Atttachment J-P Drawings and Specification Addenda.pdf

PDF 629 KB Posted

Attached to
Modify Vehicle Assembly Building High Bay-3 Platforms for Block 1B Federal contract opportunity
Solicitation number
80KSC021R0020
Issued by
National Aeronautics and Space Administration Kennedy Space Center

About this file

This document package includes specifications and drawings for a federal construction contract to modify platforms in a Vehicle Assembly Building. The contractor shall fabricate and install new platforms weighing approximately 300,000 pounds each, consisting of support structures, mechanical and electrical systems for platform movement, and communications, lighting and fire suppression systems. Additional scope includes new floors and rooms, as well as modification and extension of building systems including fire suppression pipes and valves, fire alarm, high-pressure gas tubing, and electrical power. Work will occur at heights from 280 to 450 feet above ground and must be completed during operational downtime between launches, with potential for dual occupancy. The specifications include requirements for materials, cleaning and passivation of stainless steel, and construction phasing.

View the file

Other files for this federal contract opportunity

Show all 21

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment J-P

Drawings and Specification Amendments

Dated 8/30/2021

Note - Deleted text is shown striked through and new text is underlined.

Drawing 79K40461 Volume 1

All Sheets - Tasks indicated as occurring in Phase 3 are not in contract.

Sheet V-002 – Delete Sheets C-002, S-101T, S-400T, and S-500T from the index.

Sheet V-007 Mandatory Inspection List – Add MP-11 as follows:

Reference drawings: FP1343, FP3053, FP5013, FP5033, and

FP5043

Construction Phase: Phase 2 MIP Description: Prior to any other testing of the Fire Protection equipment, verify complete installation of each quad valve assembly and all components in accordance with specification 79K40462, section 21 13 29.00 (Water Spray Fixed Systems), Part

3.2 (Actuated Butterfly Valve Installation) in the presence of the Contracting Officer’s Representative. Provide hardcopies of applicable contract documentation (drawing sheets and specification), approved shop drawings, manufacturers’ installation instructions for various components, and a certificate for the correct installation, including presence of the upstream labels on valves, written confirmation of manufacturer’s intended orientation to ensure proper operation and prevent water hammer, and signatures of personnel who verified the installation.

Sheet V-007 Mandatory Inspection List – Add MP-12 as follows:

Reference drawings: FP1343, FP3053, FP5013, FP5033, and

FP5043

Construction Phase: Phase 2 MIP Description: After complete installation of each quad valve assembly and all components, adjust the flow control valves for each assembly in accordance with specification 79K40462, section 21 13 29.00 (Water Spray Fixed Systems), Parts 2.2.4.2 (Actuated Butterfly Valves) and 3.6.3.2 (Type II Riser Valve Dry Cycle Test).

Manually activate each quad valve assembly and record the time for the valves to fully open. Deactivate the quad valve assemblies and record the time for the valves to fully close. Submit all results to the Contracting Officer for review and approval.

Sheet V-007 Construction Phasing Notes, Phase 1 – Delete Note 8 in its entirety.

Sheet V-007 Construction Phasing Notes, Phase 1 – Add following:

Note 8: FABRICATION OF VEHICLE PLATFORM CORBEL

TRACKS.

Note 9: INSTALLATION OF VEHICLE PLATFORM CORBEL

TRACKS IN THE VAB.

Note 10: REINFORCING OF THE VAB EXISTING

STRUCTURE (PER DRAWING PACKAGE 79K40725) IN HB-3.

Sheet V-007 Construction Phasing Notes, Phase 2 – Delete Notes 1, 2, 4, and 13 in their entirety Sheet V-007 Construction Phasing Notes, Phase 2 – Change Note 3 as follows:

From: NOTE 3. REINFORCING OF THE VAB EXISTING

STRUCTURE (PER DRAWING PACKAGE 79K40725).

To: NOTE 3. REINFORCING OF THE VAB EXISTING

STRUCTURE (PER DRAWING PACKAGE 79K40725) IN HB-1,

HB-2, HB-4, AND TRANSFER AISLE.

Sheet V-007 Construction Phasing Notes, Phase 2 – Change Note 5 as follows:

From: NOTE 5. FABRICATION AND INSTALLATION OF NEW

CATWALK AND MECHANICAL PLATFORM ADDITION FOR

QUAD VALVES (PER THIS DRAWING PACKAGE) AND STRAND

JACK PLATFORM EGRESS (PER DRAWING PACKAGE

79K40596) AT VAB LEVEL 34.

To: NOTE 5. FABRICATION AND INSTALLATION OF NEW

CATWALK AND MECHANICAL PLATFORM ADDITION FOR

QUAD VALVES (PER THIS DRAWING PACKAGE) AND STRAND

JACK PLATFORM EGRESS (PER DRAWING PACKAGE

79K40596) AT VAB LEVEL 34.

Sheet V-007 Construction Phasing Legend – Change Phasing Legend as follows:

From: THE CONSTRUCTION PHASING LEGEND APPLIES TO

ALL SHEETS IN THE FOLLOWING DRAWING PACKAGES:

- 79K40461, MODIFY VAB FOR SLS BLOCK 1B CREW

- 79K40596, INSTALL VAB HB-3 SLS PLATFORM LIFTING

SUPPORT STRUCTURE

- 79K40725, MODIFY VAB FOR SLS BLOCK 1B CREW -

STRUCTURAL REINFORCEMENTS

SEE SHEET V-007 IN DRAWING PACKAGE 79K40461 FOR

CONSTRUCTION PHASING NOTES.

To: THE CONSTRUCTION PHASING LEGEND APPLIES TO

ALL SHEETS IN THE FOLLOWING DRAWING PACKAGES:

- 79K40461, MODIFY VAB FOR SLS BLOCK 1B CREW

- 79K40596, INSTALL VAB HB-3 SLS PLATFORM LIFTING

SUPPORT STRUCTURE

- 79K40725, MODIFY VAB FOR SLS BLOCK 1B CREW -

STRUCTURAL REINFORCEMENTS

SEE SHEET V-007 IN DRAWING PACKAGE 79K40461 FOR

CONSTRUCTION PHASING NOTES.

IF A PHASE NUMBER AND CORRESPONDING PHASING

PHANTOM LINE BUBBLE IS INDICATED AROUND THE

SHEET NUMBER IN ZONE A2, THEN THAT PHASE APPLIES

TO THE ENTIRE SHEET UNLESS NOTED OTHERWISE. IF A

SHEET DOESN’T HAVE A PHASE DESIGNATOR, THEN IT

APPLIES/ IS FOR INFORMATION RELATED TO ALL PHASES.

(example below)

PHASE 3 ITEMS ARE NOT IN CONTRACT.

Sheet V-007 Project Notes – Add Note F:

NOTE F - PROJECT NOTES ARE PROVIDED FOR

INFORMATION OF THE OVERALL SEQUENCE OF

OPERATIONS THAT WAS ANTICIPATED DURING DESIGN.

SOME OF THESE ITEMS/ TASKS ARE IN PHASE 3 OR OTHER

TASK ORDERS THAT ARE NOT INCLUDED IN THIS CURRENT

PROJECT SCOPE.

Sheet V-009 Specific Note N change as follows:

From: DRILL HOLES 24” APART WHILE PLATFORM IS IN THE

EXTENDED POSTION ACCORDING TO FOLLOWING DETAIL.

To: DRILL HOLES 24” APART WHILE PLATFORM IS IN THE

EXTENDED POSTION ACCORDING TO FOLLOWING PAINTING

DETAIL ON SHEET V-008.

Sheet V-010 Add new note to sheet:

PLATFORM ELEVATIONS INDICATED ARE NOMINAL.

COORDINATE EXACT ELEVATIONS WITH CORBEL HOLES.

Sheet C-002 – Delete this sheet in its entirety Sheet C-003 – Change plan, general notes, and specific notes as shown in sketch CSK-001 Sheet S-101T – Delete this sheet in its entirety Sheet S-400T – Delete this sheet in its entirety Sheet S-500T – Delete this sheet in its entirety

Sheet S-001 – Delete Special Inspection Notes in entirety Sheet S-003 Structural Steel Note 4 change as follows:

From: WELDING: ALL WELDING SHALL BE IN CONFORMANCE

WITH AWS D1.1, EXCEPT THAT THE WELDING OF THE

PLATFORMS SHALL BE IN CONFORMANCE WITH AWS D17.1.

To: WELDING: ALL WELDING SHALL BE IN CONFORMANCE

WITH AWS D1.1, EXCEPT THAT THE WELDING OF THE

VEHICLE PLATFORMS, ELEVATOR LANDING PLATFORMS

(ELPs), AND VEHICLE PLATFORM CORBEL TRACKS SHALL BE

IN CONFORMANCE WITH AWS D17.1.

Sheet S-4203 Specific Note Flag Note B change as follows:

From: SEE SHEETS S-4213 AND Q-7503 TO Q-7533 FOR

LIFTING LUG ASSEMBLY DETAILS.

To: SEE SHEETS S-4213 AND Q-7503 TO Q-7533 FOR

LIFTING LUG ASSEMBLY DETAILS. SEE DETAIL 3/S-5203

FOR CONNECTION OF W10’s TO W10’s OF LIFTING LUG

ASSEMBLY.

Sheet S-4203 Legend change as follows:

From: SPAN DIRECTION OF INVERTED 1.5B 16 GAUGE METAL

DECK WITH 3/16" THICK STEEL PLATE ATTACHED TO METAL

DECK PER THE SDI FABRICATION REQUIREMENTS. PROVIDE

1-3/8" HOLE THRU TOP OF DECK FOR FASTENER

INSTALLATION. INSTALL 1/2" DIA. - 13 (A307/A325 HDG) THRU

BOLT WITH HEAVY DUTY, LOCKING HEX NUTS. ONLY 2

BOLTS PER 24" WIDE DECK PANEL AT EACH BEAM ARE

REQUIRED. PROVIDE TEST TITE CLEANOUT REPAIR PLUGS

(OR APPROVED EQUIVALENT) FOR ALL OPENINGS OF 2", 3"

OR 4" DIAMETER. EXTEND DECKING TO EDGE OF

PERIMETER BEAM FLANGES.

To: SPAN DIRECTION OF INVERTED 1.5B 16 GAUGE METAL

CELLULAR DECK WITH 3/16" THICK STEEL PLATE ATTACHED

TO METAL DECK PER THE SDI FABRICATION REQUIREMENTS

(SEE DETAIL 9/S-504 FOR DECKING DETAIL). PROVIDE 1-3/8"

HOLE THRU TOP OF DECK FOR FASTENER INSTALLATION.

INSTALL 1/2" DIA. - 13 (A307/A325 HDG) THRU BOLT WITH

HEAVY DUTY, LOCKING HEX NUTS. ONLY 2 BOLTS PER 24"

WIDE DECK PANEL AT EACH BEAM ARE REQUIRED. PROVIDE

TEST TITE CLEANOUT REPAIR PLUGS (OR APPROVED

EQUIVALENT) FOR ALL OPENINGS OF 2", 3" OR 4" DIAMETER.

EXTEND DECKING TO EDGE OF PERIMETER BEAM FLANGES.

Sheet S-4203 Detail 1 Zone C8-E8 Add Note (see example below):

PROVIDE (5) PLATES PER 2/S-5203, EQUALLY SPACED

Sheet S-4203 Detail 1 Zone F7 – Delete Square Groove Weld Symbol (see example below)

Sheet S-4203 Detail 2 Zone C5-E5 Add Note (see example below):

PROVIDE (5) PLATES PER 2/S-5203, EQUALLY SPACED

Sheet S-4203 Detail 2 Zone E4 – Delete Square Groove Weld Symbol (see example below)

Sheet S-4613 sheet number, zone A2 – change as follows:

From: “PHASE 2” callout at sheet number S-4613.

To: “PHASE 1” callout at sheet number S-4613.

Sheet S-5203 add specific notes and detail 8/S-5203 as shown in sketch SSK-001.

Sheet S-5203 Detail 2: Change the shift angle such that inside face of the vertical leg is on outside edge of plate as detailed below.

Sheet S-5223 Legend change as follows:

From: SPAN DIRECTION OF INVERTED 1.5B 16 GAUGE METAL

DECK WITH 3/16" THICK STEEL PLATE ATTACHED TO METAL

DECK PER THE SDI FABRICATION REQUIREMENTS. PROVIDE

1-3/8" HOLE THRU TOP OF DECK FOR FASTENER

INSTALLATION. INSTALL 1/2" DIA. - 13 (A307/A325 HDG) THRU

BOLT WITH HEAVY DUTY, LOCKING HEX NUTS. ONLY 2

BOLTS PER 24" WIDE DECK PANEL AT EACH BEAM ARE

REQUIRED. LONGITUDINALLY POSITION THE THRU BOLT

SUCH THAT IT IS CENTERED BETWEEN THE OUTERMOST

RIBS OF THE INVERTED DECK; TRANSVERSELY POSITION

THE THRU BOLT TO PROVIDE THE MINIMUM EDGE DISTANCE

PER AISC. PROVIDE TEST TITE CLEANOUT REPAIR PLUGS

(OR APPROVED EQUIVALENT) FOR ALL OPENINGS OF 2", 3"

OR 4" DIAMETER. EXTEND DECKING TO EDGE OF

PERIMETER BEAM FLANGES.

To: SPAN DIRECTION OF INVERTED 1.5B 16 GAUGE METAL

CELLULAR DECK WITH 3/16" THICK STEEL PLATE ATTACHED

TO METAL DECK PER THE SDI FABRICATION REQUIREMENTS

(SEE DETAIL 9/S-504 FOR DECKING DETAIL). PROVIDE 1-3/8"

HOLE THRU TOP OF DECK FOR FASTENER INSTALLATION.

INSTALL 1/2" DIA. - 13 (A307/A325 HDG) THRU BOLT WITH

HEAVY DUTY, LOCKING HEX NUTS. ONLY 2 BOLTS PER 24"

WIDE DECK PANEL AT EACH BEAM ARE REQUIRED.

LONGITUDINALLY POSITION THE THRU BOLT SUCH THAT IT

IS CENTERED BETWEEN THE OUTERMOST RIBS OF THE

INVERTED DECK; TRANSVERSELY POSITION THE THRU BOLT

TO PROVIDE THE MINIMUM EDGE DISTANCE PER AISC.

PROVIDE TEST TITE CLEANOUT REPAIR PLUGS (OR

APPROVED EQUIVALENT) FOR ALL OPENINGS OF 2", 3" OR 4"

DIAMETER. EXTEND DECKING TO EDGE OF PERIMETER

BEAM FLANGES.

Sheet S-5613 sheet number, zone A2 – change as follows:

From: “PHASE 2” callout at sheet number S-5613.

To: “PHASE 1” callout at sheet number S-5613.

Sheet AD1283 Zones D6 and C6 – Delete Flag Note U (2 places).

Sheet A-1323 Specific Notes – Delete Flag Note M in its entirety.

Sheet A-1323 Zones D6 and C6 – Delete Flag Note M (2 places).

Sheet A-1343 – Add extents of striping in new walkway in Tower F as mentioned in Flag Note P per example below.

Sheet A-4063 Detail 1 – Add extents of striping in new walkway in Tower F as mentioned in Specific Note B per example below.

Sheet A-4063 Detail 2 – Add extents of striping in new walkway in Tower F as mentioned in Specific Note B per example below.

Sheet A-4113 Specific Notes, Flag Note F – Add PHASE 1 callout and phantom line around note and change note as follows:

From: GALVANIZED STEEL SAFETY GATE. REF: SPEC

SECTION 05 52 2.4.

To: GALVANIZED STEEL SAFETY GATE. REF: SPEC SECTION

05 52 2.4 SPECIFICATION SECTION 05 52 00, PARAGRAPH 2.4.

Sheet A-4113 Specific Notes – add Note G as follows:

Note G – REFER TO DETAIL 8/S-5203 FOR FIXED GUARDRAIL

DETAILS AT THE ELP.

Sheet A-4123 Specific Notes, Flag Note A –change note as follows:

From: GALVANIZED STEEL SAFETY GATE. REF: SPEC

SECTION 05 52 2.4.

To: GALVANIZED STEEL SAFETY GATE. REF: SPEC SECTION

05 52 2.4 SPECIFICATION SECTION 05 52 00, PARAGRAPH 2.4.

Sheet A-4123 Specific Notes – add Notes G, H, and I as follows:

Note G – ALL GUARDRAILS SHALL BE INSTALLED SUCH THAT

THE TOP SURFACE OF THE UPPER RAIL IS 42” ABOVE THE

DECK.

Note H – CONTRACTOR MAY LEAVE EXTENSION OF

TOEBOARD LONGER THAN SPECIFIED AND FIELD TRIM THE

FINAL LENGTH.

Note I – SEE S-5203 FOR ADDITIONAL GUARDRAIL

INFORMATION.

Sheet A-5053 sheet number, zone A2 – change as follows:

From: “PHASE 1 & 3” callout at sheet number A-5053.

To: “PHASE 1 & 3, UNO” callout at sheet number A-5053.

Sheet A-5053 Specific Note B – add PHASE 2 & 3 callout and phantom lines around Note B.

Drawing 79K40461 Volume 2 contract.

Sheet Q-0013 Aluminum Design change as follows:

From:

PLATE OR SHEET – ALLOY 6060, TEMPTER T6, ASTM B209

STRUCTURAL SHAPES – ALLOY 6060, TEMPER T6, ASTM

B308

ANGLES – ALLOY 6060, TEMPER T6, ASTM B308

PIPE – ALLOY 6060, TEMPER T6, ASTM B241

ROUND TUBE – ALLOY 6060, TEMPER T6, ASTM B210

SQUARE OR RECTANGULAR TUBE – ALLOY 6060, TEMPER 6,

ASTM B241

To:

PLATE OR SHEET – ALLOY 6060, ALLOY 6061, TEMPTER T6,

ASTM B209

STRUCTURAL SHAPES – ALLOY 6060, ALLOY 6061, TEMPER

T6, ASTM B308

ANGLES – ALLOY 6060, ALLOY 6061, TEMPER T6, ASTM B308

PIPE – ALLOY 6060, ALLOY 6061, TEMPER T6, ASTM B241

ROUND TUBE – ALLOY 6060, ALLOY 6061, TEMPER T6, ASTM

B210

SQUARE OR RECTANGULAR TUBE – ALLOY 6060, ALLOY

6061, TEMPER 6, ASTM B241

Sheet Q-1203 Platform Insert Support Detail, Zone B6, change 4-1/2” dimension to 6” where shown:

Drawing 79K40461 Volume 3 contract.

Sheet Q-4003 Parts List, Line Item #29 changes as follows:

From: SAFETY GATE, PER SPECIFICATION SECTION 05 52 00

PARAGRAPH 2.3

To: SAFETY GATE, PER SPECIFICATION SECTION 05 52 00

PARAGRAPH 2.3 2.4.

Sheet Q-7523 Detail 2, Lifting Lug Detail, Material change as follows:

From: MATERIAL: ROD, ROUND, ASTM 4140 To: MATERIAL: ROD, ROUND, ASTM 4140 AISI 4140

Drawing 79K40461 Volume 4

Sheet FP-5013 add detail 3/FP5013 as shown in sketch FSPK001.

Sheet FP-5043 add model number for flow control valve (near Flag

Note V) as shown in sketch FPSK002.

Sheet FP-5043 add detail 7/FP5043, General Notes and Specific

Notes as shown in sketch FPSK003.

Sheet M-001 Legend add Pnuematic Valves and Components per sketch MSK-001.

Sheet M-501 add new detail 8, parts list and general notes per sketch

MSK-002.

Sheet M-1343 Specific Notes add Note C:

NOTE C – GN2 IS FED FROM THE 130 PSIG SYSTEM TO THE

SOLENOID CABINETS. PROVIDE 80 GALLON, 200 PSIG

RATED, ASME RATED ACCUMULATOR/ RECEIVER UPSTREAM

OF SOLENOID CABINET, AND PROVIDE ALL ASSOCIATED

COMPONENTS (SEE DETAIL 8/M-501).

Sheet M-4003 Detail 1 add new accumulator/receiver towers in E & F at VAB Level 34 as shown in Sketch MSK-003.

Sheet M-4003 GN2 Riser – Add new details 2 & 3 with tables as shown in sketch MSK-004.

Sheet FA-502 add new detail 4/FA502 and specific notes as shown in sketch FASK-001.

Sheet FA6013 add tamper switch at level 34.

Sheet FA6023 add tamper switch at level 34.

Specification 79K40462

All Specification Sections – Tasks indicated as Phase 3 are not in

Specification Section 01 11 00 part 1.2.1 change as follows:

From:

Phase 1 construction activities will consist of the following construction activities:

1. Fabrication of 4 new extensible platform halves.

2. Installation of mechanical, electrical, plumbing, and fire protection components on the new extensible platform halves.

3. Fabrication of 6 new inserts.

4. Fabrication of 2 new OMLs.

5. Fabrication of 6 new fixed landing platforms.

6. Fabrication of 4 new egress ramps.

7. Fabrication of 4 new elevator landing platforms.

8. Fabrication of 4 new strand jack support platforms (per drawing package

79K40596).

To:

Phase 1 construction activities will consist of the following construction activities:

1. Fabrication of 4 new extensible platform halves.

2. Installation of mechanical, electrical, plumbing, and fire protection components on the new extensible platform halves.

3. Fabrication of 6 new inserts.

4. Fabrication of 2 new OMLs.

5. Fabrication of 6 new fixed landing platforms.

6. Fabrication of 4 new egress ramps.

7. Fabrication of 4 new elevator landing platforms.

8. Fabrication of 4 new strand jack support platforms (per drawing package 79K40596).

8. Fabrication of vehicle platform corbel tracks.

9. Installation of vehicle platform corbel tracks in the VAB.

10. Reinforcing of the VAB existing structure (per drawing package

79K40725) in HB-3.

Specification Section 01 11 00 part 1.2.1 change as follows:

From:

Phase 2 will consist of the following construction activities:

1. Fabrication of vehicle platform corbel tracks and track support columns.

2. Installation of vehicle platform corbel tracks and track support columns in the VAB.

3. Reinforcing of the VAB existing structure (per drawing package

79K40725).

4. Installation of 4 new strand jack support platforms (per drawing package 79K40596).

5. Fabrication and installation of new catwalk and mechanical platform addition for quad valves (per this drawing package) and strand jack platform (per drawing package 79K40596) at VAB

LEVEL 34.

6. Fabrication and installation of new supports for piping/duct in

VAB HB-3.

7. Installation of 2 New Quad Valves and associated pipes.

8. Installation and testing of fire alarm and fire protection systems.

9. Programming of elevator controls for VAB elevator numbers 13 through 16.

10. Architectural modifications in VAB HB-3.

11. Installation of mechanical, electrical, and plumbing components for VAB HB-3.

12. Modification of gas lines (for quad valves) in the building.

13. Pressure grouting under Slap Stand slab panel in Transfer

Aisle.

14. Installation of 4 new extensible platform halves without inserts

(new Platform A at final Block lB elevation, new Platform Bat temporary elevation = 364'-0").

15. Installation of 6 new fixed landing platforms: at VAB Levels 24, 29, and 32.

16. Installation of 2 new egress ramps: new Platform A egress ramp will be installed at final Block 1B elevation; new Platform B egress ramp will be stored during Phase 2.

17. Installation of 4 new elevator landing platforms (new Platform A ELP at final Block 1B elevation, new Platform B ELP at temporary elevation = 364'-0").

18. Install, terminate, and test communication cables for new extensible halves of Platform A.

Phase 2 will consist of the following construction activities:

1. Fabrication of vehicle platform corbel tracks and track support columns.

2. Installation of vehicle platform corbel tracks and track support columns in the VAB.

3. Reinforcing of the VAB existing structure (per drawing package

79K40725) in HB-1, HB-2, HB-4, and Transfer Aisle.

4. Installation of 4 new strand jack support platforms (per drawing package 79K40596).

5. Fabrication and installation of new catwalk and mechanical platform addition for quad valves (per this drawing package) and strand jack platform (per drawing package 79K40596) at VAB

LEVEL 34.

6. Fabrication and installation of new supports for piping/duct in

VAB HB-3.

7. Installation of 2 New Quad Valves and associated pipes.

8. Installation and testing of fire alarm and fire protection systems.

9. Programming of elevator controls for VAB elevator numbers 13 through 16.

10. Architectural modifications in VAB HB-3.

11. Installation of mechanical, electrical, and plumbing components for VAB HB-3.

12. Modification of gas lines (for quad valves) in the building.

13. Pressure grouting under Slap Stand slab panel in Transfer

Aisle.

14. Installation of 4 new extensible platform halves without inserts (new Platform A at final Block lB elevation, new Platform Bat temporary elevation = 364'-0").

15. Installation of 6 new fixed landing platforms: at VAB Levels 24, 29, and 32.

16. Installation of 2 new egress ramps: new Platform A egress ramp will be installed at final Block 1B elevation; new Platform B egress ramp will be stored during Phase 2.

17. Installation of 4 new elevator landing platforms (new Platform A ELP at final Block 1B elevation, new Platform B ELP at temporary elevation = 364'-0").

18. Install, terminate, and test communication cables for new extensible halves of Platform A.

Specification Section 01 33 00 part 1.12 change as follows:

The Contracting Officer's approval or acceptance of submittals is not to be construed as a complete check, and indicates only that the general method of construction, materials, detailing and other information are satisfactory. design, general method of construction, materials, detailing and other information appear to meet the Solicitation and Accepted Proposal.

Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor under the Contractor Quality Control (CQC) requirements of this contract is responsible for dimensions, the design of adequate connections and details, and the satisfactory construction of all work design, dimensions, all design extensions, such as the design of adequate connections and details, etc., and the satisfactory construction of all work.

To:

The Contracting Officer's approval or acceptance of submittals is not to be construed as a complete check, and indicates only that the general method of construction, materials, detailing and other information are satisfactory. design, general method of construction, materials, detailing and other information appear to meet the Solicitation and Accepted Proposal.contract requirements.

Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor under the Contractor Quality Control (CQC) requirements of this contract is responsible for dimensions, the design of adequate connections and details, and the satisfactory construction of all work design, dimensions, all design extensions, such as the design of adequate connections and details, etc., and the satisfactory construction of all work.

Specification Section 05 12 00 part 3.2.2 change as follows:

3.2.2. Tension Control Bolts

If Contractor elects to use tension control bolts, bolts must be installed in connection holes and initially brought to a snug tight fit.

After the initial tightening procedure, bolts must then be fully tensioned, progressing from the most rigid part of a connection to the free edges. Fastener pre-load shall not exceed 70% of the yield stress of the net cross-section.

To:

3.2.1.2 3.2.2 Tension Control Bolts

If Contractor elects to use tension control bolts, bolts must be installed in connection holes and initially brought to a snug tight fit.

After the initial tightening procedure, bolts must then be fully tensioned, progressing from the most rigid part of a connection to the free edges. Fastener pre-load shall not exceed 70% of the yield stress of the net cross-section.

Specification Section 01 45 35 Delete this section in its entirety.

Specification Section 22 15 14.00 40 part 1.1 add:

ASTM A380 Standard Practice for Cleaning, Descaling, and Passivation of Stainless-Steel Parts, Equipment, and Systems ASTM A967 Standard Specification for Chemical Passivation Treatments for Stainless Steel Parts NASA STD-8719.17 Requirements for Ground-Based Pressure Vessels and Pressurization Systems

Specification Section 22 15 14.00 40 part 3.1.2.1 change as follows:

From:

Ensure pipe, tubing, fittings, valves, equipment, and accessories is clean and free of all foreign material before being installed in their respective systems. Clean pipe by a method approved by the Contracting Officer. Purge lines with dry, oil-free compressed air after erection, but do not rely on purging for removing all foreign matter. Purge lines at a velocity equal to 1-1/2 times maximum normal flow velocity. During the progress of construction, protect open ends of pipe, fittings, and valves at all times to prevent the admission of foreign matter. Except when connections are actually underway, install plugs or caps on all pipe and component openings. Use plugs or caps that are commercially manufactured products.

To:

Ensure pipe, tubing, fittings, valves, equipment, and accessories is clean and free of all foreign material before being installed in their respective systems. Clean pipe by a method approved by the Contracting Officer. Purge lines with dry, oil-free compressed air after erection, but do not rely on purging for removing all foreign matter. Purge lines at a velocity equal to 1-1/2 times maximum normal flow velocity. During the progress of construction, protect open ends of pipe, fittings, and valves at all times to prevent the admission of foreign matter. Except when connections are actually underway, install plugs or caps on all pipe and component openings. Use plugs or caps that are commercially manufactured products. Stainless-steel materials and equipment will follow the requirements and comply with ASTM A967 for the specification of passivation of the stainless-steel parts.

Specification Section 22 15 14.00 40 part 3.3 change as follows:

Remove rust and dirt from the bore and exterior surface of all piping and equipment. Clean pipeline strainers, temporary and permanent, during purging operations, after startup, and immediately prior to final acceptance by the Government.

To:

Remove rust and dirt from the bore and exterior surface of all piping and equipment. Clean pipeline strainers, temporary and permanent, during purging operations, after startup, and immediately prior to final acceptance by the Government. Stainless-steel materials, piping, and equipment will follow the requirements and comply with ASTM A380 for cleaning, descaling, and passivation of stainless-steel parts.

Specification section 31 32 23 Delete this section in its entirety Specification section 31 99 99 Delete this section it its entirety Specification section 40 34 10 part 1.1 add:

ASTM A380 Standard Practice for Cleaning, Descaling, and

Passivation of Stainless-Steel Parts, Equipment, and Systems ASTM A967 Standard Specification for Chemical Passivation Treatments for Stainless Steel Parts NASA STD-8719.17 Requirements for Ground-Based Pressure Vessels and Pressurization Systems

Specification Section 40 34 10 part 1.3 change as follows:

From:

Tube Cleanliness; G

The Contractor shall submit for approval prior to the start of fabrication a cleaning procedure to show compliance with ISO 14952. The Contractor is also responsible for maintaining and preserving the cleanliness of all existing precision cleaned components, GFE and tubing in accordance with the cleanliness level indicated on the drawing. A certification of cleanliness shall be submitted in the final data package.

To:

Tube Cleanliness; G

The Contractor shall submit for approval prior to the start of fabrication a cleaning procedure to show compliance with ISO 14952, ASTM A380 and ASTM A967. The Contractor is also responsible for maintaining and preserving the cleanliness of all existing precision cleaned components, GFE and tubing in accordance with the cleanliness level indicated on the drawing. A certification of cleanliness shall be submitted in the final data package.

Specification Section 40 34 10 part 2.2 change as follows:

2.2 STAINLESS STEEL TUBING SYSTEM

Stainless steel tubing shall be fabricated and installed per KSC-SPEC-Z-0008. Tube material shall be AL6XN per KSC-SPEC- P-0027. Tubing thickness requirements are shown on the drawings.

All tubing shall be provided by the contractor.

NOTE: KSC-SPEC-Z-0008 does not address the use of AL6XN tube material. All requirements in KSC-SPEC-Z-0008 shall apply to AL6XN tubing except the following:

The test ball size used for checking the tube inside diameter after bending shall be 0.344" for 1/2"x0.049" wall tube and 0.250" for 3/8"x0.035" wall tube. Note: These tube sizes are not presently used for this project.

A schedule showing all tubing sizes and thicknesses shall be developed by the Contractor.

To:

Stainless steel tubing shall be fabricated and installed per KSC-SPEC-Z-0008. Tube material shall be AL6XN per KSC-SPEC- P-0027. Tubing thickness requirements are shown on the drawings.

All tubing shall be provided by the contractor. All tubing materials shall be cleaned and passivated per ASTM A380 and ASTM A967.

NOTE: KSC-SPEC-Z-0008 does not address the use of AL6XN tube material. All requirements in KSC-SPEC-Z-0008 shall apply to AL6XN tubing except the following:

The test ball size used for checking the tube inside diameter after bending shall be 0.344" for 1/2"x0.049" wall tube and 0.250" for 3/8"x0.035" wall tube. Note: These tube sizes are not presently used for this project.

A schedule showing all tubing sizes and thicknesses shall be developed by the Contractor.

Specification Section 40 34 10 part 3.7 change as follows:

3.7 CLEANING

Tube cleanliness shall be verified in accordance with ISO 14952, flushing media shall be per ISO 14952.

Required Cleanliness Levels:

Fluid Type Cleanliness Level (per ISO 14952)

Gaseous Nitrogen (GN2) 300A, Breathing Air (BA) l00A, and Gaseous Helium (GHe) 300A.

Submit the cleaning Procedure to the Government prior to cleaning implementation.

Waste water shall be disposed per Contractors submitted plan.

3.7 CLEANING

Tube cleanliness shall be verified in accordance with ISO 14952, flushing media shall be per ISO 14952. All tubing materials shall be cleaned and passivated per ASTM A380 and ASTM A967.

Required Cleanliness Levels:

Fluid Type Cleanliness Level (per ISO 14952)

Gaseous Nitrogen (GN2) 300A, Breathing Air (BA) l00A, and Gaseous Helium (GHe) 300A.

Submit the cleaning Procedure to the Government prior to cleaning implementation.

Waste water shall be disposed per Contractors submitted plan.

Specification Section 40 50 00 part 1.1 add:

ASTM A380 Standard Practice for Cleaning, Descaling, and Passivation of Stainless-Steel Parts, Equipment, and Systems ASTM A967 Standard Specification for Chemical Passivation Treatments for Stainless Steel Parts NASA STD-8719.17 Requirements for Ground-Based Pressure Vessels and Pressurization Systems

Specification Section 40 50 00 part 1.5 SD-11 change as follows:

Cleaning Reports

Note: See the following specification sections for detailed submittal requirements: 22 15 14.00 40, General Service Compressed-Air Systems, Low Pressure; 40 05 13.96, Welding Process Piping; and 40 34 10, Stainless Steel Tubing.

To:

Cleaning Reports

Systems shall also be in compliance with NASA STD-8719.17.

Note: See the following specification sections for detailed submittal requirements: 22 15 14.00 40, General Service Compressed-Air Systems, Low Pressure; 40 05 13.96, Welding Process Piping; and 40 34 10, Stainless Steel Tubing.

Specification Section 40 50 00 part 3.7 change as follows:

Refer to 40 34 10, "STAINLESS STEEL TUBING" for tubing cleaning. Surface cleanliness of fluid systems shall be in accordance with ASTM G93. Cleanliness and test method shall be specified in the design documentation. All piping shall be cleaned and verified clean, in accordance with ISO 14952 as follows:

To:

Refer to 40 34 10, "STAINLESS STEEL TUBING" for tubing cleaning. Surface cleanliness of fluid systems shall be in accordance with ASTM G93. Cleanliness and test method shall be specified in the design documentation. All piping shall be cleaned and verified clean, in accordance with ISO 14952, ASTM A380, and ASTM A967 as follows: