Attachment 4 AFD Volume 1 Construction Specifications.pdf
PDF 5 MB Posted
- Attached to
- AFD Visitor Center Remodel Federal contract opportunity
- Solicitation number
- 1240LU26Q0022
- Issued by
- Department of Agriculture Forest Service
About this file
This document is a comprehensive construction specification manual (Project Manual, Volume 1) for the AFD Smokejumper Visitor Center project located at 5765 US Highway 10 West, Missoula, Montana. The 100% construction specifications were prepared by Mosaic Architecture, P.C. (Helena, Montana) and include detailed requirements across 34 divisions covering site work, structural systems, finishes, and specialty items.
The specifications establish quality standards, submission procedures, and execution requirements for all construction work. Key specifications include: unclassified excavation and earthwork with compaction density testing (95% maximum dry density per ASTM D698); concrete work (M-4000 strength for slabs and structural elements); steel and wood framing with fire-retardant treatments where required; exterior and interior finishes including gypsum board assemblies, ceramic tile, resilient flooring (LVT and carpet tile), and paint systems; aluminum-framed storefronts and wood windows with thermal performance requirements; hollow metal and wood doors with hardware scheduling; and specialized systems such as an incline wheelchair lift (Garaventa Stair-Lift Model GSLArtira), fire protection equipment, and accessible toilet/bath accessories. All materials must comply with VOC content restrictions, include USA Certificates of Origin, and meet accessibility standards (ADA/ICC A117.1). Contractors must submit shop drawings, product data, samples, and test reports for architect review; substitutions require written approval via addendum prior to bid date. Quality assurance testing by independent laboratories is required for concrete (cylinder strength, air content, slump), soils (in-place density, moisture), and pipe installation. The project emphasizes erosion and sediment control, waste management and recycling, and closeout documentation including operation and maintenance manuals, warranties, and as-built records.
View the file
Other files for this federal contract opportunity
Show all 21
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT MANUAL FOR:
AFD SMOKEJUMPERAFD SMOKEJUMPERAFD SMOKEJUMPERAFD SMOKEJUMPER
VISITOR CENTERVISITOR CENTERVISITOR CENTERVISITOR CENTER
VOLUME VOLUME VOLUME VOLUME 1111
Date: September 30, 2024
100% Construction Specifications
ARCHITECTARCHITECTARCHITECTARCHITECT
MOSAIC ARCHITECTURE, P.C.MOSAIC ARCHITECTURE, P.C.MOSAIC ARCHITECTURE, P.C.MOSAIC ARCHITECTURE, P.C.
317 North Cruse Ave, Suite 201
Helena, Montana 59601
Phone: 406-449-2013 www.mosaicarch.com
PROJECT INFORMATION SHEET
AFD SMOKEJUMPER VISITOR CENTER
PROJECT LOCATION
5765 US Highway 10 West Missoula, MT 59808
ARCHITECT:
Mosaic Architecture, P.C.
317 Cruse Ave Suite 201 Helena, Montana 59601 ph: 406-449-2013 Matt Aune, AIA matta@mosaicarch.com Katie Brodowy, AIA katie@mosaicarch.com
CIVIL ENGINEER:
Great West Engineering, Inc 2501 Belt View Drive Helena, MT 59601 ph: 406-449-8627 Josh Sommer, PE jsommer@greatwesteng.com
MECHANICAL/PLUMBING ENGINEER:
Morrison-Maierle 1055 Mount Avenue Missoula, MT 59801 ph: 406-542-8880 Garth Stevens, PE gstevens@m-m.net
ELECTRICAL ENGINEER:
Morrison-Maierle 1055 Mount Avenue Missoula, MT 59801 ph: 406-542-8880 Lukash Pruss, PE lpruss@m-m.net mailto:matta@mosaicarch.com mailto:katie@mosaicarch.com mailto:jsommer@greatwesteng.com mailto:gstevens@m-m.net mailto:lpruss@m-m.net
TABLE OF CONTENTS Page 1
124LU22F0155/ AFD
Smokejumper Visitor Center
TABLE OF CONTENTS
DIVISION 01 – GENERAL REQUIRMENTS
01 2105 SUBSTITUTION PROCEDURE
01 3000 ADMINISTRATIVE REQUIRMENTS
01 4000 QUALITY REQUIREMENTS
01 5000 TEMPORARY FACILITIES AND CONTROLS
01 5713 TEMPORARY EROSION AND SEDIMENT CONTROL
01 6000 PRODUCT REQUIRMENTS
01 6116 VOLATILE ORGANIC COMPOUND (VOC)
01 7000 EXECUTION AND CLOSEOUT REQUIRMENTS
01 7419 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
01 7800 CLOSEOUT SUBMITTALS
DIVISION 02 – EXISTING CONDITION
02 4100 DEMOLITION
02 4113 SELECTIVE SITE DEMOLITION
DIVISION 03 - CONCRETE
03 3000 CAST-IN-PLACE CONCRETE – (SITE)
DIVISION 05 - METALS
05 5213 PIPE AND TUBE RAILINGS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 1000 ROUGH CARPENTRY
06 2000 FINISH CARPENTRY
06 4100 ARCHITECTURAL WOOD CASEWORK
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 2100 THERMAL INSULATION
07 7123 MANUFACTURED GUTTERS AND DOWNSPOUTS
07 9200 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 1113 HOLLOW METAL DOORS AND FRAMES
08 1416 FLUSH WOOD DOORS
08 3100 ACCESS DOORS AND PANELS
08 4313 ALUMINUM-FRAMED STOREFRONTS
08 5200 WOOD WINDOWS
08 7100 DOOR HARDWARE
08 8000 GLAZING
DIVISION 09 - FINISHES
09 2116 GYPSUM BOARD ASSEMBLIES
09 3000 TILING
09 6500 RESILIENT WALL BASE
09 6516.23 LVT FLOORING
TABLE OF CONTENTS Page 2
124LU22F0155/ AFD
09 6813 TILE CARPETING
09 8311 ACOUSTICAL BATT INSULATION
09 9000 PAINTING AND COATING
DIVISION 10 - SPECIALTIES
10 1400 SIGNAGE
10 2113.13 METAL TOILET COMPARTMENTS
10 2800 TOILET, BATH, AND LAUNDRY ACCESSORIES
10 4400 FIRE PROTECTION SPECIALTIES
DIVISION 14 – CONVEYING EQUIPMENT
14 4213 INCLINE WHEELCHAIR LIFT
DIVISION 31 - EARTHWORK
31 2000 EARTH MOVING
31 2333 TRENCHING AND BACKFILLING
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 1100 CRUSHED BASE COURSE
32 1313 CONCRETE SIDEWALK AND MISCELLANEOUS NEW CONCRETE CONSTRUCTION
DIVISION 33 - UTILITIES
33 4000 STORM DRAINAGE UTILITIES
124LU22F0155 / AFD
01 2105 - 1 Substitution Procedure
SECTION 01 2105
SUBSTITUTION PROCEDURE
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Section includes administrative and procedural requirements for substitutions.
1.02 DEFINITIONS
A. Substitutions: Changes proposed by contractor in products, materials, equipment and methods of construction from those required by the contract documents.
1.03 SUBMITTALS
A. Submit electronic written request for approval of substitutions to the Architect a minimum of days prior to the date of receipt of bids. Include the following information:
1. Identify product or fabrication or installation method to be replaced. Include Specification
Section number and title and drawing numbers and titles.
2. Documentation: Show compliance with requirements for substitution and the following, as applicable:
a. Coordination information, including a list of changes or modifications needed to other parts of the work and to construction performed by Owner and separate contractors that will be necessary to accommodate proposed substitution.
b. Detailed comparison of significant qualities or proposed substitution with those of the work specified. Include annotated copy of applicable specification section. Significant qualities may include attributes such as performance, weight, size, durability, visual effect, substantial design characteristics, warranties and specific features and requirements indicated. Indicate deviations, if any, from work specified.
c. Product data, including drawings and descriptions of products and fabrication and installation procedures.
d. Samples, where applicable or requested.
e. Certificates and qualification data, where applicable and requested.
f. Material test reports from qualified testing agency indicating and interpreting test results for compliance with requirements indicated.
g. Research reports evidencing compliance with building code in effect for project, from
ICC-ES.
h. Contractors certification that proposed substitution complies with requirements in the contract documents except as indicated in substitution request, is compatible with related materials, and is appropriate for applications indicated.
i. Contractors waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.
3. Architect's Action: After evaluation by Architect, approval will be issued via addendum. No verbal approval will be given.
a. Forms of Acceptance: Addendum.
b. Architect's decision is final on all substitution requests.
c. Use product specified if Architect does not issue a decision by bid day.
d. Substitutions following award of contract are not allowed.
PART 2 PRODUCTS - (NOT USED)
PART 3 - NOT USED
END OF SECTION
01 3000 - 1 Administrative Requirements
SECTION 01 3000
ADMINISTRATIVE REQUIREMENTS
PART 1 GENERAL
1.01 SECTION INCLUDES
A. General administrative requirements.
B. Electronic document submittals.
C. General admisistrative requirement.
D. Electronic document submittal service.
E. Preconstruction meeting.
F. Progress meetings.
G. Construction progress schedule.
H. Submittals for review, information, and project closeout.
I. Requests for Interpretation (RFI) procedures.
1.02 RELATED REQUIREMENTS
A. Section 01 16000 - Product Requirements: General product requirements.
B. Section 01 6000 - Product Requirements: General product requirements.
1.03 GENERAL ADMINISTRATIVE REQUIREMENTS
A. Comply with requirements of Section 01 7000 - Execution and Closeout Requirements for coordination of execution of administrative tasks with timing of construction activities.
B. Make the following types of submittals to Mosaic Architecture:
1. Requests for Interpretation (RFI).
2. Requests for substitution.
3. Shop drawings, product data, and samples.
4. Test and inspection reports.
5. Design data.
6. Manufacturer's instructions and field reports.
7. Applications for payment and change order requests.
8. Progress schedules.
9. Coordination drawings.
10. Correction Punch List and Final Correction Punch List for Substantial Completion.
11. Closeout submittals.
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION
3.01 ELECTRONIC DOCUMENT SUBMITTAL
A. All documents transmitted for purposes of administration of the contract are to be in electronic (PDF, MS Word, or MS Excel) format, as appropriate to the document, and transmitted via an Internet-based submittal service that receives, logs and stores documents, provides electronic stamping and signatures, and notifies addressees via email.
1. Besides submittals for review, information, and closeout, this procedure applies to
Requests for Interpretation (RFIs), progress documentation, contract modification documents (e.g. supplementary instructions, change proposals, change orders), applications for payment, field reports and meeting minutes, Contractor's correction punchlist, and any other document any participant wishes to make part of the project record.
2. Contractor and Mosaic Architecture are required to use this service.
3. It is Contractor's responsibility to submit documents in allowable format.
4. Subcontractors, suppliers, and Mosaic Architecture's consultants will be permitted to use the service at no extra charge.
01 3000 - 2 Administrative Requirements
5. Users of the service need an email address, internet access, and PDF review software that includes ability to mark up and apply electronic stamps (such as Adobe Acrobat, www.adobe.com, or Bluebeam PDF Revu, www.bluebeam.com), unless such software capability is provided by the service provider.
6. Paper document transmittals will not be reviewed; emailed electronic documents will not be reviewed.
7. All other specified submittal and document transmission procedures apply, except that electronic document requirements do not apply to samples or color selection charts.
B. Submittal Service: The selected service is:
1. Procore; wwwprocore.com.
3.02 PRECONSTRUCTION MEETING
A. Attendance Required:
1. Forest Service.
2. Mosaic Architecture.
3. Contractor.
4. All major sub-contractors.
B. Agenda:
1. Execution of Forest Service-Contractor Agreement.
2. Submission of executed bonds and insurance certificates.
3. Distribution of Contract Documents.
4. Submission of list of subcontractors, list of products, schedule of values, and progress schedule.
5. Designation of personnel representing the parties to Contract and <1|A/E|>.
6. Procedures and processing of field decisions, submittals, substitutions, applications for payments, proposal request, Change Orders, and Contract closeout procedures.
7. Scheduling.
C. Contractor will record minutes and distribute copies within seven days after meeting to participates, with one copy to Owner, participants, and those affected by decisions made.
3.03 PROGRESS MEETINGS
A. Schedule and administer meetings throughout progress of the work at maximum bi-monthly intervals.
B. Attendance Required:
1. Contractor.
2. Forest Service.
3. Mosaic Architecture.
4. Contractor's superintendent.
C. Agenda:
1. Review minutes of previous meetings.
2. Review of work progress.
3. Field observations, problems, and decisions.
4. Identification of problems that impede, or will impede, planned progress.
5. Review of submittals schedule and status of submittals.
6. Maintenance of progress schedule.
7. Corrective measures to regain projected schedules.
8. Planned progress during succeeding work period.
9. Maintenance of quality and work standards.
10. Effect of proposed changes on progress schedule and coordination.
11. Other business relating to work.
D. Record minutes and distribute copies within two days after meeting to participants, with two copies to Mosaic Architecture, Forest Service, participants, and those affected by decisions made.
01 3000 - 3 Administrative Requirements
3.04 CONSTRUCTION PROGRESS SCHEDULE
A. If preliminary schedule requires revision after review, submit revised schedule within 10 days.
B. Within 20 days after review of preliminary schedule, submit draft of proposed complete schedule for review.
C. Within 10 days after joint review, submit complete schedule.
D. Submit updated schedule with each Application for Payment.
3.05 REQUESTS FOR INTERPRETATION (RFI)
A. Definition: A request seeking one of the following:
1. An interpretation, amplification, or clarification of some requirement of Contract
Documents arising from inability to determine from them the exact material, process, or system to be installed; or when the elements of construction are required to occupy the same space (interference); or when an item of work is described differently at more than one place in Contract Documents.
2. A resolution to an issue which has arisen due to field conditions and affects design intent.
B. Whenever possible, request clarifications at the next appropriate project progress meeting, with response entered into meeting minutes, rendering unnecessary the issuance of a formal RFI.
C. Preparation: Prepare an RFI immediately upon discovery of a need for interpretation of Contract Documents. Failure to submit a RFI in a timely manner is not a legitimate cause for claiming additional costs or delays in execution of the work.
1. Prepare a separate RFI for each specific item.
a. Review, coordinate, and comment on requests originating with subcontractors and/or materials suppliers.
b. Do not forward requests which solely require internal coordination between subcontractors.
2. Prepare in a format and with content acceptable to Forest Service.
D. Reason for the RFI: Prior to initiation of an RFI, carefully study all Contract Documents to confirm that information sufficient for their interpretation is definitely not included.
1. Include in each request Contractor's signature attesting to good faith effort to determine from Contract Documents information requiring interpretation.
2. Unacceptable Uses for RFIs: Do not use RFIs to request the following::
a. Approval of submittals (use procedures specified elsewhere in this section).
b. Approval of substitutions (see Section - 01 6000 - Product Requirements)
c. Changes that entail change in Contract Time and Contract Sum (comply with provisions of the Conditions of the Contract).
E. Content: Include identifiers necessary for tracking the status of each RFI, and information necessary to provide an actionable response.
1. Official Project name and number, and any additional required identifiers established in
Contract Documents.
2. Forest Service's, Mosaic Architecture's, and Contractor's names.
3. Discrete and consecutive RFI number, and descriptive subject/title.
4. Issue date, and requested reply date.
5. Reference to particular Contract Document(s) requiring additional information/interpretation. Identify pertinent drawing and detail number and/or specification section number, title, and paragraph(s).
6. Annotations: Field dimensions and/or description of conditions which have engendered the request.
7. Contractor's suggested resolution: A written and/or a graphic solution, to scale, is required in cases where clarification of coordination issues is involved, for example;
routing, clearances, and/or specific locations of work shown diagrammatically in Contract Documents. If applicable, state the likely impact of the suggested resolution on Contract Time or the Contract Sum.
01 3000 - 4 Administrative Requirements
F. Attachments: Include sketches, coordination drawings, descriptions, photos, submittals, and other information necessary to substantiate the reason for the request.
G. RFI Log: Prepare and maintain a tabular log of RFIs for the duration of the project.
1. Indicate current status of every RFI. Update log promptly and on a regular basis.
2. Note dates of when each request is made, and when a response is received.
3. Highlight items requiring priority or expedited response.
4. Highlight items for which a timely response has not been received to date.
H. Review Time: Mosaic Architecture will respond and return RFIs to Contractor within seven calendar days of receipt. For the purpose of establishing the start of the mandated response period, RFIs received after 12:00 noon will be considered as having been received on the following regular working day.
1. Response period may be shortened or lengthened for specific items, subject to mutual agreement, and recorded in a timely manner in progress meeting minutes.
I. Responses: Content of answered RFIs will not constitute in any manner a directive or authorization to perform extra work or delay the project. If in Contractor's belief it is likely to lead to a change to Contract Sum or Contract Time, promptly issue a notice to this effect, and follow up with an appropriate Change Order request to Forest Service.
1. Response may include a request for additional information, in which case the original RFI will be deemed as having been answered, and an amended one is to be issued forthwith.
Identify the amended RFI with an R suffix to the original number.
2. Do not extend applicability of a response to specific item to encompass other similar conditions, unless specifically so noted in the response.
3. Upon receipt of a response, promptly review and distribute it to all affected parties, and update the RFI Log.
4. Notify Mosaic Architecture within seven calendar days if an additional or corrected response is required by submitting an amended version of the original RFI, identified as specified above.
3.06 SUBMITTALS FOR REVIEW
A. When the following are specified in individual sections, submit them for review:
1. Product data.
2. Shop drawings.
3. Samples for selection.
4. Samples for verification.
B. Electronic submittals are required.
C. Submit to Mosaic Architecture for review for the limited purpose of checking for compliance with information given and the design concept expressed in Contract Documents.
D. Samples will be reviewed for aesthetic, color, or finish selection.
E. After review, provide copies and distribute in accordance with SUBMITTAL PROCEDURES article below and for record documents purposes described in Section 01 7800 - Closeout Submittals.
3.07 SUBMITTALS FOR INFORMATION
A. When the following are specified in individual sections, submit them for information:
1. Design data.
2. Certificates.
3. Test reports.
4. Inspection reports.
5. Manufacturer's field reports.
6. Other types indicated.
B. Submit for Mosaic Architecture's knowledge as contract administrator or for Forest Service.
01 3000 - 5 Administrative Requirements
3.08 SUBMITTALS FOR PROJECT CLOSEOUT
A. Submit Correction Punch List for Substantial Completion.
B. Submit Final Correction Punch List for Substantial Completion.
C. When the following are specified in individual sections, submit them at project closeout in compliance with requirements of Section 01 7800 - Closeout Submittals:
1. Project record documents.
2. Operation and maintenance data.
3. Warranties.
4. Bonds.
5. Other types as indicated.
D. Submit for Forest Service's benefit during and after project completion.
3.09 NUMBER OF COPIES OF SUBMITTALS
A. Electronic Documents: Submit one electronic copy in PDF format; an electronically-marked up file will be returned. Create PDFs at native size and right-side up; illegible files will be rejected.
B. Samples: Submit the number specified in individual specification sections; one of which will be retained by Mosaic Architecture.
1. After review, produce duplicates.
2. Retained samples will not be returned to Contractor unless specifically so stated.
3.10 SUBMITTAL PROCEDURES
A. General Requirements:
1. Use a single transmittal for related items.
2. Sequentially identify each item. For revised submittals use original number and a sequential numerical suffix.
3. Identify: Project; Contractor; subcontractor or supplier; pertinent drawing and detail number; and specification section number and article/paragraph, as appropriate on each copy.
4. Apply Contractor's stamp, signed or initialed certifying that review, approval, verification of products required, field dimensions, adjacent construction work, and coordination of information is in accordance with the requirements of the work and Contract Documents.
a. Submittals from sources other than the Contractor, or without Contractor's stamp will not be acknowledged, reviewed, or returned.
5. Schedule submittals to expedite the Project, and coordinate submission of related items.
a. For sequential reviews involving Mosaic Architecture's consultants, Forest Service, or another affected party, allow an additional 7 days.
b. For sequential reviews involving approval from authorities having jurisdiction (AHJ), in addition to Mosaic Architecture's approval, allow an additional 30 days.
6. Identify variations from Contract Documents and product or system limitations that may be detrimental to successful performance of the completed work.
7. Provide space for Contractor and Mosaic Architecture review stamps.
8. When revised for resubmission, identify all changes made since previous submission.
B. Product Data Procedures:
1. Submit only information required by individual specification sections.
2. Collect required information into a single submittal.
3. Submit concurrently with related shop drawing submittal.
4. Do not submit (Material) Safety Data Sheets for materials or products.
C. Shop Drawing Procedures:
1. Prepare accurate, drawn-to-scale, original shop drawing documentation by interpreting
Contract Documents and coordinating related work.
2. Generic, non-project-specific information submitted as shop drawings do not meet the requirements for shop drawings.
D. Samples Procedures:
01 3000 - 6 Administrative Requirements
1. Transmit related items together as single package.
2. Identify each item to allow review for applicability in relation to shop drawings showing installation locations.
3. Include with transmittal high-resolution image files of samples to facilitate electronic review and approval. Provide separate submittal page for each item image.
3.11 SUBMITTAL REVIEW
A. Submittals for Review: Mosaic Architecture will review each submittal, and approve, or take other appropriate action.
B. Submittals for Information: Mosaic Architecture will acknowledge receipt and review. See below for actions to be taken.
C. Mosaic Architecture's actions will be reflected by marking each returned submittal using virtual stamp on electronic submittals.
D. Mosaic Architecture's and consultants' actions on items submitted for review:
1. Authorizing purchasing, fabrication, delivery, and installation:
a. "Approved", or language with same legal meaning.
b. "Approved as Noted, Resubmission not required", or language with same legal meaning.
1) At Contractor's option, submit corrected item, with review notations acknowledged and incorporated.
c. "Approved as Noted, Resubmit for Record", or language with same legal meaning.
1) Resubmit corrected item, with review notations acknowledged and incorporated.
Resubmit separately, or as part of project record documents.
2) Non-responsive resubmittals may be rejected.
2. Not Authorizing fabrication, delivery, and installation:
a. "Revise and Resubmit".
1) Resubmit revised item, with review notations acknowledged and incorporated.
2) Non-responsive resubmittals may be rejected.
b. "Rejected".
1) Submit item complying with requirements of Contract Documents.
E. Mosaic Architecture's and consultants' actions on items submitted for information:
1. Items for which no action was taken:
a. "Received" - to notify the Contractor that the submittal has been received for record only.
2. Items for which action was taken:
a. "Reviewed" - no further action is required from Contractor.
01 4000 - 1 Quality Requirements
SECTION 01 4000
QUALITY REQUIREMENTS
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Submittals.
B. Quality assurance.
C. Testing and inspection agencies and services.
D. Control of installation.
E. Mock-ups.
F. Tolerances.
1.02 RELATED REQUIREMENTS
A. Section 01 3000 - Administrative Requirements: Submittal procedures.
B. Section 01 6000 - Product Requirements: Requirements for material and product quality.
1.03 SUBMITTALS
A. See Section 01 3000 - Administrative Requirements, for submittal procedures.
B. Test Reports: After each test/inspection, promptly submit a copy of report to Mosaic Architecture and to Contractor.
1. Include:
a. Date issued.
b. Project title and number.
c. Name of inspector.
d. Date and time of sampling or inspection.
e. Identification of product and specifications section.
f. Location in the Project.
g. Type of test/inspection.
h. Date of test/inspection.
i. Results of test/inspection.
j. Compliance with Contract Documents.
k. When requested by Mosaic Architecture, provide interpretation of results.
2. Test report submittals are for Mosaic Architecture's knowledge as contract administrator for the limited purpose of assessing compliance with information given and the design concept expressed in the Contract Documents, or for Forest Service's information.
C. Certificates: When specified in individual specification sections, submit certification by the manufacturer and Contractor or installation/application subcontractor to Mosaic Architecture, in quantities specified for Product Data.
1. Indicate material or product complies with or exceeds specified requirements. Submit supporting reference data, affidavits, and certifications as appropriate.
D. Manufacturer's Instructions: When specified in individual specification sections, submit printed instructions for delivery, storage, assembly, installation, start-up, adjusting, and finishing, for the Forest Service's information. Indicate special procedures, perimeter conditions requiring special attention, and special environmental criteria required for application or installation.
1.04 QUALITY ASSURANCE
A. Testing Agency Qualifications:
1. Prior to start of work, submit agency name, address, and telephone number, and names of full time registered Engineer and responsible officer.
1.05 TESTING AND INSPECTION AGENCIES AND SERVICES
A. Contractor will employ and pay for services of an independent testing agency to perform other specified testing.
01 4000 - 2 Quality Requirements
1. Provide all structural code required testing.
2. Soils testing in accordance with Geotech report.
3. Provide blower door testing inaccordance with 2012 IECC.
B. Employment of agency in no way relieves Contractor of obligation to perform Work in accordance with requirements of Contract Documents.
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION
3.01 CONTROL OF INSTALLATION
A. Monitor quality control over suppliers, manufacturers, products, services, site conditions, and workmanship, to produce work of specified quality.
B. Comply with manufacturers' instructions, including each step in sequence.
C. Should manufacturers' instructions conflict with Contract Documents, request clarification from Mosaic Architecture before proceeding.
D. Comply with specified standards as minimum quality for the work except where more stringent tolerances, codes, or specified requirements indicate higher standards or more precise workmanship.
E. Have work performed by persons qualified to produce required and specified quality.
F. Verify that field measurements are as indicated on shop drawings or as instructed by the manufacturer.
G. Secure products in place with positive anchorage devices designed and sized to withstand stresses, vibration, physical distortion, and disfigurement.
3.02 MOCK-UPS
A. Before installing portions of the Work where mock-ups are required, construct mock-ups in location and size indicated for each form of construction and finish required to comply with the following requirements, using materials indicated for the completed Work. The purpose of mock-up is to demonstrate the proposed range of aesthetic effects and workmanship.
B. Accepted mock-ups establish the standard of quality the Mosaic Architecture will use to judge the Work.
C. Provide supervisory personnel who will oversee mock-up construction. Provide workers that will be employed during the construction at Project.
D. Tests shall be performed under provisions identified in this section and identified in the respective product specification sections.
E. Assemble and erect specified items with specified attachment and anchorage devices, flashings, seals, and finishes.
F. Obtain Mosaic Architecture's approval of mock-ups before starting work, fabrication, or construction.
G. Accepted mock-ups shall be a comparison standard for the remaining Work.
H. Where mock-up has been accepted by Mosaic Architecture and is specified in product specification sections to be removed, protect mock-up throughout construction, remove mock-up and clear area when directed to do so by Mosaic Architecture.
3.03 TOLERANCES
A. Monitor fabrication and installation tolerance control of products to produce acceptable Work.
Do not permit tolerances to accumulate.
B. Comply with manufacturers' tolerances. Should manufacturers' tolerances conflict with Contract Documents, request clarification from Mosaic Architecture before proceeding.
C. Adjust products to appropriate dimensions; position before securing products in place.
01 4000 - 3 Quality Requirements
3.04 TESTING AND INSPECTION
A. Testing Agency Duties:
1. Provide qualified personnel at site. Cooperate with Mosaic Architecture and Contractor in performance of services.
2. Perform specified sampling and testing of products in accordance with specified standards.
3. Ascertain compliance of materials and mixes with requirements of Contract Documents.
4. Promptly notify Mosaic Architecture and Contractor of observed irregularities or non-compliance of Work or products.
5. Perform additional tests and inspections required by Mosaic Architecture.
6. Submit reports of all tests/inspections specified.
B. Limits on Testing/Inspection Agency Authority:
1. Agency may not release, revoke, alter, or enlarge on requirements of Contract
Documents.
2. Agency may not approve or accept any portion of the Work.
3. Agency may not assume any duties of Contractor.
4. Agency has no authority to stop the Work.
C. Contractor Responsibilities:
1. Deliver to agency at designated location, adequate samples of materials proposed to be used that require testing, along with proposed mix designs.
2. Cooperate with laboratory personnel, and provide access to the Work and to manufacturers' facilities.
3. Provide incidental labor and facilities:
a. To provide access to Work to be tested/inspected.
b. To obtain and handle samples at the site or at source of Products to be tested/inspected.
c. To facilitate tests/inspections.
d. To provide storage and curing of test samples.
4. Notify Mosaic Architecture and laboratory 24 hours prior to expected time for operations requiring testing/inspection services.
5. Employ services of an independent qualified testing laboratory and pay for additional samples, tests, and inspections required by Contractor beyond specified requirements.
6. Arrange with Forest Service's agency and pay for additional samples, tests, and inspections required by Contractor beyond specified requirements.
D. Re-testing required because of non-compliance with specified requirements shall be performed by the same agency on instructions by Mosaic Architecture.
E. Re-testing required because of non-compliance with specified requirements shall be paid for by Contractor.
3.05 DEFECT ASSESSMENT
A. Replace Work or portions of the Work not complying with specified requirements.
B. If, in the opinion of Mosaic Architecture, it is not practical to remove and replace the work, Mosaic Architecture will direct an appropriate remedy or adjust payment.
01 5000 - 1 Temporary Facilities and Controls
SECTION 01 5000
TEMPORARY FACILITIES AND CONTROLS
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Temporary utilities.
B. Temporary telecommunications services.
C. Temporary sanitary facilities.
D. Temporary Controls: Barriers, enclosures, and fencing.
E. Security requirements.
F. Waste removal facilities and services.
G. Project identification sign.
H. Field offices.
1.02 TEMPORARY UTILITIES
A. Provide and pay for all electrical power, lighting, and water required for construction purposes.
B. Use trigger-operated nozzles for water hoses, to avoid waste of water.
1.03 TELECOMMUNICATIONS SERVICES
A. Provide, maintain, and pay for telecommunications services to field office at time of project mobilization.
B. Telecommunications services shall include:
1. Windows-based personal computer dedicated to project telecommunications, with necessary software and laser printer.
2. Internet Connections: Minimum of one; DSL modem or faster.
3. Email: Account/address reserved for project use.
1.04 TEMPORARY SANITARY FACILITIES
A. Provide and maintain required facilities and enclosures. Provide at time of project mobilization.
B. Maintain daily in clean and sanitary condition.
1.05 BARRIERS
A. Provide barriers to prevent unauthorized entry to construction areas, to prevent access to areas that could be hazardous to workers or the public, to allow for owner's use of site and to protect existing facilities and adjacent properties from damage from construction operations and demolition.
B. Provide barricades and covered walkways required by governing authorities for public rights-of-way and for public access to existing building.
C. Protect non-owned vehicular traffic, stored materials, site, and structures from damage.
1.06 FENCING
A. Provide 6 foot high fence around construction site; equip with vehicular and pedestrian gates with locks.
1.07 EXTERIOR ENCLOSURES
A. Provide temporary weather tight closure of exterior openings to accommodate acceptable working conditions and protection for Products, to allow for temporary heating and maintenance of required ambient temperatures identified in individual specification sections, and to prevent entry of unauthorized persons. Provide access doors with self-closing hardware and locks.
1.08 SECURITY
A. Provide security and facilities to protect Work, existing facilities, and Forest Service's operations from unauthorized entry, vandalism, or theft.
01 5000 - 2 Temporary Facilities and Controls
1.09 VEHICULAR ACCESS AND PARKING
A. Coordinate access and haul routes with governing authorities and Forest Service.
B. Provide and maintain access to fire hydrants, free of obstructions.
C. Provide means of removing mud from vehicle wheels before entering streets.
D. Provide temporary parking areas to accommodate construction personnel. When site space is not adequate, provide additional off-site parking.
1.10 WASTE REMOVAL
A. Provide waste removal facilities and services as required to maintain the site in clean and orderly condition.
B. Provide containers with lids. Remove trash from site periodically.
C. If materials to be recycled or re-used on the project must be stored on-site, provide suitable non-combustible containers; locate containers holding flammable material outside the structure unless otherwise approved by the authorities having jurisdiction.
D. Open free-fall chutes are not permitted. Terminate closed chutes into appropriate containers with lids.
1.11 PROJECT IDENTIFICATION
A. Provide project identification sign of design and construction indicated on drawings.
B. Erect on site at location indicated.
C. No other signs are allowed without Forest Service permission except those required by law.
1.12 FIELD OFFICES
A. Office: Weathertight, with lighting, electrical outlets, heating, cooling equipment, and equipped with sturdy furniture, drawing rack, and drawing display table.
B. Provide space for Project meetings, with table and chairs to accommodate 6 persons.
C. Locate offices a minimum distance of 30 feet from existing and new structures.
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION - NOT USED
01 5713 - 1 Temporary Erosion and Sediment
Control
SECTION 01 5713
TEMPORARY EROSION AND SEDIMENT CONTROL
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Prevention of erosion due to construction activities.
B. Prevention of sedimentation of waterways, open drainage ways, and storm and sanitary sewers due to construction activities.
C. Restoration of areas eroded due to insufficient preventive measures.
D. Compensation of Forest Service for fines levied by authorities having jurisdiction due to non-compliance by Contractor.
1.02 RELATED REQUIREMENTS
A. MT DEQ General Permit for Stormwater Discharges Associated with Construction Activity.
1.03 REFERENCE STANDARDS
A. ASTM D4355/D4355M - Standard Test Method for Deterioration of Geotextiles by Exposure to Light, Moisture, and Heat in a Xenon Arc-Type Apparatus; 2021.
B. ASTM D4491 - Standard Test Methods for Water Permeability of Geotextiles by Permittivity.;
1999a (Reapproved 2014).
C. ASTM D4533/D4533M - Standard Test Method for Trapezoid Tearing Strength of Geotextiles;
2015.
D. ASTM D4632/D4632M - Standard Test Method for Grab Breaking Load and Elongation of Geotextiles; 2015a.
E. ASTM D4751 - Standard Test Method for Determining Apparent Opening Size of a Geotextile;
2016.
F. ASTM D4873/D4873M - Standard Guide for Identification, Storage, and Handling of Geosynthetic Rolls and Samples; 2017.
G. EPA (NPDES) - National Pollutant Discharge Elimination System (NPDES), Construction General Permit; Current Edition.
H. USDA TR-55 - Urban Hydrology for Small Watersheds; USDA Natural Resources Conservation Service; 2013.
1.04 PERFORMANCE REQUIREMENTS
A. Obtain MT DEQ General Permit for Stormwater Discharges Associated with Construction Activity (SWWPP).
B. Comply with requirements of EPA (NPDES) for erosion and sedimentation control, as specified by the NPDES, for Phases I and II, and in compliance with requirements of Construction General Permit (CGP), whether the project is required by law to comply or not.
C. Develop and follow an Erosion and Sedimentation Prevention Plan and submit periodic inspection reports.
D. Do not begin clearing, grading, or other work involving disturbance of ground surface cover until applicable permits have been obtained; furnish all documentation required to obtain applicable permits.
E. Timing: Put preventive measures in place as soon as possible after disturbance of surface cover and before precipitation occurs.
F. Storm Water Runoff: Control increased storm water runoff due to disturbance of surface cover due to construction activities for this project.
1. Prevent runoff into storm and sanitary sewer systems, including open drainage channels, in excess of actual capacity or amount allowed by authorities having jurisdiction, whichever is less.
01 5713 - 2 Temporary Erosion and Sediment
Control
2. Anticipate runoff volume due to the most extreme short term and 24-hour rainfall events that might occur in 25 years.
G. Erosion On Site: Minimize wind, water, and vehicular erosion of soil on project site due to construction activities for this project.
1. Control movement of sediment and soil from temporary stockpiles of soil.
2. Prevent development of ruts due to equipment and vehicular traffic.
3. If erosion occurs due to non-compliance with these requirements, restore eroded areas at no cost to Forest Service.
H. Erosion Off Site: Prevent erosion of soil and deposition of sediment on other properties caused by water leaving the project site due to construction activities for this project.
1. Prevent windblown soil from leaving the project site.
2. Prevent tracking of mud onto public roads outside site.
3. Prevent mud and sediment from flowing onto sidewalks and pavements.
4. If erosion occurs due to non-compliance with these requirements, restore eroded areas at no cost to Forest Service.
I. Sedimentation of Waterways On Site: Prevent sedimentation of waterways on the project site, including rivers, streams, lakes, ponds, open drainage ways, storm sewers, and sanitary sewers.
1. If sedimentation occurs, install or correct preventive measures immediately at no cost to
Forest Service; remove deposited sediments; comply with requirements of authorities having jurisdiction.
2. If sediment basins are used as temporary preventive measures, pump dry and remove deposited sediment after each storm.
J. Sedimentation of Waterways Off Site: Prevent sedimentation of waterways off the project site, including rivers, streams, lakes, ponds, open drainage ways, storm sewers, and sanitary sewers.
1. If sedimentation occurs, install or correct preventive measures immediately at no cost to
Forest Service; remove deposited sediments; comply with requirements of authorities having jurisdiction.
K. Open Water: Prevent standing water that could become stagnant.
L. Maintenance: Maintain temporary preventive measures until permanent measures have been established.
1.05 SUBMITTALS
A. See Section 01 3000 - Administrative Requirements, for submittal procedures.
B. Erosion and Sedimentation Control Plan:
1. Submit not less than 30 days prior to anticipated start of clearing, grading, or other work involving disturbance of ground surface cover.
2. Include:
a. Site plan identifying soils and vegetation, existing erosion problems, and areas vulnerable to erosion due to topography, soils, vegetation, or drainage.
b. Site plan showing grading; new improvements; temporary roads, traffic accesses, and other temporary construction; and proposed preventive measures.
c. Where extensive areas of soil will be disturbed, include storm water flow and volume calculations, soil loss predictions, and proposed preventive measures.
d. Schedule of temporary preventive measures, in relation to ground disturbing activities.
e. Other information required by law.
f. Format required by law is acceptable, provided any additional information specified is also included.
3. Obtain the approval of the Plan by authorities having jurisdiction.
4. Obtain the approval of the Plan by Forest Service.
01 5713 - 3 Temporary Erosion and Sediment
Control
C. Certificate: Mill certificate for silt fence fabric attesting that fabric and factory seams comply with specified requirements, signed by legally authorized official of manufacturer; indicate actual minimum average roll values; identify fabric by roll identification numbers.
D. Inspection Reports: Submit report of each inspection; identify each preventive measure, indicate condition, and specify maintenance or repair required and accomplished.
PART 2 PRODUCTS
2.01 MATERIALS
A. Mulch: Use one of the following:
1. Straw or hay.
2. Wood waste, chips, or bark.
3. Erosion control matting or netting.
B. Grass Seed For Temporary Cover: Select a species appropriate to climate, planting season, and intended purpose. If same area will later be planted with permanent vegetation, do not use species known to be excessively competitive or prone to volunteer in subsequent seasons.
C. Bales: Air dry, rectangular straw bales.
1. Cross Section: 14 by 18 inches, minimum.
2. Bindings: Wire or string, around long dimension.
D. Bale Stakes: One of the following, minimum 3 feet long:
1. Steel U- or T-section, with minimum mass of 1.33 pound per linear foot.
2. Wood, 2 by 2 inches in cross section.
E. Silt Fence Fabric: Polypropylene geotextile resistant to common soil chemicals, mildew, and insects; non-biodegradable; in longest lengths possible; fabric including seams with the following minimum average roll lengths:
1. Average Opening Size: 30 U.S. Std. Sieve, maximum, when tested in accordance with
ASTM D4751.
2. Permittivity: 0.05 sec^-1, minimum, when tested in accordance with ASTM D4491.
3. Ultraviolet Resistance: Retaining at least 70 percent of tensile strength, when tested in accordance with ASTM D4355/D4355M after 500 hours exposure.
4. Tensile Strength: 100 pounds-force, minimum, in cross-machine direction; 124 pounds-force, minimum, in machine direction; when tested in accordance with ASTM D4632/D4632M.
5. Elongation: 15 to 30 percent, when tested in accordance with ASTM D4632/D4632M.
6. Tear Strength: 55 pounds-force, minimum, when tested in accordance with ASTM
D4533/D4533M.
7. Color: Manufacturer's standard, with embedment and fastener lines preprinted.
8. Manufacturers:
a. TenCate: www.tencate.com/#sle.
b. North American Green: www.nagreen.com/#sle.
c. Propex Geosynthetics: www.geotextile.com/#sle.
F. Silt Fence Posts: One of the following, minimum 5 feet long:
1. Steel U- or T-section, with minimum mass of 1.33 pound per linear foot.
2. Softwood, 4 by 4 inches in cross section.
PART 3 EXECUTION
3.01 EXAMINATION
A. Examine site and identify existing features that contribute to erosion resistance; maintain such existing features to greatest extent possible.
3.02 PREPARATION
A. Schedule work so that soil surfaces are left exposed for the minimum amount of time.
01 5713 - 4 Temporary Erosion and Sediment
Control
3.03 SCOPE OF PREVENTIVE MEASURES
A. In all cases, if permanent erosion resistant measures have been installed temporary preventive measures are not required.
B. Construction Entrances: Traffic-bearing aggregate surface.
1. Width: As required; 20 feet, minimum.
2. Length: 50 feet, minimum.
3. Provide at each construction entrance from public right-of-way.
4. Where necessary to prevent tracking of mud onto right-of-way, provide wheel washing area out of direct traffic lane, with drain into sediment trap or basin.
C. Linear Sediment Barriers: Made of silt fences.
1. Provide linear sediment barriers:
a. Along downhill perimeter edge of disturbed areas, including soil stockpiles.
2. Space sediment barriers with the following maximum slope length upslope from barrier:
a. Slope of Less Than 2 Percent: 100 feet..
b. Slope Between 2 and 5 Percent: 75 feet.
c. Slope Between 5 and 10 Percent: 50 feet.
d. Slope Between 10 and 20 Percent: 25 feet.
e. Slope Over 20 Percent: 15 feet.
D. Storm Drain Curb Inlet Sediment Trap: Protect each curb inlet using one of the following measures:
1. Filter fabric wrapped around hollow concrete blocks blocking entire inlet face area; use one piece of fabric wrapped at least 1-1/2 times around concrete blocks and secured to prevent dislodging; orient cores of blocks so runoff passes into inlet.
2. Straw bale row blocking entire inlet face area; anchor into pavement.
E. Storm Drain Drop Inlet Sediment Traps: As detailed on drawings.
F. Temporary Splash Pads: Stone aggregate over filter fabric; size to suit application; provide at downspout outlets and storm water outlets.
G. Soil Stockpiles: Protect using one of the following measures:
1. Cover with polyethylene film, secured by placing soil on outer edges.
2. Cover with mulch at least 4 inches thickness of pine needles, sawdust, bark, wood chips, or shredded leaves, or 6 inches of straw or hay.
H. Mulching: Use only for areas that may be subjected to erosion for less than 6 months.
1. Wood Waste: Use only on slopes 3:1 or flatter; no anchoring required.
I. Temporary Seeding: Use where temporary vegetated cover is required.
3.04 INSTALLATION
A. Traffic-Bearing Aggregate Surface:
1. Excavate minimum of 6 inches.
2. Place geotextile fabric full width and length, with minimum 12 inch overlap at joints.
3. Place and compact at least 6 inches of 1 1/2 to 3 1/2 inch diameter stone.
B. Silt Fences:
1. Store and handle fabric in accordance with ASTM D4873/D4873M.
2. Where slope gradient is less than 3:1 or barriers will be in place less than 6 months, use nominal 16 inch high barriers with minimum 36 inch long posts spaced at 6 feet maximum, with fabric embedded at least 4 inches in ground.
3. Where slope gradient is steeper than 3:1 or barriers will be in place over 6 months, use nominal 28 inch high barriers, minimum 48 inch long posts spaced at 6 feet maximum, with fabric embedded at least 6 inches in ground.
4. Where slope gradient is steeper than 3:1 and vertical height of slope between barriers is more than 20 feet, use nominal 32 inch high barriers with woven wire reinforcement and steel posts spaced at 4 feet maximum, with fabric embedded at least 6 inches in ground.
5. Install with top of fabric at nominal height and embedment as specified.
01 5713 - 5 Temporary Erosion and Sediment
Control
6. Do not splice fabric width; minimize splices in fabric length; splice at post only, overlapping at least 18 inches, with extra post.
7. Fasten fabric to wood posts using one of the following:
a. Four nails per post with 3/4 inch diameter flat or button head, 1 inch long, and 14 gage, 0.083 inch shank diameter.
b. Five staples per post with at least 17 gage, 0.0453 inch wire, 3/4 inch crown width and 1/2 inch long legs.
8. Fasten fabric to steel posts using wire, nylon cord, or integral pockets.
9. Wherever runoff will flow around end of barrier or over the top, provide temporary splash pad or other outlet protection; at such outlets in the run of the barrier, make barrier not more than 12 inches high with post spacing not more than 4 feet.
C. Straw Bale Rows:
1. Install bales in continuous rows with ends butting tightly, with one bale at each end of row turned uphill.
2. Install bales so that bindings are not in contact with the ground.
3. Embed bales at least 4 inches in the ground.
4. Anchor bales with at least two stakes per bale, driven at least 18 inches into the ground;
drive first stake in each bale toward the previously placed bale to force bales together.
5. Fill gaps between ends of bales with loose straw wedged tightly.
6. Place soil excavated for trench against bales on the upslope side of the row, compacted.
D. Temporary Seeding:
1. When hydraulic seeder is used, seedbed preparation is not required.
2. When surface soil has been sealed by rainfall or consists of smooth undisturbed cut slopes, and conventional or manual seeding is to be used, prepare seedbed by scarifying sufficiently to allow seed to lodge and germinate.
3. If temporary mulching was used on planting area but not removed, apply nitrogen fertilizer at 1 pound per 1000 sq ft.
4. On soils of very low fertility, apply 10-10-10 fertilizer at rate of 12 to 16 pounds per 1000 sq ft.
5. Incorporate fertilizer into soil before seeding.
6. Apply seed uniformly; if using drill or cultipacker seeders place seed 1/2 to 1 inch deep.
7. Irrigate as required to thoroughly wet soil to depth that will ensure germination, without causing runoff or erosion.
8. Repeat irrigation as required until grass is established.
3.05 MAINTENANCE
A. Inspect preventive measures weekly, within 24 hours after the end of any storm that produces
0.5 inches or more rainfall at the project site, and daily during prolonged rainfall.
B. Repair deficiencies immediately.
C. Silt Fences:
1. Promptly replace fabric that deteriorates unless need for fence has passed.
2. Remove silt deposits that exceed one-third of the height of the fence.
3. Repair fences that are undercut by runoff or otherwise damaged, whether by runoff or other causes.
D. Straw Bale Rows:
1. Promptly replace bales that fall apart or otherwise deteriorate unless need has passed.
2. Remove silt deposits that exceed one-half of the height of the bales.
3. Repair bale rows that are undercut by runoff or otherwise damaged, whether by runoff or other causes.
E. Clean out temporary sediment control structures weekly and relocate soil on site.
F. Place sediment in appropriate locations on site; do not remove from site.
01 5713 - 6 Temporary Erosion and Sediment
Control
3.06 CLEAN UP
A. Remove temporary measures after permanent measures have been installed, unless permitted to remain by Mosaic…