This is an Invitation to Bid (ITB) document for construction services issued by the City of Waterbury Department of Education in Connecticut for elevator additions at two elementary schools. The project involves constructing new elevator shafts, vestibules, and interior elevator lobbies with associated mechanical, electrical, plumbing, and life safety systems at Driggs Elementary School (77 Woodlawn Terrace) and Woodrow Wilson Elementary School (235 Birch Street). Sealed bids must be received by March 25, 2026 at 11:30 a.m. at the City Hall Building, 235 Grand Street, Waterbury. A mandatory pre-bid conference will be held on March 9, 2026 at 9:00 a.m., starting at Driggs Elementary and continuing to Woodrow Wilson Elementary; attendance is mandatory for all bidders. The project includes two separate bid items (one for each school), and the contractor must complete all demolition work and site restoration by August 20, 2026, achieve substantial completion by December 15, 2026, and final completion by February 10, 2027. Questions regarding the bid documents must be submitted by March 12, 2026 at 2:00 p.m., with clarifications issued by March 18, 2026 at 2:00 p.m.

Bids must include a bid security of ten percent of the total bid price in the form of a certified check or bid bond for projects of $50,000 or greater. The selected contractor must furnish a one hundred percent performance bond and potentially a one hundred percent payment bond acceptable to the City. This project is subject to state set-aside requirements, specifically Connecticut General Statutes Section 4a-60g, which requires a minimum of twenty-five percent of the state-funded contract value be awarded to DAS-certified small businesses and subcontractors, with an additional 6.25 percent set-aside for DAS-certified minority-, women-, and/or disabled-owned businesses. The contractor must comply with prevailing wage requirements per Connecticut General Statutes Section 31-53 and the City of Waterbury Good Jobs Ordinance (Chapter 34), which requires that thirty percent of total worker hours be performed by Waterbury residents and establishes goals for apprentice employment, economically disadvantaged workers, minorities, and women. The project is funded through state and local sources and is subject to all applicable federal, state, and local compliance requirements including OSHA, environmental protection, and ADA accessibility standards.

View the file

Other files

File Type Posted
Wilson Elevator Bid Documents.pdf PDF
ITB 8703- Wtby_Mar_2_26_solicitation_doc.pdf PDF
RFP 8703 Addendum 2.pdf PDF
RFP 8703 Addendum 2.pdf.crdownload CRDOWNLOAD file
Driggs Elevator Bid Documents.pdf PDF
ITB 8703- Wtby_Mar_30_26_solicitation_doc.pdf PDF
Driggs Elevator Bid Documents.pdf.crdownload CRDOWNLOAD file
RFP 8703 Addendum 1.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CITY OF WATERBURY

DRIGGS ELEMENTARY SCHOOL & WOODROW WILSON ELEMENTARY SCHOOL

ELEVATOR ADDITIONS

Driggs Elementary: 77 Woodlawn Terrace

Woodrow Wilson Elementary: 235 Birch Street

WATERBURY, CONNECTICUT

JANUARY 15, 2026

ISSUE FOR BID: FEBRUARY 27, 2026

CONTRACT AND SPECIFICATIONS

City Project No.: 8703

State Project No.: Driggs Elementary: 151-0315 LUE; Wilson Elementary: 151-0316 LUE

Mayor: Honorable Paul K. Pernerewski, Jr.

Superintendent of Schools: Dr. Darren Schwartz

Chief Opera9ng Officer: Nicholas J. Albini

Architect: Friar Architecture, Inc.

This page intentionally left blank

00 01 10 TABLE OF CONTENTS 1/15/2026

2022-049A

Driggs & Wilson Elementary

- Elevator Additions

Waterbury, CT

00 01 10 - 1

SECTION 00 01 10

TABLE OF CONTENTS

PROCUREMENT AND CONTRACTING REQUIREMENTS

DIVISION 00 -- PROCUREMENT AND CONTRACTING REQUIREMENTS

Invitation to Bid

00100 Instructions to Bidders

00200 Addendum Acknowledgment Form

00300 Bid Form

00400 Technical Specifications

Attachment A

Annual Statement of Financial Interest

Debarment Certification

City of Waterbury Disclosure of Outstanding Obligations

Attachment B

Sample Contract

General Conditions

Special Conditions

Sample Corporate Resolution

Sample LLC Resolution

Prevailing Wage Rates (place holder)

Good Jobs Ordinance

HBMI Report – Driggs Elementary School

HBMI Report – Woodrow Wilson Elementary School

Geotechnical Engineering Recommendations – Driggs Elementary School

Geotechnical Engineering Recommendations – Woodrow Wilson Elementary School

SPECIFICATIONS

DIVISION 01 -- GENERAL REQUIREMENTS

01 10 00 – Summary

01 14 01 – Preservation and Restoration

01 25 00 - Substitution Procedures

01 31 00 - Payment Procedures

01 31 00 - Project Management and Coordination

01 32 00 - Construction Progress Documentation

01 32 33 - Photographic Documentation

01 33 00 - Submittal Procedures

01 40 00 - Quality Requirements

01 42 00 - References

01 50 00 - Temporary Facilities and Controls

- Elevator Additions

Waterbury, CT

00 01 10 - 2

Project Sign Template

01 57 13 - Temporary Erosion and Sediment Control

01 57 14 - Temporary Dust Control

01 60 00 - Product Requirements

01 73 00 - Execution

01 74 19 - Construction Waste Management and Disposal

01 77 00 - Closeout Procedures

01 78 23 - Operation and Maintenance Data

DIVISION 02 -- EXISTING CONDITIONS

02 41 00 - Demolition

02 41 23 - Site Demolition

02 82 13.31 – Non-Disturbrance Asbestos Removal and Disposal

02 83 33.13 – Lead Paint (Driggs)

02 83 33.13 – Lead Paint (Wilson)

02 84 11 – Polychlorinated Biphenyl (PCB) Abatement (Driggs)

02 84 11 – Polychlorinated Biphenyl (PCB) Abatement (Wilson)

Abatement Plan – Driggs

Abatement Plan – Wilson

DIVISION 03 -- CONCRETE

03 30 00 - Cast-in-Place Concrete

03 32 00 - Site Cast-in-Place Concrete

DIVISION 04 -- MASONRY

04 20 00 - Unit Masonry

DIVISION 05 -- METALS

05 12 00 - Structural Steel Framing

05 50 00 - Metal Fabrications

DIVISION 06 -- WOOD, PLASTICS, AND COMPOSITES

06 10 53 - Miscellaneous Rough Carpentry

06 16 00 - Sheathing – USG

DIVISION 07 -- THERMAL AND MOISTURE PROTECTION

07 13 00 - Sheet Waterproofing

07 21 00 - Thermal Insulation

07 27 00 - Air Barriers

07 42 13 - Metal Wall Panels

- Elevator Additions

Waterbury, CT

00 01 10 - 3

07 53 23 - Ethylene-Propylene-Diene-Monomer Roofing (EPDM) - Elevate

07 62 00 - Sheet Metal Flashing and Trim

07 71 23 - Manufactured Gutters and Downspouts

07 84 00 - Firestopping

07 92 00 - Joint Sealants

07 95 13 - Expansion Joint Cover Assemblies

DIVISION 08 -- OPENINGS

08 06 71 – Driggs Hardware Schedule

08 06 71 – Wilson Hardware Schedule

08 71 00 – Driggs Door Hardware

08 71 00 – Wilson Door Hardware

08 11 13 - Hollow Metal Doors and Frames

08 14 16 - Flush Wood Doors

08 43 13 - Aluminum-Framed Storefronts

08 80 00 – Glazing

DIVISION 09 -- FINISHES

09 21 16 - Gypsum Board Assemblies

09 22 16 - Non-Structural Metal Framing

09 51 00 - Acoustical Ceilings

09 65 00 - Resilient Flooring

09 91 23 - Interior Painting

DIVISION 10 -- SPECIALTIES

10 14 23 - Panel Signage

10 14 26 - Post and Panel Signage

10 26 00 - Wall and Door Protection

DIVISION 11 – EQUIPMENT (NOT USED)

DIVISION 12 – FURNISHINGS (NOT USED)

DIVISION 13 -- SPECIAL CONSTRUCTION (NOT USED)

DIVISION 14 -- CONVEYING EQUIPMENT

14 21 00 - Electric Traction Elevators

DIVISION 21 -- FIRE SUPPRESSION (NOT USED)

DIVISION 22 -- PLUMBING

22 04 00 - General Conditions for Plumbing Trades

22 04 10 - General Conditions for Plumbing Demolition

- Elevator Additions

Waterbury, CT

00 01 10 - 4

22 05 17 - Sleeves and Sleeve Seals for Plumbing Piping

22 05 23 - General-Duty Valves for Plumbing Piping

22 05 29 - Hangers and Supports for Plumbing Piping and Equipment

22 05 53 - Identification for Plumbing Piping and Equipment

22 07 00 - Plumbing Insulation

22 10 05 - Plumbing Piping

22 40 00 - Plumbing Fixtures and Specialties

DIVISION 23 -- HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC)

23 04 00 - General Conditions for Mechanical Trades

23 05 29 - Hangers and Supports for HVAC Piping, Ductwork and Equipment

23 05 53 - Identification for HVAC Piping and Equipment

23 05 93 - Testing, Adjusting, and Balancing for HVAC

23 07 00 - HVAC Insulation

23 31 00 - HVAC Ducts and Casings

23 33 00 - Air Duct Accessories

DIVISION 25 -- INTEGRATED AUTOMATION

DIVISION 26 -- ELECTRICAL

26 04 00 - General Conditions for Electrical Trades

26 05 01 - Electrical Demolition

26 05 03 - Equipment Wiring Connections

26 05 19 - Electrical Power Conductors and Cables

26 05 26 - Grounding and Bonding for Electrical Systems

26 05 29 - Hangers and Supports for Electrical Systems

26 05 33 - Raceway and Boxes for Electrical Systems

26 05 53 - Identification for Electrical Systems

26 09 23 - Lighting Control Devices

26 24 16 - Panelboards

26 27 26 - Wiring Devices

26 28 13 - Fuses

26 28 19 - Enclosed Switches

26 51 00 – Lighting

DIVISION 27 -- COMMUNICATIONS

27 05 29 – Hangers and Supports for Communications Systems

27 05 33 – Raceway and Boxes for Communication Systems

27 51 29 – Emergency 2-Way Communication System

- Elevator Additions

Waterbury, CT

00 01 10 - 5

DIVISION 28 -- ELECTRONIC SAFETY AND SECURITY

28 05 29 - Hangers and Supports for Electronic Safety and Security

28 05 33 - Raceway and Boxes for Electronic Safety and Security

28 31 00 - Fire Detection and Alarm

DIVISION 31 -- EARTHWORK

31 23 10 - Earthwork

DIVISION 32 -- EXTERIOR IMPROVEMENTS

32 12 16 - Bituminous Concrete Pavement

32 16 23 - Curbing

32 17 23 - Pavement Markings

32 31 13 – Chain Link Fences and Gates

DIVISION 33 -- UTILITIES

33 40 00 – Storm Drainage System

DIVISION 34 -- TRANSPORTATION

DIVISION 40 -- PROCESS INTEGRATION

DIVISION 46 -- WATER AND WASTEWATER EQUIPMENT

END OF SECTION

THE CITY OF WATERBURY

DEPARTMENT OF EDUCATION

INVITATION TO BID NO. 8703

ELEVATOR PROJECTS

AT

THE DRIGGS ELEMENTARY AND WOODROW WILSON ELEMENTARY SCHOOLS

Pursuant to this Invitation to Bid (“ITB”), sealed bids (the “Bids”) for The Driggs and Woodrow Wilson Elementary Schools Elevator Projects will be received by the City of Waterbury (the “City”) at the office of the Director of Purchasing, Room 103, City Hall Building, 235 Grand Street, Waterbury, CT 06702 until 11:30 a.m. on March 25, 2026 and at that time and place will be publicly opened and read aloud. No bids will be received after 11:30 a.m. on the day the bids are to be opened.

Waterbury Public Schools invites qualified third parties (each a “Bidder” or “Contractor” and, collectively “Bidders” or “Contractors”) to submit Bids for the construction of new elevator additions at Driggs Elementary School and Woodrow Wilson Elementary School. The projects have been designed by Friar Architects and are intended to provide ADA-compliant vertical circulation and improved accessibility for students, staff, and visitors. The selected Contractor(s) will be responsible for furnishing all labor, materials, equipment, and supervision necessary to complete the work in accordance with the construction documents prepared by Friar Architecture, Inc.

Bids must be enclosed in an opaque sealed envelope and plainly marked with the name of the Project Title The Driggs and Woodrow Wilson Elementary Schools Elevator Projects and shall contain the name and address of the Bidder on the envelope.

Each Bid of $50,0000.00 or more shall be submitted in accordance with the Instructions to Bidders and be accompanied by a Bid Security (a Certified Check or Bid Bond) in the amount of ten (10) percent of the Total Bid Price. The Bidder to whom a contract is offered with a total cost greater than $50,000 must furnish to the City a one hundred (100) percent performance bond with a surety, and in a form, acceptable to the City. In the City's sole discretion, it may also require a one hundred (100) percent payment bond and/or other additional security with a surety, and in a form, acceptable to the City.

Complete instructions for filing Bids are included in the Instructions to Bidders.

After review of the factors set forth in the Instructions to Bidders, the City reserves the right to reject any and all Bids, to make an award, or to decline to make an award.

A mandatory pre-bid conference will be held at 9:00 a.m. on March 9, 2026 with the conference commencing at The Driggs Elementary School (77 Woodlawn Terrace) and continuing on to The Woodrow Wilson Elementary School (235 Birch Street).

Attendance and on-time sign-in at the pre-bid conference at each location by a representative of each Bidder is mandatory.

This contract is subject to state set-aside and contract compliance requirements.

Contact the Office of the Director of Purchasing, at 203-574-6748 for further information.

ELEVATOR PROJECTS

AT

THE DRIGGS ELEMENTARY AND WOODROW WILSON ELEMENTARY SCHOOLS

SECTION 00100

INSTRUCTIONS TO BIDDERS

ARTICLE 1. QUALIFICATIONS OF BIDDERS.

1.1 In evaluating Bids, the CITY will consider the qualifications of only those Bidders whose

Bids, among other factors, follow the requirements set forth elsewhere in the Bid Documents.

1.2 The CITY reserves the right to reject any Bid based upon Bidder’s prior history with the CITY or with any other party that demonstrates, without limitation, failure to perform or unsatisfactory performance in accordance with the terms of one or more contracts or purchase orders or significant failure(s) to meet contractual obligations.

ARTICLE 2. COPIES OF BID DOCUMENTS.

2.1 Complete sets of Bid Documents shall be used in preparing Bids; neither the CITY nor its representative assume any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bid Documents.

2.2 The CITY and its representative in making copies of Bid Documents available do so only for the purpose of obtaining Bids on the Work and do not confer a license or grant for any other use.

ARTICLE 3. EXAMINATION OF BID DOCUMENTS AND SITE.

3.1 Before submitting a Bid, each Bidder must (a) examine the Bid Documents thoroughly, (b) familiarize itself with all Federal, State and local laws, ordinances, rules and regulations that may in any manner affect cost, progress or performance of the Work; and (c) study and carefully correlate the Bidder's observations and findings with the requirements of the Bid Documents.

3.2 The submission of a Bid will constitute an incontrovertible representation by the Bidder that it has complied with every requirement of this Article 3 and that the Bid Documents are sufficient in scope and detail to indicate and convey all terms and conditions necessary for the Bidder's proposed performance of the Work.

ARTICLE 4. INTERPRETATIONS.

4.1 All questions about the meaning or intent of the Bid Documents must be submitted to the

CITY’s ProcureWare website by March 12, 2026, 2:00PM.

4.2 The CITY will issue written clarifications or interpretations by Addenda online at the CITY’s

ProcureWare website not later than March 18, 2026, 2:00PM. Only information issued by such CITY written Addenda will be binding. Oral and other clarifications or interpretations will not be binding and will be without legal effect.

4.3 Each Bidder shall be responsible for determining that it has received all Addenda issued and shall acknowledge receipt of all Addenda on the Addendum Acknowledgment Form and the Bidder shall list therein all written Addenda number(s) issued by the CITY.

ARTICLE 5. PRE-BID CONFERENCE.

5.1 A mandatory pre-bid conference will be held at the time and place indicated in the

Invitation to Bid to discuss the requirements of the Bid Documents. Attendance at the pre-bid conference is mandatory by a representative of each prospective Bidder.

ARTICLE 6. BID FORM.

6.1 Each Bid shall be submitted on the Bid Form included in Section 00300 of the Bid

Documents. The Bid Form shall be removed from the Bid Documents, filled in as required below, and submitted to the CITY. Bidders must fill in all blank spaces on the Bid Form for Bid prices, including without limitation unit prices, extended prices and total price or the Bid will not be considered and shall be void.

6.2 Bid Forms shall be completed in ink. The Bid price of each item on the form shall be stated in figures. If unit prices are required on the Bid Form, discrepancies between unit prices and their respective total amounts will be resolved in favor of the unit prices.

Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum.

6.3 All names shall be typed or printed below the signature.

6.4 The name and address to which communications regarding the Bid are to be directed shall be shown.

6.5 One (1) original, one (1) paper copy, as well as a copy of the original Bid in pdf format on a

CD or flash drive. Each Bid shall be submitted in a sealed opaque envelope bearing on the outside the name of Bidder, its address, and the Project Title for which the Bid is submitted. (If forwarded by mail, Bid and sealed envelope marked as described above shall be enclosed in another envelope with the notation "BID ENCLOSED" on the face and addressed as indicated in the Invitation to Bid.)

ARTICLE 7. RECEIPT OF BIDS.

7.1 Sealed Bids for the Work of this Project will be received at the time and place indicated in the Invitation to Bid.

7.2 The CITY, in its sole discretion, may refuse to consider any Bid not prepared and/or not submitted in accordance with the Bid Documents. Bids will not be received or accepted by the CITY from prospective Bidders who did not attend a mandatory pre-bid conference.

7.3 Bidders are cautioned that it is the responsibility of each individual Bidder to assure that its

Bid is in the possession of the Director of Purchasing, or an alternate designated by him, prior to the stated time and at the place of the Bid Opening. The CITY is not responsible for Bids delayed by mail and/or delivery services of any nature.

ARTICLE 8. MODIFICATION AND WITHDRAWAL OF BIDS.

8.1 Bids may be modified only by an appropriate document duly executed in the same manner that a Bid must be executed and delivered to the place where Bids are to be submitted prior to that time scheduled by the CITY for the opening of Bids.

8.2 A Bid may be withdrawn by the Bidder prior to the scheduled time (or authorized postponement thereof by the CITY) for the opening of Bids.

8.3 Any Bid received after the time and date specified as the time for the CITY's opening of Bids shall not be considered. Once bids are opened by the CITY, no Bidder may withdraw its Bid for a period of ninety (90) days, excluding Saturdays, Sundays and legal holidays, after the actual date of the CITY's opening of the Bids.

ARTICLE 9. LOWEST RESPONSIBLE BIDDER.

9.1 A contract may be awarded to the Lowest Responsible Bidder. The term "Lowest

Responsible Bidder" as used herein shall mean the Bidder whose Total Bid Price is the lowest of those Bidders possessing, without limitation, the skill, ability, expertise, experience, qualifications and integrity necessary for the faithful performance of the Work, as determined by the CITY.

9.2 After review of these and other factors, including without limitation, responsiveness, qualifications and price, the CITY reserves the right to reject any and all Bids, to decline to make an award, to waive any and all informalities if it is in the CITY's best interest to do

so. The CITY reserves the right to disregard all nonconforming, nonresponsive, conditional Bids, and Bids taking exception(s) to the Bid Documents.

9.3 A Bid which includes, for any Item(s), a Bid Price that is abnormally low or high may be rejected in its entirety.

9.4 The CITY reserves the right to reject the Bid of any Bidder that the CITY considers not to possess the qualities set forth in Article 1 herein.

ARTICLE 10. PURCHASE ORDER ISSUANCE/AWARD AND EXECUTION OF CONTRACT.

10.1 If a contract is to be awarded, the CITY will give the Lowest Responsible Bidder a Notice of Award within ninety (90) calendar days, excluding Saturdays, Sundays, and legal holidays, after the actual date of the opening of the Bids.

ARTICLE 11. ACCESS TO SITE.

11.1 Representatives of the State and any local or federal agencies having an interest in the Work shall have access to the Work wherever it is in preparation or progress and the Contractor shall provide proper facilities for such access and inspection.

ARTICLE 12. SALES TAX.

12.1 The goods and services to be provided under any contract or purchase order awarded pursuant to this Invitation to Bid is exempt from the sales taxes of the State of Connecticut.

ARTICLE 13. INSURANCE.

13.1. The Contractor shall not commence work under this Contract until all insurance required under this Section 13 has been obtained by the Contractor and such insurance has been approved by the CITY. The Contractor shall not allow any subcontractor to commence work on any subcontract until all insurance required of any such subcontractor has been so obtained and approved by the CITY. Insurance shall be provided by insurers, satisfactory to the CITY and authorized to do business in the State of Connecticut, an "A-" Best's Rating and at least a Class V3 or better financial size category as shown in the most current A.M. Best Company ratings.

13.2. At no additional cost to the CITY, the Contractor shall purchase and maintain the insurance coverages set forth below which shall protect the CITY from claims which may arise out of or result from the Contractor’s obligation under this Contract, whether such obligations are the Contractor’s or subcontractor or person or entity directly or indirectly employed by said Contractor or subcontractor, or by any person or entity for whose acts said Contractor or subcontractor may be liable.

13.3. Each insurance policy shall state that the insurance company shall agree to investigate and defend the insured against all claims for damages, even if groundless. If any insurance required herein is to be issued or renewed on a claims made form as opposed to an occurrence form, the retroactive date for coverage shall be no later than the commencement date of this Contract and shall provide that in the event of cancellation or non-renewal, the discovery period for insurance claims (“Tail Coverage”) shall be available for at least 60 months.

13.4. The following policies with stated limits shall be maintained, in full force and effect, at all times during which the services are to be performed by the Contractor:

13.4.1 General Liability Insurance: $1,000,000.00 per occurrence and $2,000,000.00 aggregate and $2,000,000.00 Products and completed operations aggregate; providing coverage to protect the CITY for all damages arising out of bodily injuries, sickness to or death of all persons in any one accident or occurrence and for all damages arising out of destruction of property in any one accident or occurrence.

13.4.2 Automobile Liability Insurance: $1,000,000.00 combined single limit (CSL); providing coverage to protect the CITY with respect to claims for damage for bodily injury and or property damage arising out of ownership, maintenance, operation, use or loading and unloading of any auto including hired & non-owned autos.

13.4.3 Workers’ Compensation: Statutory Limits within the State of Connecticut:

Employers’ Liability:

EL Each Accident: $1,000,000.00 EL Disease Each Employee: $1,000,000.00 EL Disease Policy Limit: $1,000,000.00

Contractor shall comply with all State of Connecticut statutes as it relates to workers’ compensation.

13.4.4 Excess/Umbrella Liability Insurance: Excess or Umbrella insurance coverage that follows form or sits over General Liability, Automobile Liability and Workers Compensation insurances: $5,000,000.00 each occurrence and $5,000,000.00 in the aggregate.

13.4.5 Builder's Risk Insurance: coverage equaling the monetary value of the construction component of the Project. “All Risk” Builders Risk insurance (also know as “course of construction”) coverage with limits equal to or better than the maximum possible loss of all materials of construction used or contemplated under this Contract, including all materials in transit and all materials in storage wherever stored and the value of any and all subsequent Contract changes. This insurance shall include the interests of the CITY, the Contractor and any and all subcontractors. If deemed necessary by the CITY’s Risk Manager, this insurance shall also include coverage for the total value of the Project's constructed property and shall be valid until a certificate of occupancy is issued. Upon the issuance of said certificate, the CITY will assume responsibility for insuring said property.

13.4.6 Contractors Pollution Liability Insurance: $1,000,000.00 each occurrence/claim and $1,000,000.00 aggregate coverage. The foregoing per claim coverage plus appropriate aggregate coverage depending on the size of the job for contractor caused pollution events such as asbestos or lead abatement, but not limited to only these pollution causes of loss. Note that there can be no exclusions for hazardous materials, including no exclusions for lead or asbestos.

13.5. Failure to Maintain Insurance: In the event the Contractor fails to maintain the minimum required coverage as set forth herein, the CITY may at its option purchase same and offset the Contractor’s invoices for the cost of said insurance.

13.6. Cancellation: The CITY shall receive written notice of cancellation from the Contractor at least thirty (30) calendar days prior to the date of actual cancellation, regardless of the reason for such cancellation.

13.7. Certificates of Insurance: The Contractor’s General, Automobile, Builder’s Risk and Excess/Umbrella Liability Insurance policies shall be endorsed to add the CITY and State of Connecticut as additional insureds and provide waivers of subrogation on all policies except Builder’s Risk and Pollution Liability. The insurance afforded the additional insured shall be primary and non-contributory insurance and the coverage and limits provided under the Contractor’s policies shall not be reduced or prorated by the existence of any other insurance applicable to any loss the additional insured may have suffered.

Prior to the execution of this Contract by the CITY, the Contractor shall furnish to the CITY, subject to CITY approval, certificate(s) of insurance and Additional Insured Endorsement and Waiver of Subrogation Endorsement verifying the above coverages, including the naming of the CITY, as follows: “The City of Waterbury and State of Connecticut are listed as additional insured on all lines of coverage except Pollution Liability and waiver of subrogation applies to all lines of coverage except Pollution Liability and Builder’s Risk as their interest may appear”. The CITY's Invitation to Bid Number must be shown on the certificate of insurance to assure correct filing. The Contractor must supply replacement/renewal certificates at least 30 days prior to the expiration of the policy(ies). Said certificates shall contain a provision that coverage afforded under the policies shall not be cancelled or reduced for any reasons unless notice of than thirty (30) calendar days has been mailed to the CITY's Using Agency and a copy to the CITY's Office of Corporation Counsel, 235 Grand Street, Waterbury, CT 06702.

13.8. No later than thirty (30) calendar days after receipt by the Contractor, the Contractor shall deliver to the CITY a copy of the Contractor's insurance policies and endorsements and riders.

ARTICLE 14. PURCHASE ORDER/CONTRACT TIME.

14.1 BIDDER agrees and covenants that the Contract Time shall commence upon delivery of the CITY’s written notice to proceed, which shall occur after contract execution by both parties. BIDDER guarantees that it shall complete all work in accordance with the following deadlines:

A. On or before August 20, 2026, the following work shall be completed:

(i) All demolition work including openings through the existing building envelope to the new elevator shaft with weathertight protection over openings;

(ii) All work in Storage 103, Corridor 104, Storage 104, Corridor 202, Teacher Work Room 203, Corridor 302 and Storage 303 to be complete including all openings, finishes, MEP fixtures, and life safety systems;

(iii) Provide locking, secure, fire rated barriers separating new corridor/elevator lobby from the existing school corridors, and all finish work within existing corridor area outside of this barrier providing access to Corridors, Teacher Work Room and Storage spaces; and

(iv) The elevator shaft foundation is to be backfilled and complete prior to the start of school in August 2026.

B. The Project’s Substantial Completion Date is December 15, 2026.

C. The Project’s Final Completion Date is February 10, 2027.

ARTICLE 15. BID DOCUMENTS.

15.1 Bid Documents shall be any and all sections, terms, conditions, forms, drawings, data, etc., listed in the Table of Contents of the Bid Documents.

ARTICLE 16. FEDERAL, STATE AND LOCAL EMPLOYMENT REQUIREMENTS.

16.1 Contractors, if applicable, shall be obligated to fully comply with the attached Hiring of

Waterbury Residents on Certain Publicly Funded Construction Projects, i.e. City of Waterbury Ordinances Chapter 34 (“Good Jobs Ordinance“), Federal Davis-Bacon Act, Federal American Recovery and Reinvestment Act of 2009, and the Housing and Urban Development Section 3 Clause, all as further specified in the attached City of Waterbury Contract form. Also attached hereto, is a full copy of the aforesaid City of Waterbury Ordinance, commonly referred to as the “Good Jobs Ordinance“.

16.2 i. The contractor who is selected to perform this municipal public works project, funded in whole or part by the State, must comply with CONN. GEN. STAT. §§ 4a-60, 4a-60a, 4a- 60g, and 46a-68b through 46a-68f, inclusive, as amended by Public Act 23-204 and Public Act 25-168. An Affirmative Action Plan must be filed with and approved by the Commission on Human Rights and Opportunities prior to the commencement of construction.

ii.State law requires a minimum of twenty-five (25%) percent of the state-funded portion of the contract be set aside for award to subcontractors holding current certification from the Connecticut Department of Administrative Services (“DAS”) under the provisions of CONN. GEN. STAT. § 4a-60g. (25% of the total state-funded value with DAS-certified Small Businesses and 6.25% of the total state-funded value with DAS-certified Minority-, Women-, and/or Disabled-owned Businesses.) The contractor must demonstrate good faith effort to meet the 25% set-aside goals.

iii. For municipal public works contracts, the contractor must file a written or electronic non-discrimination certification with the Commission on Human Rights and Opportunities.

Forms can be found at:

https://portal.ct.gov/chro/contract-compliance/contract-compliance/contract-compliance-forms-and-reports.

https://portal.ct.gov/chro/contract-compliance/contract-compliance/contract-compliance-forms-and-reports https://portal.ct.gov/chro/contract-compliance/contract-compliance/contract-compliance-forms-and-reports

ELEVATOR PROJECTS

SECTION 00200

ADDENDUM ACKNOWLEDGEMENT FORM

NOTE: The Bidder is to complete, sign and date this form. The completed form shall be submitted with the BID FORM in accordance with ARTICLE 6 of the INSTRUCTIONS TO

BIDDERS.

The undersigned, as Bidder’s Authorized Representative, acknowledges receipt of the following Addenda and that the modifications to the Bid Documents noted therein have been considered and all costs related thereto are included in the Bid Prices:

Addendum # _______ Dated Issued ____________________

Addendum # _______ Dated Issued ____________________

Addendum # _______ Dated Issued ____________________

Business Name of Bidder: _______________________________________________

(Print or Type)

By Bidder’s Authorized Representative:

Signature: ___________________________________________________________

Name: ___________________________________________________________ (Print or Type) Title: ___________________________________________________________ (Print or Type) Email: ___________________________________________________________ (Print or Type) Date: ___________________________________________________________

(Print or Type) END OF SECTION

ELEVATOR PROJECTS

SECTION 00300

ITEM # QTY DESCRIPTION

COST

EACH TOTAL COST

1.0 1 Driggs ES Elevator Addition (per scope) $ $

2.0 1 Wilson ES Elevator Addition (per scope) $ $

GRAND TOTAL ALL CHARGES $

In the event of mathematically incorrect calculations of individual items or totals, the mathematically correct amount as determined by the City shall govern in determining the TOTAL

BID PRICE.

The undersigned also agrees that the quantities indicated are for Bid comparison purposes only and are not represented to be actual quantities for completion of the Work.

The undersigned hereby certifies under the penalties of perjury that this Bid is in all respects bona fide, fair and made without collusion or fraud with any other person. As used in this section, the work "person" shall mean any natural person, joint venture, partnership, corporation, or other business or legal entity.

Social Security Number Signature of Individual or or Federal Identification Number Corporate Name

Corporate Officer

(if applicable)

Notice of acceptance should be mailed, telegraphed or delivered to the (undersigned Bidder at the following address):

(Company Name)

By:

(Title)

(Business Address)

(City, State, Zip Code)

Date: Email:___________________________

Note: If the Bidder is a corporation, indicate State of incorporation under signature, and affix corporate seal; if a partnership, give full names and residential addresses, if different from business address.

The following documents are attached to and made a condition of the Bid:

a. Instructions to Bidders – Section 00100

b. Addendum Acknowledgement – Section 00200

c. Bid Form – Section 00300

d. Technical Specifications – Section 00400

ELEVATOR PROJECTS

AT

THE DRIGGS ELEMENTARY AND WOODROW WILSON ELEMENTARY SCHOOLS

SECTION 00400

TECHNICAL SPECIFICATIONS

Each project consists of the construction of a new elevator addition integrated into the existing school building. Work is expected to include, but is not limited to:

• New elevator shaft and cab

• Elevator equipment and controls

• Structural modifications and foundations

• Architectural finishes

• Mechanical, electrical, fire alarm, and life safety systems

• Coordination with existing building systems

• Site work related to the addition

Project Locations

• The Driggs Elementary School - 77 Woodlawn Terrace, Waterbury, CT 06710. State project #151-0315 LUE

• The Woodrow Wilson Elementary School – 235 Birch St, Waterbury, CT 06704, state project #151-0316 LUE

Scope of Work

The Contractor shall:

1. Construct elevator additions in strict accordance with the drawings and specifications prepared by Friar Architects and attached in attachment #

2. Coordinate all trades, subcontractors, inspections, and testing.

3. Maintain safe operations in an occupied school environment.

4. Comply with all federal, state, and local codes, including ADA and fire/life safety requirements.

5. Provide all permits, inspections, and approvals required for project completion.

6. Coordinate construction activities with school administration to minimize disruption.

Proposal Requirements

Proposals shall include the following:

1. Cover Letter signed by an authorized representative

2. Company Profile & Experience o Similar elevator or vertical transportation projects o Experience in occupied school facilities

3. Project Team o Project Manager o Superintendent o Key subcontractors

4. Project Approach & Schedule

5. Cost Proposal o Lump sum price or breakdown as requested o Alternates, if applicable

6. References (minimum of three)

7. Bonding Capacity & Insurance Information

Attachment A

• ANNUAL STATEMENT OF FINANCIAL INTEREST

• DEBARMENT CERTIFICATION

• CITY OF WATERBURY DISCLOSURE OF OUTSTANDING OBLIGATIONS

ANNUAL STATEMENT OF FINANCIAL INTERESTS (Calendar Year 202__) Persons or Entities Conducting Business with the City d:\attach-a-annual statement of financial interests.doc 1

I. Outstanding Purchase Orders of Contracts with the City

A. Contracts

No Contracts with the City

(Service or Commodity Covered by Contract)

(Term of Contract)

(Service or Commodity Covered by Contract)

(Term of Contract)

(Service or Commodity Covered by Contract)

(Term of Contract)

FILL IN AND RETURN WITH YOUR SUBMISSION

Persons or Entities Conducting Business with the City d:\attach-a-annual statement of financial interests.doc 2

B. Purchase Order(s).

No Purchase Order(s) with the City

(Service or Commodity Covered by Purchase Order)

(Date of Purchase Order)

(Service or Commodity Covered by Purchase Order)

(Date of Purchase Order)

(Service or Commodity Covered by Purchase Order)

(Date of Purchase Order)

Persons or Entities Conducting Business with the City d:\attach-a-annual statement of financial interests.doc 3

II. Financial Interest Disclosure (Public Officials, Employees or Board and Commission Members with interest in

Person or Entity Conducting Business with the City)

No Officials, Employees or Board and Commission Members with Financial Interest

(Name of Official)

(Position with City)

(Nature of Business Interest) (e.g. Owner, Director etc…)

Interest Held By:

Self Spouse Joint Child

(Name of Official)

(Position with City)

(Nature of Business Interest) (e.g. Owner, Director etc…)

Interest Held By:

Self Spouse Joint Child d:\attach-a-annual statement of financial interests.doc 4

1. I certify that this Annual Statement of Financial Interests is a complete and accurate statement of those matter required to be disclosed by me pursuant to §39.061 of the Code of Ordinances.

2. I understand that if I fail to file an Annual Statement (or amendment thereto) or an inaccurate Statement I will be in violation with Chapter 39 of the Code of Ordinance and, thereby, subject to the remedies set forth in §§38.71 and

39.101 of said Code.

3. I understand that I must file with the City Clerk, within fifteen (15) days following any reportable occurrence, any amendments to the Annual Statement.

I have read and agree to the above certification.

(Name of Company, if applicable)

Signature of Individual (or Authorized Signatory) Date

Print or Type Name and Title (if applicable)

DELIVERED By Mail Hand-Delivered

DISCLOSURE AND CERTIFICATION AFFIDAVIT REGARDING OUTSTANDING

OBLIGATIONS TO THE CITY OF WATERBURY

For the purposes of this Disclosure of Outstanding Financial Obligations, the following definitions apply:

(a) “Contract” means any Public Contract as defined below.

(b) "Person” means one (1) or more individuals, partnerships, corporations, associations, or joint ventures.

(c) “Public Contract” means any agreement or formal commitment entered into by the city to expend funds in return for work, labor, services, supplies, equipment, materials or any combination of the foregoing, or any lease, lease by way of concession, concession agreement, permit, or per agreement whereby the city leases, grants or demises property belonging to the city, or otherwise grants a right of privilege to occupy or to use said property of the city.

(d) “City” means any official agency, board, authority, department office, or other subdivision of the City of Waterbury.

State of_____________________________

SS.:___________________

County of___________________________

_____________________________________________________, being first duly sworn, deposes and says that:

1. I am the owner, partner, officer, representative, agent or ___________________ of __________________________(Contractor’s Name), the Contractor that has submitted the attached agreement.

2. I am fully informed respecting the preparation and contents of the attached Agreement and of all pertinent circumstances respecting such Agreement;

3. That as a person desiring to contract with the City (check all that apply):

____ The Contractor and each owner, partner, officer, representative, agent or affiliate of the Contractor has filed a list of taxable personal property with the City of Waterbury for the most recent grand list, as required by Conn.

Gen. Stat. §12-42.

____ Neither the Contractor nor any owner, partner, officer, representative, agent or affiliate of the Contractor are required to file a list of taxable personal property with the City of Waterbury for the most recent grand list, as required by Conn. Gen. Stat. §12-42.

____ Neither the Contractor nor any owner, partner, officer, representative, agent or affiliate of the Contractor either directly or through a lease agreement, owes back taxes to the City of Waterbury

OBLIGATIONS TO THE CITY OF WATERBURY

____ Neither the Contractor nor any owner, partner, officer, representative, agent or affiliate of the Contractor either directly or through a lease agreement, has any other outstanding obligations to the City of Waterbury

4. The following list is a list of the names of all persons affiliated with the business of the Contractor, if none state none. Use additional sheet if necessary (Must be on company letterhead and notarized):

Name Title Affiliated Company (if none state NONE)

Service or

Material

DOB

5. That as a person desiring to contract with the City:

(a) The Contractor or an owner, partner, officer, representative, agent or affiliate of the Contractor provides, or has provided, services or materials to the City within one (1) year prior to the date of this disclosure, if none, state none.

Use additional sheet if necessary (Must be on company letterhead and notarized):

Name Title Affiliated Company (if none state NONE)

Service or

Material

DOB

(b) The Contractor possesses an ownership interest in the following business organizations, if none, state none. Use additional sheet if necessary (Must be on company letterhead and notarized) :

Organization Name

Address Type of Ownership

(c) The following persons possess an ownership interest in the Contractor. If the Contractor is a corporation, list all of the officers of the corporation and the names of each stockholder whose shares exceed twenty-five

OBLIGATIONS TO THE CITY OF WATERBURY

(25) percent of the outstanding stock, if none, state none. Use additional sheet if necessary (Must be on company letterhead and notarized):

Name Title DOB Stock %

(d) Of the following of the affiliates, individuals or business entities identified in this affidavit, list each that owns, owned, or within one (1) year prior to the date of this disclosure has owned, taxable property situated in the City of Waterbury, if none state none. Use additional sheet if necessary (Must be on company letterhead and notarized):

Name Title Affiliated Company (if none state NONE)

Address DOB

(e) If the Contractor conducts business under a trade name, the following additional information is required: the place where such entity is incorporated or is registered to conduct such business; and the address of its principal place of business, if none, state none:

TRADE NAME PLACE OF INCORPORATION/REGISTRY PRINCIPAL

PLACE

OF BUSINESS

I hereby certify that the statements set forth above are true and complete, and I understand that any incorrect information or omission of information from this affidavit may result in the immediate termination of the Contractor’s agreement with the City of Waterbury.

For Partnership/Sole Proprietor

In presence of:

Witness Name of Partnership/Business

OBLIGATIONS TO THE CITY OF WATERBURY

By: ______________________________ Name of General Partner/ Sole Proprietor

Address of Business

State of _____________________ )

) SS

County of ____________________ )

______________________________________________ being duly sworn, Deposes and says that he/she is _____________________ of _____________ and that he/she answers to the foregoing questions and all statements therein are true and correct.

Subscribed and sworn to before me this _________ day of _________ 202_.

(Notary Public)

My Commission Expires: ________________________________

For Corporation

Witness Name of Corporate Signatory

Address of Business

Affix Corporate

Seal

By:__________________________________ Name of Authorized Corporate Officer

Its:_____________________________ Title

OBLIGATIONS TO THE CITY OF WATERBURY

State of _____________________ )

) SS

County of ____________________ )

______________________________________________ being duly sworn, deposes and says that he/she is _____________________ of _____________ and that he/she answers to the foregoing questions and all statements therein are true and correct.

Subscribed and sworn to before me this _________ day of _________ 202__.

(Notary Public)

My Commission Expires: ________________________________

Attachment B Documents

• SAMPLE CONTRACT

• GENERAL CONDITIONS

• SPECIAL CONDITIONS

• SAMPLE CORPORATE RESOLUTION

• SAMPLE LLC RESOLUTION

ITB #8703

ATTACHMENT A-1.1

GENERAL CONDITIONS

INTRODUCTORY NOTE:

These General Conditions supplement the provisions and requirements of Contract and modify all Contract Documents which follow it numerically, as set forth in Section 1.2 of the Contract. The General Conditions may be amended, revised or supplemented by the Special Conditions, which are project specific. The Contractor’s attention is directed to the attached Special Conditions for any amendments, revisions or supplements to the General Conditions for this project. The terms used in these General Conditions which are defined in the Contract have the meanings assigned to them in said Contract.

This section applies equally and specifically to all contractors supplying labor and/or equipment and/or materials for this Project and all drawings, specifications and general provisions of the Contract apply to these General Conditions. Where items of the Contract are repeated, it is intended to call particular attention to or qualify them; it is not intended that any other parts of the Contract shall be assumed to be omitted if not repeated herein.

Unless expressly provided for otherwise in the Contract Documents, all costs associated with any work/services required or necessary under the General Conditions shall be considered as included in the Contract Amount (also referred to as Total Compensation). No separate or additional payment will be made for this work and/or services.

ARTICLE 1. PLANS AND SPECIFICATIONS AT THE SITE / AS-BUILTS

1.01 The Contractor shall maintain at the Project site two (2) copies of all Plans, Specifications, Addenda, approved Shop Drawings, Change Orders and other Modifications, Schedules and Instructions, in good order. One copy is to be marked to record all changes made during construction. These shall always be available to the Project Engineer and the City or their authorized representatives. At the conclusion of construction, the Contractor is to turn one (1) corrected set of all documents over to the Project Engineer.

ARTICLE 2. CONSTRUCTION PROGRESS SCHEDULE

2.01 Within seven (7) consecutive calendar days of the written Notice to Proceed, and prior to commencement of any work on site, the Contractor shall prepare and submit for the approval of the City three

(3) copies of a complete Construction Progress Schedule which shall be comprised of a critical path method network. (At the same time, the Contractor shall submit the Schedule of Values, Sedimentation and Erosion Control Measures, Water Control Plan and Environmental Protection Plan, as outlined in the various Articles of these General Conditions).

2.02 The critical path of the Project must be identified on the Construction Progress Schedule which shall provide a workable plan for monitoring the progress of all the elements of the Project, establish and clearly display the critical elements of the Work, on which each part or division of the Work is expected to be started and completed, forecast completion of the elements of the Project, and match the Contract duration in time. The Construction Progress Schedule shall also indicate the logic of the work for the major elements and components of work under the Contract, such as the planned mobilization of plant and equipment, sequences of operations, procurement of materials and equipment, duration of activities, type of relationship, lag time (if any), and such other information as it is necessary to present a clear statement of the intended activities.

2.03 The Construction Progress Schedule shall, at a minimum, indicate the proposed scheduling of all major items of work and Project components. The schedule shall state the methods for doing each portion of the work and show the significant on-site construction activities with planned early/late start early/late completion dates and total float for each activity, including activities of the Contractor, subcontractors, fabricators, and suppliers to ensure adequate planning and communication. Activities shall include, the following items, as applicable: (a) milestone events; (b) seasonal weather limitations (c) the procurement and fabrication of materials, plant and equipment and any associated submittals; (d) the order in which the Contractor proposes to complete activities; (e) temporary structures or systems; (f) major construction or work zone traffic control stages; (g) activities assigned to Utilities, railroads and other parties; (h) activities assigned to the City and other State or municipal entities; (i) sampling and testing of materials; (j) settlement, surcharge or cure periods; (k) punch list work, (l) inspection activities assigned to the City, including final inspection and (m) all project closeout activities and requirements. The Contractor shall evaluate the status of the Project at least monthly, comparing it to the original schedule, which shall be revised as required herein.

The Contractor shall notify the Project Engineer immediately of any circumstances that may affect the current schedule.

2.04 Upon approval of the initial Construction Progress Schedule by the Project Engineer, this schedule shall also be referred to as the "Baseline Construction Progress Schedule” or “Baseline Schedule.”

2.05 The Contractor shall perform the work of this Contract to satisfy the approved Construction Progress Schedule; however, the Project Engineer and City reserve the right to amend and alter the Construction Progress Schedule, as approved, at any time and in a manner which the Project Engineer deems to be in the best interests of the City. The latest version of the Construction Progress Schedule, as amended and approved by the Project Engineer, shall also be referred to as the "Current Construction Progress Schedule” or “Current Schedule.” The approval of the Construction Progress Schedule, or any revision thereof, shall in no way waive the requirements of the Contract nor shall it excuse the Contractor from any obligations under the Contract.

2.06 The Contractor shall be required to execute his work in accordance with the Construction Progress and in accordance with any additional requirements specified herein and/or revisions approved by the Project Engineer.

2.07 The Construction Progress Schedule shall forecast the times for doing each portion of the work. The Contractor shall arrange the work under this Contract to conform with the Construction Progress Schedule, as it may be revised by the Project Engineer from time to time, at no additional expense to the City.

2.08 Contractor shall provide, at a minimum, the following:

a. Monthly Updates: Each month, as of a calendar date mutually acceptable to the Contractor and to the Project Engineer, the Contractor shall deliver to the Engineer three (3) prints of all required schedule diagrams and tabulations. Until Final Completion of the work, Contractor shall continually evaluate the status of the Project, comparing it to the current Construction Progress Schedule, or approved revision thereof. The Contractor shall notify the Project Engineer immediately of any circumstances that may affect the Current Schedule, or any component thereof.

b. Biweekly Schedules: Each week, the Contractor shall be required to produce and submit to the Project Engineer a biweekly schedule showing all activities planned for the following two-week period. This short-term schedule may be handwritten; however, a two week “look ahead” filter from the Construction Progress Schedule is preferred. The biweekly schedule shall clearly indicate all work planned on a crew basis for the two-week period.

c. Recovery Schedules: If completion of any part of the work, delivery of equipment or materials, or submission of submittals or required documentation is behind the approved Construction Progress Schedule and will impact the end date of the work past the Contract completion dates (create negative float), the Contractor shall submit in writing, a revised Construction Project Schedule acceptable to the City for completing the work on or before the current Contract completion dates.

d. The revised Construction Project Schedule shall take some or all the following actions to demonstrate the manner in which an acceptable rate of progress will be regained, by the following methods:

i. Increase construction manpower in such quantities and crafts as shall substantially eliminate the backlog of work and meet the current Contract completion date.

ii. Increase the number of working hours per shift, the number of shifts per day, the number of workdays per week, or the amount of construction equipment, or any combination of the foregoing.

iii. Reschedule work items to achieve concurrent…