This scope of work document outlines the requirements for a renovation project at building B239 of an Air Force base. The contractor will be responsible for renovating bay G of building B239, including new construction work associated with a reconfigured layout, such as new stud walls, flooring, ceilings and doors. The contractor will also renovate the existing mechanical, electrical and communication systems in the project area, including all equipment, ductwork, diffusers, piping and controls. The exterior mechanical enclosure will be demolished and replaced to accommodate new equipment. The contractor must test for lead paint and asbestos, follow the Air Force interior design policy manual for materials selection, and adhere to the general requirements and mitigation measures specified in the attachments. References and attachments include design drawings, basis of design documents, structural designs, policy manuals and specification sections.
View the file
Other files for this federal contract opportunity
Show all 24
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCOPE OF WORK
Project Name: Interior Renovation Bay G B239
XDAT # 17-1064
09 June 2020
1. SCOPE
1.2 Renovate B239 Bay G.
1.3 Work to include:
i. New construction associated with reconfigured building layout, as noted including, but not limited to, new stud walls, floor and wall finishes, ceilings, and doors.
ii. Renovation of the existing mechanical, electrical, and communication systems in the project area including all equipment, ductwork, diffusers, piping, and controls as noted.
iii. Demolition of the existing exterior mechanical enclosure and construction of new exterior mechanical enclosure to accommodate new equipment.
2. REQUIREMENTS
2.1 General Requirements
2.1.1 Contractor to test for lead paint & asbestos.
2.1.2 Contractor to follow AFRC Interior Design Policy Manual for materials
2.1.3 Contractor to follow Division 01 General Requirements Section 01000.
2.2 Special Requirements
2.2.1 See Design Drawings (Attachment 1), Basis of Design (Attachment 2) and Structural
Design (Attachment 3).
2.2.2 Contractor shall follow mitigation measures/requirements as required in Section 01 56 00, Environmental General Requirements
2.2.3 Contractor shall subcontract any work on Johnson EMS controllers to Johnson Controls.
3. REFERENCES
3.1.1 See A-E Design Drawings (Attachment 1), Basis of Designs (Attachment 2) and Structural
Design (attachment 3).
4. ATTACHMENTS
Attachment 1: 100% B239 Design Drawings Attachment 2: 100% B239 Basis of Design Attachment 3: 100% B239 Structural Design Attachment 4: AFRC Interior Design Policy Manual Attachment 5: Division 01 General Requirements 01000 (03/22/2019) Attachment 6: Section 01 56 00 Environmental General Requirements (04/05/2019) Attachment 7: 23 90 00 Johnson Controls Specification
//End of S.O.W. //
| SCOPE OF WORK |
| Project Name: Interior Renovation Bay G B239 |
| XDAT # 17-1064 |
1.2 Renovate B239 Bay G.