CN-370000-CN808-T3.pdf
PDF 582 KB Posted
- Contract number
- CN808
- Issued by
- Florida
About this file
This Consultant's Task Assignment Notification is issued by the Florida Department of Environmental Protection (FDEP), Division of Recreation and Parks, to George and Associates Consulting Engineers, Inc. for work on the Edward Ball Wakulla Springs State Park HVAC Injection Well and Tower project (Project 61530). The contract number is CN808, expiring December 18, 2029, and this specific task assignment is TA3, effective February 15, 2025 through February 15, 2026. James Petersen, PE, serves as the consultant's representative, with Vu Nguyen as the FDEP contract manager and Don Finkbeiner as the project manager.
The task involves moving subtasks 1g, 5a, and 5b from a previous contract (CN214 TA47) to CN808 TA3 per the proposal dated January 31, 2025. Work encompasses three subtasks: (1) Lead and Asbestos Testing conducted by Southern Earth Sciences, Inc., including NESHAPS demolition survey and lead-based paint analysis ($889.00); (2) Site Visit Inspection by George & Associates for construction progress review and documentation ($1,103.64); and (3) Substantial Completion Inspection including a punch list for final completion ($1,103.64). The total fixed-price task amount is $3,096.28 with no cost reimbursement authorization. All encumbered costs are charged to Project 61530, Grant 37501011204, under Organization Code 080039/22, Fund 423001, Module U3100, Object 131500. Payment is contingent upon FDEP approval of deliverables for each subtask.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-370000-CN808-T14.pdf | ||
| CN-370000-CN808-T15.pdf | ||
| CN-370000-CN808-T4.pdf | ||
| CN-370000-CN808-T6CO1.pdf | ||
| CN-370000-CN808-T7.pdf | ||
| PC-370000-CN808.pdf | ||
| CN-370000-CN808-T11.pdf | ||
| CN-370000-CN808-T2CO1.pdf | ||
| CN-370000-CN808-T6CO2.pdf | ||
| CN-370000-CN808-T8.pdf | ||
| CN-370000-CN808-T9.pdf | ||
| CN-370000-CN808-T10.pdf | ||
| CN-370000-CN808-T2.pdf | ||
| CN-370000-CN808-CMC1.pdf | ||
| CN-370000-CN808-T1.pdf | ||
| CN-370000-CN808-T12.pdf | ||
| CN-370000-CN808-T13.pdf | ||
| CN-370000-CN808-T1CO1.pdf | ||
| CN-370000-CN808-T5.pdf | ||
| CN-370000-CN808-T6.pdf | ||
| CN-370000-CN808.pdf |
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FLORIDAA DEPARTMENTT OFF
ENVIRONMENTALL PROTECTION
Divisionn off Recreationn andd Parkss
Consultant’ss Taskk Assignmentt Notification
FDEP Contract No Contract Expiration Task Assignment No
Project Location Project
Consultant’s Name:
Consultant’s Representative:
Phone: Email:
FDEP Contract Manager:
Phone: Email:
Task Description:
Project Manager:
Schedule:
Start Date: Completion Date:
Fixed Price Cost: Cost Reimbursement not to exceed:
Total Task Amount:
Signatures and Date:
1.
Contract Manager, FDEP Signature Date
2.
Project Manager, FDEP Signature Date
3.
Budget Representative, FDEP Signature Date
4.
Consultant Signature Date
5.
Contract Authority, FDEP Signature Date
DRP-084
Rev. 08/07/2020 1 of 2
Da mb at
P
Moving subtasks 1g, 5a, and 5b from CN214 TA47 to CN808 TA3 per the attached proposal dated 1/31/2025. CN214 rates are indicated with an *.
CN808 12/18/2029
Wakulla Springs HVAC Injection Well & Tower 61530
George and Associates Consulting Engineers, Inc James Petersen, PE
850-521-0344 jpeterson@gaceng.net
Vu Nguyen 850-245-2630 vu.nguyen@floridadep.gov
Don Finkbeiner
2/15/2025 2/15/2026 $3,096.28 0
$3,096.28
Vu Nguyen Vu Nguyen Digitally signed by Vu Nguyen Date: 2025.02.11 14:46:37 -05'00'
Donald Finkbeiner Donald J. Finkbeiner Digitally signed by Donald J. Finkbeiner Date: 2025.02.06 09:32:09 -05'00'
Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2025.02.04 09:28:42 -05'00'
James Peterson Digitally signed by JAMES H PETERSON DN: c=US, o=Unaffiliated, dnQualifier=A01410C0000019104FE2A2700077AFF, cn=JAMES
H PETERSON
Date: 2025.02.12 08:45:43 -05'00'
Michael W. Foster Jr., P.E. Michael W. Foster Jr., P.E. Digitally signed by Michael W. Foster Jr., P.E.
Date: 2025.02.14 08:32:55 -05'00'
TA3
FFLORIDAA DEPARTMENTT OF Divisionn off Recreationn andd Parks ENVIRONMENTALL PROTECTIONN Consultant’s Task Assignment Notification
Encumbrance Information:
Project # Grant # Organization Code Category/Yr Fund Module Object EO Amount
Total
DRP-084
Rev. 08/07/2020 2 of 2
61530 37501011204 080039/22 423001 U3100 131500 QK $3,096.28
$3,096.28
1967 COMMONWEALTH LANE, SUITE 200 - TALLAHASSEE, FLORIDA 32303
PHONE 850-521-0344 - FAX 850-521-0345
www.gaceng.net CIVIL ENGINEERING - LAND USE PLANNING - ENVIRONMENTAL - SYSTEMS PLANNING - TRANSPORTATION
January 31, 2025
Don Finkbeiner Construction Project Consultant II Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard, MS 520 Tallahassee, FL 32399
RE: CN808-TA___: Edward Ball Wakulla Springs State Park – HVAC Injection Well
For your review, George & Associates, Consulting Engineers, Inc. has prepared a fee proposal summary and man-hour documentation for the proposed Edward Ball Wakulla Springs State Park – HVAC Injection Well Project for the design and permitting phase. Tasks include field data gathering, surveying, permitting and construction planning documents.
Please review the attached Proposal Summary and deliverables.
Sincerely, James H. Peterson IV, P.E.
George & Associates, Consulting Engineers, Inc.
Wakulla Springs HVAC Injection Well
CN808 -TA__
Subtask 1: Lead & Asbestos Testing Description: Southern Earth Sciences, Inc. (SESI) proposes to perform an Asbestos NESHAPS Demolition Survey (40 CFR Part 61) for the identified Lodge terracotta drainpipe & above ground features identified for potential removal at Edward Ball Wakulla Springs State Park.
SESI will perform bulk sampling of accessible portions of the terracotta pipe & above ground features (suspect materials) following the AHERA Sample Protocol and send the samples to a NVLAP Laboratory for bulk PLM Analysis.
SESI will sample painted surfaces using a Heuresis Pb200i Lead Analyzer (XRF) for Lead Based Paint (LBP). SESI will issue a brief report with the identified ACM present, approximate quantities, locations and appropriate actions for renovation. LBP will be summarized, and suggestions provided regarding the handling and disposal of these materials.
Deliverables:
• Asbestos & Lead-Paint Survey Report, pdf
Performance Measures: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Total Subtask 1 Costs:
Subtask 1: Lead & Asbestos Testing
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost Southern Earth Sciences Asbestos Consultant $127.00 7 $889.00
Fixed Price Total Cost: $889.00 Total for Subtask 1: $889.00
Subtask 2: Site Visit Inspection Description: G&A will make a site visit during construction at the BDC’s request to review ongoing construction progress. Inspection to include review of construction to date. On-going documentation in the form of photos, field notes and/or recommendations to be provided after each site visit.
Deliverable:
• Construction progress report, pdf
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 2: Site Visit Inspection
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
George & Associates Project Manager $129.00 5 $645.00 Project Engineer II $76.44 6 $458.64
Fixed Price Total Cost: $1,103.64 Total for Subtask 2: $1,103.64
Subtask 3: Substantial Completion Inspection Description: Attend one Substantial Completion Meeting to review the completed improvements upon request by the BDC and upon notification of substantial completion of the civil related work.
A report will be prepared with the recommendations considering the project substantially complete or not. A punch list of any remaining minor deficiencies that are noted during the visit will be created to serve as the punch list for final completion. Any applicable project closeout that can be submitted to the FDEP Regional office will be done at this time.
Deliverable:
• Provide substantial completion punch list, pdf
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 3: Substantial Inspection
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
George & Associates Project Manager $129.00 5 $645.00 Project Engineer II $76.44 6 $458.64 Fixed Price Total Cost: $1,103.64 Total for Subtask 3: $1,103.64
Summary of Fees:
Subtask Subtask Fixed Price Cost
Subtask Reimbursable
Subtask 1: Lead & Asbestos Testing $889.00 Subtask 2: Site Visit Inspection $1,103.64 Subtask 3: Substantial Inspection $1,103.64
Total Fixed Cost: $3,096.28 Overall Total Cost: $3,096.28
Project Schedule:
Activity Duration (calendar days) Dates
Subtask 1: Lead & Asbestos Testing 35 Concurrent with Utility Survey of Existing HVAC Discharge Lines (Southeastern Surveying)
Subtask 2 & 3: Construction Administration TBD
* - Does not include FDEP review time from previous phases or submittals that may require feedback to proceed.
Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.