Summary

This document is a Consultant's Task Assignment Notification (Form DRP-084) issued by the Florida Department of Environmental Protection (FDEP), Division of Recreation and Parks, for Contract CN808 with an expiration date of December 19, 2029. The assignment, designated as Task Assignment 1 (TA1), engages George and Associates Consulting Engineers, Inc. (represented by Robert George, PE) to provide design and permitting services for the Florida Caverns State Park New Campground project located in Florida. The FDEP Contract Manager is Vu Nguyen, and the Project Manager is Theresa Carron. This task involves relocating subtasks from a previous contract (CN214 TA37) to the continuing services contract CN808 using established rates per an attached proposal dated January 21, 2025.

The contract scope encompasses 14 subtasks including utility surveying, field services review, fire code compliance analysis, environmental resource permitting, municipal permitting, construction plan development at 90% and 100% design phases, State Fire Marshal permit applications, building permit services, Florida Historical Marker applications, and a putting green planning exhibit. The total task amount is $187,802.85, comprised of $181,552.85 in fixed price costs and $6,250.00 in reimbursable costs. The schedule runs from January 30, 2025, to January 30, 2026, with payment to be made upon FDEP approval of deliverables for each subtask. The work involves multiple subconsultants including Southeastern Surveying and Mapping Corp., Dodstone Architects, FSM Engineering, Applied Research & Design, Bliss & Niytray, Chronicle Heritage, and FELSI.

View the file

Other files

File Type Posted
CN-370000-CN808-T10.pdf PDF
CN-370000-CN808-T2.pdf PDF
CN-370000-CN808-T14.pdf PDF
CN-370000-CN808-T15.pdf PDF
CN-370000-CN808-T4.pdf PDF
CN-370000-CN808-T6CO1.pdf PDF
CN-370000-CN808-T7.pdf PDF
PC-370000-CN808.pdf PDF
CN-370000-CN808-T11.pdf PDF
CN-370000-CN808-T2CO1.pdf PDF
CN-370000-CN808-T6CO2.pdf PDF
CN-370000-CN808-T8.pdf PDF
CN-370000-CN808-T9.pdf PDF
CN-370000-CN808-CMC1.pdf PDF
CN-370000-CN808-T12.pdf PDF
CN-370000-CN808-T13.pdf PDF
CN-370000-CN808-T1CO1.pdf PDF
CN-370000-CN808-T3.pdf PDF
CN-370000-CN808-T5.pdf PDF
CN-370000-CN808-T6.pdf PDF
CN-370000-CN808.pdf PDF
Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FLORIDADEPARTMENTOF

ENVIRONMENTALPROTECTION

Division of Recreation and Parks

Consultant’s Task Assignment Notification

FDEP Contract No Contract Expiration Task Assignment No

Project Location Project

Consultant’s Name:

Consultant’s Representative:

Phone: Email:

FDEP Contract Manager:

Phone: Email:

Task Description:

Project Manager:

Schedule:

Start Date: Completion Date:

Fixed Price Cost: Cost Reimbursement not to exceed:

Total Task Amount:

Signatures and Date:

1.

Contract Manager, FDEP Signature Date

2.

Project Manager, FDEP Signature Date

3.

Budget Representative, FDEP Signature Date

4.

Consultant Signature Date

5.

Contract Authority, FDEP Signature Date

DRP-084

Rev. 08/07/2020 1 of 2 tion Date:

Cost Reimbursement not to exceed:

Date:

Contract Manager, FDEP

FLORIDA DEPARTMENT OF Division of Recreation and Parks

ENVIRONMENTAL PROTECTION Consultant’s Task Assignment Notification

Encumbrance Information:

Project # Grant # Organization Code Category/Yr Fund Module Object EO Amount

Total

DRP-084

Rev. 08/07/2020 2 of 2

1967 COMMONWEALTH LANE, SUITE 200 - TALLAHASSEE, FLORIDA 32303

PHONE 850-521-0344 - FAX 850-521-0345

www.gaceng.net CIVIL ENGINEERING - LAND USE PLANNING - ENVIRONMENTAL - SYSTEMS PLANNING - TRANSPORTATION

January 21, 2025

Theresa Carron Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard 260K, MS 520 Tallahassee, FL 32399

RE: CN808 TA1: Florida Caverns State Park � New Campground

For your review, George & Associates, Consulting Engineers, Inc. has prepared a fee proposal summary and staff hour documentation for the proposed Florida Caverns State Park � New Campground Project design and permitting phase. Tasks include field data gathering, surveying, permitting, and construction planning documents.

Please review the attached Proposal Summary and deliverables.

Sincerely, Clay Courson George & Associates, Consulting Engineers, Inc.

www.gaceng.net CIVIL ENGINEERING - LAND USE PLANNING - ENVIRONMENTAL - SYSTEMS PLANNING - TRANSPORTATION

Florida Caverns State Park New Campground

CN808 TA1

Subtask 1: Utility Survey Description: Southeastern Surveying and Mapping Corp. (SSMC) will provide Subsurface Utility Designation Services on the project. This includes reviewing the proposed project area for existing utilities via desktop review of available information and then a site specific survey of utilities along Caverns Road, in the proposed campground area, and existing pressure water/sewer lines. SSMC will also perform utility designation and test holes on Caverns Road and within the park at areas to be affected by the work.

Utility Designation & Verification (Test Holes):

1. Horizontally locate and field mark (paint & flags) all public subsurface utility mains found excluding gravity sewer lines and irrigation in the project area.

2. Coordinate Sunshine 811 and utility locates to include supplemental calls to each locator to expedite the field marking of each subsurface utility as required by law.

3. Expose the subject utilities by using non destructive vacuum excavation methods at up to eight (8) specific locations as directed by the engineer.

4. Confirm/determine the vertical and horizontal position of the subject utilities and record the information, using the locate marks provided by the utility owners and/or their representatives unless otherwise requested by client.

5. Any asphalt/concrete removed will be repaired using like materials.

6. Tie each test hole location to a minimum of three visible physical features to enable this data to be added to the survey.

7. Provide project management and coordination throughout the duration of all field activities.

Deliverables:

Test hole reports/sketches, .pdf

Performance Measures: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Total Subtask 1 Costs:

Subtask 1: Utility Survey

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

Southeastern Surveying Surveyor & Mapper PSM $101.64 6 $609.84 Survey/CADD. Technician $67.06 7 $469.42 5 Person Survey Crew Rate $244.45 54 $13,200.30

$14,279.56 Total for Subtask 1: $14,279.56 www.gaceng.net CIVIL ENGINEERING - LAND USE PLANNING - ENVIRONMENTAL - SYSTEMS PLANNING - TRANSPORTATION

Subtask 2: Survey and Field Services Review Description: George & Associates (G&A) will visit the site to confirm/review the topographic survey, environmental survey limits, and geotechnical boring locations. A field report detailing our findings or noting any discrepancies with the data gathered will be provided.

Deliverable:

Field Report, pdf

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Total Subtask 2 Costs:

Subtask 2: Survey and Field Services Review

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

George & Associates Senior Engineer 1 $180.00 11 $1,980.00 Engineer 1 $114.00 12 $1,368.00

Fixed Price Total Cost: $3,348.00 Total for Subtask 2: $3,348.00

Subtask 3: National Fire Protection Association (NFPA) 1 18 Resolution Description: Dodstone and FSM Engineers (FSM) will assist G&A in determining what will be required to address NFPA1 18 at this location for fire code requirements by the local fire department/Authority Having Jurisdiction (AHJ). Tasks include review of nearby available water flow and whether or not it will be sufficient. Dodstone will contact the local fire chief to determine if they have any water tankers that are sufficient to serve this location, or if alternate means such as extending a 6� line to serve a fire hydrant, a water tower, or a sprinkler system will be required.

Deliverable:

Documentation of coordination with the AHJ, pdf

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Total Subtask 3 Costs:

Subtask 3: NFPA 1 18 Resolution

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

Dodstone Architects Architect/Principal $168.00 1 $168.00 Registered Architect $133.00 7 $931.00 CADD Operator $60.00 2 $120.00 Clerical/Support Staff $48.41 2 $96.82

$1,315.82

FSM Engineering Principal/Senior Engineer $130.64 1 $130.64 Project Engineer $110.15 2 $220.30

$350.94 Fixed Price Total Cost: $1,666.76

Total for Subtask 3: $1,666.76

Subtask 4: FDEP Northwest District Permitting Description: G&A expects to submit permit applications to the FDEP for water (potable/fire) and sewer wastewater. A verification of exemption for a separate potable and fire protection will be submitted to the FDEP. For the potable water an individual service for the campground is anticipated with its own meter. This is anticipated to be permitted through the FDEP self permitting portal which is governed by 62 555.520 FAC. A separate dedicated fire main is also anticipated to serve fire protection for the structures and is expected to be exempt through the same FAC rule.

The sewer system and lift station will require the FDEP Form 62 604.300_3a Notification/Application for Constructing a Domestic Wastewater Collection/Transmission System. This application will require a signature from The City of Marianna, the owner of the receiving WWTP.

Deliverables:

FDEP Self Permitting Exemption verification for the water service and fire main/hydrant, pdf FDEP Form 62 604.300_3a Issued Notification/Application for Constructing a Domestic

Wastewater Collection/Transmission System, pdf

Performance Measures: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Total Subtask 4 Costs:

Subtask 4: FDEP Northwest District Permitting

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

George & Associates Senior Engineer 1 $180.00 8 $1,440.00 Engineer 1 $114.00 24 $2,736.00

Fixed Price Total Cost: $4,176.00

Reimbursable Cost:

FDEP General Permit for water/fire lines @ $100 (x2) Form 62 555.520(1)(d) (12 & 13 $200.00 FDEP Construct Wastewater Collection and Transmission System, 62 604.333(8)(a) $250.00

Reimbursable Total Cost: $450.00

Note: Permitting reimbursable costs shown above have been estimated. Permitting costs beyond costs noted shall require a change order or direct payment by FDEP.

Total for Subtask 4: $4,626.00

Subtask 5: NWFWMD Permitting Description: G&A expects to submit permit applications to the Northwest Florida Water Management District (NWFWMD) for State level environmental resource permitting.

An Individual Environmental Resource Permit (ERP) will be required for construction of the campground. This is to permit the construction of the added impervious related to the buildings, roadways and campsites. Additional water quality standards will apply to stormwater runoff due to the project being in the Chipola River basin. The Chipola River and State Parks are categorized as an Outstanding Florida Water (OFW) and an impaired water body. The performance criteria for projects discharging into OFWs is 95% removal of pollutants. Through previous coordination with the

NWFWMD, it is understood that pre and post development nutrient analysis and calculations will be required for permitting. Anticipated permitting ERP form 62 330.060(1) include Sections A, C, & E.

A site visit by FELSI is included to verify the extent of the project and delineation with permitting agencies. FELSI will accompany the agency to the site and take points or notes as needed to support the processing of the applications.

Deliverables:

NWFWMD Individual ERP Application Form 62 330.060(1), pdf

Performance Measures: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Total Subtask 5 Costs:

Subtask 5: NWFWMD Permitting

Firm Name Position Classification Hourly Rate Hours

Total Fixed Price Cost

FELSI Principle Consultant $109.83 10 $1,098.30 Staff Assistant/Project Assistant $60.00 2 $120.00

$1,218.30

George & Associates Principal Engineer $240.00 2 $480.00 Senior Engineer 1 $180.00 24 $4,320.00 Engineer 1 $114.00 60 $6,840.00

$11,640.00 Fixed Price Total Cost: $12,858.30

Environmental Resource Program Individual Permit $500.00

Reimbursable Total Cost: $500.00

Note: Permitting reimbursable costs shown above have been estimated. Permitting costs beyond costs noted shall

Total for Subtask 5: $13,358.30

Subtask 6: NWFWMD Permit Issuance Description: Respond to NWFWMD requests for information (RFI) and coordinate as necessary with state regulatory staff to get an issued permit.

Deliverables:

Issued NWFWMD Individual ERP Form 62 330.060(1), pdf

Performance Measures: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Total Subtask 6 Costs:

Subtask 6: NWFWMD Permit Issuance

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

George & Associates Senior Engineer 1 $180.00 4 $720.00 Engineer 1 $114.00 8 $912.00

Fixed Price Total Cost: $1,632.00

Total for Subtask 6: $1,632.00

Subtask 7: City of Marianna Permitting Description: This project is within the City of Marianna limits. Marianna is the Utility Owner that provides water and sewer services to the park. G&A and Dodstone will review new connections to the water and sewer system which will require review and approval by the City of Marianna Public Works department. G&A will design the connections according to city codes. A City of Marianna Municipal Development Order � Major Development application will be submitted for the project. Review of items

Exclusions:

Alteration to the Caverns Road (SR 166) or the park�s driveway entrance are currently not included in the scope of work nor FDOT Permitting beyond coordination. If required, additional services may be necessary.

Deliverables:

City of Marianna Municipal Development Order � Major Development issued permit, pdf

Performance Measures: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Total Subtask 7 Costs:

Subtask 7: City of Marianna Permitting

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

Dodstone Architects Registered Architect $133.00 3 $399.00

George & Associates Senior Engineer 1 $180.00 4 $720.00 Engineer 1 $114.00 12 $1,368.00 Senior Engineer Technician 1 $90.00 6 $540.00

$2,628.00 Fixed Price Total Cost: $3,027.00

City of Marianna Municipal Development Order Application $2,500.00

Reimbursable Total Cost: $2,500.00

Note: Permitting reimbursable costs shown above have been estimated. Permitting costs beyond costs noted shall

Total for Subtask 7: $5,527.00

Subtask 7: 90% Civil Construction Plans Description: The design team will incorporate any comments received from BDC during the previous subtasks and will prepare 90% construction documents for the new campground, affiliated bathhouses and utilities.

Plan Set Summary will be the same as listed in the 60% plans.

Deliverables:

90% Construction Plans 22�x36�, pdf & dwg 90% Construction Specifications, pdf

90% Opinion of Probable Cost, pdf Response to 60% Comments, pdf

Performance Measures: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Total Subtask 8 Costs:

Subtask 8: 90% Construction Plans

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

Dodstone Architects Architect/Principal $168.00 4 $672.00 Registered Architect $133.00 48 $6,384.00 Graduate Architect $88.00 60 $5,280.00 CADD Operator $60.00 45 $2,700.00 Clerical/Support Staff $48.41 5 $242.05

$15,278.05

FSM Engineering Principal/Senior Engineer $130.64 2 $261.28 Project Engineer $110.15 8 $881.20 CADD Tech $49.23 20 $984.60 Admin $34.02 1 $34.02

$2,161.10

Applied Research & Design Professional Engineer $134.00 8 $1,072.00 CAD/Designer $59.00 11 $649.00 Clerical $35.00 5 $175.00

$1,896.00

Bliss & Niytray Sr. Principal $178.77 6 $1,072.62 Engineer $83.43 24 $2,002.32 CADD Technician $93.86 24 $2,252.64

$5,327.58

George & Associates Principal Engineer $240.00 2 $480.00 Senior Engineer 1 $180.00 127 $22,860.00 Engineer 1 $114.00 193 $22,002.00 Senior Engineer Technician 1 $90.00 202 $18,180.00

$63,522.00 Fixed Price Total Cost: $88,184.73

Total for Subtask 8: $88,184.73

Subtask 9: 100% Construction Plans Description: The design team will incorporate any comments received from BDC during the previous subtasks and will prepare 100% construction documents for the new campground, affiliated bathhouses and utilities.

Plan Set Summary is expected to be the same as the 90% plans.

Deliverables:

100% Construction Plans, signed and sealed, pdf & dwg 100% Construction Specifications, pdf

100% Opinion of Probable Cost, pdf Response to 90% Comments, pdf

Performance Measures: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Total Subtask 9 Costs:

Subtask 9: 100% Construction Plans

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Dodstone Architects Architect/Principal $168.00 2 $336.00 Registered Architect $133.00 10 $1,330.00 Graduate Architect $88.00 7 $616.00 CADD Operator $60.00 5 $300.00 Clerical/Support Staff $48.41 5 $242.05

$2,824.05

FSM Engineering Principal/Senior Engineer $130.64 4 $522.56 Project Engineer $110.15 8 $881.20 CADD Tech $49.23 12 $590.76 Admin $34.02 1 $34.02

$2,028.54

Applied Research & Design Professional Engineer $134.00 4 $536.00 CAD/Designer $59.00 6 $354.00 Clerical $35.00 1 $35.00

$925.00

Bliss & Niytray Sr. Principal $178.77 6 $1,072.62 Engineer $83.43 12 $1,001.16 CADD Technician $93.86 12 $1,126.32

$3,200.10

George & Associates Principal Engineer $240.00 2 $480.00 Senior Engineer 1 $180.00 53 $9,540.00 Engineer 1 $114.00 81 $9,234.00 Senior Engineer Technician 1 $90.00 85 $7,650.00

$26,904.00 Fixed Price Total Cost: $35,881.69

Printing Costs (Dodstone) $400.00 Reimbursable Total Cost: $400.00

Total for Subtask 9: $36,281.69

Subtask 10: SFM Permit Application Description: Dodstone will serve as the applicant on behalf of BDC and submit the restroom drawings for permit review to the State Fire Marshall. Submission will need to include information pertaining to the restroom and elements pertaining to NFPA1 18 compliance (such as documentation regarding the availability of the 3,000 gallon tanker etc.).

The Design Team will respond to any comments received in writing pertaining to their scope of work. A copy of any responses to comments will be issued to BDC�s designated project manager.

Notes and Exclusions:

Reimbursable costs not to exceed $2000. A receipt of the actual permit fee collected will be provided.

Deliverables:

SFM acceptance letter, pdf

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Total Subtask 10 Costs:

Subtask 10: SFM Permit Application

Firm Name Position Classification Hourly Rate Hours

Total Fixed Price Cost

Dodstone Architect/Principal $168.00 1 $168.00 Registered Architect $133.00 3 $399.00 Graduate Architect $88.00 4 $352.00 Clerical/Support Staff $48.41 2 $96.82

Fixed Price Total Cost: $1,015.82

Reimbursable Cost:

State Fire Marshal NFPA 1 18 Compliance Submission $2,000.00

Reimbursable Total Cost: $2,000.00 Total for Subtask 10: $3,015.82

Subtask 11: Permitting Services Description: The Design Team will provide signed and sealed sets in the format(s) required for BDC�s use in acquiring a building permit for the bathhouses. The Design Team will respond in writing to any permitting comments received related to their scope of work. It is assumed that the permit application and delivery/upload of any drawings to The City of Marianna is being handled by the contractor or others.

Notes and Exclusions:

Permit application and upload/delivery of any drawings is being handled by others No permitting fees are included

Deliverable:

Up to (2) physically signed and sealed plans, 22�x34�, and/or digital .pdf format Response to comments, or confirmation of no comments, pdf

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Total Subtask 11 Costs:

Subtask 11: Permitting Services

Firm Name Position Classification Hourly Rate Hours

Total Fixed Price Cost

Dodstone Architects Architect/Principal $168.00 1 $168.00 Registered Architect $133.00 12 $1,596.00 Graduate Architect $88.00 6 $528.00 CADD operator $60.00 2 $120.00

$2,412.00

FSM Engineering Principal/Senior Engineer $130.64 2 $261.28 Project Engineer $110.15 1 $110.15 Admin $34.02 1 $34.02

$405.45

Applied Research & Design

Professional Engineer $134.00 2 $268.00

CAD/Designer $59.00 1 $59.00 Clerical $35.00 4 $140.00

$467.00

Bliss & Niytray Sr. Principal $178.77 2 $357.54 $357.54

George & Associates Senior Engineer 1 $180.00 2 $360.00 Engineer 1 $114.00 2 $228.00 Senior Engineer Technician 1 $90.00 2 $180.00

$768.00 Fixed Price Total Cost: $4,409.99

Reimbursable Cost:

Printing Costs $400.00

Reimbursable Total Cost: $400.00 Total for Subtask 11: $4,809.99

Subtask 12: Florida Historical Marker Application Description: Chronicle Heritage will conduct the necessary background research and develop text for a Florida Historical Marker. The text will be submitted to George & Associates (G&A) and FDEP for initial review prior to submission to the State Historic Preservation Officer (SHPO). Once SHPO approves, the text and application package will be submitted to the Florida Historical Marker Program. The scope assumes Chronicle staff will attend the applicable Florida Historical Marker Council meeting, where the application will be reviewed, edited as necessary, and approved.

Notes/Exclusions: This scope/fee does not include the cost of the marker. For a single sided marker with the same text on both sides of the marker, the cost is estimated at $2,540. For a double sided marker with different text on both sides of the marker, the cost is estimated as $2,920.

Deliverable:

Florida Historical Marker Application, pdf

Approval Letter of marker text by Florida Historical Marker Council, pdf

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Subtask 12: Florida Historical Marker Application

Firm Name Position Classification Hourly Rate

Hours Total Fixed

Price Cost George & Associates Senior Engineer 1 $180.00 3 $540.00

Chronicle Heritage Principal in Charge $135.00 10 $1,350.00 Chronicle Heritage Senior Archaeologist $95.00 23 $2,185.00 Chronicle Heritage Project Manager $85.00 10 $850.00 Chronicle Heritage Administrative Assistant $60.00 2 $120.00

$4,505.00 Fixed Price Total Cost: $5,045.00

Total for Subtask 12: $5,045.00

Subtask 13: Florida Master Site File Form Description: Chronicle Heritage will use the background research developed pursuant to Task 1 to prep a Florida Master Site File (FMSF) form for the Florida Caverns Golf Course (8JA01777) resource group. The draft form will be submitted to G&A and FDEP for initial review prior to submission to the SHPO. Once SHPO approves, the form and associated maps and photographs will be submitted to the FMSF.

Deliverable:

FMSF Form, pdf

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price Cost Subtask 13: Florida Master Site File Form

Firm Name Position Classification Hourly Rate Hours Total Fixed

Price Cost George & Associates Senior Engineer 1 $180.00 3 $540.00

Chronicle Heritage Principal in Charge $135.00 1 $135.00 Chronicle Heritage Senior Archaeologist $95.00 5 $475.00 Chronicle Heritage GIS Specialist $65.00 6 $390.00

$1,000.00 Fixed Price Total Cost: $1,540.00

Total for Subtask 13: $1,540.00

Subtask 14: Putting Green Planning Exhibit and Scope of Work Description: George & Associates Engineering (G&A) will prepare planning exhibits and a scope of work for a putting green as proposed in the DHR Resolution of Adverse Effects letter.

The DHR requirement was for FDEP to fund the design and construction of a putting green with a low maintenance, synthetic green. The green shall be constructed within the footprint of the original Florida Caverns Golf Course and may use materials or equipment that are salvaged pursuant to Item 3 in the letter.

The design and location of the green shall be coordinated with the SHPO and FDEP for review.

Tasks include a Scope of Work to include planning exhibits and details showing the location, extent, cross section, and size of the proposed putting green. Included will be the material of the putting green and surrounding rough. The Scope of Work will include specifications for materials and the work.

Deliverable:

Putting Green Scope of Work, pdf

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price Cost Subtask 14: Putting Green Planning Exhibit and Scope of Work

Firm Name Position Classification Hourly Rate Hours Total Fixed

Price Cost

George & Associates Principal Engineer $240.00 1 $240.00

George & Associates Senior Engineer 1 $180.00 8 $1,440.00

George & Associates Engineer 1 $114.00 12 $1,368.00

George & Associates Senior Engineer Technician 1 $90.00 16 $1,440.00

Fixed Price Total Cost: $4,488.00

Total for Subtask 14: $4,488.00

Summary of Fees:

Subtask Subtask Fixed Price Cost

Subtask Reimbursable

Subtask 1: Utility Survey $14,279.56

Subtask 2: Survey and Field Services Review $3,348.00 Subtask 3: NFPA 1 18 Resolution $1,666.76 Subtask 4: FDEP Northwest District Permitting $4,176.00 $450.00 Subtask 5: NWFWMD Permitting $12,858.30 $500.00 Subtask 6: NWFWMD Permit Issuance $1,632.00

Subtask 7: City of Marianna Permitting $3,027.00 $2,500.00

Subtask 8: 90% Construction Plans $88,184.73

Subtask 9: 100% Construction Plans $35,881.69 $400.00

Subtask 10: SFM Permit Application $1,015.82 $2,000.00

Subtask 11: Permitting Services $4,409.99 $400.00

Subtask 12: Florida Historical Marker Application $5,045.00 Subtask 13: Florida Master Site File Form $1,540.00 Subtask 14: Putting Green Planning Exhibit and Scope of Work

$4,488.00

Total Fixed Cost: $181,552.85

Total Reimbursable Cost $6,250.00

Overall Total Cost: $187,802.85 www.gaceng.net CIVIL ENGINEERING - LAND USE PLANNING - ENVIRONMENTAL - SYSTEMS PLANNING - TRANSPORTATION

Project Schedule:

Activity Duration (calendar days)

Dates

Subtask 1: Utility Survey 45

Subtask 2: Survey and Field Services Review 21 Subtask 3: NFPA 1 18 Resolution 60 Subtask 4: FDEP Northwest District Permitting 45 Subtask 5: NWFWMD Permitting 45 Subtask 6: NWFWMD Permit Issuance 30

Subtask 7: City of Marianna Permitting 60

Subtask 8: 90% Construction Plans 60

Subtask 9: 100% Construction Plans 30

Subtask 10: SFM Permit Application 45

Subtask 11: Permitting Services 30 Subtask 12: Florida Historical Marker Application 45*

Subtask 13: Florida Master Site File Form 14* Subtask 14: Putting Green Planning Exhibit and Scope of Work 21

Calendar Days do not include FDEP review time from previous phases or submittals that may require feedback to proceed.

* Assumes agency responsiveness (DHR). Includes review and comment phase by BDC between draft and final document.

Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.