Attachment 5 - UFGS 01 14 00 WORK RESTRICTIONS.pdf

PDF 34 KB Posted

Attached to
349 AMW Facility Project B239 Renovation Federal contract opportunity
Solicitation number
FA442720R0044
Issued by
Department of the Air Force Air Mobility Command

About this file

This document contains specifications for a federal contract opportunity to renovate Building 239 at Travis Air Force Base in California. The contractor will be responsible for all professional services, permits, equipment, labor, materials, and ancillary items necessary to complete HVAC upgrades and relocation work, interior room repurposing with new stud walls and floor/wall finishes, ceilings, doors, electrical and communication systems, and construction of an outside mechanical HVAC enclosure. The designs will be provided by the 60th Contracting Squadron. The specifications outline work restrictions including requirements to request permission for interruptions to roads or utilities at least 15 days in advance, comply with base regulations, and obtain approvals for any work outside regular hours from 7:30am to 4:30pm Monday through Friday or involving penetrations of restricted areas.

View the file

Other files for this federal contract opportunity

Other files attached to 349 AMW Facility Project B239 Renovation, newest first.
File Type Posted
Solicitation Amendment FA442720R00440004 SF 30.pdf PDF
Bldg 239 Bay G RFIs 8-31-2020.pdf PDF
239 BayDPanel.pdf PDF
239 As-builts Combined Files.pdf PDF
Solicitation Amendment FA442720R00440003 SF 30.pdf PDF
Solicitation Amendment FA442720R00440002 SF 30.pdf PDF
Solicitation Amendment FA442720R00440001 SF 30 (1).pdf PDF
Attachment 1 - SOW B239 dated 9 June 2020.pdf PDF
Attachment 6 - UFGS 01 33 00- SUBMITTAL PROCEDURES.pdf PDF
23 09 00 Johnson Controls Spec.pdf PDF
Travis AFB_B239_Final Specifications.pdf PDF
Attachment 8 - UFGS 01 45 00.00 40-QUALITY CONTROL.pdf PDF
Attachment 3 - WD CA20190007 dated 08 May 2020.pdf PDF
SECTION 01 56 00_Environmental Specifications April 2019.pdf PDF
Attachment 10 - UFGS 01 78 00 Closeout Submittals.pdf PDF
Attachment 4 - Travis Design Guide FEG.PDF PDF
Travis AFB_B239_Final Drawings.pdf PDF
Solicitation - FA442720R0044.pdf PDF
Attachment 11 - Past Performance Questionnaire.pdf PDF
AFRC Interior Design Policy Manual.pdf PDF
Attachment 2 - TAFB Security Clause dated 05 Mar 19.pdf PDF
Attachment 7 - UFGS 01 35 26-GOVERNMENTAL SAFETY REQUIREMENTS.pdf PDF
Attachment 9 - UFGS 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS.pdf PDF
SECTION 01000 Updated 07 Jun 19.pdf PDF
Show all 24

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 01 14 00, Page 1

SECTION 01 14 00

WORK RESTRICTIONS

11/11

PART 1 GENERAL

1.1 SPECIAL SCHEDULING REQUIREMENTS

a. Permission to interrupt any Activity roads, railroads, and/or utility service shall be requested in writing a minimum of 15 calendar days prior to the desired date of interruption.

1.2 CONTRACTOR ACCESS AND USE OF PREMISES

1.2.1 Activity Regulations

Ensure that Contractor personnel employed on the Project become familiar with and obey Project regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. To minimize traffic congestion, delivery of materials shall be outside of peak traffic hours (6:30 to 8:00 a.m. and 3:30 to 5:00 p.m.) unless otherwise approved by the Contracting Officer. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. The Contractor's equipment shall be conspicuously marked for identification.

1.2.1.1 Employee List

The Contractor shall provide to the Contracting officer, in writing, the names of two designated representatives authorized to request personnel and vehicle passes for employees and subcontractor's employees prior to commencement of work under this contract. The Contractor shall adhere to the requirements of the Air Force Background Checks requirements in obtaining access to Travis Air Force Base for the life of the contract. A copy of these requirements will be provided at the preconstruction conference.

1.2.2 Travis Air Force Base

Ensure that Contractor personnel employed on the Project become familiar with and obey Travis Air Force Base regulations. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. The Contractor's equipment shall be conspicuously marked for identification. Comply with the following conditions:

a. Restrict employees/representatives to the work site and control travel directly to and from the work site.

b. Restore all traffic/parking/security signs and markings, including space numbers, designations, and lines, to their original form if such signs/markings are defaced or deleted during construction/repair.

c. Be responsible for control and security of Contractor-owned equipment and materials at the work site. Report immediately

SECTION 01 14 00, Page 2 missing/lost/stolen property to the Travis Air Force Base Police Department as each case occurs.

d. Seventy-two hours prior to making any penetrations (such as tunneling under, cutting through a fence or building) in a restricted area, contact the Travis Air Force Base Security Office to make arrangements for a security guard or other measures required to meet all security requirements. Cost of security guard will be charged to the Contractor.

e. Seventy-two hours prior to performing any work on the airfield, contact the Travis Air Force Base Airfield Management Operations Desk at 707-424-2836 for prior approval and publishing of the Notice-to-Airman (NOTAM) prior to any work commencing.

1.2.3 Working Hours

Regular working hours shall consist of an 8-1/2 hour period, established by the Contractor Officer, between 7:30 a.m. and 4:30 p.m., Monday through Friday, excluding Government holidays.

1.2.4 Work Outside Regular Hours

Work outside regular working hours requires Contracting Officer approval.

Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work shall be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.

1.2.5 Utility Cutovers and Interruptions

a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in the paragraph "Work Outside Regular Hours."

b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.

c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, and compressed air shall be considered utility cutovers pursuant to the paragraph entitled "Work Outside Regular Hours."

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --