This document is a Contract Amendment Summary from the Arizona Department of Transportation (ADOT) for P3 Program Management Services, involving HDR Engineering Inc. as the primary contractor and KPMG as a subconsultant. The amendment adds several key personnel from HDR and KPMG, including Laura Rios, Bryce Coffey, Marisa Maez, Nick LaFronz, Neil Richards, and Brandon Niday. Additionally, Jana Kading PLLC dba K2 Site Assessments is being added as a new subconsultant to the contract.

The contract is being extended from March 3, 2024, through March 2, 2025, with no changes to other terms and conditions. The proposed staff have various roles including planners, senior planners, senior consultants, and a senior financial analyst, with proposed rates ranging from $100 to $375 per hour. The contract appears to be for state-funded program management services, with the added personnel expected to support various transportation-related projects and initiatives, including public outreach, communications, geotechnical support, construction oversight, and program analysis for the Arizona Department of Transportation.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ARIZONA DEPARTMENT OF TRANSPORTATION

1655 W. Jackson Street, MD 100P

Phoenix, AZ 85007 602.712.7211

Contract Amendment Summary CONTRACTOR: HDR Engineering Inc AMENDMENT NO.: 4 DESCRIPTION: P3 Program Management Services – State Funded

Rev. 04/2020

Procurement

Pursuant to the Uniform Terms and Conditions, Section 5, Contract Changes, the above referenced contract is amended. Summary of changes is as follows:

1. The following Key Personnel are hereby added:

HDR Engineering Inc:

Laura Rios, Planner Bryce Coffey, Planner Marisa Maez, Senior Planner Nick LaFronz, Senior Consultant Neil Richards, Senior Consultant

KPMG:

Brandon Niday, Senior Financial Analyst

2. The following firm is hereby added as a subconsultant:

Jana Kading PLLC dba K2 Site Assessments

3. This contract is hereby mutually extended from March 3, 2024 through March 2, 2025 unless terminated, canceled or extended as otherwise provided in the contract.

4. All other terms, conditions and provisions of this contract remain unchanged.

CTR064771 Contract Amendment 4
CTR064771 Contract Amendment 4
20231121_Staff approval request_signed

Subconsltant addition letter_K2_20231020 w Resume_signed

File details come from the government source that posted it. Updated .