This document is a compilation of contract amendment, change orders, and related documents for the ADOT Tucson North MVD Renovation project located at 7330 N Shannon Road in Tucson, Arizona. The primary parties involved include the Arizona Department of Transportation (ADOT), SD Crane Builders Inc. as the primary contractor, and Shive-Hattery as the architectural design firm. Other subcontractors and vendors include Romanoski Glass & Mirror, S&H Steel Co. LLC, Hansen-Kramer Stucco Inc., and Design Drywall West, Inc.
The contract amendment and change orders detail various modifications to the original contract, including adjustments to the Tucson North MVD Remodel line items, with the total contract sum increasing from $3,021,688.18 to $3,317,146.79. The changes involve specific scope modifications such as ceiling repairs in the road test canopy, electrical panel installations, wall thickness adjustments, and additional metal stud and drywall work. The project includes renovations to the building's interior, including ceiling modifications, electrical panel installations, and architectural adjustments. The contract amendment extends the substantial completion date to 12/17/2026 and includes a 15-day schedule adjustment. The total additional costs across various change orders and subcontractor work amount to approximately $295,458.61.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ARIZONA DEPARTMENT OF TRANSPORTATION
1655 W. Jackson Street, MD 100P
Phoenix, AZ 85007
Contract Amendment Summary CONTRACTOR: SD Crane Builders Inc. AMENDMENT NO.: Six (6) DESCRIPTION: Tucson North MVD Remodel
Rev. 03/2025
Pursuant to the Uniform Terms and Conditions, Section 5, Contract Changes, the above referenced contract is amended. Summary of changes is as follows:
1. Line item CTR075036-1 Tucson North MVD Remodel per the technical specifications & drawings, increased from $2,640,222.85 to $2,660,773.45 total cost. See attached CO.
2. Line item CTR075036-3 Base Bid Tax increased from $149,304.59 to $150,466.73. See attached CO.
3. All other terms, conditions and provisions of this contract remain unchanged.
javascript:void('0') javascript:void('0')
Construction Contract Change Order Summary No. ____
Contract/APP No. Contract/APP Amendment No:
Project Name: Project No: Statutory Review No:
Design Professional: Contractor: ADOT Project Manager:
ALL OTHER REQUIREMENTS, SPECIFICATIONS, TERMS AND CONDITIONS REMAIN UNCHANGED
ACKNOWLEDGEMENT AND AUTHORIZATION
Page | 1 of 1
1. Check box(es) below best describing the Construction Change Order to the Contract:
☐ Contractor cost increase to Contract due to Additional Work.
☐ Contractor cost reduction to Contract.
☐ Contractor to increase number of calendar days to date of Substantial Completion of the Project.
☐ Contractor �no cost� change to Contract.
☐ Use of Contingency ☐ Other (Provide Description) _______________________________________________________________.
2. Contractor shall provide complete description of reduced or Additional Work, including documents in support of the Change Order (e.g., drawings, material substitution literature, cost reduction or increase detail including breakout of labor, materials, markup and tax). Contractor shall use the Construction Change Order Worksheet (Exhibit J1) to provide a detailed breakdown of any change to the Project Cost.
3. By signing and executing this Change Order, the Contractor and Agency agree to a price for the Additional Work, as detailed below. This price shall cover any and all Costs associated with the Additional Work including, but not limited to, Costs associated with delay of the Contractor's Work, if any.
Should the Additional Work impact the Schedule, the Agency and Contractor have agreed to extend the date for Substantial Completion as reflected below.
4. Contractor agrees that the payment authorized by this Change Order, if any, is in full settlement of any and all causes of action, including but not limited to, any claim resulting from delays to the time to Substantial Completion caused by this Change Order which Contractor or any of its Subcontractors, suppliers and the officers, agents, and employees of each of them, may now have or may assert in the future against the Agency, or its officers, employees and agents, arising out of, or associated with, this construction Change Order.
In accordance with the terms of the Contract, the following detailed changes are proposed (attach additional information as needed):
Original Contract Sum $
Previous Change Orders to Contract $
Net Change for this Change Order to Contract (attach Exhibit J1 for details as needed) $
New Contract Sum $
Number of Calendar Days for Time Extended for Substantial Completion for this Change Order Days
Revised Substantial Completion Date due to this Change Order
Contractor (Firm Name): Address: Authorized Signature and Date:
Design Professional (Firm Name): Address: Authorized Signature and Date:
ADOT Procurement Officer Name:
Agency Name and Address: Authorized Signature and Date: ADOT Project Manager Name:
Agency Name and Address: Authorized Signature and Date:
State of Arizona Department of Transportation
206 S 17th Ave Phoenix, AZ 85007
ADOA Chief Compliance Officer Name:
Agency Name and Address: Authorized Signature and Date:
This Change Order shall modify the Contract only upon the signed approval of the Contractor, Design Professional, ADOT Procurement Officer as specified in the signature block. When signed by all parties this Change Order becomes effective immediately and the Contractor shall proceed with the change(s) identified and approved.
3,021,688.18
273,745.88 21,712.73
3,317,146.79
12/17/2026
CTR075036 06
CTR075036 HD-24-15
Shive-Hattery SD Crane Builders Andrew May
See attached J1.
SD Crane Builders, Inc.
Shive-Hattery, Inc.
Andrew May
Patrick Holt
Elizabeth Blakley
1215 W. Rio Salado Pkwy #109 Tempe, AZ 85281 4330 N. Campbell Ave., Suite 268 Tucson, AZ 85718 1655 W. Jackson St.
Phoenix, AZ 85007 1400 W. Washington St., #B200 Phoenix, AZ 85007 1655 W. Jackson St.
1655 W. Jackson St.
ADOT Tucson North MVD Renovation
08/04/2025
08/05/2025
08/07/2025
08/07/2025
08/12/2025
COR No.6
Date: 6/23/25
Item
No.
Subcontractor Trades
Q ty
U n it s
Unit Price Extension Q ty
U n it s
Unit Price Extension Totals
Ceiling on Road Test Canopy R.F.I. #7 -$ -$ 10,195.00$
ASI #7, Electrical Panels & Wall Thickness R.F.I. #45, Ceiling in Storage Room 108 R.F.I. #46 -$ -$ 6,987.00$
17,182.00$
Owner Request 4.00% 687.28$
Hidden Condition 10.00% 1,786.93$
3.00% 589.69$
Prepurchase Materials 0.50% 101.23$
Omission in Construction docs 1.00% 203.47$
Transfer to/from Contingency 5.655% 1,162.14$
Other 21,712.73$
Approval of this Change Order Request will increase (decrease) the Schedule by: Calendar Days 15
Form 8.14. rev 8.10.2021 r5
Total Cost
Address Authorized Signature & Date
Construction Services Manager Address Authorized Signature & Date
Contractor
Design Professional Address Authorized Signature & Date
ADOT Project Manager Address Authorized Signature & Date
Fee
This Change will require Statutory Review: Yes No
General Conditions
Builders Risk
Tax
Insurance
Bond
Schedule of Values by Trade
The Contractor hereby requests a Change in the Contract Sum and/or Time, conforming to Article 1.2 of the Uniform Terms and Conditions, the Work described herein will not start until this Change Order Request has been signed by all parties.
Labor Material
Check the box best describing the Cause of this Change Subtotal
Exhibit J1
Change Order Request
State of Arizona
General Services Division
1400 West Washington St
Phoenix, AZ 85007
Project Name: ADOT Tucson North MVD Renovation State Project No:CTR075036
Contractor Project No: 24-322Contractor: SD Crane Builders Inc.
SD Crane Builders Inc. 1215 W. Rio Salado Pkwy #109 Tempe, AZ 85281 7/15/25
Shive-Hattery, Inc.
Andrew May
Patrick Holt
4330 N. Campbell Ave., Suite 268 Tuscon, AZ 85718
1655 W. Jackson St.
Phoenix, AZ 85007
1400 W. Washington St., #B200 Phoenix, AZ 85007
08/05/2025
Project: HD-24-015 ADOT- Tucson North MVD Renovation
(HD-24-015)
7330 N Shannon Rd Tucson, Arizona 85741
P: 602-499-8871
RFI #7: R.F.I. #007 Ceiling on Road Test Canopy
Status Open
To Joel Mesik (Shive Hattery) From Kyle Burns (SD Crane Builders Inc.)
1215 W Rio Salado Pkwy #109 Tempe, Arizona 85281
Date Initiated Mar 7, 2025 Due Date Mar 11, 2025
Location Project Stage Course of Construction
Cost Impact Schedule Impact
Spec Section Cost Code
Drawing Number Reference
Linked Drawings
Received From Kyle Burns (SD Crane Builders Inc.)
Copies To Tom Adamcik (SD Crane Builders Inc.), Adam Cherilla (SD Crane Builders Inc.), Jeff Murray (SD Crane Builders Inc.)
Activity
Question Question from Kyle Burns SD Crane Builders Inc. on Friday, Mar 7, 2025 at 02:39 PM MST Joel, For your review please see attached R.F.I. #007 Ceiling on Road Test Canopy. Please advise.
Thank you, Attachments R.F.I. #007 Ceiling on Road Test Canopy.pdf
Awaiting an Official Response
All Replies Response from Kyle Burns SD Crane Builders Inc. on Friday, Apr 11, 2025 at 03:10 PM MST Melissa, Thank you for the response regarding this R.F.I. We will move forward accordingly. Before we send it out for pricing we will wait for the final detail from the structural engineer.
Thank you Melissa, Page 1 of 2 Printed On: Apr 11, 2025 03:10 PM MST
Response from Melissa de la Gardelle Shive Hattery on Thursday, Apr 10, 2025 at 11:04 AM MST After the site field from the structural engineer, it is concluded that the fasteners that connected the soffit to the lintel had come loose at the portion of soffit that was sagging. The structural engineer recommends that the soffit be jacked up and a new horizontal steel plate be welded to the bottom flange of the existing lintel (see attached sketch SK-06). It is recommended that the repair occur along the full length of the east and west edges of the canopy. The sizes of the plates and welds will be provided once the structural engineer has completed his calculations. Contractor shall patch and repair soffit, texture and color to match existing.
Attachments R.F.I. #007_S-H Response.pdf
RFI #7 - R.F.I. #007 Ceiling on Road Test Canopy Project: HD-24-015 ADOT- Tucson North MVD Renovation (HD-24-015)
Page 2 of 2 Printed On: Apr 11, 2025 03:10 PM MST
REQUEST FOR INFORMATION
RFI #007
Subject: Ceiling on Road Test Canopy
Project Name: ADOT Tucson North MVD Building
Spec Sec: Addendum No: 007
S.D. Crane Builders, Inc.
1901 E. University Drive Suite # 330
Mesa, Arizona 85203
Date: 3/7/25
Project Number: 23-361 Project Manager: Kyle Burns Superintendent: Jeff Murray
Submitted To: Joel Mesik Attn: Joel Mesik
Reference:
Information Request:
On sheet D2.2 keynote #3 states that the existing ceiling of the canopy is to remain. During our pre-construction walk through we noticed that the canopy framing looks like it needs to be repaired/refastened. See pictures and let us know if this is something that will need to be addressed.
See Drawings and photo attached below.
Thank you, D2.2 Keynote #3
Response Date:
Replying Company:
Name:
S.D. Crane Builders, Inc.
1901 E. University Drive Suite # 330
Mesa, Arizona 85203 Telephone (480) 832-1777 Fax (480) 832-1798 Commercial Roc#175959 Res.#ROC192686 scrane@sdcranebuilders.com
Cost Impact: Yes Schedule Impact:
Answer Required by: WSM Architects Request by: SD Crane Distribution: SD Crane
Response
After the site field from the structural engineer, it is concluded that the fasteners that connected the soffit to the lintel had come loose at the portion of soffit that was sagging. The structural engineer recommends that the soffit be jacked up and a new horizontal steel plate be welded to the bottom flange of the existing lintel (see attached sketch SK-06). It is recommended that the repair occur along the full length of the east and west edges of the canopy. The sizes of the plates and welds will be provided once the structural engineer has completed his calculations. Contractor shall patch and repair soffit, texture and color to match existing.
April 10, 2025
Shive-Hattery
Marcus Attson
Shive-Hattery
A
3 3
B
B
4 4
C
C
D
D
E
E
5 5
1 1
2 2
1 1
TYP. 7
NOTE: ALL ITEMS ARE EXISTING UNLESS NOTED OTHERWISE
SEE D2.0 DEMOLITION FLOOR PLAN AND D2.1 DEMO ROOF PLAN FOR ADDITIONAL NOTES
7 SEAL
AP
PR
O
VE
D B
Y
D R
AW
N
B Y
IS
SU
ED
F
O R
IS
SU
E D
AT
E
PR
O
JE
C
T N
U M
BE
R
FI
EL
D B
O O
K
A
B C D E F
A B C D E F Autodesk Revit 2022
N C
AM
PB
EL
L
AV
E, S
TE
TU
C
SO
N , A
R
IZ
O N
A
0.
8.
W
SM
AR
C H
.C O
M
4/ 9/
:0
7:
A M
C :\S hi ve
\R ev it_ Lo ca l_
\2
0_
A2 2_
AD
O
T Sh an no n R d M
VD
_C
EN
TR
AL
_M ar cu s_ At ts on
.rv t
D
EM
O
LI
TI
O
N R
C P
Ap pr ov er
AM
L, M A
D
EC
EM
BE
R
, 2
D2.2
AD
O
T
TU
C
SO
N N
O R
TH
M
VD
R
EM
O
D
EL
N S
H
AN
N O
N R
D
TU
C
SO
N , A
Z
1/8" = 1'-0"1 DEMOLITION REFLECTED CEILING PLAN
N
# KEYNOTES
1 DEMOLISH EXISTING ACT CEILING, LIGHTING AND HVAC DEVICES THIS AREA
2 DEMOLISH EXISTING METAL ROOFING AND STRUCTURE IN ITS ENTIRETY
3 EXISTING CEILING THIS AREA TO REMAIN, REMOVE LIGHTING AND HVAC
DEVICES, AND ANY ACCESS PANELS THIS AREA. PATCH AND REPAIR
DRYWALL AS REQUIRED.
4 DEMOLISH GWB CEILING, LIGHTING AND HVAC DEVICES, AND ANY ACCESS
PANELS THIS AREA
5 DEMOLISH EXTERIOR STUCCO CEILING AND LIGHTING THIS AREA
6 REMOVE EXISTING LIGHTING
8 EXISTING STORAGE SHED TO REMAIN
9 EXISTING FLAG POLE TO REMAIN - ELEVATION OF GRADE AT FLAGPOLE TO
REMAIN
10 DEMOLISH EXISTING GWB SOFFIT
GENERAL DEMOLITION NOTES
SEE 'GENERAL DEMOLITION NOTES' ON SHEET D2.0
DEMOLISHED DOOR BELOW - INFILL EXTERIOR WALL AT DEMOLISHED DOOR
SEAL
JOEL D.
MESIK
23507RE
G ISTERED ARCHITECT
C
ERT I F I CA T E
NO
Da t e S i g n e d
A R
I Z O N A U . S . A
3/28/2024
This side of the canopy is where the ceiling is sagging/smiling
These plans and documents have been reviewed and found to be in compliance with the applicable code requirements of the jurisdiction Issuance of a permit is recommended subject to approval by other departments and any noted conditions. The stamping of these plans shall not be held to permit or be an approval of any violation of applicable codes and standards no relieve the owner, design professional of record or contractor of compliance with the applicable codes and standards. Plan review of documents does not authorize construction to proceed in violation of any federal, state, nor local regulation.
BUREAU VERITAS NORTH AMERICA, INC.
REVIEWED FOR CODE COMPLIANCE
SIGNATURE:____________________
DATE:_________________________04/19/2024
fmyers
Approved Plans & Specifications Planning & Construction Services
04/22/2024 9:55:22 AM
EXISTING W16X26 BEAM
EXISTING CMU
EXISTING STEEL
BOTTOM PLATE
SUSPENDED STUCCO SOFFIT
WELD STEEL PLATE TO BOTTOM
OF EXISTING PLATE - SIZE OF
PLATE AND WELD TBD
EXISTING LEDGER AND
TJI JOIST
SK-06
SK-06
PROVIDE SOFFIT SUPPORT ALONG
FULL LENGTH OF EAST AND WEST
CANOPY EDGE
D
AT
E D
R
AW
N B
Y
AP
PR
O
VE
D
B Y
SC
AL
E
FI
EL
D
B O
O K
R
EV
IS
IO
N
N C
AM
PB
EL
L
AV
E, S
TE
TU
C
SO
N , A
R
IZ
O N
A
0.
8.
S
H
IV
E- H
AT
TE
R Y.
C O
M
Autodesk Revit
PROJECT NUMBER
4/9/2025 8:50:30 AM
C :\S hi ve
\R ev it_ Lo ca l_
\2
0_
A2 2_
AD
O
T Sh an no n R d M
VD
_C
A M
O D
EL
_M ar cu s_ At ts on
.rv t
As in di ca te d
2172304350
AD
O
T
TU
C
SO
N N
O R
TH
M
VD
R
EM
O
D
EL
N S
H
AN
N O
N R
D
TU
C
SO
N , A
Z
M A
JD
M
SK-06
SH
IV
E- H
AT
TE
R Y
1 1/2" = 1'-0"1 CANOPY CEILING DETAIL
1/8" = 1'-0"2 REFLECTED CEILING PLAN - ROAD TEST CANOPY
N
/1
/2
/2
1/
T h is
E le c tr o n ic
S ig n a tu re H a s B e e n A u th o ri z e d B y M e T h is
/2
/2
Date: 4/1/2025
C.O. #: 2502603
Client / Contractor: Project:
RFP #:
Contractor Project #:
Amount
$408.00
$408.00
Submitted By: Accepted By:
RCD Demolition LLC
Signature:
Eric Vazquez
Total:
Cut, remove, and legally dispose of existing stucco finish from Road Test Canopy
(24" x 24" opening - 2ea)
Attn: Kyle Burns, Jeff Murray
1215 W. Rio Salado Pkwy, Suite 109
7330 N. Shannon Road
Tucson, AZ 85741
SD Crane Builders, Inc.
CHANGE ORDER
Eric Vazquez, Project Manager
Tucson North MVD Building
Tempe, AZ 85281
Change Order Description: Remove Stucco Finish from Road Test Canopy
24322-004
Date : 5/15/2025
Job #: 24463
CO #: 1
620 W. Commerce Ave.
Gilbert, AZ 85233 Phone: 480.926.6062 Fax: 480.926.6063
S&H Steel Co. LLC
ADOT Tucson MVD Renovation
Job Location: 7330 N SHANNON RD
TUCSON AZ 85741
Change Order Request Kyle Burns SD Crane 1901 E University Drive suite 330 Mesa, AZ 85203 Phone: 480-832-1777
To:
Added Plate @ Road test Canopy ceiling sagging
Change Requested By:
Sent Via: E-mail
Description of Change:
Added Plate @ Road test Canopy ceiling sagging (SSE Sketch)
Material: $250.00 Fabrication: $ 250.00 Shipping: $170.00 Field Labor $3,325.00 Equipment $822.00 $4,817.00
OH&P : $723.00
TOTAL: $5,540.00
A signature below indicates acceptance of all changes shown herein. Any work associated with this change will begin upon receipt of a signed copy of this C.O. in our office. Please respond by 5/16/2025.
If the requested response time is not met, the project may be delayed.
Accepted By S&H Steel Co. LLC
Hansen-Kramer Stucco Inc.
Quality Since 1988
July 11, 2025
SD Crane
RE: Ceiling repairs – ADOT North
Drive through ceiling repairs per photos sent:
Lath, scratch and brown coat, dash finish to resemble existing
ADD $3,680.00
2100 E. Beverly Drive, Tucson AZ 85719
Office: (520) 743-9611 // hansenkramer@aol.com Lic. CR36-079004
Project 2172304350
October 24, 2024
ARCHITECTURAL SUPPLEMENTAL INSTRUCTIONS
A.S.I. NO. #07
Owner Architect Consultant Contractor SHEET OF Field Rep.
Other DATE
PROJECT: ADOT Tucson North MVD Renovation PROJECT DATED:
7330 N Shannon Rd Tucson, AZ 85741
OWNER: Arizona Department of Transportation CONTRACT TYPE:
1655 W Jackson St, MD129F Phoenix, AZ 85007
CONTRACTOR: SD Crane ARCHITECT’S PROJECT NO:
1901 E University Dr, Suite 330 Mesa, AZ 85203 CONTRACTOR’S PROJECT NO:
A) The following supplemental instructions are included in the original scope of work and shall be carried out in accordance with contract documents, with no change to contract sum.
B) Please acknowledge your acceptance and return a copy to the Architect.
Description:
• Additional information has been provided to address roof parapet hip detail and the wall furring at the existing split face CMU walls.
Attachments:
▪ SK-13 – Roof Hip Detail
▪ SK-14 – Enlarged Floor Plan – Wall Furring
▪ SK-15 – Aluminum Storefront Jamb Detail
BY ACCEPTED
Shive-Hattery CONTRACTOR DATE
X
June 26, 2025
1 1
ADOT
2172304350
23-361
PER RFI 24
PARAPET INFILL
PROVIDE 3-5/8" METAL STUDS @ 16"
O.C. - SLOPE @ 45 DEGREES
EXISTING CMU PARAPET TO REMAIN
METAL STUD ATTACHMENT TO DECK
PER STRUCTURAL DETAIL 213
ROOF
SLOPE
6" METAL STUD PER STRUCTURAL DETAIL 213
PARAPET HIP - SINGLY PLY TPO MEMBRANE
OVER 1/2" PLYWOOD OVER METAL STUD
4330 N CAMPBELL AVE, STE #268
TUCSON, ARIZONA 85718
520.408.1044 | SHIVE-HATTERY.COM
DATE
DRAWN BY
APPROVED BY
SCALE
FIELD BOOK
REVISION
Au to de sk
R ev it
06-24-2025
PROJECT
NUMBER
6/
/2
7:
:1
AM
C :\S hi ve
\R ev it_ Lo ca l_
\2
0_
A2 2_
AD
O
T Sh an no n R d M
VD
_C
A M
O D
EL
_M ar cu s_ At ts on
.rv t
1/4" = 1'-0"
MA
JDM
ADOT TUCSON NORTH MVD REMODEL
7330 N SHANNON RD
TUCSON, AZ 85741
2172304350
SK-13
SHIVE-HATTERY
1/4" = 1'-0"1 ENLARGED ROOF PLAN - PARAPET HIP
ALIGN
ALIGN
AL04
ALIGN
5/8" GWB OVER 3 5/8" METAL
STUDS (43-MIL) @ 16" O.C. W/ 43-
MIL BOTTOM TRACK WITH SHOT
PINS @ 16" O.C. MAX.
4' -1
/2
7'
-1 1"
5' -9
/2
2'-5 1/2" 1'-10"+/-
2 1/2"2 1/2"
SK-15
4330 N CAMPBELL AVE, STE #268
TUCSON, ARIZONA 85718
520.408.1044 | SHIVE-HATTERY.COM
DATE
DRAWN BY
APPROVED BY
SCALE
FIELD BOOK
REVISION
Au to de sk
R ev it
06-26-2025
PROJECT
NUMBER
6/
/2
7:
:4
AM
C :\S hi ve
\R ev it_ Lo ca l_
\2
0_
A2 2_
AD
O
T Sh an no n R d M
VD
_C
A M
O D
EL
_M ar cu s_ At ts on
.rv t
1/4" = 1'-0"
MA
JDM
ADOT TUCSON NORTH MVD REMODEL
7330 N SHANNON RD
TUCSON, AZ 85741
2172304350
SK-14
1/4" = 1'-0"1 ENLARGED FLOOR PLAN - ADDITION
ALUM STOREFRONT - ALIGN INTERIOR FACE
OF FRAME WITH INTERIOR FACE OF CMU
PROVIDE 3-5/8" FRAMING
PROVIDE METAL STUDS FURROUT TO ALIGN
WITH EXISTING WALL FURROUT
EXISTING CMU BLOCK TO REMAIN - AT FLUTED
PORTION OF CMU, CONTRACTOR SHALL REMOVE
FLUTE FOR INSTALLATION OF METAL STUDS
EXISTING CMU WALL TO REMAIN
EXISTING GWB WALL TO REMAIN
PATCH AND REPAIR DRYWALL TO MATCH
ADJACENT TEXTURE AND COLOR
PROVIDE PREFIN 20-GA ALUM BREAK METAL TRIM
ALONG JAMB OF STOREFRONT AS SHOWN -
WRAP BREAK METAL FOR WEATHERTIGHT
INSTALLATION - ALUM FINISH TO MATCH PAC-
CLAD SILVERSMITH
BACKER ROD AND SEALANT EA. SIDE OF
STOREFRONT
4330 N CAMPBELL AVE, STE #268
TUCSON, ARIZONA 85718
520.408.1044 | SHIVE-HATTERY.COM
DATE
DRAWN BY
APPROVED BY
SCALE
FIELD BOOK
REVISION
Au to de sk
R ev it
06-26-2025
PROJECT
NUMBER
6/
/2
7:
:4
AM
C :\S hi ve
\R ev it_ Lo ca l_
\2
0_
A2 2_
AD
O
T Sh an no n R d M
VD
_C
A M
O D
EL
_M ar cu s_ At ts on
.rv t
1 1/2" = 1'-0"
MA
JDM
ADOT TUCSON NORTH MVD REMODEL
7330 N SHANNON RD
TUCSON, AZ 85741
2172304350
SK-15
1 1/2" = 1'-0"1 ALUM STOREFRONT JAMB DETAIL
7330 N Shannon Rd Tucson, Arizona 85741
P: 602-499-8871
RFI #45: R.F.I. #045 Electrical Panels & Wall Thickness
Status Open
To Joel Mesik (Shive Hattery) From Kyle Burns (SD Crane Builders Inc.)
1215 W Rio Salado Pkwy #109 Tempe, Arizona 85281
Date Initiated Jun 13, 2025 Due Date Jun 17, 2025
Location Project Stage Course of Construction
Cost Impact Schedule Impact
Spec Section Cost Code
Drawing Number Reference
Linked Drawings
Received From
Copies To Tom Adamcik (SD Crane Builders Inc.), Marcus Attson (Shive Hattery), Melissa de la Gardelle (Shive Hattery), Andrew May (Arizona Department of Transportation), Jeff Murray (SD Crane Builders Inc.)
Activity
Question Question from Kyle Burns SD Crane Builders Inc. on Friday, Jun 13, 2025 at 06:48 AM MST Joel, For your review please see attached R.F.I. #045 Electrical Panels & Wall Thickness. Please advise.
Attachments R.F.I. #045 Electrical Panels & Wall Thickness.pdf
Awaiting an Official Response
All Replies Response from Marcus Attson Shive Hattery on Tuesday, Jun 24, 2025 at 01:54 PM MST See attached PDF for response.
Attachments R.F.I. #045 Electrical Panels & Wall Thickness_S-H Response.pdf
Page 1 of 1 Printed On: Jun 27, 2025 01:44 PM MST
RFI #045
Subject: Electrical Panels & Wall Thickness
Project Name: ADOT Tucson North MVD Building
Spec Sec: Addendum No:45
S.D. Crane Builders, Inc.
1901 E. University Drive Suite # 330
Mesa, Arizona 85203
Date: 6/13/25
Project Number: 24-322 Project Manager: Kyle Burns Superintendent: Jeff Murray
Submitted To: Joel Mesik Attn: Joel Mesik
Reference:
Information: Request:
A2.0
This RFI is regarding the panels M and L1. The panels measure 5.75” in depth and are called to be located in the corridor leading to the break room at the Employee Womens Restroom Wall which is a 3 5/8” steel framed wall. Is it acceptable to fur out this corridor wall with 1 5/8” steel studs to keep the drywall flush with the face of the panel cover? Please advise.
See drawing and photos attached.
Replying Company:
Name:
S.D. Crane Builders, Inc.
1901 E. University Drive Suite # 330
Mesa, Arizona 85203 Telephone (480) 832-1777 Fax (480) 832-1798 Commercial Roc#175959 Res.#ROC192686 scrane@sdcranebuilders.com
Cost Impact:
Schedule Impact:
Answer Required by: WSM Architects Request by: SD Crane Distribution: SD Crane
Response
Shive-Hattery
It is acceptable to furr-out the the corridor wall with 1-5/8" metal stud to provide the drywall flush with the face of electrical panels M and L1.
06/24/2025
7330 N Shannon Rd Tucson, Arizona 85741
P: 602-499-8871
RFI #46: R.F.I. #046 Ceiling in Storage Room 108
Status Open
To Joel Mesik (Shive Hattery) From Kyle Burns (SD Crane Builders Inc.)
1215 W Rio Salado Pkwy #109 Tempe, Arizona 85281
Date Initiated Jun 17, 2025 Due Date Jun 20, 2025
Location Project Stage Course of Construction
Cost Impact Schedule Impact
Spec Section Cost Code
Drawing Number Reference
Linked Drawings
Received From Kyle Burns (SD Crane Builders Inc.)
Copies To Tom Adamcik (SD Crane Builders Inc.), Marcus Attson (Shive Hattery), Melissa de la Gardelle (Shive Hattery), Andrew May (Arizona Department of Transportation), Jeff Murray (SD Crane Builders Inc.)
Activity
Question Question from Kyle Burns SD Crane Builders Inc. on Tuesday, Jun 17, 2025 at 07:03 PM MST Joel, For your review please see attached R.F.I. #046 Ceiling in Storage Room 108. Please advise.
Thank you, Attachments R.F.I. #046 Ceiling in Storage Room 108.pdf
Awaiting an Official Response
All Replies Response from Marcus Attson Shive Hattery on Tuesday, Jun 24, 2025 at 01:57 PM MST See attached PDF for response.
Attachments R.F.I. #046 Ceiling in Storage Room 108_S-H Response.pdf
Page 1 of 1 Printed On: Jun 27, 2025 01:59 PM MST
RFI #046
Subject: Ceiling in Storage Room 108
Project Name: ADOT Tucson North MVD Building
Spec Sec: Addendum No:46
S.D. Crane Builders, Inc.
1901 E. University Drive Suite # 330
Mesa, Arizona 85203
Date: 6/17/25
Project Number: 24-322 Project Manager: Kyle Burns Superintendent: Jeff Murray
Submitted To: Joel Mesik Attn: Joel Mesik
Reference:
Information: Request:
D2.2 & A2.2
This RFI is regarding the ceiling in storage room 108 and the area just outside the storage room by panel A. The RCP demo plan D2.2 calls for the existing ceiling to remain and the new RCP shows the ceiling to be a GWB hard lid and to remain at 7’. During Demo, our demo crew had removed the ACT in these areas and the existing ceiling height was 8’ with the ¾”X ¾” fry reglet shadow detail (see picture). Please provide direction on if this ceiling is to be reinstalled at 7’ or 8’ with ACT or if this area is to be framed in and GWB to be installed. This area is also calling for can lights and K3 surface mounted lighting just for reference. Please let me know if you have any questions.
Please see drawings and photo attached below, Thank you, Replying Company:
Name:
S.D. Crane Builders, Inc.
1901 E. University Drive Suite # 330
Mesa, Arizona 85203 Telephone (480) 832-1777 Fax (480) 832-1798 Commercial Roc#175959 Res.#ROC192686 scrane@sdcranebuilders.com
Cost Impact: Yes Schedule Impact:
Answer Required by: WSM Architects Request by: SD Crane Distribution: SD Crane
Response
Shive-Hattery
Contractor shall provide GWB ceiling in Storage Room 108 and the adjacent hallway. Fry reglet shadow detail trim shall be removed and ceiling shall be installed at 8' A.F.F. with 6" metal studs (30-mil) at 16" O.C.
06/24/2025
3 3
B
B
4 4
C
C
D
D
E
E
5 5
1 1
2 2
1 1
TYP. 7
NOTE: ALL ITEMS ARE EXISTING UNLESS NOTED OTHERWISE
SEE D2.0 DEMOLITION FLOOR PLAN AND D2.1 DEMO ROOF PLAN FOR ADDITIONAL NOTES
7 SEAL
AP
PR
O
VE
D B
Y
D R
AW
N
B Y
IS
SU
ED
F
O R
IS
SU
E D
AT
E
PR
O
JE
C
T N
U M
BE
R
FI
EL
D B
O O
K
A
B C D E F
A B C D E F Autodesk Revit 2022
N C
AM
PB
EL
L
AV
E, S
TE
TU
C
SO
N , A
R
IZ
O N
A
0.
8.
W
SM
AR
C H
.C O
M
4/ 9/
:0
7:
A M
C :\S hi ve
\R ev it_ Lo ca l_
\2
0_
A2 2_
AD
O
T Sh an no n R d M
VD
_C
EN
TR
AL
_M ar cu s_ At ts on
.rv t
D
EM
O
LI
TI
O
N R
C P
Ap pr ov er
AM
L, M A
D
EC
EM
BE
R
, 2
D2.2
AD
O
T
TU
C
SO
N N
O R
TH
M
VD
R
EM
O
D
EL
N S
H
AN
N O
N R
D
TU
C
SO
N , A
Z
1/8" = 1'-0"1 DEMOLITION REFLECTED CEILING PLAN
N
# KEYNOTES
1 DEMOLISH EXISTING ACT CEILING, LIGHTING AND HVAC DEVICES THIS AREA
2 DEMOLISH EXISTING METAL ROOFING AND STRUCTURE IN ITS ENTIRETY
3 EXISTING CEILING THIS AREA TO REMAIN, REMOVE LIGHTING AND HVAC
DEVICES, AND ANY ACCESS PANELS THIS AREA. PATCH AND REPAIR
DRYWALL AS REQUIRED.
4 DEMOLISH GWB CEILING, LIGHTING AND HVAC DEVICES, AND ANY ACCESS
PANELS THIS AREA
5 DEMOLISH EXTERIOR STUCCO CEILING AND LIGHTING THIS AREA
6 REMOVE EXISTING LIGHTING
8 EXISTING STORAGE SHED TO REMAIN
9 EXISTING FLAG POLE TO REMAIN - ELEVATION OF GRADE AT FLAGPOLE TO
REMAIN
10 DEMOLISH EXISTING GWB SOFFIT
GENERAL DEMOLITION NOTES
SEE 'GENERAL DEMOLITION NOTES' ON SHEET D2.0
DEMOLISHED DOOR BELOW - INFILL EXTERIOR WALL AT DEMOLISHED DOOR
SEAL
JOEL D.
MESIK
23507RE
G ISTERED ARCHITECT
C
ERT I F I CA T E
NO
Da t e S i g n e d
A R
I Z O N A U . S . A
3/28/2024
These plans and documents have been reviewed and found to be in compliance with the applicable code requirements of the jurisdiction Issuance of a permit is recommended subject to approval by other departments and any noted conditions. The stamping of these plans shall not be held to permit or be an approval of any violation of applicable codes and standards no relieve the owner, design professional of record or contractor of compliance with the applicable codes and standards. Plan review of documents does not authorize construction to proceed in violation of any federal, state, nor local regulation.
BUREAU VERITAS NORTH AMERICA, INC.
REVIEWED FOR CODE COMPLIANCE
SIGNATURE:____________________
DATE:_________________________04/19/2024
fmyers
Approved Plans & Specifications
WALL TO EXTEND TO DECK
RECESSED CAN
DOWNLIGHT LED
RECESSED 2x4 LED
WALL PACK LIGHT
2' X 2' ACT DROP CEILING
2' X 4' ACT DROP CEILING
GWB CEILING
LINEAR SUSPENDED
FIXTURE
EXIT SIGN
WALL TO EXTEND 6" ABOVE
ADJACENT CEILING
RETURN AIR GRILLE
SUPPLY AIR GRILLE
EXHAUST AIR GRILLE
WALL-MOUNTED DUCTLESS
UNIT
RCP LEGEND
GYPSUM BOARD CONTROL
JOINT
CEILING TYPE
CEILING HEIGHT
1t
SURFACE MOUNTED LIGHT
FIXTURE
INTERIOR CEILING MOUNTED
CCTV DOME - BY OWNER
EXTERIOR WALL MOUNTED
CCTV - BY OWNER
INTERIOR WALL MOUNTED
CCTV DOME - BY OWNER
MD MOTION DETECTOR - BY
OWNER
G.C.J.
ROOF ACCESS HATCH
(EXISTING)RA
SURACE MOUNTED LINEAR
LED
WALL MOUNTED LINEAR LED
18" X 18" ACCESS PANEL
SOFFIT PANELS - SMOOTH
SOFFIT PANELS - VENTED
A
A
3 3
B
B
4 4
A4.1
A4.0
C
C
D
D
E
E
5 5
1 1
2 2
ACT
9'-11"
A4.1
A4.0
OPEN TO
ABOVE -
SEE
DETAIL
2/A2.2
5' -2
/2
ETR
7'-0"
ETR
7'-0"
ETR
14'-0"
ETR
7'-0"
ETR
7'-0"
ETR
7'-0"
GWB
8'-4"
GWB
8'-4"
ACT
8'-6"
GWB
8'-0"
GWB
8'-4"
GWB
8'-4"
ACT
8'-6"
ACT
8'-4"
ACT
8'-6"
GWB
8'-0"
GWB
8'-0"
ACT
8'-4"
GWB
8'-6"
ACT
8'-0"
DIGITAL DISPLAY INDICATORS AT EACH WORKSTATION
(ALIGN WITH LIGHTING)
WIREMOLD POWER POLES TO SERVE EVERY 1-2 WORKSTATIONS
REPLACEMENT METAL ROOF
CANOPY
GWB
11'-8"
A9.0
A9.0
2'-2"
2' -2
2'-2"
GWB
8'-4"
14'-1"
'-0
ETR
7'-0"
5"
C L
EQ
EQ
CL3'-1 1/2"
CLCL
TYP.
5'-9 1/2"
SURFACE MOUNTED EXTERIOR
LED DOWNLIGHT, TYP OF 4
G .C
.J
G .C
.J
G .C
.J
G .C
.J
A8.3
A8.3
A8.3
A8.23
A8.2
A8.2
A8.3
A8.3
SIM.
A8.2
GWB
8'-0"
A9.0
1' -9
ETR
A5.0
A5.0
CCTV MOUNTED BELOW CANOPY
ROOF
MD
MD
MD
MD
MD
15'-5"
NONE
ACT
8'-6"
ACT
8'-6"
A7.0
A7.0
RA
A2.1
CABLE TRAY ABOVE CEILING
SHOWN DASHED
ACT
8'-6"
2' -2
1'-4"
2' -6
@ STOREFRONT
A2.1
6@ MTL
AWNING
A2.2
A2.2
9' -2
/2
B
B
4 4
A4.1
A4.0
21'-8"
'-2
/2
PREFINISHED METAL
SOFFIT PANELS,
CONCEALED FASTENERS
GWB ATTACHED TO
UNDERSIDE OF ROOF
JOISTS
ALUMINUM STOREFRONT
CLERESTORY WINDOWS
GWB
VARIES
PREFINISHED METAL
GUTTER & DOWNSPOUT
A7.0
A7.0
A7.0
2' -0
A7.0
2' -0
A8.2
TYP. @
JAMBS
A8.2
A8.2
CLCL
4'-10" 7'-0" 4'-10"
G.C.J.
ALIGN LIGHTS TO
CENTER OF MULLIONS,
TYP
SIM. - NO GWB
IN CHASE
SOFFIT VENT CALCULATION
SOFFIT AREA: 183.94 SF
REQUIRED: 1.23 SF
PROVIDED: 59.10 SF
C L C L
C O
LU
M
N S
7' -6
" T
YP
EQUALLY SPACED
17'-2" - [3] COLUMNS
3' -9
/2
3"
FACE OF WALL
1'-9" DIM TO
1'-1"
CL17'-8"
2'-0" DIM TO FACE OF WALL
SAME CONDITION @
NORTH BOX BEAM
B
A4.1
A4.0
JUSTIFY CENTER OF WALL
PANEL TO CENTER OF WALL
15'-5"
EXISTING
GLULAM BEAMS
(HIGH AND
LOW - TYP. 6)
TO REMAIN
METAL AWNING BELOW -
SEE DETAILS A2.1
EXISTING STEEL COLUMN TO
REMAIN
EXISTING
MASONRY
PARAPET BELOW
P1
EXISTING STEEL
COLUMN/GLULAM BEAM
ASSEMBLY TO REMAIN
EXISTING STEEL
COLUMN/GLULAM
BEAM ASSEMBLY TO
REMAIN
O
VE
R [E
] P
AR
AP
ET
'-7
FU
R
R O
U T
OVER [E] PARAPET
18'-4" +/- FURROUT
WALL MOUNTED
SCONCE LIGHT
FIXTURE
(UP/DOWN LIGHTS)
@ 11'-0"
NOTE: NEW WALLS
SHOWN GRAY FOR
CLARITY
EXISTING STEEL
COLUMN TO REMAIN
EXISTING STEEL
COLUMN TO REMAIN
JUSTIFY CENTER OF WALL
PANEL TO CENTER OF WALL
EQ.
CL
DOWNSPOUT AND
PRECAST CONC
SPLASH BLOCK @
ROOF
EQ.
E2
E2
E3
E3
SEE DETAIL 2/A2.2 FOR
CLERESTORY RCP
SEAL
AP
PR
O
VE
D B
Y
D R
AW
N
B Y
IS
SU
ED
F
O R
IS
SU
E D
AT
E
PR
O
JE
C
T N
U M
BE
R
FI
EL
D B
O O
K
A
B C D E F
A B C D E F Autodesk Revit 2022
N C
AM
PB
EL
L
AV
E, S
TE
TU
C
SO
N , A
R
IZ
O N
A
0.
8.
W
SM
AR
C H
.C O
M
4/ 9/
:0
6:
A M
C :\S hi ve
\R ev it_ Lo ca l_
\2
0_
A2 2_
AD
O
T Sh an no n R d M
VD
_C
EN
TR
AL
_M ar cu s_ At ts on
.rv t
R
EF
LE
C
TE
D
C
EI
LI
N
G P
LA
N
Ap pr ov er
AM
L, M A
D
EC
EM
BE
R
, 2
A2.2
AD
O
T
TU
C
SO
N N
O R
TH
M
VD
R
EM
O
D
EL
N S
H
AN
N O
N R
D
TU
C
SO
N , A
Z
1/8" = 1'-0"1 REFLECTED CEILING PLAN
GENERAL RCP NOTES
A. ALL INTERIOR PARTITION WALLS TO EXTEND FULL HEIGHT TO DECK ABOVE, U.N.O.
B. ALL EXPOSED BEAMS, DUCTWORK, CONDUIT, PIPING, AND METAL DECK SHALL BE
PAINTED.
C. PROVIDE ACCESS PANELS IN GYPSUM BOARD CEILINGS AT ALL LOCATIONS OF
MECHANICAL UNITS, PLUMBING VALVES, AND ELECTRICAL JUNCTION BOXES AND
DISCONNECT SWITCHES. REFER TO MECHANICAL AND ELECTRICAL DRAWINGS
FOR EXACT LOCATIONS AND QUANTITIES. PAINT TO MATCH CEILING.
D. IF ANY CONFLICTS IWTH SPECIFIED CEILING HEIGHTS ARISE FROM INSTALLED
LOCATIONS OF MECHANICAL, PLUMBING, OR ELECTRICAL SYSTEMS OR IF CEILING
HEIGHTS ARE NOT SPECIFIED, CONTACT ARCHITECT IMMEDIATELY FOR
RESOLUTION, PRIOR TO COMMENCING ANY WORK.
E. PROVIDE SEISMIC BRACING FOR SUSPENDED CEILING SYSTEM.
F. ALL WALLS IN ROOMS WITH EXPOSED STRUCTURE SHALL BE FULL HEIGHT AND
SEALED TO DECK ABOVE.
G. PROVIDE CONTROL JOINTS IN GWB PARTITIONS EXCEEDING 30'-0" IN LENGTH
N
1/8" = 1'-0"2 REFLECTED CEILING PLAN - HIGH ROOF AT ENTRY N
1/8" = 1'-0"3 REFLECTED CEILING PLAN - HIGH ROOF AT ENTRY N
UP TO 18'-0" A.F.F.ABOVE 18'-0" A.F.F.
SEAL
JOEL D.
MESIK
23507RE
G ISTERED ARCHITECT
C
ERT I F I CA T E
NO
Da t e S i g n e d
A R
I Z O N A U . S . A
3/28/2024
These plans and documents have been reviewed and found to be in compliance with the applicable code requirements of the jurisdiction Issuance of a permit is recommended subject to approval by other departments and any noted conditions. The stamping of these plans shall not be held to permit or be an approval of any violation of applicable codes and standards no relieve the owner, design professional of record or contractor of compliance with the applicable codes and standards. Plan review of documents does not authorize construction to proceed in violation of any federal, state, nor local regulation.
BUREAU VERITAS NORTH AMERICA, INC.
REVIEWED FOR CODE COMPLIANCE
SIGNATURE:____________________
DATE:_________________________04/19/2024
fmyers
Approved Plans & Specifications
Romanoski Glass & Mirror
CHANGE ORDER FORM
Phone: (520) 748-05000 psmith@romanoskiglass.com From: Paul Smith, Estimator
To: Concord Date: 07 11 25 Project: MVD Tucson North Subject: Aluminum Brake Metal Trim ADD per SK-14 No. 1 (Left Jamb Condition)
Attention: Jeff Murray Regarding:
C/O Proposal – This Change Order Proposal Includes:
Aluminum Brake Metal Trim ADD per Detail Per SK-14 No. 1 (Left Jamb Condition), requiring aluminum brake metal trim at (3-Locations.)
Includes (3-each) 1” X 4” X 1” X 98” Tall, (.063”) THICK “C” channel shape.
Clear Anodized Exposed Finish. Installed Complete at AL2, AL3 and AL5.
Complete installation in Place for the Sum of: $830.00, Tax Excluded.
Thanks!
Any questions, please hit me back.
Respectfully, Paul A. Smith Estimator/Project Manager/Drafting/Design 520-748-0500
Received by: ________________________________
Date: _________________ SHEET 1 OF 1
405 S. CLARK DR.
TEMPE, AZ 85288
PHONE: 480-951-4169
AZ ROC #339524 KB-1
Page | 1
Delivering On-time, On-Budget, and On-Satisfaction Results—Always
Date: Wednesday, July 2, 2025
Proposal to: SD Crane Project: ADOT Tucson MVD North Kyle Burns 7330 N Shannon Rd.
1215 W. Rio Salado Pkwy. #109 Tempe, AZ 85281
Tucson , AZ 85741
Phone: 480-832-1777 Architect:
Fax: Plan Date: Wednesday, July 2, 2025
SCOPE OF WORK: Metal Stud & Drywall
Scope per ASI #07,RFI #45, RFI #46
EXCLUSIONS:
▪ Hot mud or fast set mud and additional man hours required for its installation
▪ Prevailing Wages not used
▪ Payment of bonds premiums, permits & licenses
▪ Any WRAP insurance program premium that may be in place
▪ Dumpster for debris removal to be provided by others at no charge to Design
▪ Heat, lights, water, power, ventilation, and weather protection
▪ Responsibility for the drawings meeting requirements of codes, ordinances or design
▪ Shop drawings, engineering or laboratory testing
▪ State and local taxes; require AZ Form 5005 (AZ Dept. Revenue Prime Contractors Cert.)
▪ Overtime work and off hours work
▪ Supply, receiving and distribution of all frames, door and components
▪ Any and all fire safeing or caulking, except as noted above.
▪ Any and all acoustical caulking, except as noted above.
▪ Access panels, doors
▪ Backing for any & all trades, except as noted above
▪ Insulation, Vapor barriers, or Vapor Retarders, except as noted above.
▪ Any tape, sealant, caulking, or weather barrier at exterior sheathing
▪ Wood carpentry and substrates, except as noted above
▪ Painting or priming of drywall before texture
BASE BID AMOUNT (Metal Studs & Drywall) $6,157 TPT Tax $
Pricing effective on material and labor provided prior to .
Note: This proposal may be withdrawn by us if not accepted within 30 days.
Page | 2
Date: 7/2/2025
All material is guaranteed to be as specified. All work to be completed in a workmanlike manner according to standard practices. Any alteration or deviation from above specification involving extra costs will be executed only upon written orders and will become an extra charge over and above the estimate. All agreements contingent upon strikes, accidents or delays beyond our control. Owner to carry fire, tornado and other necessary insurance. Our workers are fully covered by Workmen’s Compensation Insurance.
Authorized Signature
Victor Loera
Note: This proposal may be withdrawn by us if not accepted within 30 days.
Acceptance of Proposal The above prices, specifications and conditions are satisfactory and are hereby accepted. Acceptance constitutes Design Drywall West, Inc as sub-contractor, acceptor as responsible for all sales taxes.
Signature
Date:
| CTR075036 Contract Amendment Summary 6 |
| CTR075036 Change Order 06 |
File details come from the government source that posted it. Updated .