CR 15 Trail Bid Schedule.xlsx
XLSX spreadsheet 28 KB Posted
- Attached to
- CR 15 Trail
- Solicitation number
- TOW-PRC-2025-52
- Issued by
- Colorado
About this file
The document is a bid schedule spreadsheet for the CR 15 Trail project issued by the Town of Windsor Parks, Recreation and Culture Department in Colorado, detailing a construction contract for approximately 1.3 miles of 10-foot wide concrete trail connecting Harmony Road to an existing trail and Windsor's new Middle School. The bid schedule comprehensively lists 44 line items covering various construction activities including clearing and grubbing, excavation, erosion control, concrete work, pipe installation, road base preparation, asphalt work, surveying, and traffic management. The project involves multiple construction elements such as concrete bikeway construction (spanning 7,571 square yards), aggregate base course installation (2,567 tons), erosion control measures, and infrastructure components like box culverts, curb ramps, and drainage systems.
The bid schedule indicates a lump sum contract approach with unit pricing for specific activities, allowing flexibility in project execution. The total project scope suggests a comprehensive trail construction project with detailed specifications for each construction phase. Quantities are precisely defined for each line item, enabling accurate cost estimation, with key items including unclassified excavation (1,709 cubic yards), topsoil stockpiling (1,360 cubic yards), and native seeding (1.37 acres). Additional elements like mobilization, construction surveying, traffic control management, and various force account adjustments are included, indicating a complex infrastructure development project with multiple technical and administrative components.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CR 15 Trail Bid Schedule.pdf | ||
| CR 15 Trail Specs.pdf | ||
| Project Manual - CR15.pdf | ||
| CR 15 Plan Set 09032025.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COST EST. (UPDATE HERE)
BID SCHEDULE
ITEM NO. SECTION NUMBER CONTRACT ITEM UNIT UNIT COST QUANTITY COST
| 1 | 201-00000 | Clearing & Grubbing | LS | 1 |
| 2 | 202-00010 | Removal of Tree | EACH | 2 |
| 3 | 202-00203 | Removal of Curb and Gutter | LF | 202 |
| 4 | 202-00220 | Removal of Asphalt Mat | SY | 16 |
| 5 | 203-00010 | Unclassified Excavation (Complete In Place) | CY | 1,709 |
| 6 | 203-00050 | Unsuitable Material | CY | 50 |
| 7 | 203-00510 | Rock Fill (Special) | CY | 50 |
| 8 | 203-01500 | Blading | HR | 10 |
| 9 | 203-01597 | Potholing | HR | 20 |
| 10 | 203-02330 | Laborer | HR | 40 |
| 11 | 207-00210 | Stockpile Topsoil | CY | 1,360 |
| 12 | 208-00023 | Erosion Log Type 3 (12 Inch) | LF | 7,258 |
| 13 | 208-00046 | Pre-fabricated Concrete Washout Structure | EACH | 2 |
| 14 | 208-00075 | Pre-fabricated Vehicle Tracking Pad | EACH | 2 |
| 15 | 208-00106 | Sweeping (Sediment Removal) | HR | 15 |
| 16 | 208-00207 | Erosion Control Management | DAY | 25 |
| 17 | 210-01011 | Reset Gate | EACH | 2 |
| 18 | 212-00006 | Seeding (Native) | ACRE | 1.37 |
| 19 | 212-00032 | Soil Conditioning | ACRE | 1.37 |
| 20 | 213-00002 | Mulching (Weed Free Hay) | ACRE | 1.37 |
| 21 | 213-00061 | Mulch Tackifier | LB | 270 |
| 22 | 304-06000 | Aggregate Base Course (Class 6) | TON | 2,567 |
| 23 | 306-01000 | Reconditioning | SY | 8,327 |
| 24 | 403-00721 | Hot Mix Asphalt (Patching)(Asphalt) | SY | 24 |
| 25 | 403-33752 | Hot Mix Asphalt (Grading S)(75)(PG 64-28) | SY | 265 |
| 26 | 504-00000 | Concrete Class D (Wall) Reinforced | CY | 13 |
| 27 | 603-01185 | 18 Inch Reinforced Concrete Pipe (Complete in Place) | LF | 24 |
| 28 | 603-50018 | 18 Inch Plastic Pipe | LF | 20 |
| 29 | 603-05018 | 18 Inch Reinforced Concrete End Section | EACH | 2 |
| 30 | 603-71004 | 10x4 Foot Concrete Box Culvert (Precast) | LF | 88 |
| 31 | 608-00010 | Concrete Curb Ramp | SY | 16 |
| 32 | 608-00026 | Concrete Bikeway (6 Inch) | SY | 7,483 |
| 33 | 608-00028 | Concrete Bikeway (8 Inch) | SY | 88 |
| 34 | 608-10000 | Sidewalk Drain | LF | 60 |
| 35 | 514-00100 | Handrail | LF | 262 |
| 36 | 609-21010 | Curb and Gutter Type 2 (Section I-B) | LF | 480 |
| 37 | 620-00020 | Sanitary Facility | EACH | 1 |
| 38 | 625-00000 | Construction Surveying | LS | 1 |
| 39 | 626-00000 | Mobilization | LS | 1 |
| 40 | 630-00012 | Traffic Control Management | LS | 1 |
| 41 | 700-70010 | F/A Minor Contract Revisions | FA | 1 |
| 42 | 700-70016 | F/A Fuel Cost Adjustment | FA | 1 |
| 43 | 700-70380 | F/A Erosion Control | FA | 1 |
| 44 | 700-70381 | F/A Work on Harmony | FA | 1 |
| BID TOTAL: |
File details come from the government source that posted it. Updated .