Attachment 8 - UFGS 01 45 00.00 40-QUALITY CONTROL.pdf

PDF 60 KB Posted

Attached to
349 AMW Facility Project B239 Renovation Federal contract opportunity
Solicitation number
FA442720R0044
Issued by
Department of the Air Force Air Mobility Command

About this file

This document provides quality control specifications for a federal construction contract. The contractor will be responsible for quality control and assurance programs to ensure all work meets contract requirements. This includes designating a quality control manager and maintaining systems to identify nonconforming materials, control procurement sources, and document inspections, audits, and test records. The contractor must submit qualifications for quality representatives, quality plans, inspection narratives and reports, and letters delegating quality responsibilities. The government retains inspection rights and must be notified before critical construction stages. Failure to notify or correct deficiencies may result in work being uncovered at the contractor's expense. Quality records must be kept and provided to the government for review.

View the file

Other files for this federal contract opportunity

Other files attached to 349 AMW Facility Project B239 Renovation, newest first.
File Type Posted
Solicitation Amendment FA442720R00440004 SF 30.pdf PDF
Bldg 239 Bay G RFIs 8-31-2020.pdf PDF
239 BayDPanel.pdf PDF
239 As-builts Combined Files.pdf PDF
Solicitation Amendment FA442720R00440003 SF 30.pdf PDF
Solicitation Amendment FA442720R00440002 SF 30.pdf PDF
Solicitation Amendment FA442720R00440001 SF 30 (1).pdf PDF
Attachment 10 - UFGS 01 78 00 Closeout Submittals.pdf PDF
Attachment 4 - Travis Design Guide FEG.PDF PDF
Travis AFB_B239_Final Drawings.pdf PDF
Solicitation - FA442720R0044.pdf PDF
Attachment 11 - Past Performance Questionnaire.pdf PDF
Attachment 1 - SOW B239 dated 9 June 2020.pdf PDF
Attachment 6 - UFGS 01 33 00- SUBMITTAL PROCEDURES.pdf PDF
23 09 00 Johnson Controls Spec.pdf PDF
AFRC Interior Design Policy Manual.pdf PDF
Attachment 2 - TAFB Security Clause dated 05 Mar 19.pdf PDF
Attachment 7 - UFGS 01 35 26-GOVERNMENTAL SAFETY REQUIREMENTS.pdf PDF
Attachment 9 - UFGS 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS.pdf PDF
SECTION 01000 Updated 07 Jun 19.pdf PDF
Attachment 5 - UFGS 01 14 00 WORK RESTRICTIONS.pdf PDF
Travis AFB_B239_Final Specifications.pdf PDF
Attachment 3 - WD CA20190007 dated 08 May 2020.pdf PDF
SECTION 01 56 00_Environmental Specifications April 2019.pdf PDF
Show all 24

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 01 45 00.00 40 Page 1

SECTION TABLE OF CONTENTS DIVISION

01 - GENERAL REQUIREMENTS SECTION

01 45 00.00 40

QUALITY CONTROL

11/14

PART 1 GENERAL

1.1 SUMMARY

1.2 ADMINISTRATIVE REQUIREMENTS

1.3 SUBMITTALS

1.4 QUALITY CONTROL

1.4.1 Qualifications of Quality Representative

1.4.2 Quality Control Requirements

1.4.2.1 Management and Organization

1.4.2.2 Identification and Data Retrieval

1.4.2.3 Procurement

1.4.2.4 Receiving Inspection System

1.4.2.5 Nonconforming Articles and Material Control

1.4.2.6 Fabrication, Process, and Work Control

1.4.2.7 Quality Control Records

1.4.2.8 Drawings and Change Control

1.4.3 Quality Inspections

1.4.3.1 Government Inspections

1.4.3.2 Contractor's Quality Inspections

1.4.4 Field Services

1.4.4.1 Responsibility for Inspection and Testing

1.4.4.2 Inspection and Test Records

1.5 DELIVERY, STORAGE, AND HANDLING

PART 2 PRODUCTS

2.1 SYSTEM DESCRIPTION

2.1.1 Quality Assurance (QA) Plan

2.1.2 Records

2.1.2.1 Narrative Description

2.1.2.2 Monthly Performance Report

2.1.2.3 Letters of Authority or Delegation

2.1.2.4 Off-Site Inspection and Control

PART 3 EXECUTION

-- End of Section Table of Contents --

SECTION 01 45 00.00 40 Page 2

QUALITY CONTROL

11/14

PART 1 GENERAL

1.1 SUMMARY

The requirements of this Section apply to, and are a component part of, each section of the specifications.

1.2 ADMINISTRATIVE REQUIREMENTS

Provide 24 hour advance notice to the Government of the date when the contract work begins at the site, 72 hours if on the active airfield.

Notify the Contracting Officer when work is suspended for 2 calendar days or longer prior to completion. Do not resume work without notification of the Contracting Officer.

Notify the Contracting Officer at least 24 hours in advance of backfilling or encasing any underground utility.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

Quality Assurance (QA) Plan; G

SD-06 Test Reports

Quality Control Data; G

Quality Control Coordinating Actions; G

Quality Control Training; G

Inspection Records; G

Letters of Authority or Delegation; G

Field Tests; G

Factory Tests; G

SD-07 Certificates

Contractor's Quality Representative Qualifications; G

Special Certifications; G

Monthly Reports; G

SECTION 01 45 00.00 40 Page 3

1.4 QUALITY CONTROL

1.4.1 Qualifications of Quality Representative

Submit contractor's quality representative qualifications to the Contracting Officer for approval. Quality Representative may be assigned to more than one contract provided that the assigned contracts are located at the same site.

When approval or certification of special processes, operating personnel, and special equipment or procedures is required by the specifications, obtain necessary approvals or special certifications prior to starting the work.

1.4.2 Quality Control Requirements

Provide a quality control program including: selection of construction materials and sources; suppliers; subcontractors; on-site and off-site fabrication of Contractor-furnished assemblies; on-site and off-site assembly; erection; work procedures; workmanship; inspection; and testing.

Provide document systems ensuring that quality provisions of contract schedule, specifications, and drawings have been performed.

1.4.2.1 Management and Organization

Designate an individual within the on-site organization whose sole responsibility is the day-to-day on-site management and direction of the Quality Program.

The Quality Program Manager reports to the Contractor's management and have the necessary authority to discharge contractual responsibilities.

1.4.2.2 Identification and Data Retrieval

Provide an identification and data retrieval system identifying all records, drawings, submittals, and equipment by referencing the following:

a. Contract Number

b. Contract Specification Number

c. Contract Drawing Number

d. Submittal Document Number

e. Contract Change Number

f. Contractor's Drawing Number System

1.4.2.3 Procurement

Assume responsibility for controlling procurement sources and those of the subcontractors to ensure that each purchase meets quality requirements.

1.4.2.4 Receiving Inspection System

SECTION 01 45 00.00 40 Page 4

Maintain a site receiving inspection system that ensures procured materials and equipment are inspected and tested.

Ensure receiving inspection records accompany each procurement delivery to the construction site. Maintain records of site receiving inspections.

Show defects, discrepancies, dispositions, and waivers, including evidence of Government source inspection within the records.

1.4.2.5 Nonconforming Articles and Material Control

Control nonconformance's discovered by the Contractor, subcontractors, suppliers or Government quality representatives to prevent their use and to correct deficient operations.

a. Prepare a "nonconformance" report for each instance comprising:

(1) A unique and traceable number.

(2) Identification of the nonconforming article or material.

(3) A description of the nonconformance and the applicable requirement.

(4) Cause or reason for the nonconformance.

(5) Remedial actions taken or recommended.

(6) Disposition of the nonconforming article or material.

b. Identify and mark each nonconforming article for removal from the work area.

c. Monitor and correct deficient operations.

1.4.2.6 Fabrication, Process, and Work Control

Ensure compliance of requirements in contract specifications and drawings with procedures and controls.

Establish in-process inspections, to ensure compliance with quality requirements.

Special processes may include, but are not limited to, plating, anodizing, nondestructive testing, welding, and soldering.

1.4.2.7 Quality Control Records

Maintain Quality Control records at a central on-site location.

Maintenance of quality control records does not provide relief from submitting samples; test data, detail drawings, material certificates, or other information required by each section in the specification.

Ensure each record is identified and traceable to specific requirements in the specifications and drawings.

1.4.2.8 Drawings and Change Control

Maintain drawing-control system to provide revised drawings and ensure continuous removal of obsolete drawings from work areas. Control changes

SECTION 01 45 00.00 40 Page 5 involving interface with other work areas, or affecting materials controlled by others. Integrate this system with the document requirements of the contract.

Clearly annotate and identify drawing changes and associated drawings for implementation ion that are to be revised accordingly. Use for fabrication and inspection drawings that have been approved, or approved as noted, by the Contracting Officer.

1.4.3 Quality Inspections

1.4.3.1 Government Inspections

Work performed under this contract is subject to inspection by the Contracting Officer. Changes to the specifications or drawings will not be allowed without written authorization of the Contracting Officer.

When the Contracting Officer determines that inspected work needs to be corrected, the Contracting Officer will be allowed 24 hours to complete re-inspection of the corrected work.

Notify Contracting Officer in writing before backfilling or encasing any underground utility (covering of any work attribute) so that work may be inspected. Failure to notify the Contracting Officer before backfill or encasement occurs will require the work be uncovered at no additional cost to the Government.

Contractor's program is subject to continuous evaluation, review, and verification by the Contracting Officer. Contractor will be notified in writing of any noncompliance and will be given 7 calendar days to correct identified deficiencies.

1.4.3.2 Contractor's Quality Inspections

Implement an inspection system that documents and indicates quality control through records of inspections, tests, and procedures.

Include the following within the Quality Assurance System:

a. Identify the representative responsible for on-site communication and operation of the inspection program.

b. Purchasing control system documenting project procurement to drawings, specifications, and approved submittals.

c. A receiving inspection system documenting inspections for each procurement.

d. Documentation for handling and disposing of nonconforming components and materials.

e. Inspection records for each specific section of the specification and drawings.

f. Identification of test(s) to be performed, test procedures, records, and independent organizations used.

g. Documenting and maintaining certification or re-certification of procedures.

h. Management of government-furnished equipment, components, and

SECTION 01 45 00.00 40 Page 6 materials.

i. Calibration of gages, tools, measuring instruments, and independent laboratories used.

Establish a system of scheduled or random audits to ensure task completion.

1.4.4 Field Services

1.4.4.1 Responsibility for Inspection and Testing

Assume responsibility for all inspections and tests, and the accompanying documentation for each inspection and test. Utilize independent inspection and testing laboratories or services as approved by the Contracting Officer.

Assume responsibility for tests of construction materials utilizing the services of an approved independent testing laboratory.

1.4.4.2 Inspection and Test Records

Provide on-site records of each inspection and test performed throughout the life of the contract including, but not be limited to; factual evidence that the required inspections or tests have been performed, including type and number of inspections or tests involved, identification of operators and inspectors, result of inspections or tests, nature of defects, causes for rejection, proposed remedial action, and corrective actions taken.

Ensure all inspection records, test procedures, test results, and associated forms are verified by and provided to the Contracting Officer. Submit final test data with a cover letter/sheet clearly marked with the system name, date, and the words "Final Test Data - Forward to the Systems

Engineer/Condition Monitoring Office/Predictive Testing Group for inclusion in the Maintenance Database".

Notify the Government at least 24 hours prior to scheduled inspections and tests.

1.5 DELIVERY, STORAGE, AND HANDLING

Provide controls, procedures and documentation with each shipment that meet requirements of each section of the specifications.

Include documentation with each shipment that consist of documentation required by the contract along with specifications required to identify, store, preserve, operate, and maintain the items shipped.

PART 2 PRODUCTS

2.1 SYSTEM DESCRIPTION

2.1.1 Quality Assurance (QA) Plan

Submit a QA Plan that addresses the following:

a. Description of the authority, responsibilities and coordinating procedures, of on-site/off-site quality assurance personnel, SECTION 01 45 00.00 40 Page 7 including those QA personnel not under direct control of the Contractor.

b. List personnel designated to accomplish the work required by the contract.

c. Provide an appendix with a copy of each form, report format, or similar record to be used in the QA program.

d. The organization that handles construction contract activities.

e. The operational plan for accomplishing and reviewing work controls, fabrication controls, certifications, and documentation of quality control operations, inspections, and test records, including those for subcontractors.

f. Include within these provisions the methods used during the procurement cycle (order to delivery) for those materials or equipment that require source inspections, shop fabrications, or similar operations located separately from the work site.

g. Description of on-site personnel training.

h. Certification(s) of personnel, procedures, processes, and equipment.

i. Non-Destructive Testing (NDT) requirements.

j. Identification of independent certifying and testing laboratories.

2.1.2 Records

Include all quality control data; factory tests or manufacturer's certifications, quality control coordinating actions; records of quality control training/certifications as well as routine hydrostatic, electrical continuity, grounding, welding, line cleaning, field tests and similar tests. Ensure quality records are available for examination by the Contracting Officer.

Furnish legible copies of the test and inspection records to the Contracting Officer. Ensure records cover work placement traceable to the contract schedule, specifications and drawings, and are verifiable.

2.1.2.1 Narrative Description

Submit for approval, the narrative description of an inspection system which provides for compliance with the quality requirements and technical criteria of the contract within 7 calendar days after notice to proceed.

2.1.2.2 Monthly Performance Report

Submit a monthly performance report monthly reports that summarizes the quality operations. Identify inspections made, tests performed, nonconformance's, corrective actions taken, status of plans/procedures being developed, and status of open items/problems in work.

2.1.2.3 Letters of Authority or Delegation

Submit letters of authority or delegation outlining the authority and responsibilities of quality control personnel along with a copy of the letter of delegation to the Contracting Officer that defines delegated duties and responsibilities.

SECTION 01 45 00.00 40 Page 8

2.1.2.4 Off-Site Inspection and Control

In-process inspection records and control away from the job site may be used as evidence of quality of materials/work and may reduce further inspection or testing after delivery to the job site.

PART 3 EXECUTION

Not Used

-- End of Section --