About this file
This document is a Supplemental Letter #4 from Arias, Inc. regarding a geotechnical engineering study for the USDA ARS KBUSLIRL project in Kerrville, Texas. The letter serves to correct a typographical error in Table 23 of the original geotechnical report, which covers non-structural fills for site work. Specifically, the "Stripping Depth" item should read "Strip away existing asphalt, concrete, soil, deleterious and soft/wet materials. Provide at least 4 inches deep of clearing and grubbing to removal all roots." All other previous recommendations from the original report and previous supplements remain in effect.
The related federal contract opportunity is for the "Construct Stanchion Barn and Cattle Working Barn" project in Kerrville, TX, with Solicitation Number 12805B24R0035. The contractor must have knowledge of all aspects of the Statement of Work. There is a mandatory site visit on August 5th, and all RFI questions must be submitted in writing by 4:00 PM on August 11, 2024. The agency involved is the Department of Agriculture Agricultural Research Service Field Research Implementation and Information Delivery Plains Area.
View the file
Other files for this federal contract opportunity
Show all 29
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
142 Chula Vista San Antonio, Texas 78232
To: Mr. Jon C. DeLay, P.E. Date: September 16, 2021
Company: Merrick & Company Page: 1 of 1
From: Jerry D. Shepherd, P.E., D.GE Arias Job No.: 2018-933 Mark J. O’Connor, P.E.
Subject: Supplement #4, Table 23 Removal & Replace Correction
USDA ARS KBUSLIRL
Kerrville, Texas
Arias, Inc. (Arias) previously prepared a geotechnical engineering study for the above referenced project. The results of our study were originally presented in the Arias Geotechnical Engineering Study Report, 2018-933, dated May 29, 2019, and revised on July 3, 2019. Supplemental Letter #1 dated January 10, 2020, provided additional foundation recommendations, Supplemental Letter #2 dated April 21, 2020, provided retaining wall design parameters, and Supplemental Letter #3 dated October 6, 2020, provided recommendations for drilled piers at the proposed Cattle Working Barn.
This Supplemental Letter #4 will serve to correct a typographical error in Table 23 of the original Report. Table 23 is entitled “Site Work (Non-Structural/General Fill) Requirements”.
So, this table only refers to non-structural fills in site work areas. The “Stripping Depth” item in Table 23 should read “Strip away existing asphalt, concrete, soil, deleterious and soft/wet materials. Provide at least 4 inches deep of clearing and grubbing to removal all roots.”
Unless stated otherwise, all other previous recommendations provided in our Geotechnical Engineering Study Report and previous recommendations in Supplements 1, 2 and 3, that are not specifically addressed in this Letter should be followed. Please feel free to call with questions or comments.
Please contact us with any questions or if additional information is needed.
Sincerely, Arias, Inc.
TBPE Registration No: F-32
Jerry D. Shepherd, P.E., D.GE Mark J. O’Connor, P.E.
Senior Geotechnical Engineer Senior Geotechnical Engineer
W9126G21R0034-0005
File details come from the government source that posted it. Updated .