CTR064774_Contract_Amendment_4.pdf

PDF 7 MB Posted

Attached to
Master Agreement AZ|CTR064774
Contract number
CTR064774
Issued by
Arizona

About this file

This document is a Contract Amendment Summary from the Arizona Department of Transportation (ADOT) for P3 Program Management Services, involving HDR Engineering Inc. as the primary contractor and KPMG as a subconsultant. The amendment, numbered 4, pertains to federally funded contracts and includes the addition of six key personnel across HDR and KPMG, as well as the introduction of a new subconsultant, Jana Kading PLLC dba K2 Site Assessment.

The contract is being extended from March 3, 2024, through March 2, 2025, with all other terms and conditions remaining unchanged. The added personnel include Laura Rios and Bryce Coffey (Planners), Marisa Maez (Senior Planner), Nick LaFronz (Senior Consultant), Neil Richards (Senior Consultant) from HDR, and Brandon Niday (Senior Financial Analyst) from KPMG. The proposed billing rates for these new staff members range from $100 to $375 per hour, with roles primarily focused on public outreach, communications, geotechnical support, construction oversight, and program support and analysis.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ARIZONA DEPARTMENT OF TRANSPORTATION

1655 W. Jackson Street, MD 100P

Phoenix, AZ 85007 602.712.7211

Contract Amendment Summary CONTRACTOR: HDR Engineering Inc AMENDMENT NO.: 4 DESCRIPTION: P3 Program Management Services – Federal Funded

Rev. 04/2020

Procurement

Pursuant to the Uniform Terms and Conditions, Section 5, Contract Changes, the above referenced contract is amended. Summary of changes is as follows:

1. The following Key Personnel are hereby added:

HDR Engineering Inc:

Laura Rios, Planner Bryce Coffey, Planner Marisa Maez, Senior Planner Nick LaFronz, Senior Consultant Neil Richards, Senior Consultant

KPMG:

Brandon Niday, Senior Financial Analyst

2. The following firm is hereby added as a subconsultant:

Jana Kading PLLC dba K2 Site Assessment

3. This contract is hereby mutually extended from March 3, 2024 through March 2, 2025 unless terminated, canceled or extended as otherwise provided in the contract.

4. All other terms, conditions and provisions of this contract remain unchanged.

CTR064774 Contract Amendment 4
CTR064774 Contract Amendment 4
20231121_Staff approval request_signed

Subconsltant addition letter_K2_20231020 w Resume_signed

File details come from the government source that posted it. Updated .