Attachment 8 Geotech Supplemental 3.pdf
PDF 2 MB Posted
- Attached to
- Construct Stanchion Barn and Cattle Working Barn Federal contract opportunity
- Solicitation number
- 12805B24R0035
About this file
This document is a Supplemental Letter #3 from Arias Geoprofessionals providing additional geotechnical design recommendations for the construction of a new cattle working barn at the USDA ARS KBUSLIRL facility in Kerrville, Texas.
The letter provides detailed recommendations for the design of a drilled pier foundation system, including allowable axial and lateral capacities, as well as construction considerations. Key details include recommended minimum pier depth of 15-25 feet, minimum diameter of 18 inches, and requirements for pilot holes to verify subsurface conditions. The letter also presents geotechnical input parameters for use in lateral pile analyses. Soil conditions encountered primarily consist of very hard marlstone with clay-filled voids, which could impact pier installation and require specialized equipment. The letter recommends procedures for addressing potential voids or clay seams encountered during pier drilling. Overall, the document provides comprehensive geotechnical engineering guidance to support the structural design and construction of the cattle working barn.
View the file
Other files for this federal contract opportunity
Show all 29
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Austin • Corpus Christi • Eagle Pass • Fort Worth • San Antonio
To: Mr. Jon C. DeLay, P.E. Date: October 8, 2020
Company: Merrick & Company Page: 1 of 11
From: Jerry D. Shepherd, P.E., D.GE Arias Job No.: 2018-933 Kacy M. Crawford, P.E.
Subject: Supplemental Letter #3 Drilled Pier Parameters: USDA ARS KBUSLIRL New Cattle Working Barn Kerrville, Texas
Arias Geoprofessionals, Inc. (Arias) previously prepared a geotechnical engineering study for the above referenced project. The results of our study were originally presented in the Arias
Geotechnical Engineering Study Report, 2018-933, dated May 29, 2019 and revised on July
3, 2019. Supplemental Letter #1 dated January 10, 2020 provided additional foundation recommendations, and Supplemental Letter #2 dated April 21, 2020 provided retaining wall design parameters.
The proposed project will consist of the construction of a new cattle working barn with an earthen floor at the USDA ARS KBUSLIRL facility in Kerrville, Texas. In the original report, recommendations were provided for the barn to be supported on a slab on grade foundation, and in Supplemental Letter #1, recommendations were provided for a mud mat foundation.
This supplemental letter is to provide design criteria for the drilled piers, and applicable construction recommendations. One (1) additional boring was drilled at the site, to provide additional data and a summary of the field work completed is also included in this letter.
A site vicinity map is provided in Appendix A, Figure 1 of this report.
Field Exploration One (1) soil boring was drilled at the approximate location shown on the Boring Location
Plan provided as Figure 2 in Appendix A. Boring B-15 was drilled to a depth of thirty-five (35) feet below the existing ground surface that existed on September 15, 2020. Boring data is summarized in the following table.
Table 1: Boring Locations
Boring No. Structure Depth, ft As Drilled Coordinates
Latitude Longitude
B-15 Cattle Barn 35 30° 4' 23.16" N 99° 6' 41.51" W
Note: Borings B-1 through B-14 are summarized in the original Geotechnical Report dated May 29, 2019 and revised on July 3, 2019.
Supplemental Letter #3 Arias Geoprofessionals Arias Job No. 2018-933
The boring was sampled in accordance with ASTM D1586 procedures for Split Spoon sampling techniques as described in Appendix C of the original report. A truck-mounted drill rig using continuous flight augers together with the split spoon sampler was used to secure the subsurface soil samples. The boring was backfilled with soil cuttings generated during the drilling process.
Soil classifications and borehole logging were conducted during the exploration by our engineering technician working under the supervision of the Project Geotechnical Engineer.
Final soil classifications, as seen on the boring log included in Appendix B, were determined by the Project Geotechnical Engineer based on laboratory and field test results and applicable ASTM procedures. A key to the terms and symbols used on the boring log is also included in Appendix B.
Laboratory Tests As a supplement to the field exploration, laboratory testing was performed to determine soil water content, Atterberg Limits, and percent passing the US Standard No. 200 sieve. The laboratory test results are reported in the attached boring log included in Appendix B and the soil laboratory testing for this project was done in accordance with applicable ASTM procedures (as noted in Appendix C of the original report). Remaining soil samples recovered from this exploration will be routinely discarded following submittal of this report.
Subsurface Conditions Generalized stratigraphy and groundwater conditions encountered are discussed in the following sections. The subsurface and groundwater conditions are based on conditions encountered at the boring locations to the depths explored.
Geology
Geology at the site is mapped as Fluviatile Terrace Deposits (Qt), underlain by the Glen
Rose (Kgr) formation.
The Fluviatile Terrace Deposits are alluvium soils which are floodplain deposits and consist primarily of clays, along with various amounts of silt, sand, and gravel. These materials are typically tan to gray in color, although significant variation can occur across the site.
Localized zones of the alluvial soils encountered may include significant gravel deposits, which will typically contain angular, and cherty material. Because of the potential for increased permeability within the gravels relative to the much lower permeabilities of the underlying formational soils, a “perched” water zone could be encountered at the contact between the gravels and underlying clay formation. Due to the alluvial nature of these deposits, significant variations can occur over short distances.
Glen Rose Marlstone is an extensive formation along many areas north and west of the San
Antonio Area and can reach an overall thickness of over 1,000 feet. This formation consists of hard Marlstone strata, that alternate with marl or marly Marlstone, which is typically softer and prone to a higher degree of weathering and void development. This rock is typically fine grained to aphanitic and can be highly fossiliferous containing predominantly marine fossils.
Voids can occur, which are typically filled with either clay, or sandy clay, and may be up to several feet in diameter.
Site Stratigraphy and Engineering Properties
The generalized subsurface stratigraphy encountered at the location of Boring B-15 is summarized in Table 2 below. The presence and thickness of the various subsurface materials can be expected to vary away from and between the exploration locations. The descriptions generally conform to the Unified Soils Classification System.
Table 2: Generalized Subsurface Conditions: Boring B-15
Stratum Depth
(ft) Material Type
PI
range
No. 200 range
N range
II 0 to 2 Gray and Light Brown –
SANDY LEAN CLAY (CL) –
very stiff
21* 56* 17*
III 2 to 35
Tan, Light Gray and Tan – MARLSTONE – very hard
Lean Clay filled void from 4 to
8 feet
-- -- **50/1 - **50/5
Note: Stratum I soils were encountered in borings drilled during the initial geotechnical study. They were not encountered in this phase of work.
Where: Depth - Depth from existing ground surface at the time of geotechnical study, feet PI - Plasticity Index, % No. 200 - Percent passing #200 sieve, N - Standard Penetration Test (SPT) N-value, blows per foot
* - Only one test in Stratum -- - No test applicable in Stratum ** - Indicates blows during seating penetration
Groundwater
A dry soil sampling method was used to obtain the samples at the project site, and groundwater was not encountered during field operations on September 15, 2020.
Groundwater levels will often change significantly over time and should be verified immediately prior to construction.
Water levels in open boreholes may require several hours to several days to stabilize depending on the permeability of the soils. Groundwater levels at this site may differ during construction because fluctuations in groundwater levels can result from seasonal conditions, rainfall, drought, or temperature effects. Pockets or seams of gravels, sands, silts or open fractures and joints can store and transmit “perched” groundwater flow or seepage. Should dewatering become necessary, it is considered means and methods and is solely the responsibility of the contractor.
Drilled Piers Foundation Recommendations A drilled pier foundation is being considered for the Cattle Working Barn. Recommendations for evaluation of axial capacity and lateral capacity are presented in the Tables 3 and 4 below. Pier capacities for axial loading were evaluated using the design methodologies included in FHWA-IF-99-025 - Drilled Shafts: Construction Procedures and Design Methods.
Both end bearing and side friction resistance may be used in evaluating the allowable bearing capacity of the pier shafts.
Table 3: Drilled Pier Design Parameters Axial Capacity
Depth Material
Recommended Design Parameters
Allowable Skin
Friction, psf
Allowable End
Bearing, psf
Uplift Force, kips
0 to 5 Sandy Lean Clay & Marlstone with clay filled void Neglect
5 to 8 Marlstone with a lean clay filled void - --
25*D 8 to 35
Very hard & weathered Marlstone with clay filled voids
1,000 10,000
Constraints to be Imposed During Pier Design
Minimum depth of drilled piers, (measured from surface)
A minimum depth of 15 to 25 feet is recommended.
Deeper depths may be required to resist compressive, uplift, pullout, or lateral loads as determined by the Project Structural Engineer. If piers are designed to be deeper than 35-feet, we should be contacted to provide additional borings and recommendations.
Minimum shaft diameter 18 inches
Minimum Void Space Below Grade Beams and Pier Caps
12 inches
Notes:
1. For straight shaft piers, the contribution of the soils for the top eight feet of soil embedment and for a length equal to at least 1 pier diameter from the bottom of the shaft should be neglected in determination of friction capacity for compression loading. The recommended design parameters include a factor of safety of 2 for skin friction and of 3 for end bearing.
2. Total and differential settlement of piers is expected to be less than 1 inch and ½ inch, respectively. Estimated settlements are based on performance of properly installed piers in the Kerrville, Texas area. A detailed settlement estimate is outside of the scope of this service.
3. Sufficient reinforcing steel should be placed within the pier to account for tension and lateral loading as applicable.
Pier vertical reinforcing steel should be designed to resist the uplift forces from swelling soils and uplift and lateral forces from wind loading. The final reinforcing requirements should be determined by the project structural engineer.
Tensile rebar steel should be designed in accordance with ACI Code Requirements.
4. A minimum shaft diameter of 18 inches is recommended. Larger shaft diameters may be required. Straight shaft piers should be spaced at least 3 diameters apart center-to-center. If the recommended pier spacing cannot be maintained, Arias should be consulted to consider the group effect of closely spaced piers.
5. The uplift force resulting from expansion of soils in the active zone may be computed using the above formula where D is the shaft diameter in feet. For drilled straight-sided piers, the contribution from soils to resist uplift is the allowable skin friction resistance of the soils below the basement floor slab. For uplift loading only, the allowable skin resistance for the bottom 1 pier diameter can be used to size the pier. Sustained dead loads will also aid in resisting uplift forces. Pier depths greater than 30 feet may be required to: (1) resist expansive soil uplift forces, and/or (2) as a result of axial or lateral loading requirements.
Lateral pile analyses including capacity, maximum shear, and maximum bending moment will be evaluated by the project structural engineer using LPILE or similar software. In the following table, Arias presents geotechnical input parameters for the encountered soils at the
Cattle Working Barn site. Please note that the depths to the top and bottom of each layer were interpreted using approximate elevation data at the explored boring location and layer boundaries as shown on the boring log.
Table 4: Drilled Pier Geotechnical Input Parameters for LPILE Analyses
Depth, (ft) Material e ER qur RQD Krm
0 - 8 Sandy Lean Clay & Marlstone with clay filled void NEGLECT
8 - 35 Very hard & weathered
Marlstone with clay filled voids 130 150,000 1,000 25 0.0005
Note: The parameters given above are for use in the “Weak Rock” criteria for the LPILE analysis.
Where: Depth: Stratum depth in feet from below the existing ground surface on 9/15/2020 ge : Effective unit weight, pcf Er : Young’s modulus for weak rock, psi qur : Uniaxial compressive strength, psi RQD: Rock Quality Designation, % Krm : Axial strain parameter for weak rock
Table 5: Summary of Pilot Hole Requirements
Foundation Type Summary of Pilot Program
Drilled Pier
Pilot holes should be performed at each pier location at a minimum depth below the expected pier tip elevation of 2 pier diameters, or 10 feet, whichever results in a deeper pilot hole.
(Not required if piers are designed as frictional units, i.e. supported by side friction only without an end-bearing component)
Notes:
1. All pilot holes should be grouted using a lean concrete having a 28-day compressive strength of at least 3,000 psi.
2. Arias can assist in developing a pilot hole schedule to meet the above criteria once the type of foundation system has been selected, and once the foundation layout has been determined.
3. Pilot holes are typically performed with a small diameter drill (i.e. ½ inch or similar). The pilot hole program should be monitored by a representative of Arias Geoprofessionals.
The subsurface conditions encountered during the field exploration at the project site indicates that the depth to competent rock could vary, and there is a potential for encountering voids.
pfinley Cloud+ pfinley Cloud+ something is not correct here pfinley Cloud+ pfinley Cloud+ need add to notes and specs
Variations in bedrock depths is common in the Glen Rose Marlstones which may be the result of the uneven weathering, voids, softer layers, and clay seams that can be present. A
Lean Clay (CL) filled void was also encountered in the boring. The presence of these conditions reduces the side resistance along the shafts, and if they are unknowingly present below the pier tip elevations, the end bearing capacity of the piers could be significantly less than the design values. The following two design approaches can be taken. Pilot hole recommendations are presented below as well as previously in Table 5 (Summary of Pilot
Hole Requirements).
If a karst feature is encountered during construction and/or pilot hole drilling, we should be notified immediately so that we may evaluate the feature and its potential impacts on the proposed construction. Minor solution features are often grouted with lean concrete or flowable fill. Arias should be provided an opportunity to evaluate Karst features on a case-by-case basis and provide geotechnical recommendations as appropriate.
Design the Piers for Side Friction and End Bearing - If fractured rock with voids, and/or clay filled seams/layers are encountered during the drilling of a pier, the pier length should be extended an additional length equal to the thickness of the non-rock material to achieve the required side friction. For example, once competent bedrock is encountered, if a one-foot thick clay layer is encountered within the bedrock during drilling, the pier should be extended an additional foot of depth into the underlying competent bedrock.
If fractured rock with voids, and/or clay filled seams/layers conditions is present below the pier tip elevation, the design end bearing capacity may not be achieved.
Accordingly, if the pier is designed for end bearing, it will be necessary to check for the presence of apparent non rock bearing conditions by drilling a “pilot hole” that extends at least two (2) pier diameters or 10 feet below each pier bottom, whichever results in the deeper pilot hole. If fractured rock with voids, and/or clay seams/layers conditions are encountered in the pilot hole, it will be necessary to extend the pier bottom a minimum of one (1) pier diameter below the fractured rock with voids, and/or clay filled seams/layers in order to use the design end bearing capacity (i.e. this is in addition to extending the pier depth for side friction considerations previously noted).
A representative of the Geotechnical Engineer must be present to verify that all of the pilot holes are taken to the recommended depth including the additional pier depths when clay-filled seams/layers or a void is encountered in the pilot holes.
Design the Piers for Side Friction Only – An alternative to performing pilot holes is to design the piers for side friction only (i.e. end bearing is neglected). If fractured rock with voids, and/or clay filled seams/layers conditions is encountered during the drilling of a pier, the pier length would have to be extended an additional length equal pfinley Cloud+ pfinley Cloud+ add to notes and specs to the thickness of the non-rock material to achieve the required side friction. For example, once competent bedrock is encountered, if a one-foot thick clay layer is encountered within the bedrock during drilling, the pier should be extended an additional foot into the underlying competent bedrock. Pilot holes will not be required for drilled piers designed using side friction only
Drilled Piers Construction Considerations
The contractor should verify groundwater conditions before production pier installation begins. Comments pertaining to high-torque drilling equipment, groundwater, slurry, and temporary casing are based on generalized conditions encountered at the explored locations. Conditions at individual pier locations may differ from those presented and may require that these issues be implemented to successfully install piers. Construction considerations for drilled pier foundations are outlined in the following table.
Table 6: Drilled Pier Installation Considerations
Recommended installation procedure FHWA-NHI-10-016, May 2010
High-torque drilling equipment anticipated
Yes; dense and very hard clayey soils and Marlstone encountered
Groundwater anticipated Possible, not encountered during field operations
Temporary casing anticipated Possible, only if drilling conditions require
Slurry installation anticipated Possible if subsurface soil and groundwater conditions dictate
Concrete placement
Same day as drilling. If a pier excavation cannot be drilled and filled with concrete on the same day, temporary casing or slurry may be needed to maintain an open excavation. The concrete should be placed using a tremie or pump and not allow the concrete to ricochet off the reinforcing cage or side pier side walls.
Maximum water accumulation in excavation at time of concrete placement
2 inches - MAXIMUM
Concrete installation method needed if water accumulates
Tremie or pump to displace water beginning at the bottom of the pier excavation.
Quality assurance monitoring
Geotechnical engineer’s representative should be present during drilling of all piers, should observe drilling and verify the installed depth and diameter, should verify material type at the base of excavation and cleanliness of base, and should observe placement of reinforcing and concrete.
Notes:
1. The contractor should verify groundwater conditions before production pier installation begins. Temporary casing may be needed due to groundwater conditions, dependent on seasonal conditions. Payment provisions for temporary casing and for placement of concrete by the tremie method are recommended for inclusion in the Contract Documents.
2. Comments pertaining to high-torque drilling equipment, groundwater, temporary casing, and slurry drilling methods are based on generalized conditions encountered at the explored locations. Importantly, these are considered means and methods and are the sole responsibility of the contractor. Conditions at individual pier locations may differ from those presented and may require that these techniques be implemented to successfully install piers.
3. The following installation techniques will aid in successful construction of the shafts:
a. The clear spacing between rebar or behind the rebar cage should be at least 3 times the maximum size of coarse aggregate.
b. Centralizers on the rebar cage should be installed to keep the cage properly positioned.
c. Cross-bracing of a reinforcing cage may be used when fabricating, transporting, and/or lifting.
However, experience has shown that cross-bracing can contribute to the development of voids in a concrete shaft. Therefore, we recommend the removal of the cross-bracing prior to lowering the cage in the open shaft.
d. The use of a tremie should be employed so that concrete is directed in a controlled manner down the center of the shaft to the pier bottom. The concrete should not be allowed to ricochet off the pier reinforcing steel nor off the pier side walls.
e. The pier concrete should be designed to achieve the desired design strength when placed at a 7-inch slump, plus or minus 1-inch tolerance. Adding water to a concrete mix designed for a lower slump does not meet these recommendations.
It should also be noted that the subsurface materials encountered in our borings generally consisted of hard to very hard Maristone. Thus, we anticipate that high-torque drilling equipment will be required for pier installation at this site. The Contractor should be familiar with and prepared for such conditions.
Closing Unless stated otherwise, all other previous recommendations provided in our Geotechnical Engineering Study Report dated May 29, 2019 and revised on July 3, 2019 that are not specifically addressed in this Letter should be followed. Please feel free to call with questions or comments.
Please contact us with any questions or if additional information is needed.
Sincerely, Arias & Associates, Inc.
TBPE Registration No: F-32
~hep’~erd,.E.,D.GE Senior Geotechnical Engineer Supplemental Letter #3 Arias Geoprofessionals
Kacy . Crawford, P.E.
Geotechnical Engineer
10/8/2020 •.~... ••••••• ••
JERRY D. SHEPHERD
112142
Arias Job No. 2018-933
Arias Geoprofessionals A-1 Arias Job No. 2018-933
APPENDIX A: FIGURES
142 Chula Vista, San Antonio, Texas 78232 Phone: (210) 308-5884 • Fax: (210) 308-5886
VICINITY MAP
USDA ARS KBUSLIRL
Cattle Working Barn: B-15 Kerrville, Texas
Date: May 20, 2019 Job No.: 2018-933 Figure 1
Drawn By: RWL Checked By: JDS Approved By: CMS Scale: N.T.S.
Approximate Site Limits
142 Chula Vista, San Antonio, Texas 78232 Phone: (210) 308-5884 • Fax: (210) 308-5886
BORING LOCATION PLAN
USDA ARS KBUSLIRL
Cattle Working Barn: B-15
Kerrville, Texas
Date: October 8, 2020 Job No.: 2018-933 REVISIONS: Drawn By: RWL Checked By: JDS No.: Date: Description: Approved By: CMS Scale: N.T.S.
Figure 2 1 of 1 D
IS
C
LA
IM
E R
T hi s dr aw in g is f or il lu st ra tio n on ly a nd s ho ul d no t be u se d fo r de si gn o r co ns tr uc tio n pu rp os es
A ll lo ca tio ns a re a pp ro xi m at e.
Arias Geoprofessionals B-1 Arias Job No. 2018-933
APPENDIX B: BORING LOGS AND SYMBOL KEY SHEET
SANDY LEAN CLAY (CL), very stiff, gray and light brown
STRATUM II
MARLSTONE, very hard, gray, highly weathered, marly, with clay filled voids.
STRATUM III
FILLED VOID: Lean Clay with Sand (CL), light gray and tan, from 4 feet to 8 feet
MARLSTONE, continued from above, STRATUM III.
**50/5"
**50/3"
**50/1"
**50/1"
**50/1"
**50/1"
**50/4"
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
Location: Cattle Working Barn: See Boring Location Plan
Coordinates: N30o4'23.16'' W99o6'41.51''
WC = Water Content (%) PL = Plastic Limit LL = Liquid Limit PI = Plasticity Index N = SPT Blow Count
** = Blow Counts During Seating Penetration
-200 = % Passing #200 Sieve
Soil Description
Nomenclature Used on Boring LogGroundwater Data:
During drilling: Not encountered
Field Drilling Data:
Coordinates: Hand-held GPS Unit Logged By: L. Arizola Driller: Eagle Drilling, Inc.
Equipment: Truck-mounted drill rig
Single flight auger: 0 - 35 ft
Backfill: Cuttings
(continued)
Split Spoon (SS)
Job No.: 2018-933
Project: USDA ARS KBUSLIRL Kerrville, Texas
Sampling Date: 9/15/20
Arias Geoprofessionals
Boring Log No. B-15
-9
.G
P J
/5
/2
(B O
R
IN
G L
O G
S A
-0
2, A
R
IA
S S
A
-0 1.
G D
T ,L
IB
R
A R
Y
-0
1.
G
LB
-200NPL LL PIWCSNDepth (ft)
MARLSTONE, continued from above, STRATUM III. (continued)
Borehole terminated at 35 feet
**50/3"11SS
Location: Cattle Working Barn: See Boring Location Plan
Coordinates: N30o4'23.16'' W99o6'41.51''
WC = Water Content (%) PL = Plastic Limit LL = Liquid Limit PI = Plasticity Index N = SPT Blow Count
** = Blow Counts During Seating Penetration
-200 = % Passing #200 Sieve
Soil Description
Nomenclature Used on Boring LogGroundwater Data:
During drilling: Not encountered
Field Drilling Data:
Coordinates: Hand-held GPS Unit Logged By: L. Arizola Driller: Eagle Drilling, Inc.
Equipment: Truck-mounted drill rig
Single flight auger: 0 - 35 ft
Backfill: Cuttings
Split Spoon (SS)
Job No.: 2018-933
Project: USDA ARS KBUSLIRL Kerrville, Texas
Sampling Date: 9/15/20
Arias Geoprofessionals
Boring Log No. B-15 (continued)
-9
.G
P J
/5
/2
(B O
R
IN
G L
O G
S A
-0
2, A
R
IA
S S
A
-0 1.
G D
T ,L
IB
R
A R
Y
-0
1.
G
LB
-200NPL LL PIWCSNDepth (ft)
GW
GP
GM
GC
SW
SP
SM
SC
ML
CL
MH
CH
Massive or Weakly Bedded Limestones
M o re t h a n h a lf o f m a te ri a l S
M A
L L E
R th a n N o S ie v e s iz e
F O
R M
A T
IO
N
A L
M A
T E
R
IA
L S
GROUP
SYMBOLS
KEY TO TERMS AND SYMBOLS USED ON BORING LOGS
C O
A R
S E
-G R
A
IN
E D
S O
IL
S
G R
A V
E L
S S
A N
D S
M o re t h a n H a lf o f C o a rs e f ra c ti o n i s
L A
R G
E R t h a n N o S ie v e s iz e
M o re t h a n h a lf o f m a te ri a l L A
R G
E R t h a n N o S ie v e s iz e
MAJOR DIVISIONS
Silty Gravels, Gravel-Sand-Silt Mixtures
Poorly-Graded Gravels, Gravel-Sand Mixtures, Little or no Fines
Well-Graded Gravels, Gravel-Sand Mixtures, Little or no Fines
DESCRIPTIONS
Clayey Sands, Sand-Clay Mixtures
Silty Sands, Sand-Silt Mixtures
Poorly-Graded Sands, Gravelly Sands, Little or no Fines
Well-Graded Sands, Gravelly Sands, Little or no Fines C le a n G ra v e ls
(l it tl e o r n o F in e s
G ra v e ls w h
F in
(A p p re c ia b le m o u n t o f F in e s
C le a n S a n d
(l tl e o r n o F in e s
S a n d s w it h F in
(A p p re c ia b le m o u n t o f F in e s
L iq u id
L im it l e th n
L iq u id
L im g re a te r th a n
LIMESTONE
MARLSTONE
SANDSTONE
Clayey Gravels, Gravel-Sand-Clay Mixtures
Massive Sandstones, Sandstones with Gravel Clasts
Inorganic Clays of High Plasticity, Fat Clays
Inorganic Silts, Micaceous or Diatomaceous Fine Sand or Silty Soils, Elastic Silts
Inorganic Clays of Low to Medium Plasticity, Gravelly Clays, Sandy Clays, Silty Clays, Lean Clays
Inorganic Silts & Very Fine Sands, Rock Flour, Silty or Clayey Fine Sands or Clayey Silts with Slight
Plasticity
Indurated Argillaceous Limestones
Indicates Final Observed Groundwater Level
Indicates Initial Observed Groundwater Location
Cretaceous Clay Deposits
Massive or Poorly Bedded Chalk Deposits
Mudstone or Massive Claystones
F
IN
E -G
R A
IN
E
D S
O
IL
S
M o re t h a n h a lf o f C o a rs e f ra c ti o n i
S M
A L L E
R t h a n N o S ie v e s iz e
S
IL
T
C
A Y
S
S
IL
T
C
A Y
S
GROUNDWATER
MARINE CLAYS
CHALK
CLAYSTONE
Very Dense
30 - 50
Over 50
10 - 30
Consistency and Strength of Cohesive Soils
Number of Blows per ft., N
Unconfined
Compressive
Strength, qᵤ (tsf)
Consistency
Density of Granular Soils
Relative Density
Very Loose
Number of
Blows per ft., N
0 - 4
4 - 10 Loose
Medium
Dense
Below 2
2 - 4 Soft
Very Soft
Stiff
Less than 0.25
0.25 - 0.5
0.5 - 1.0
1.0 - 2.0
Medium (Firm)
Very Stiff
Hard
4 - 8
8 - 15
15 - 30
Over 30 Over 4.0
2.0 - 4.0
Arias Geoprofessionals
Group
Symbol
GW
(Less than 5% fines C
Cu < 4 and/or GP
[Cc < 1 or Cc > 3] D
Gravels with Fines GM
(More than 12% fines C
GC
Sands Clean Sands SW
(Less than 5% fines H
) Cu < 6 and/or SP
[Cc < 1 or Cc > 3] D
Sands with Fines SM
(More than 12% fines H
SC
Silts and Clays inorganic CL
ML
organic OL
Silts and Clays inorganic CH
MH
organic OH
HIGHLY ORGANIC SOILS PT
A Based on the material passing the 3-inch (75mm) sieve B If field sample contained cobbles or boulders, or both, add "with cobbles or boulders, or both" to group name C Gravels with 5% to 12% fines require dual symbols:
GW-GM well-graded gravel with silt
GW-GC well-graded gravel with clay
GP-GM poorly-graded gravel with silt
GP-GC poorly-graded gravel with clay D
Cu = D60/D10 Cc =
E If soil contains ≥ 15% sand, add "with sand" to group name F If fines classify as CL-ML, use dual symbol GC-GM, or SC-SM G If fines are organic, add "with organic fines" to group name H Sand with 5% to 12% fines require dual symbols:
SW-SM well-graded sand with silt
SW-SC well-graded sand with clay
SP-SM poorly-graded sand with silt
SP-SC poorly-graded sand with clay I If soil contains ≥ 15% gravel, add "with gravel" to group name J If Atterberg limits plot in hatched area, soil is a CL-ML, silty clay K If soil contains 15% to < 30% plus No. 200, add "with sand" or "with gravel," whichever is predominant L If soil contains ≥ 30% plus No. 200, predominantly sand, add "sandy" to group name M If soil contains ≥ 30% plus No. 200, predominantly gravel, add "gravelly" to group name N PI ≥ 4 and plots on or above "A" line O PI < 4 or plots below "A" line P PI plots on or above "A" line Q PI plots below "A" line
TERMINOLOGY
Boulders Over 12-inches (300mm) Parting Inclusion < 1/8-inch thick extending through samples
Cobbles 12-inches to 3-inches (300mm to 75mm) Seam Inclusion 1/8-inch to 3-inches thick extending through sample
Gravel 3-inches to No. 4 sieve (75mm to 4.75mm) Layer Inclusion > 3-inches thick extending through sample
Sand No. 4 sieve to No. 200 sieve (4.75mm to 0.075mm)
Silt or Clay Passing No. 200 sieve (0.075mm)
Calcareous Containing appreciable quantities of calcium carbonate, generally nodular
Stratified Alternating layers of varying material or color with layers at least 6mm thick
Laminated Alternating layers of varying material or color with the layers less than 6mm thick
Fissured Breaks along definite planes of fracture with little resistance to fracturing
Slickensided Fracture planes appear polished or glossy sometimes striated
Blocky Cohesive soil that can be broken down into small angular lumps which resist further breakdown
Lensed Inclusion of small pockets of different soils, such as small lenses of sand scattered through a mass of clay
Homogeneous Same color and appearance throughout
(D30)
D10 x D60
KEY TO TERMS AND SYMBOLS USED ON BORING LOGS
TABLE 1 Soil Classification Chart (ASTM D 2487-11)
Group Name B
Organic Clay K,L,M,N
Organi Silt K,L,M,O
Fat Clay K,L,M
Clayey Gravel E,F,G
Well-Graded Sand I
Poorly-Graded Sand I
Silty Sand F,G,I
Clayey Sand F,G,I
Well-Graded Gravel E
Poorly-Graded Gravel E
Silty Gravel E,F,G
Soil Classification
Criteria of Assigning Group Symbols and Group Names Using Laboratory Tests A
More than 50% retained on No.
200 sieve
FINE-GRAINED SOILS
COARSE-GRAINED SOILS
Primarily organic matter, dark in color, and organic odor
Liquid limit less than 50
Liquid limit 50 or more
PI > 7 and plots on or above "A" line J
PI < 4 or plots below "A" line J
PI plots on or above "A" line
PI plots on or below "A" line
Fines classify as CL or
CH
(50% or more of coarse fraction passes No. 4 sieve)
50% or more passes the No.
200 sieve
Cu ≥ 4 and 1 ≤ Cc ≤ 3 DGravels Clean Gravels
Elastic Silt K,L,M
Organic Clay K,L,M,P
Organic Silt K,L,M,Q
Peat
Lean Clay K,L,M
Silt K,L,M
Fines classify as CL or
CH
Cu ≥ 6 and 1 ≤ Cc ≤ 3 D
Fines classify as ML or
MH
(More than 50% of coarse fraction retained on No. 4 sieve)
Fines classify as ML or
MH
<0.75
<0.75
Liquid limit - oven dried
Liquid limit - not dried
Liquid limit - oven dried
Liquid limit - not dried
Excellent
Rock Mass QualityVelocity IndexRQD %
90 – 100
75 – 90
50 – 75
25 – 50
0 – 25
0.80 – 1.00
0.60 – 0.80
0.40 – 0.60
0.20 – 0.40
0 – 0.20
Good
Fair
Very Poor
Poor
Very widely (fractured or jointed)
Widely
Medium
Closely
Very closely
Descriptions for Joints, Faults, or Other Fractures
Extremely close
Diagnostic Features
No visible sign of Decomposition or discoloration. Rings under hammer impact.
Slight discoloration inwards from open fractures, otherwise similar to F.
Discoloration throughout. Weaker minerals such as feldspar decomposed. Strength somewhat less than fresh rock, but cores cannot be broken by hand or scraped by knife. Texture preserved.
Most minerals somewhat decomposed. Specimens can be broken by hand with effort or shaved with knife. Core stones present in rock mass. Texture becoming indistinct, but fabric preserved.
Minerals decomposed to soil, but fabric and structure preserved (Saprolite). Specimens easily crumbled or penetrated.
Advanced state of decomposition resulting in plastic soils. Rock fabric and structure completely destroyed. Large volume change.
Spacing Description for Joints, Faults or Other Fractures
Thickly
Medium
Thinly
Very thinly
Description for Micro-Structural
Features: Lamination, Foliation, or
Cleavage
Intensely (laminated, foliated, or cleaved)
Very intensely
Spacing
¼ – ¾ inch
2 – 6 feet
Description for Structural Features:
Bedding, Foliation, or Flow Banding
Very thickly (bedded, foliated, or banded)
Symbol
F
WS
WM
WH
WC
RS
More than 6 feet
Engineering Classification for in Situ Rock Quality
Class
I
II
III
IV
V
Extremely hard
Hardness
Very hard
Hard
Soft
Very soft
Less than ¼ inch
¾ – 2½ inches
2½ – 8 inches
8 – 24 inches
Grade
Fresh
Slightly Weathered
Moderately Weathered
Highly Weathered
Completely Weathered
KEY TO TERMS AND SYMBOLS USED ON BORING LOGS
Hardness Classification of Intact Rock
Rock Weathering Classifications
Rock Discontinuity Spacing
Residual Soil
> 2,000
Approximate Range of Uniaxial
Compression Strength kg/cm²
(tons/ft²)
2,000 – 1,000
1,000 – 500
500 – 250
250 – 10
Field Test
Many blows with geologic hammer required to break intact specimen.
Hand held specimen breaks with hammer end of pick under more than one blow.
Cannot be scraped or pealed with knife, hand held specimen can be broken with single moderate blow with pick.
Can just be scraped or peeled with knife. Indentations 1mm to 3mm show in specimen with moderate blow with pick.
Material crumbles under moderate blow with sharp end of pick and can be peeled with a knife, but is too hard to hand-trim for triaxial test specimen.
File details come from the government source that posted it. Updated .