Attachment 1 Specification Booklet.pdf

PDF 6 MB Posted

Attached to
Construct Stanchion Barn and Cattle Working Barn Federal contract opportunity
Solicitation number
12805B24R0035
Issued by
Department of Agriculture Agricultural Research Service Field Research Implementation and Information Delivery Plains Area

About this file

This document is a specification booklet for the construction of a stanchion barn and cattle working barn at the Knipling-Bushland U.S. Livestock Insect Research Laboratory (KBUSLIRL) in Kerrville, Texas.

The specification booklet provides details on the design, construction, and turnover requirements for the project. It includes information on the construction schedule, utility services, security requirements, permitting, and other administrative requirements. The project involves the demolition of existing buildings and the construction of new buildings and associated site work. The specification booklet also includes details on the required submittals, project scheduling, workforce requirements, and other contract administration details.

View the file

Other files for this federal contract opportunity

Other files attached to Construct Stanchion Barn and Cattle Working Barn, newest first.
File Type Posted
12805B24R0035 REV 6.pdf PDF
12805B24R0035 Amendment 6.pdf PDF
Attachment 11 Questions from Industry.pdf PDF
Exhibit B Bid Schedule Breakdown of Tasks.pdf PDF
Stanchion Barn signin sheet.pdf PDF
12805B24R0035 REV 5.pdf PDF
12805B24R0035 Amendment 5.pdf PDF
Attachment 2 REV 1 Project Drawings.pdf PDF
Attachment 10 Pier Specifications.pdf PDF
Attachment 11 Questions from Industry.pdf PDF
12805B24R0035 Amendment 4.pdf PDF
Exhibit A REV 1- Bid Schedule - 12805B24R0035.xlsx XLSX spreadsheet
12805B24R0035 REV 4.pdf PDF
Attachment 6 Geotech Report Through Supplement 1.pdf PDF
Attachment 9 Geotech Supplemental 4.pdf PDF
Attachment 7 Geotech Supplemental 2.PDF PDF
Attachment 8 Geotech Supplemental 3.pdf PDF
12805B24R0035 REV 3.pdf PDF
12805B24R0035 Amendment 3.pdf PDF
12805B24R0035 REV 2.pdf PDF
12805B24R0035 Amendment 2.pdf PDF
12805B24R0035 Amendment 1.pdf PDF
12805B24R0035 REV 1.pdf PDF
Attachment 5 ARS-372 Request for Payment.pdf PDF
Exhibit A REV 0- Bid Schedule - 12805B24R0035.xlsx XLSX spreadsheet
Attachment 3 WD TX20240161 Mod 1 Dated 5 July 2024.pdf PDF
Attachment 2 Project Drawings.pdf PDF
Attachment 4 ARS-371 Construction Progress and Payment Schedule.pdf PDF
Exhibit B Bid Schedule Breakdown of Tasks.pdf PDF
Show all 29

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPECIFICATIONS

FINAL TURNOVER DOCUMENTS

KNIPLING-BUSHLAND U.S. LIVESTOCK INSECT

RESEARCH LABORATORY

CATTLE WORKING STRUCTURES (CWS)

KERRVILLE, TX

24 OCTOBER 2023

Submitted to:

U.S. DEPARTMENT OF AGRICULTURE

AGRICULTURAL RESEARCH SERVICE

Submitted by:

Merrick & Company

KBUSLIRL CWS 11992702

SECTION 000020 Page 1

PROFESSIONAL SEALS

DATE: OCTOBER 20, 2023

The construction work for the KBUSLIRL Stanchion Barn and Working Barn Project at USDA-ARS

Campus at Kerrville, TX, is issued under a single contract with a single Project Specification in two (2)

Volumes. The following pages document the Designer of Record responsible for each Section.

CIVIL ENGINEER

Geoffrey Leaf, Merrick & Company, Inc.

The seal above is the Designer of Record responsible for the following Sections:

All Sections in Division 01, Section 02 41

00, and all Sections in Divisions 31-33, except for those noted by other disciplines.

STRUCTURAL ENGINEER

Patrick Finley, Merrick & Company, Inc.

03 30 00 05 50 13 31 63 29

ARCHITECT

Alain Rivard, Merrick & Company, Inc.

All Sections in Divisions 02-13, except for those noted by other disciplines.

10/17/23

10-20-2023

THE SEAL APPEARING ON THIS

DOCUMENT WAS AUTHORIZED

BY ALAIN RIVARD JR. 23038 ON

17 OCT 2023

THE SEAL APPEARING ON THIS

DOCUMENT WAS AUTHORIZED

BY ALAIN RIVARD JR. 23038 ON

17 OCT 2023

KBUSLIRL CWS 11992702

SECTION 000020 Page 2

PLUMBING ENGINEER

Yang Lu, Merrick & Company, Inc.

All Sections in Division 22.

ELECTRICAL ENGINEER

Daniel Harrington, Merrick & Company, Inc.

The Seal above is the Designer of Record

All Sections is Divisions 26-28 and

Sections 33 71 02 and 33 82 00.

MECHANICAL ENGINEER

Yang Lu, Matthews, Merrick & Company

All Sections in Division 23.

18 Oct 2023

3... # I

YANG LU

10/17/2023

3... # I

YANG LU

10/17/2023

USDA ARS KBUSLIRL CWS

Kerrville, TX Work Order Number 12805B23F0031

PROJECT TABLE OF CONTENTS

DI VI SI ON 01 - GENERAL REQUI REMENTS

01 00 00.00 44 10/2015 CONSTRUCTION SCHEDULE

01 11 00 08/15, CHG 2: 08/21 SUMMARY OF WORK

01 30 00 08/15 ADMINISTRATIVE REQUIREMENTS

01 32 01.00 10 02/15 PROJECT SCHEDULE

01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES

01 33 29 02/21 SUSTAINABILITY REQUIREMENTS

01 35 26 11/20, CHG 3: 02/22 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 02/19 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.00 10 11/16, CHG 2: 11/21 QUALITY CONTROL

01 45 00.15 10 11/16, CHG 2: 08/19 RESIDENT MANAGEMENT SYSTEM CONTRACTOR

MODE (RMS CM)

01 45 35 11/20 SPECIAL INSPECTIONS

01 50 00 05/18 TEMPORARY CONSTRUCTION FACILITIES AND

CONTROLS

01 57 19 08/22 TEMPORARY ENVIRONMENTAL CONTROLS

01 57 20 09/21 ENVIRONMENTAL PROTECTION

01 57 24.01 44 03/17 STORM WATER POLLUTION PREVENTION PLAN

(TEXAS)

01 57 25.00 44 06/2009 SWPP PLAN INSPECTION AND MAINTENANCE

REPORT FORM

01 58 00 08/19, CHG 5: 08/22 PROJECT IDENTIFICATION

01 74 19 02/19, CHG 3: 11/21 CONSTRUCTION WASTE MANAGEMENT AND

DISPOSAL

01 78 00 05/19, CHG 1: 08/21 CLOSEOUT SUBMITTALS

01 78 23 05/23 OPERATION AND MAINTENANCE DATA

01 78 24.00 10 05/23 FACILITY DATA REQUIREMENTS

01 91 00.15 05/23 BUILDING COMMISSIONING

01 91 13 03/20 COMMISSIONING FORMS

DI VI SI ON 02 - EXI STI NG CONDI TI ONS

02 41 00 08/22 DEMOLITION

02 81 00 11/18 TRANSPORTATION AND DISPOSAL OF

HAZARDOUS MATERIALS

DI VI SI ON 03 - CONCRETE

03 30 00 02/19, CHG 4: 08/22 CAST-IN-PLACE CONCRETE

DI VI SI ON 05 - METALS

05 50 13 05/17, CHG 1: 08/18 MISCELLANEOUS METAL FABRICATIONS

DI VI SI ON 06 - WOOD, PLASTI CS, AND COMPOSI TES

06 10 00 08/16, CHG 2: 11/18 ROUGH CARPENTRY

DI VI SI ON 07 - THERMAL AND MOI STURE PROTECTI ON

07 21 16 11/11, CHG 4: 08/18 MINERAL FIBER BLANKET INSULATION

07 60 00 05/17, CHG 2: 11/18 FLASHING AND SHEET METAL

07 95 13.16 01/20 EXTERIOR EXPANSION JOINT COVER

ASSEMBLIES

DI VI SI ON 08 - OPENI NGS

PROJECT TABLE OF CONTENTS Page 1

08 11 13 08/20 STEEL DOORS AND FRAMES

08 31 00 05/17, CHG 1: 08/18 ACCESS DOORS AND PANELS

08 33 23 08/20, CHG 1: 02/22 OVERHEAD COILING DOORS

08 71 00 02/16, CHG 4: 02/22 DOOR HARDWARE

08 81 00 05/19 GLAZING

08 91 00 08/20 METAL WALL LOUVERS

DI VI SI ON 09 - FI NI SHES

09 22 00 02/10, CHG 2: 08/18 SUPPORTS FOR INTERIOR WALLS

09 90 00 02/21 PAINTS AND COATINGS

09 97 13.00 40 11/19 STEEL COATINGS

DI VI SI ON 10 - SPECI ALTI ES

10 14 00.10 08/17, CHG 1: 11/18 EXTERIOR SIGNAGE

10 14 00.20 08/20 INTERIOR SIGNAGE

10 26 00 08/20 WALL AND DOOR PROTECTION

10 57 00 04/20 ANIMAL PENNING AND GATING

DI VI SI ON 12 - FURNI SHI NGS

12 31 00 11/14 MANUFACTURED METAL CASEWORK

12 36 00 08/18 COUNTERTOPS

DI VI SI ON 13 - SPECI AL CONSTRUCTI ON

13 34 19 08/20, CHG 1: 02/21 METAL BUILDING SYSTEMS

DI VI SI ON 22 - PLUMBI NG

22 00 00 11/15, CHG 4: 05/21 PLUMBING, GENERAL PURPOSE

22 07 19.00 40 02/23 PLUMBING PIPING INSULATION

22 08 00 02/16 COMMISSIONING OF PLUMBING SYSTEMS

DI VI SI ON 23 - HEATI NG, VENTI LATI NG, AND AI R CONDI TI ONI NG ( HVAC)

23 00 00 08/18 AIR SUPPLY, DISTRIBUTION, VENTILATION,

AND EXHAUST SYSTEMS

23 03 00.00 20 08/10, CHG 3: 08/18 BASIC MECHANICAL MATERIALS AND METHODS

23 05 48.00 40 08/15 VIBRATION AND SEISMIC CONTROLS FOR

HVAC PIPING AND EQUIPMENT

23 05 93 11/15 TESTING, ADJUSTING, AND BALANCING FOR

HVAC

23 08 00 12/13 COMMISSIONING OF HVAC SYSTEMS

23 09 00 02/19 INSTRUMENTATION AND CONTROL FOR HVAC

23 11 20 05/20 FACILITY GAS PIPING

23 82 00.00 20 02/16, CHG 1: 08/18 TERMINAL HEATING UNITS

DI VI SI ON 26 - ELECTRI CAL

26 08 00 11/22 APPARATUS INSPECTION AND TESTING

26 20 00 08/19, CHG 3: 11/21 INTERIOR DISTRIBUTION SYSTEM

26 28 01.00 10 08/21 COORDINATED POWER SYSTEM PROTECTION

26 41 00 11/13 LIGHTNING PROTECTION SYSTEM

26 51 00 05/20, CHG 2: 11/21 INTERIOR LIGHTING

26 72 00 12/13 COMMISSIONING OF ELECTRICAL SYSTEMS

PROJECT TABLE OF CONTENTS Page 2

DI VI SI ON 27 - COMMUNI CATI ONS

27 10 00 08/11 BUILDING TELECOMMUNICATIONS CABLING

SYSTEM

DI VI SI ON 28 - ELECTRONI C SAFETY AND SECURI TY

28 08 00 12/13 COMMISSIONING OF ACCESS CONTROL SYSTEMS

28 10 05 05/16 ELECTRONIC SECURITY SYSTEMS (ESS)

28 31 64.00 10 08/09 FIRE DETECTION AND ALARM SYSTEM,

ADDRESSABLE

DI VI SI ON 31 - EARTHWORK

31 00 00 08/08, CHG 2: 02/21 EARTHWORK

31 11 00 11/18 CLEARING AND GRUBBING

31 63 29 11/19 DRILLED CONCRETE PIERS

DI VI SI ON 32 - EXTERI OR I MPROVEMENTS

32 11 13.13 11/19 LIME TREATED SUBGRADE

32 11 23 05/22 AGGREGATE BASE COURSE FOR FLEXIBLE

PAVING

32 12 13 05/17 BITUMINOUS TACK AND PRIME COATS

32 12 16 08/09 HOT-MIX ASPHALT (HMA) FOR ROADS

32 16 19 05/18 CONCRETE CURBS, GUTTERS AND SIDEWALKS

32 17 23 08/16, CHG 5: 11/18 PAVEMENT MARKINGS

32 31 13 11/21 CHAIN LINK FENCES AND GATES

DI VI SI ON 33 - UTI LI TI ES

33 11 00 02/18, CHG 1: 02/22 WATER UTILITY DISTRIBUTION PIPING

33 11 23 11/09, CHG 1: 08/17 NATURAL GAS AND LIQUID PETROLEUM PIPING

33 30 00 05/18 SANITARY SEWERAGE

33 40 00 11/21 STORMWATER UTILITIES

33 71 02 08/21 UNDERGROUND ELECTRICAL DISTRIBUTION

33 82 00 04/06 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 3

SECTION 01 00 00.00 44

CONSTRUCTION SCHEDULE

10/2015

PART 1 GENERAL

1.1 SCHEDULE

Commence, prosecute, and complete the work under this contract in accordance with the following schedule and Section 00 73 00 CONTRACT CLAUSES COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK and LIQUIDATED

DAMAGES:

Item of Work Commencement of Work

(Calendar days)

Completion of Work

(Calendar days)

Liquidated Damages per calendar days

(1) All work, including O&M Manuals and Final Record Drawings, Knipling-Bushland US Livestock Insect Research Laboratory.

See form . ____ $ ______

NOTE: All work on this project shall be completed within the number of calendar days stated in Item of Work (1) above, inclusive of all review periods and Government sequence requirements specified. If the Government accepts a proposal for a completion period of lesser duration, and such proposal alters the time periods for review and sequence, the Contract shall be read to include the original periods for review and phasing. If a completion period of lesser duration is proposed and accepted by the Government, the accepted completion period will replace the original construction schedule listed above in the Schedule. If an alternate completion period is proposed, the Bid Schedule must reflect pricing information for the alternate proposed completion period. The liquidated damages stated above will be applied for each calendar day the Contractor exceeds the Contract scheduled duration.

* 3Options:

(a) Commencement of Work

Work for each option shall start within 10 days of receipt of

SECTION 01 00 00.00 44 Page 1 notice to proceed following the award of the option. See the notes to the bidding schedule concerning award of options.

(b) Liquidated Damages

See Section 00 72 00 CONTRACT CLAUSES clause LIQUIDATED DAMAGES

- CONSTRUCTION. Liquidated damages for the option(s) will be applicable only when the option's completion time falls beyond the original contract period. Liquidated damages are not accumulative.

** Operation and Maintenance Manuals: See Section 01 78 00 CLOSEOUT SUBMITTALS, paragraph OPERATION AND MAINTENANCE MANUALS for requirements and withholding amount to ensure completion of O&M Manuals.

*** Record Drawings: See Section 01 78 00 CLOSEOUT SUBMITTALS, paragraph titled RECORD DRAWINGS for requirements and withholding amount to ensure completion of record drawings.

1.1.1 Testing of Heating and Air-Conditioning Systems

The times stated for completion of this project includes all required testing specified in appropriate specification sections of heating, air conditioning and ventilation systems including HVAC Commissioning.

1.2 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER (OCT 1989)

(ER 415-1-15)(52.0001-4038 1/96)

a. This provision specifies the procedure for determination of time extensions for unusually severe weather in accordance with the contract clause FAR 52.249-10 entitled "DEFAULT: (FIXED PRICE CONSTRUCTION)." In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:

(1) The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.

(2) The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the contractor.

b. The following schedule of monthly anticipated adverse weather delays due to precipitation and temperature is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations.

The contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities. Wind is not considered in the Monthly Anticipated Adverse Weather Calendar Day Schedule.

MONTHLY ANTICIPATED ADVERSE WEATHER DELAY

WORK DAYS BASED ON (5) DAY WORK WEEK

JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

2 3 4 3 4 6 3 4 5 5 5 3

c. Upon receipt of the Notice to Proceed (NTP) and continuing throughout the contract, the contractor will record on the daily CQC report, the

SECTION 01 00 00.00 44 Page 2 occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the contractor's scheduled work day.

d. The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in paragraph "b", above, the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the contract clause entitled "Default (Fixed Price Construction)."

1.3 CONSTRUCTION SEQUENCING

1.3.1 Definition of Sequences

The KBUSLIRL Campus will be occupied and operational during this reconstruction project. Some existing buildings must be demolished to provide space for new buildings; new buildings. Temporary or new roadways must be complete before existing roadways are removed or otherwise taken out of service.

Note that the plans represent the order of construction and do not include certain details (e.g. how the new utility infrastructure installation will be staged to serve new buildings) that shall be developed by the Contractor as part of the overall construction approach and schedule.

1.3.2 Sequence Requirements

KBUSLIRL will remain in operation during the entire construction period.

The Contractor must conduct operations so as to cause the least possible interference with normal operations.

1.3.2.1 Construction Work

All construction work in each sequence must be prepared and coordinated with KBUSLIRL and the Contracting Officer at least two (2) weeks before work is started to prevent interference with normal KBUSLIRL operations.

1.3.2.2 Operation Interruption

Permission to interrupt any operation, roads, or utility service must be requested in writing a minimum of 14 calendar days prior to the desired date(s) of interruption.

1.4 WORK RESTRICTIONS

1.4.1 Working Hours

Normal working hours are Monday through Friday, 7:30 a.m. to 4:00 p.m., unless otherwise indicated at the preconstruction conference. Requests to work at times other than the stated working hours, including scheduled utility outages discussed below, shall be submitted to the Contracting Officer for approval. Contractor shall not work outside of the above stated working hours without prior written approval of the Contracting Officer.

SECTION 01 00 00.00 44 Page 3

1.4.2 Security Requirements

1.4.3 Identification of Employees

The Contractor shall be responsible for furnishing to each employee, and for requiring each employee engaged on the work to display, identification as approved and directed by the Contracting Officer. Prescribed identification shall immediately be delivered to the Contracting Officer for cancellation upon release of any employee. When required, the Contractor shall obtain and provide fingerprints of persons employed on the project. Contractor and subcontractor personnel shall wear identifying markings on hard hats clearly identifying the company for whom the employee works.

Contractor personnel shall wear visible Contractor-furnished employee identification badges while physically on the Installation. Each badge shall include, as a minimum, the company name, employee name, photograph, Contract Title, Contract Number, and the expiration date of the badge.

1.5 TEXAS PARKS AND WILDLIFE REQUIREMENTS

Texas Parks and Wildlife Department (TPWD) has reviewed the site condition and USACE has performed a site survey to confirm that no flora or fauna species of concern should be encountered in the project areas. Refer to the Environmental Assessment (EA) completed for KBUSLIRL main campus renovation project for confirmation of site-related requirements.

1.6 UTILITIES

1.6.1 Payment for Utility Services

Utility availability and Payment For Utility Services are specified in Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROL.

1.6.2 Coordination

For Contractor Telephone And Internet Service, the Contractor shall coordinate with ITBC and the local phone company for contractor telephone and internet service during construction.

1.7 PAPERLESS CONTRACT SUBMISSION

a. GENERAL INFORMATION ON PAPERLESS CONTRACT SUBMISSION

The goal is to reduce waste, decrease time, decrease associated costs, and to streamline most file transmission procedures.

b. METHODS OF DIGITAL SUBMISSION

This contract shall use digital submission methods to the greatest extent practicable. Acceptable methods are as follows, in order of precedence:

1. RMS - will be used to the greatest extent practicable. Some items may not be submittable via RMS due to program constraints.

Those items shall use an alternate method. All ENGR 4025’s shall be generated and submitted in RMS.

2. Secure, Password Protected Web-Based System Access must be

SECTION 01 00 00.00 44 Page 4 allowed and approved by the Government Representative. Access must be allowed and approved by the Government Representative. This method shall not be used for security sensitive documents.

3. E-mail – Items not submitted via RMS, as discussed above, shall be submitted via e-mail, if possible. E-mail limitations for file size must be considered prior to submission. Under current conditions, 5 megabytes is the limitation for any single file/e-mail.

4. CD/DVD – Will be accepted if no other method is possible and upon prior approval.

c. ITEMS TO BE SUBMITTED VIA HARDCOPY

Product samples, color boards, and any other item not feasible to submit digitally, shall be submitted hard copy. ENGR 4025 shall be submitted digitally always. The Government reserves the right to request hard copy submission on any item, if deemed necessary.

Contractor shall be prepared to provide requested hard copy at any time.

1.8 CONTRACTOR PERFORMANCE EVALUATIONS

In accordance with the provisions of Subpart 36.201 (Evaluation of Contractor Performance) of the Federal Acquisition Regulation (FAR), construction contractor’s performance shall be evaluated throughout the performance of the contract. The United States Army Corps of Engineers (USACE) follows the procedures outlined in Engineering Regulation 415-1-17 to fulfill this FAR requirement. For construction contracts awarded at or above $700,000.00, the USACE will evaluate contractor’s performance and prepare a performance report using the Contractor Performance Assessment Reporting System (CPARS), which is now a web-based system. After an evaluation (interim or final) is written up by the USACE, the contractor will have the ability to access, review and comment on the evaluation for a period of 60 days. Accessing and using CPARS requires specific software, called PKI certification, which is installed on the user’s computer. The certification is a Department of Defense requirement and was implemented to provide security in electronic transactions. The certification software could cost approximately $110 - $125 per certificate per year and is purchased from an External Certificate Authorities (ECA) vendor. Current information about the PKI certification process and for contacting vendors can be found on the web site: http://www.cpars.csd.disa.mil/ . If the Contractor wishes to participate in the performance evaluation process, access to CPARS and PKI certification is the sole responsibility of the Contractor.

1.9 CONTRACTOR PAYROLL RECORD

Contractor shall be required to log payrolls for all their own employees and subcontractors utilizing ENG Form 3180. Each subcontractor requires a separate ENG 3180 for their payrolls. The Contractor shall maintain the ENG 3180, along with the payrolls, on site and available for review by the Contracting Officer's Representative. The ENG 3180's shall be updated weekly as payrolls are submitted. After making copies for their files, the Contractor is required to submit the originals of each week’s payrolls to the Resident Office. Before final payment, the Contractor shall provide the completed ENG 3180’s to the Contracting Officer's Representatives.

SECTION 01 00 00.00 44 Page 5

1.10 CONTRACTOR SUPPLY and USE OF ELECTRONIC SOFTWARE FOR PROCESSING WAGE

RATE REQUIREMENTS CERTIFIED LABOR PAYROLLS

(a) The contractor is required to use a commercially-available electronic system to process and submit certified payrolls electronically to the Government. The requirements for preparing, processing and providing certified labor payrolls are established by the Wage Rate Requirements statute.

(b) The contractor shall be responsible for obtaining and providing for all access, licenses, and other services required to provide for receipt, processing, certifying, electronically transmitting to the Government, and storing weekly payrolls and other data required for the contractor to comply with the Wage Rate Requirements statute. When the contractor uses an electronic payroll system, the electronic payroll service shall be used by the contractor to prepare, process, and maintain the relevant payrolls and basic records during all work under this construction contract and the electronic payroll service shall be capable of preserving these payrolls and related basic records for the required 3 years after contract completion. The contractor shall obtain and provide electronic system access to the Government, as required to comply with the Wage Rate Requirements over the duration of this construction contract. The access shall include electronic review access by the Government contract administration office to the electronic payroll processing system used by the contractor.

(c) The contractor's provision and use of an electronic payroll processing system shall meet the following basic functional criteria:

(1) commercially available;

(2) compliant with appropriate Wage Rate Requirements statute payroll provisions in the Federal Acquisition Regulation (FAR);

(3) able to accommodate the required numbers of employees and subcontractors planned to be employed under the contract

(4) capable of producing an Excel spreadsheet-compatible electronic output of weekly payroll records for export in an Excel spreadsheet;

(5) demonstrated security of data and data entry rights;

(6) ability to produce contractor-certified electronic versions of weekly payroll data;

(7) ability to identify erroneous entries and track the date/time of all versions of the certified Wage Rate Requirements statute payrolls submitted to the government over the life of the contract;

(8) capable of generating a durable record copy, that is, a CD or DVD and PDF file record of data from the system database at end of the contract closeout. This durable record copy of data from the electronic payroll processing system shall be provided to the Government during contract closeout.

(d) All contractor-incurred costs related to the contractor's provision and use of an electronic payroll processing service shall be included in the contractor's price for the overall work under the contract. The costs for compliance with the Wage Rate Requirements statute by using electronic

SECTION 01 00 00.00 44 Page 6 payroll processing services shall not be a separately bid or reimbursed item under this contract.

1.11 ADDITIONAL CONTRACTOR PAYROLL RECORD

(1) The Fort Worth District requires the contractor and all sub-contractors to use an electronic payroll system meeting the requirements above referenced and the following.

(a) The Certified Labor Payrolls must be tracked electronically via WEB-based software and all data must be submitted via WEB. Payroll guidelines,"Instructions to Contractors on Contract Labor Requirements, published as "Appendix A, SWFP 1185-1-1" (also known as the Green book), will be provided to advise/inform contractors how these labor provisions will be administered and enforced.

(b) The WEB-based software must be capable of downloading data directly from existing electronic payrolls, track workers to ensure that overtime is being paid when overtime status is reached on Government contracts whether on one or multiple contracts or different sub-contractors. The software must track apprentices and journeyman ratios, create and track SF-1444 "Request for Authorization of Additional Classification and Rate", track workers by name/address/with or without Social Security Numbers, allow automated redaction of information appearing on payroll statements for agency response to Freedom of Information Act (FOIA requests), and provide free online training by the software provider to any user of the software.

(c) The software must allow fringe benefit statement to track fringe benefits "whether cash or into an approved plan, fund, or program. If the fringe benefits are paid into a plan, fund, or program the company's name (receiving benefits), phone number, and address shall be listed on the Statement of Compliance Form (DD Form 879 or WH-347).

(d) Software must provide a method of tracking standard and non-standard deductions such as restitution, alimony, child support, and allow for custom entries. Method of tracking must list the deductions on the statement of compliance or be listed as an attachment.

(e) The Contractor is required to provide the updated 3080's and notify the Contracting Officer's Representatives weekly by email when the current payrolls are complete and ready for inspection/review on the WEB. Before final payment, the Contractor shall provide the completed ENG For 3180's and 3 disks (CD/DVD) which include complete copies of the Contractor and sub-contractor's payrolls/attachments, to the Contracting Officer's Representatives.

(2) Electronic copies of electronically/manually signed forms/memos/letters such as SF 1413 Statement of Acknowledgement (sub-contractor agreement), SF-1444 "Request for Authorization of Additional Classification and Rate", employee deduction authorization, certification of apprentices and trainees shall be provided to the Contracting Officer's Representative as required by FAR.

1.12 DAMAGE TO WORK (CESWF-CD)

The responsibility for damage to any part of the permanent work shall be as set forth in the Contract Clause entitled "Permits and Responsibilities." However, if, in the judgement of the Contracting

SECTION 01 00 00.00 44 Page 7

Officer, any part of the permanent work performed by the Contractor is damaged by flood or earthquake, which damage is not due to the failure of the Contractor to take reasonable precautions or to exercise sound engineering and construction practices in the conduct of the work, the Contractor will make the repairs as ordered by the Contracting Officer and full compensation for such repairs will be made at the applicable contract unit or lump sum prices as fixed and established in the contract. If, in the opinion of the Contracting Officer, there are no contract unit or lump sum prices applicable to any part of such work an equitable adjustment pursuant to Contract Clause "Changes," will be made as full compensation for the repairs of that part of the permanent work for which there are no applicable contract unit or lump sum prices. Except as herein provided, damage to all work (including temporary construction), utilities, materials, equipment and plant shall be repaired to the satisfaction of the Contracting Officer at the Contractor's expense, regardless of the cause of such damage.

1.13 PERMITTING

The City of Kerrville has been introduced to the reconstruction project scope and has performed code-compliance reviews for the building. City engineers have reviewed and commented on the design of the water and sewer services, which has been incorporated into the Contract Documents.

1.13.1 Demolition Permits

Each building will have its own separate demolition permit. Follow-up information is the responsibility of the Contractor (such as the Contractor's registration with the City) shall be provided by the Contractor for posting for the permit. Per the following schedule, demolition permits are $100 each.

1.13.2 Construction Permits

Each building will have its own separate construction permit. Follow-up information and coordination with the City shall be the responsibility of the Contractor. Inspections for mechanical, plumbing and electrical systems shall be coordinated between the Contractor and the City of Kerrville. Per the following schedule, construction permits are:

a. Building Permit: Permit (value up to $1,000) plus $25 per permit, $5 per $1,000 construction cost.

b. Plumbing Permit: $30 +additions per fixture, etc.

c. HVAC Permit: $3 per $1,000 construction cost.

d. Electrical Permit: $40 +additions per circuit, etc.

e. Additional Permits not specifically listed, such as utility fees, sewer & water taps, etc. shall also be the responsibility of the Contractor.

SECTION 01 00 00.00 44 Page 8

1.13.3 Borrow, Excavation, Welding, and Burning Permits

ACTIVITY SUBMISSION DATE

Borrow Permits 10 calendar days prior to work

Excavation Permits 5 calendar days prior to work

Welding Permits 3 calendar days prior to work

Post permits at a conspicuous location in the construction area.

Burning of trash or rubbish is not permitted.

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

Not Used.

-- End of Section --

SECTION 01 00 00.00 44 Page 9

SECTION 01 11 00

SUMMARY OF WORK

08/ 15, CHG 2: 08/ 21

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Utility Outage Requests

Utility Connection Requests

Excavation Permits

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

The work includes replacement of the large animal Stanchion Barn and construction of a Working Barn, with associated sitework and incidental related work.

1.2.2 Location

The Projects is located at the Knipling-Bushland U.S. Livestock Insects Research Laboratory (KBUSLIRL) at 2700 Fredericksburg Road, Kerrville Texas, 78028

1.3 OCCUPANCY OF PREMISES

Building(s) will be occupied during performance of work under this Contract. See Section 01 00 00.00 44 CONSTRUCTION SCHEDULE or more information.

Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.

1.4 EXISTING WORK

In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that

SECTION 01 11 00 Page 1 which existed before new work started.

1.5 ON-SITE PERMITS

1.5.1 Utility Outage Requests and Utility Connection Requests

Schedule work to minimize outages. For utility outages and connections required during the execution of work that affect existing systems, schedule outside the regular working hours or on weekends, as approved by the Contracting Officer. Schedule utility outages and connections to minimize disruptions tothe Government. No additional payment will be provided for utility outages and connections required to be performed outside the regular work hours.

Submit requests for utility outages and connections in writing to the Contracting Officer for approval at least 15 calendar days in advance of the time required. In each request, state the system involved, area involved, approximate duration of outage, and the nature of work involved.

1.6 LOCATION OF UNDERGROUND UTILITIES

Obtain digging permits prior to start of excavation, and comply with Installation requirements for locating and marking underground utilities.

Contact local utility locating service a minimum of 48 hours prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday. Verify existing utility locations indicated on contract drawings, within area of work.

Identify and mark all other utilities not managed and located by the local utility companies. Scan the construction site with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities or utilities encased in pier structures ]are discovered. Verify the elevations of existing piping, utilities,and any type of underground or encased obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.

1.6.1 Notification Prior to Excavation

Notify the Contracting Officer at least 15 days prior to starting excavation work.

1.7 SITE ELECTRICALO UTILITIES

Kerrville Public Utility Board (KPUB will provide demolition of the existing power line and transformers, and switches. The Contractor shall coordiante with KPUB on electrical site utilities.

The Contractor shall cary an allowance as noted in Dividion 00 to cover the cost of KPUB to provide and install new electrical utilities and to demolish existing electrical utilities.

1.7.1 Kerrville Pulbic Utility Board Information

Contact: Lou Graves, Kerrville Public Utility Board, 2250 Memorial Blvd., Kerrville, TX 78028, 830-257-3050.

SECTION 01 11 00 Page 2

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

SECTION 01 11 00 Page 3

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

08/15

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29.01 SUSTAINABLE DESIGN REQUIREMENTS. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

View Location Map ; G, AE

Progress and Completion Pictures ; G, AE

1.2 VIEW LOCATION MAP

Submit, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.

1.3 PROGRESS AND COMPLETION PICTURES

Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color minimum resolution in JPEG file format showing the sequence and progress of work. Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten views from points located by the Contracting Officer. Submit with the monthly invoice two sets of digital photographs, each set on a separate compact USB Drive, CD, and/or posted on the Contractor's project management website, cumulative of all photos to date. Indicate photographs demonstrating environmental procedures.

Provide photographs for each month in a separate monthly directory and name each file to indicate its location on the view location sketch. Also provide the view location sketch as a digital file. Include a date designator in file names. Cross reference submittals in the appropriate daily report. Photographs provided are for unrestricted use by the Government.

1.4 MINIMUM INSURANCE REQUIREMENTS

Provide the minimum insurance coverage required by FAR 28.307-2 Liability, during the entire period of performance under this contract.

1.5 SUPERVISION

1.5.1 Minimum Communication Requirements

Have at least one qualified superintendent, or competent alternate, SECTION 01 30 00 Page 1 capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of contract work. In addition, if a Quality Control (QC) representative is required on the contract, then that individual must also have fluent English communication skills.

1.5.2 Superintendent Qualifications

The project superintendent must have a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.

1.5.2.1 Duties

The project superintendent is primarily responsible for managing and coordinating day-to-day production and schedule adherence on the project.

The superintendent is required to attend meetings . The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.

1.5.3 Project Manager

Assign a Project Manager with the responsibility for the overall management of the project. The Contracting Officer may request proof of the Project Manager's qualifications at any point in the project if the performance of the Project Manager is in question.

1.5.3.1 Project Manager Qualifications

The Project Manager must have a minimum 10 years experience as a Project Manager or Superintendent on projects of similar size and complexity.

1.5.4 Non-Compliance Actions

The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to insure timely completion.

Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.

1.6 PRECONSTRUCTION MEETING

After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule of prices or earned value report, shop drawings, and other submittals, scheduling programming, prosecution of the work, and clear expectations. Major subcontractors who will engage in the work must also attend.

SECTION 01 30 00 Page 2

1.7 FACILITY TURNOVER PLANNING MEETINGS

The project involves completion and turnover of buildings. Contractor shall inform the Government in writing at least four (4) weeks before targeted building turnover.

Meet with the Government to identify strategies to ensure the project is carried to expeditious closure and turnover to the Client. Start the turnover process at the Pre-Construction Conference meeting with a discussion of the process. Include the following in the facility Turnover effort:

1.7.1 Checklist

a. Prior to 75 percent completion add/delete critical activities to the Checklist template as necessary to match the project scope, and schedule critical activities and insert planned completion dates in the checklist for each critical activity. Present the Checklist and review during a regularly scheduled QC Meeting.

1.7.2 Meetings

a. Upon Government acceptance of the Checklist, the Project Superintendent is required to lead regular Meetings beginning at approximately 75 percent project completion, or three to six months prior to Beneficial Occupancy Date (BOD), whichever comes first.

b. The Contracting Officer will determine the frequency of the meetings, which is expected to increase as the project completion draws nearer.

c. Using the Checklist as a Plan of Action and Milestones (POAM) and basis for discussion, review upcoming critical activities and strategies to ensure work is completed on time.

d. Coordinate with the COTR any upcoming activities that require Government involvement.

e. Maintain the Checklist by documenting the actual completion dates as work is completed and update the Checklist with revised planned completion dates as necessary to match progress. Distribute copies of the current Checklist to attendees at each Meeting.

1.8 PARTNERING

1.8.1 Informal Partnering

The Contracting Officer will organize the Partnering Sessions with key personnel of the project team, including Contractor personnel and Government personnel.

The Initial Partnering session should be a part of the Pre-Construction Meeting. Partnering sessions will be held at a location agreed to by the Contracting Officer and the Contractor. The Initial Informal Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by the Contracting Officer. The Partners will determine the frequency of the follow-on sessions, at no more than 3 to six month intervals.

SECTION 01 30 00 Page 3

1.9 ELECTRONIC MAIL (E-MAIL) ADDRESS

Establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments as text files, pdf files, and other similar formats. Within 10 days after contract award, provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes or terrorist threats. Multiple email addresses are not allowed.

It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). Promptly notify the Contracting Officer, in writing, of any changes to this email address.

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

Not Used.

SECTION 01 30 00 Page 4

SECTION 01 32 01.00 10

PROJECT SCHEDULE

02/15

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AACE INTERNATIONAL (AACE)

AACE 29R-03 (2011) Forensic Schedule Analysis

AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29.01 SUSTAINABLE DESIGN REQUIREMENTS. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Project Scheduler Qualifications ; G

Preliminary Project Schedule ; G

Initial Project Schedule ; G

Periodic Schedule Update ; G

1.3 PROJECT SCHEDULER QUALIFICATIONS

Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The authorized representative must have a minimum of 2-years experience scheduling construction projects similar in size and nature to this project with scheduling software that meets the requirements of this specification. Representative must have a comprehensive knowledge of CPM scheduling principles and application.

PART 2 PRODUCTS

2.1 SOFTWARE

The scheduling software utilized to produce and update the schedules required herein must be capable of meeting all requirements of this specification.

SECTION 01 32 01.00 10 Page 1

2.1.1 Contractor Software

Scheduling software used by the contractor must be Primavera P6 (preferred) or be commercially available from the software vendor for purchase with vendor software support agreements available. The software routine used to create the required sdef file must be created and supported by the software manufacturer.

2.1.1.1 Software

Provide two (2) license copies of the software to the Government for use during the project. If Primavera P6 is selected for use, provide the "xer" export file in a version of P6 importable by the Government system.

If another software is selected that is compliant with this specification, the Contractor shall provide training for two Government employees in use of the software. Software licenses will be returned to the Contractor at project completion.

2.1.1.2 Hardware

Provide two (2) computers to the Government for use. These computers will be stand-alone and not connected to Government networks. The computers will be returned to the Contractor at project completion.

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15 Schedules for Construction Contracts. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of design and construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development. Designers, Subcontractors and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules. Prepare each Project Schedule using the Precedence Diagram Method (PDM).

3.2 BASIS FOR PAYMENT AND COST LOADING

The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a contract CLIN must equal the value of the CLIN.

3.2.1 Activity Cost Loading

Activity cost loading must be reasonable and without front-end loading.

Provide additional documentation to demonstrate reasonableness if requested by the Contracting Officer.

3.2.2 Withholdings / Payment Rejection

Failure to meet the requirements of this specification may result in the

SECTION 01 32 01.00 10 Page 2 disapproval of the preliminary, initial or periodic schedule updates and subsequent rejection of payment requests until compliance is met.

In the event that the Contracting Officer directs schedule revisions and those revisions have not been included in subsequent Project Schedule revisions or updates, the Contracting Officer may withhold 10 percent of pay request amount from each payment period until such revisions to the project schedule have been made.

3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS

3.3.1 Level of Detail Required

Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:

3.3.2 Activity Durations

Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods.

Less than 2 percent of all non-procurement activities may have Original Durations (OD) greater than 20 work days or 30 calendar days.

3.3.3 Procurement Activities

Include activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.

3.3.4 Mandatory Tasks

Include the following activities/tasks in the initial project schedule and all updates.

a. Submission, review and acceptance of SD-01 Preconstruction Submittals (individual activity for each).

c. Submission of mechanical/electrical/information systems layout drawings.

d. Long procurement activities

e. Submission and approval of O & M manuals.

f. Submission and approval of as-built drawings.

g. Submission and approval of DD1354 data and installed equipment lists.

h. Submission and approval of testing and air balance (TAB).

i. Submission of TAB specialist design review report.

j. Submission and approval of fire protection specialist.

SECTION 01 32 01.00 10 Page 3

k. Submission and approval of Building Commissioning Plan, test data, and reports: Develop the schedule logic associated with testing and commissioning of mechanical systems to a level of detail consistent with the contract commissioning requirements. All tasks associated with all building testing and commissioning will be completed prior to submission of building commissioning report and subsequent contract completion.

m. Building commissioning - Functional Performance Testing.

n. Controls testing plan submission.

o. Controls testing.

p. Performance Verification testing.

q. Other systems testing, if required.

r. Contractor's pre-final inspection.

s. Correction of punch list from Contractor's pre-final inspection.

t. Government's pre-final inspection.

u. Correction of punch list from Government's pre-final inspection.

v. Final inspection.

3.3.5 Government Activities

Show Government and other agency activities that could impact progress.

These activities include, but are not limited to: environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.

3.3.6 Standard Activity Coding Dictionary

Develop and assign all Activity Codes to activities as detailed herein.

The SDEF format is as follows:

Field Activity Code Length Description

1 WRKP 3 Workers per day

2 RESP 4 Responsible party

3 AREA 4 Area of work

4 MODF 6 Modification Number

5 BIDI 6 Bid Item (CLIN)

SECTION 01 32 01.00 10 Page 4

Field Activity Code Length Description

6 PHAS 2 Phase of work

7 CATW 1 Category of work

8 FOW 20 Feature of work*

*Some systems require that FEATURE OF WORK values be placed in several activity code fields. The notation shown is for Primavera P6. Refer to the specific software guidelines with respect to the FEATURE OF WORK field requirements.

3.3.6.1 Workers Per Day (WRKP)

Assign Workers per Day for all field…