPs used to prevent them from becoming contaminated.

SECTION 4: SELECTING POST-CONSTRUCTION BMPs

BMP Description: NA

Installation Schedule:

― Describe all post-construction stormwater management measures that will be installed during the construction process to control pollutants in stormwater discharges after construction operations have been completed. Examples of post-construction BMPs include the following:

Biofilters Detention/retention devices Earth dikes, drainage swales, and lined ditches Infiltration basins Porous pavement Other proprietary permanent structural BMPs Outlet protection/velocity dissipation devices Slope protection Vegetated strips and/or swales

― Identify any applicable federal, state, local, or tribal requirements for design or installation.

― Describe how low-impact designs or smart growth considerations have been incorporated into the design.

― For any structural BMPs, you should have design specifications and details and refer to them. Attach them as appendices to the SWPPP or within the text of the SWPPP.

― For more information on this topic, see your state’s stormwater manual.

― You might also want to consult one of the references listed in Appendix D of the SWPPP Guide.

― Visit the post-construction section of EPA’s Menu of BMPs at: www.epa.gov/npes/menuofbmps http://www.epa.gov/npes/menuofbmps

SECTION 5: INSPECTIONS

5.1 Inspections

1. Inspection Personnel: Identify the person(s) who will be responsible for conducting inspections and describe their qualifications: TBD

2. Inspection Schedule and Procedures:

Describe the inspection schedules and procedures you have developed for your site (include frequency of inspections for each BMP or group of BMPs, indicate when you will inspect, e.g., before/during/and after rain events, spot inspections): See Attached Erosion Control Narrative

Describe the general procedures for correcting problems when they are identified. Include responsible staff and time frames for making corrections: TBD

Attach a copy of the inspection report you will use for your site.

REFERENCE ATTACHMENT

Instructions:

― Identify the individual(s) responsible for conducting inspections and describe their qualifications.

Reference or attach the inspection form that will be used.

― Describe the frequency that inspections will occur at your site including any correlations to storm frequency and intensity.

― Note that inspection details for particular BMPs should be included in Sections 2 and 3.

― You should also document the repairs and maintenance that you undertake as a result of your inspections.

These actions can be documented in the corrective action log described in Part 5.3 below.

― For more on this topic, see SWPPP Guide, Chapters 6 and 8.

― Also, see suggested inspection form in Appendix B of the SWPPP Guide.

5.2 Delegation of Authority

Duly Authorized Representative(s) or Position(s):

Insert Company or Organization Name: TBD Insert Name:

Insert Position:

Insert Address:

Insert City, State, Zip Code:

Insert Telephone Number:

Insert Fax/Email:

Attach a copy of the signed delegation of authority form in Appendix K.

5.3 Corrective Action Log

Corrective Action Log:

INSERT LOG HERE or REFERENCE ATTACHMENT

Instructions:

― Create here, or as an attachment, a corrective action log. This log should describe repair, replacement, and maintenance of BMPs undertaken as a result of the inspections and maintenance procedures described above. Actions related to the findings of inspections should reference the specific inspection report.

― This log should describe actions taken, date completed, and note the person that completed the work.

― Identify the individual(s) or specifically describe the position where the construction site operator has delegated authority for the purposes of signing inspection reports, certifications, or other information.

― Attach the delegation of authority form that will be used.

― For more on this topic, see SWPPP Guide, Chapter 7.

SECTION 6: RECORDKEEPING AND TRAINING

6.1 Recordkeeping

Records will be retained for a minimum period of at least 3 years after the permit is terminated.

Date(s) when major grading activities occur:

INSERT LOG HERE or REFERENCE ATTACHMENT Date(s) when construction activities temporarily or permanently cease on a portion of the site:

INSERT LOG HERE or REFERENCE ATTACHMENT Date(s) when an area is either temporarily or permanently stabilized:

6.2 Log of Changes to the SWPPP

Log of changes and updates to the SWPPP

Instructions:

― Create a log here, or as an attachment, of changes and updates to the SWPPP. You should include additions of new BMPs, replacement of failed BMPs, significant changes in the activities or their timing on the project, changes in personnel, changes in inspection and maintenance procedures, updates to site maps, and so on.

― The following is a list of records you should keep at your project site available for inspectors to review:

― Dates of grading, construction activity, and stabilization (which is covered in Sections 2 and 3) ― A copy of the construction general permit (attach) ― The signed and certified NOI form or permit application form (attach) ― A copy of the letter from EPA or/the state notifying you of their receipt of your complete NOI/application

(attach) ― Inspection reports (attach) ― Records relating to endangered species and historic preservation (attach) ― Check your permit for additional details ― For more on this subject, see SWPPP Guide, Chapter 6.C.

6.3 Training

Individual(s) Responsible for Training:

INSERT TEXT or TABLE HERE Describe Training Conducted:

• General stormwater and BMP awareness training for staff and subcontractors:

• Detailed training for staff and subcontractors with specific stormwater responsibilities:

― Training your staff and subcontractors is an effective BMP. As with the other steps you take to prevent stormwater problems at your site, you should document the training that you conduct for your staff, for those with specific stormwater responsibilities (e.g. installing, inspecting, and maintaining BMPs), and for subcontractors.

― Include dates, number of attendees, subjects covered, and length of training.

― For more on this subject, see SWPPP Guide, Chapter 8.

SECTION 7: FINAL STABILIZATION

― Describe procedures for final stabilization. If you complete major construction activities on part of your site, you can document your final stabilization efforts for that portion of the site. Many permits will allow you to then discontinue inspection activities in these areas (be sure to check your permit for exact requirements). You can amend or add to this section as areas of your project are finally stabilized.

― Update your site plans to indicate areas that have achieved final stabilization.

― Note that dates for areas that have achieved final stabilization should be included in Section 6, Part 6.1 of this SWPPP.

― For more on this topic, see SWPPP Guide, Chapter 9.

SECTION 8: CERTIFICATION AND NOTIFICATION

I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gathered and evaluated the information submitted. Based on my inquiry of the person or persons who manage the system, or those persons directly responsible for gathering the information, the information submitted is, to the best of my knowledge and belief, true, accurate, and complete. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment for knowing violations.

Name: Title:

Signature: Date:

Repeat as needed for multiple construction operators at the site

― The SWPPP should be signed and certified by the construction operator(s). Attach a copy of the NOI and permit authorization letter received from EPA or the state in Appendix D.

SWPPP APPENDICES

Attach the following documentation to the SWPPP:

Appendix A – General Location Map

Appendix B – Site Maps

Appendix C – Construction General Permit

Appendix D – NOI and Acknowledgement Letter from EPA/State

Appendix E – Inspection Reports

Appendix F – Corrective Action Log (or in Part 5.3)

Appendix G – SWPPP Amendment Log (or in Part 6.2)

Appendix H – Subcontractor Certifications/Agreements

Appendix I – Grading and Stabilization Activities Log (or in Part 6.1)

Appendix J – Training Log

Appendix K – Delegation of Authority

Appendix L – Additional Information (i.e., Endangered Species and Historic Preservation Documentation)

EPA SWPPP Template, Version 1.1, September 17, 2007

Appendix F – Sample Corrective Action Log

Project Name:

SWPPP Contact:

Inspection Date

Inspector Name(s)

Description of BMP Deficiency Corrective Action Needed (including planned date/responsible person)

Date Action Taken/Responsible person

Appendix G – Sample SWPPP Amendment Log

SWPPP Contact:

Amendment No. Description of the Amendment Date of Amendment Amendment Prepared by

[Name(s) and Title]

Appendix H – Sample Subcontractor Certifications/Agreements

SUBCONTRACTOR CERTIFICATION

STORMWATER POLLUTION PREVENTION PLAN

Project Number:

Project Title:

Operator(s):

As a subcontractor, you are required to comply with the Stormwater Pollution Prevention Plan (SWPPP) for any work that you perform on-site. Any person or group who violates any condition of the SWPPP may be subject to substantial penalties or loss of contract. You are encouraged to advise each of your employees working on this project of the requirements of the SWPPP. A copy of the SWPPP is available for your review at the office trailer.

Each subcontractor engaged in activities at the construction site that could impact stormwater must be identified and sign the following certification statement:

I certify under the penalty of law that I have read and understand the terms and conditions of the SWPPP for the above designated project and agree to follow the BMPs and practices described in the SWPPP.

This certification is hereby signed in reference to the above named project:

Company:

Address:

Telephone Number:

Type of construction service to be provided:

Signature:

Title:

Date:

Appendix I – Sample Grading and Stabilization Activities Log

SWPPP Contact:

Date Grading Activity Initiated

Description of Grading Activity Date Grading Activity Ceased (Indicate Temporary or Permanent)

Date When Stabilization Measures are Initiated

Description of Stabilization Measure and Location

Appendix J – Sample SWPPP Training Log

Stormwater Pollution Prevention Training Log

Project Location:

Instructor’s Name(s):

Instructor’s Title(s):

Course Location: Date:

Course Length (hours):

Stormwater Training Topic: (check as appropriate)

Erosion Control BMPs Emergency Procedures

Sediment Control BMPs Good Housekeeping BMPs

Non-Stormwater BMPs

Specific Training Objective:

Attendee Roster: (attach additional pages as necessary)

No. Name of Attendee Company

Appendix K – Sample Delegation of Authority Form

Delegation of Authority

I, _______________________ (name), hereby designate the person or specifically described position below to be a duly authorized representative for the purpose of overseeing compliance with environmental requirements, including the Construction General Permit, at the ____________________________________ construction site. The designee is authorized to sign any reports, stormwater pollution prevention plans and all other documents required by the permit.

________________________________________ (name of person or position) ________________________________________ (company) ________________________________________ (address) ________________________________________ (city, state, zip) ________________________________________ (phone)

By signing this authorization, I confirm that I meet the requirements to make such a designation as set forth in ____________________________________ (Reference State Permit), and that the designee above meets the definition of a “duly authorized representative” as set forth in ____________________________________ (Reference State Permit).

I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gathered and evaluated the information submitted. Based on my inquiry of the person or persons who manage the system, or those persons directly responsible for gathering the information, the information submitted is, to the best of my knowledge and belief, true, accurate, and complete. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment for knowing violations.

Name:

Company:

Title:

Signature:

Date:

United States Department of Agriculture

A product of the National Cooperative Soil Survey, a joint effort of the United States Department of Agriculture and other Federal agencies, State agencies including the Agricultural Experiment Stations, and local participants

Custom Soil Resource Report for Great Smoky Mountains National Park, Tennessee and North Carolina, and Sevier County Area, Tennessee

Natural Resources Conservation Service

September 16, 2013

Preface Soil surveys contain information that affects land use planning in survey areas. They highlight soil limitations that affect various land uses and provide information about the properties of the soils in the survey areas. Soil surveys are designed for many different users, including farmers, ranchers, foresters, agronomists, urban planners, community officials, engineers, developers, builders, and home buyers. Also, conservationists, teachers, students, and specialists in recreation, waste disposal, and pollution control can use the surveys to help them understand, protect, or enhance the environment.

Various land use regulations of Federal, State, and local governments may impose special restrictions on land use or land treatment. Soil surveys identify soil properties that are used in making various land use or land treatment decisions. The information is intended to help the land users identify and reduce the effects of soil limitations on various land uses. The landowner or user is responsible for identifying and complying with existing laws and regulations.

Although soil survey information can be used for general farm, local, and wider area planning, onsite investigation is needed to supplement this information in some cases.

Examples include soil quality assessments (http://soils.usda.gov/sqi/) and certain conservation and engineering applications. For more detailed information, contact your local USDA Service Center (http://offices.sc.egov.usda.gov/locator/app?

agency=nrcs) or your NRCS State Soil Scientist (http://soils.usda.gov/contact/ state_offices/).

Great differences in soil properties can occur within short distances. Some soils are seasonally wet or subject to flooding. Some are too unstable to be used as a foundation for buildings or roads. Clayey or wet soils are poorly suited to use as septic tank absorption fields. A high water table makes a soil poorly suited to basements or underground installations.

The National Cooperative Soil Survey is a joint effort of the United States Department of Agriculture and other Federal agencies, State agencies including the Agricultural Experiment Stations, and local agencies. The Natural Resources Conservation Service (NRCS) has leadership for the Federal part of the National Cooperative Soil Survey.

Information about soils is updated periodically. Updated information is available through the NRCS Soil Data Mart Web site or the NRCS Web Soil Survey. The Soil Data Mart is the data storage site for the official soil survey information.

The U.S. Department of Agriculture (USDA) prohibits discrimination in all its programs and activities on the basis of race, color, national origin, age, disability, and where applicable, sex, marital status, familial status, parental status, religion, sexual orientation, genetic information, political beliefs, reprisal, or because all or a part of an individual's income is derived from any public assistance program. (Not all prohibited bases apply to all programs.) Persons with disabilities who require alternative means http://soils.usda.gov/sqi/ http://offices.sc.egov.usda.gov/locator/app?agency=nrcs http://offices.sc.egov.usda.gov/locator/app?agency=nrcs http://soils.usda.gov/contact/state_offices/ http://soils.usda.gov/contact/state_offices/ for communication of program information (Braille, large print, audiotape, etc.) should contact USDA's TARGET Center at (202) 720-2600 (voice and TDD). To file a complaint of discrimination, write to USDA, Director, Office of Civil Rights, 1400 Independence Avenue, S.W., Washington, D.C. 20250-9410 or call (800) 795-3272 (voice) or (202) 720-6382 (TDD). USDA is an equal opportunity provider and employer.

Contents Preface How Soil Surveys Are Made Soil Map

Soil Map Legend Map Unit Legend Map Unit Descriptions

Great Smoky Mountains National Park, Tennessee and North Carolina CcF—Cataska-Sylco complex, 30 to 95 percent slopes, very rocky Dg—Dellwood-Smokemont complex, 0 to 5 percent slopes, frequently flooded DtF—Ditney-Unicoi complex, 30 to 95 percent slopes, very rocky JbD—Junaluska-Brasstown complex, 15 to 30 percent slopes, stony JbE—Junaluska-Brasstown complex, 30 to 50 percent slopes, stony LoC—Lonon silty clay loam, 8 to 15 percent slopes NtC—Northcove-Maymead-Nowhere complex, 8 to 15 percent slopes, very stony RxF—Rubble land-Spivey complex, 50 to 95 percent slopes, extremely bouldery RZ—Rubble land, 30 to 95 percent slopes SnF—Snowbird loam, 30 to 95 percent slopes, stony SoF—Soco-Stecoah complex, 30 to 95 percent slopes, stony SsC—Spivey-Santeetlah-Nowhere complex, 8 to 15 percent slopes, very stony SsD—Spivey-Santeetlah complex, 15 to 30 percent slopes, very stony SsE—Spivey-Santeetlah complex, 30 to 50 percent slopes, very stony

Sevier County Area, Tennessee CcE—Cataska-Sylco complex, 25 to 80 percent slopes Ur—Urban land W—Water

References

How Soil Surveys Are Made Soil surveys are made to provide information about the soils and miscellaneous areas in a specific area. They include a description of the soils and miscellaneous areas and their location on the landscape and tables that show soil properties and limitations affecting various uses. Soil scientists observed the steepness, length, and shape of the slopes; the general pattern of drainage; the kinds of crops and native plants; and the kinds of bedrock. They observed and described many soil profiles.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .