BR_65_2601 Addendum No_ 2.pdf
PDF 168 KB Posted
- Solicitation number
- PE-47200-RFQ-2026-000000110
- Issued by
- Barrow County, Georgia
About this file
This is an Addendum No. 2 to a Request for Proposals issued by the Board of Regents of the University System of Georgia for design-build services related to Project No. BR-65-2601, "Baseball Softball Complex Upgrades" at Georgia College and State University in Milledgeville, Georgia. The addendum addresses clarifications regarding the scope of work for the project, which includes upgrades to the baseball and softball complex facilities. The document provides responses to ten questions submitted by prospective bidders, clarifying project requirements and existing conditions. Key clarifications include that existing bleacher capacity is nominally 451 seats, concept renderings are available for viewing, lighting and scoreboards are excluded from the project scope, and the new field surface type (synthetic, natural, or hybrid) remains to be determined under a separate design project. The design must incorporate prevailing accessibility standards for ADA compliance, with the determination of a new ADA ramp versus use of existing infrastructure to be made during the design phase.
Additional clarifications indicate that rough-ins and infrastructure to accommodate audiovisual systems are included in the scope of construction and landscaping (SCL), while Jumbotron and other AV hardware will be acquired separately. The outdoor grill will be demolished as part of the project, while the existing pavilion and restrooms will remain, with three toilet fixtures available for both men and women. The existing locker rooms are located in Peeler Hall to the northeast of the outfield. Georgia College and State University maintains design standards that will govern the project development.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| GCSU BR_65_2601 DB RFQ_RFP.pdf | ||
| Exhibit E _ General Conditions Breakdown.xlsx | XLSX spreadsheet | |
| Exhibit F _ Project Cost Matrix.xlsx | XLSX spreadsheet | |
| Exhibit C _ DB Fee Proposal.docx | DOCX document | |
| Exhibit D _ Precon Cost and Expenses.xlsx | XLSX spreadsheet | |
| Egnyte Upload Instructions.pdf | ||
| GCSU BR_65_2601 Addendum No_ 1.pdf | ||
| GCSU_BR_65_2601 DB_NOIA.pdf | ||
| Exhibit B _ Contractor Affidavit.docx | DOCX document | |
| GCSU BR_65_2601 DB shortlist_gpr.pdf | ||
| Exhibit G _ Proposer_s Disclosure Statement.doc | DOC document | |
| BR_65_2601 DB AWARD.docx | DOCX document | |
| Exhibit A _ Certification Form.docx | DOCX document |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Board of Regents of the University
System of Georgia Request for Proposals
(Step I)
To Provide
Design-Build Services
For
Project No. BR-65-2601 “Baseball Softball Complex Upgrades” Georgia College and State University
Milledgeville, Georgia February 19, 2026
Response to Request for Clarifications
Addendum No. 2
1. Question: What is the existing capacity?
Answer: Existing bleacher capacity is comparable to proposed chairback seating (nominally 451).
2. Question: Can the concept renderings be made available for viewing?
Answer: Yes, attached to addendum.
3. Question: Will lighting and Scoreboard be part of the project?
Answer: No.
4. Question: Will the new field be synthetic, natural, or hybrid?
Answer: TBD (separate project under design)
5. Question: Will there be a new ADA ramp or use the existing?
Answer: Will depend upon new design concept--new design should incorporate prevailing accessibility standards.
6. Question: Does GC&SU have design standards?
Answer: Yes
7. Question: Will AV, PA System, Jumbotron, and/or infrastructure be part of the SCL?
Answer: Rough-ins and infrastructure to accommodate new A/V are part of the SCL. Jumbotron and other A/V hardware will be acquired separately
8. Will the current outdoor grill be demolished?
Answer: Yes
9. Will the existing gazebo and restrooms stay? If so, how many current fixtures are available?
Answer: Yes, existing pavilion restrooms have 3 toilet fixtures each for men and women.
10. Question: Where are the locker rooms located?
Answer: Peeler Hall (NE of outfield)
End of Addendum #2
| Board of Regents of the University |
| System of Georgia |
| Request for Proposals |
| (Step I) |
| To Provide |
| Design-Build Services |
File details come from the government source that posted it. Updated .