This document is a design alert from the Healthcare Engineering Facilities Program (HEFP) Special Engineering Projects (SEP) team, providing detailed telecommunications system submission requirements for Veteran Affairs (VA) Minor and Non-Recurring Maintenance (NRM) Construction Program projects.

The document outlines the required narrative elements and drawings to be included at various design stages (10% Schematic Design, 35% Design Development, 65% Construction Documents, and 95% Construction Documents) for telecommunications systems. Key requirements include a XMATRIX summary table, existing conditions, assumptions, media types, design descriptions, load levels, CFD analysis, campus pathways, telecommunications space layouts, cabling schedules, riser diagrams, and equipment submittals. This guidance is intended to be incorporated into new Architect/Engineer (A/E) scopes of work and provided to current A/E firms to address the lack of detailed telecommunications requirements in the existing PG-18-15 Volume C guidance.

View the file

Other files

File Type Posted
03-HJ OUTPATIENT - LVL.7 & 8-03.HJ.7-8.pdf PDF
01-BC INPATIENT - LVL.4-01.BC.4.pdf PDF
INTERSTITIAL LEVEL 4i AREA E1-Model.pdf PDF
00-A CONCOURSE - LVL.2-00.AX-2 L.S..pdf PDF
09.Q.pdf PDF
THIRD FLOOR.pdf PDF
03-HJ OUTPATIENT - LVL.1-03.HJ.1.pdf PDF
01-BC INPATIENT - LVL.3-01.BC.3.pdf PDF
RESEARCH -LEVEL 5.5-LIFE SAFETY.pdf PDF
INTERSTITIAL LEVEL 3i AREA D1.1-Model.pdf PDF
06.SUM.pdf PDF
09.SUM.pdf PDF
07.N.SUM.pdf PDF
07-N CEP - LVL.3 & 3.5-07.N.3-3.5.pdf PDF
FOURTH FLOOR-LIFE SAFETY.pdf PDF
INTERSTITIAL LEVEL 3i AREA E1-Model.pdf PDF
01.BC.pdf PDF
INTERSTITIAL LEVEL 2i AREA G2.1-Model.pdf PDF
01-BC INPATIENT - LVL.5-01.5.pdf PDF
INTERSTITIAL LEVEL 3i AREA G1-Model.pdf PDF
06.M.pdf PDF
INTERSTITIAL LEVEL 3i AREA G2-Model.pdf PDF
INTERSTITIAL LEVEL 3i AREA G2.1-Model.pdf PDF
LARGE FIFTH FLOOR.pdf PDF
LARGE SIXTH FLOOR.pdf PDF
AC.0.pdf PDF
SECOND FLOOR -LIFE SAFETY.pdf PDF
SECOND FLOOR.pdf PDF
00-A CONCOURSE - LVL.4-00.AX-4 L.S..pdf PDF
INTERSTITIAL LEVEL 4i AREA G2.1-Model.pdf PDF
INTERSTITIAL LEVEL 2i AREA G2-Model.pdf PDF
01.SUM.pdf PDF
03-HJ OUTPATIENT - LVL.4-03.HJ.4.pdf PDF
09-Q ADMIN - LVL.2, 3, 4, 5 & 6-09.Q.2-6.pdf PDF
INTERSTITIAL LEVEL 2i AREA F1-Model.pdf PDF
FOURTH FLOOR.pdf PDF
FIRST FLOOR.pdf PDF
04-K STAFF PARKING - LVL.7-04.K.7 L.S..pdf PDF
01-BC INPATIENT - LVL.6-01.BC.6.pdf PDF
LEVEL 3.5-LIFE SAFETY.pdf PDF
INTERSTITIAL LEVEL 3i AREA D1-Model.pdf PDF
05.L.pdf PDF
INTERSTITIAL LEVEL 3i AREA D2.1-Model.pdf PDF
INTERSTITIAL LEVEL 3i AREA E2-Model.pdf PDF
05.SUM.pdf PDF
LARGE FOURTH FLOOR.pdf PDF
06-M TRANSITIONAL - LVL.3 & 4-06.M.3-4 (1).pdf PDF
00-A CONCOURSE - LVL.4I-00.AX-4I L.S..pdf PDF
09-Q ADMIN -.BASEMENT.pdf PDF
06-M TRANSITIONAL - LVL.1 & 2-06.M.1-2 (1).pdf PDF
Show 40 more

Latest 50 of 193 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

HEFP SEP/02May2023

PG 18-15 Volume C, AE Submission Instructions for Minor and NRM Construction Program A/E Submission Instructions - Minor and NRM (va.gov) does not provide detailed requirements for telecommunication system submissions. As a result, HEFP SEP receives incomplete design packages. - Incomplete design packages are often rejected which result in significant schedule delays.

PG-18-15, Volume C was updated in November 2008 when telecommunications systems were not as complex and robust; therefore, it does not include detailed requirements for telecommunications system submissions. Due to the unique elements that must be addressed in the EHRM designs, HEFP SEP developed detailed telecommunication system submission requirements.

Include the below document in new AE Scopes of Work and/or distribute to AE firms that are currently in design. This document is limited to HEFP-SEP EHRM NRM projects. This document does not supersede PG-18-15 Volume C or other associated attachments to the A/E’s awarded Scope of Work.

Solution

HEFP SEP (SOCAMES 6) Design Alert 12 Design

Problem

Background https://www.cfm.va.gov/til/ae/aesubmin.pdf https://www.cfm.va.gov/til/ae/aesubmin.pdf

HEFP SEP/02May2023

Telecommunications: 10% SD (35%) DD (65%) CD (95%)

Narrative Elements:

XMATRIX Summary Table (From HEFP-SEP Site Self-Assessment) X X X X

Existing Conditions X X X X

Assumptions X X X X

Media Types (copper cabling, fiber (inside plant and outside plant if applicable) X X X X

Design Description X X X

At-Commissioning Load Levels X X

Ultimate Design Load Levels X X

Computational Fluid Dynamics (CFD) analysis X X

Drawings showing:

Diamond analysis for horizontal distribution X X X X

Campus telecommunications pathways X X X

Telecommunications space locations X X X

Templated Layouts for 1, 2, 3, 4 rack TRs (aligned to ISTS) X X X

Internal telecommunications pathways between Entrance Rooms, MCR, and TRs X X

Telecommunications space layouts & outfitting (equipment & electrical/HVAC locations, clearances, etc.) X X

Telecommunications space elevation drawings (equipment, deconfliction of services, etc.) X X

Space & enclosure bonding details X X

Cable media schedules (type, quantity, length, termination points, termination type, etc.) X X

Structured cabling maps X X

Riser diagrams X X

Telecommunications equipment details X X

Enclosure elevations X

Cable labeling matrices for cable plant and patch cord media X

Equipment submittals:

IT equipment enclosures X

Fiber & UTP patch panels X

Cable media X

Cable media conveyances X

Power distribution equipment supporting telecommunications spaces (Rack UPS systems, Data

Center UPS, busways, Zone PDUs, Rack PDUs, etc.) X

Heat rejection equipment supporting telecommunications spaces (CRACs, mini -split air conditioners, etc.) X

Accessories for the above equipment necessary to complete the design X