CN-370000-CN201-T7CO1.pdf
PDF 345 KB Posted
- Contract number
- CN201
- Issued by
- Florida
About this file
This is a Task Assignment Change Order Form issued by the Florida Department of Environmental Protection (FDEP) for Contract CN201, Task 7, involving the consultant firm WET Engineering. The change order was executed on December 22, 2023, and pertains to the Weeki Wachee State Park Concession Building and Kiddie Pool project located in Florida. The key parties include FDEP Contract Manager Ralph Perkins, WET Engineering's representative Heather Baxter, and FDEP Contract Authority Michael W. Foster Jr., P.E.
The change order extends the contract timeline for Construction Administration services from the original end date of December 31, 2023, to December 31, 2024, representing a net extension of 366 days. This is a time-only extension with no change to the financial obligations; the task amount remains $37,161.76 total, comprised of $987.00 in reimbursement and $36,174.76 in fixed fees. The extension was requested because project construction had not been initiated as of the change order date but was anticipated to commence in 2024. WET Engineering had met all contracted deadlines to date and maintained compliance with the original agreement terms.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-370000-CN201-CMC1.pdf | ||
| CN-370000-CN201-T6CO1.pdf | ||
| CN-370000-CN201-T7.pdf | ||
| CN-370000-CN201-TA1.pdf | ||
| CN-370000-CN201-T3.pdf | ||
| PC-370000-CN201.pdf | ||
| CN-370000-CN201-AM1.pdf | ||
| CN-370000-CN201-CMC3.pdf | ||
| CN-370000-CN201-CMC2.pdf | ||
| CN-370000-CN201-T4.pdf | ||
| CN-370000-CN201-T4CO1.pdf | ||
| CN-370000-CN201-T5.pdf | ||
| CN-370000-CN201-T6.pdf | ||
| CN-370000-CN201-T6CO2.pdf | ||
| CN-370000-CN201-TA2.pdf | ||
| CN-370000-CN201.pdf |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
( ) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN201 7 1 6A003
Weeki Wachee State Park Concession Building and Kiddie Pool
WET Engineering
Heather Baxter 904-223-9773 hwb@wetengineering.net
Ralph Perkins 850-245-2460 ralph.perkins@floridadep.gov
Time-only contract extension to utilize Construction Administration services per attached dated 12/22/2023.
$ 987.00 $ 36,174.76 $ 37,161.76 $ 987.00 $ 36,174.76 $ 37,161.76 $ 0.00 $ 0.00 $ 0.00
$ 987.00 $ 36,174.76 $ 37,161.76
12/06/2022
12/31/2023
12/31/2023
12/31/2024
Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2023.12.22 13:51:38 -05'00'
Jasper Gebhardt Jasper Gebhardt Digitally signed by Jasper Gebhardt Date: 2023.12.22 14:05:37 -05'00'
David Matson for Ralph Perkins David Matson Digitally signed by David Matson Date: 2023.12.22 14:15:55 -05'00'
Heather Baxter Heather W Baxter Digitally signed by Heather W Baxter Date: 2023.12.22 14:23:00 -05'00'
Michael W. Foster Jr., P.E. Michael W. Foster Jr., P.E.
Digitally signed by Michael W.
Foster Jr., P.E.
Date: 2023.12.22 14:57:26 -05'00'
$ 0.00
From: Heather Baxter To: Gebhardt, Jasper Cc: Rowe, Richard J.
Subject: RE: TA Contract Extension - Weeki Wachee Concession Building Date: Friday, December 22, 2023 10:39:23 AM
EXTERNAL MESSAGE
This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.
Jasper –
Based on the status of the project, WET is requesting an extension on the contract for Weeki Wachee Concession Building, Contract CN201, Task 7 (FCO Project 60938). WET has met its contracted deadlines to date; however, the project construction has not been initiated and is anticipated to begin in 2024.
We respectively request an extension to December 31, 2024.
Thanks, Heather W. Baxter, P.E.
Principal 4337 Pablo Oaks Ct., Suite 101 Jacksonville, FL 32224
(904) 223-9773 (Phone) hwb@wetengineering.net
File details come from the government source that posted it. Updated .