Appendix A - Mechanical Drawing Set (FOUO).pdf
PDF 22 MB Posted
- Attached to
- Condenser Water Filtration System Upgrade Federal contract opportunity
- Solicitation number
- HC102821R0018
- Issued by
- Defense Information Systems Agency
About this file
This request for proposal concerns upgrading the condenser water filtration, controls and piping system at a Defense Information Systems Agency facility in San Antonio, Texas. The contractor will enhance the cooling towers, replace piping, adjust the water pump, run temporary chillers for redundancy testing and adjust the water filtration controls. This capital equipment project focuses on the IT mechanical system separately from the building mechanical system. A site visit is scheduled for March 31, 2021 with two sessions for contractors to better understand the work location and conditions. Questions are due by April 9, 2021. The goal is to improve reliability, energy use and redundancy to meet Department of Defense standards for the condenser water system.
View the file
Other files for this federal contract opportunity
Show all 50
Condenser Water Filtration System Upgrade has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
44 35
El Paso
Amarillo
Lubbock
Abilene
Dallas
Waco
Austin
San Antonio
Houston
LOCATION MAP
PROJECT
LOCATION
Laredo
N.T.S.
PROJECT LOCATION
CLARENCE TINKER DRIVE
GENERAL HUDNELL DRIVE
DEFENSE INFORMATION SYSTEMS AGENCY
CONDENSER WATER FILTRATION AND UPGRADES
DATA CENTER SAN ANTONIO (BLDG 200)
COVER SHEET
SHEET
IDENTIFICATION
D
ES
IG
N
B Y:
D R
AW
N
B Y:
SU
BM
IT
TE
D B
Y:
PL
O
T
SC
AL
E:
SI
ZE
AN
SI
D
C H
EC
KE
D B
Y:
PL
O
T D
AT
E:
FI
LE
N
AM
E:
SU
BM
IT
TA
L D
AT
E:
SO
LI
C
IT
AT
IO
N N
O
C O
N
TR
AC
T
N O
FI
LE
N U
M
BE
R
M
AR
K D
ES
C
R
IP
TI
O
N D
AT
E:
AP
PR
:M
AR
K D
ES
C
R
IP
TI
O
N D
AT
E:
AP
PR
B
C
D
1 2 3 4 5
1 2 3 4 5
Defense Information Systems Agency A Combat Support Agency
A
B
D
C
P.
O
.B O
X
G
R
EE
N W
O O
D V
IL
LA
G E
SE
L
F
AC
IL
IT
IE
S
EN
G
IN
EE
R
IN
G
C O
.8
* FOR OFFICIAL USE ONLY *
* FOR OFFICIAL USE ONLY *
A D
ES
IG
N
R M
F
AK
S
N /A
AS
S
H O
W N
JE
S
1/
/2
G -0
N /A
N /A
N /A
1/
/2
G-001
D
AT
A C
EN
TE
R S
AN
A
N
TO
N
IO
C O
N D
EN
SE
R W
AT
ER
F
IL
TR
AT
IO
N
A N
D U
PG
R
AD
ES
C O
VE
R
S H
EE
T
G
EN
ER
AL
SHEET
IDENTIFICATION
D
ES
IG
N
B Y:
D R
AW
N
B Y:
SU
BM
IT
TE
D B
Y:
PL
O
T
SC
AL
E:
SI
ZE
AN
SI
D
C H
EC
KE
D B
Y:
PL
O
T D
AT
E:
FI
LE
N
AM
E:
SU
BM
IT
TA
L D
AT
E:
SO
LI
C
IT
AT
IO
N N
O
C O
N
TR
AC
T
N O
FI
LE
N U
M
BE
R
M
AR
K D
ES
C
R
IP
TI
O
N D
AT
E:
AP
PR
M
AR
K
D
ES
C R
IP
TI
O N
D
AT
E:
AP
PR
B
C
D
1 2 3 4 5
1 2 3 4 5
Defense Information Systems Agency A Combat Support Agency
A
B
D
C
P.
O
.B O
X
G
R
EE
N W
O O
D V
IL
LA
G E
SE
L
F
AC
IL
IT
IE
S
EN
G
IN
EE
R
IN
G
C O
.8
234567 14 13 12 11 10 9 8
* FOR OFFICIAL USE ONLY *
* FOR OFFICIAL USE ONLY *
A
LG-001
C O
N D
EN
SE
R W
AT
ER
F
IL
TR
AT
IO
N
A N
D U
PG
R
AD
ES
D
AT
A C
EN
TE
R S
AN
A
N
TO
N
IO
LE
G
EN
D
M
EC
H
AN
IC
AL
D
ES
IG
N
N /A
AK
S
N /A
AS
S
H O
W N
JE
S
1/
/2
LG
-0
.D
W G
N /A
N /A
N /A
1/
/2
LEGEND
SYMBOLS ABBREVIATIONS
A
AFF
AH
AHU
AS
BFP
BTU
CFM
CH
CHEM
CHWR
CHWS
COMS
CRAH
CRU
CT
CW
CWP
CWR
CWS
D
DCWR
DCWS
DISA
EAT
EF
ELEC
ESP
EWT
FC
FO
FOR
FOS
FOV
FPV
FR
FS
FT
FW
GAL
GPH
GPM
HB
HC
HD
HP
HR
HUM
HW
HWR
HWS
HX
HZ
IN
KW
LAT
LB
LPC
LPS
LWT
MBH
MFR
NA
NG
NO.
P
PD
PH
PL
PSIG
QTY
RECIRC
RF
RHC
RPM
TEL
TYP
UH
UPS
V
VAV
VC
VF
AMPERES
ABOVE FINISHED FLOOR
AIR HANDLER
AIR HANDLER UNIT
AIR SEPARATOR
BACK FLOW PREVENTER
BRITISH THERMAL UNIT
CUBIC FEET PER MINUTE
CHILLER
CHEMICAL
CHILLED WATER RETURN
CHILLED WATER SUPPLY
COMMUNICATIONS
COMPUTER ROOM AIR HANDLER
COMPUTER ROOM UNIT
COOLING TOWER
COLD WATER (DOMESTIC)
CONDENSER WATER PUMP
CONDENSER WATER RETURN
CONDENSER WATER SUPPLY
DRAIN
DIESEL COOLING WATER RETURN
DIESEL COOLING WATER SUPPLY
DEFENSE INFORMATION SYSTEMS AGENCY
ENTERING AIR TEMPERATURE
EXHAUST FAN
ELECTRICAL
EXTERNAL STATIC PRESSURE
ENTERING WATER TEMPERATURE
FAN COIL
FUEL OIL
FUEL OIL RETURN
FUEL OIL SUPPLY
FUEL OIL VENT
FAN POWERED VAV
FLOOR RADIATOR (BASEBOARD)
FLOW SWITCH
FEET
FEED WATER
GALLONS
GALLONS PER HOUR
GALLONS PER MINUTE
HOSE BIB
HEATING COIL
HEAD
HORSE POWER
HOUR
HUMIDIFIER
HOT WATER
HOT WATER RETURN
HOT WATER SUPPLY
HEAT EXCHANGER
HERTZ
INCHES
KILOWATT
LEAVING AIR TEMPERATURE
POUNDS
LOW PRESSURE CONDENSATE
LOW PRESSURE STEAM
LEAVING WATER TEMPERATURE
MEGA BTU
MANUFACTURER
NOT AVAILABLE
NATURAL GAS
NUMBER
PUMP
PRESSURE DROP
PHASE
PLACES
POUNDS PER SQUARE INCH GAUGE
QUANTITY
RECIRCULATING
RETURN FAN
REHEAT COIL
REVOLUTIONS PER MINUTE
TELEPHONE
TYPICAL
UNIT HEATER
UNINTERRUPTIBLE POWER SUPPLY
VOLTS
VARIABLE AIR VOLUME
VACUUM
VENTILATING FAN
T
S
FS
TS
B4
A B
A X B
X
LS
DPS
AP
PS
F
AV
TS
AS
VAV
FS
P
FD
PIPE TEE SIDE OUTLET FACING
TOWARD
PIPE TEE STRAIGHT SIZE
M
M
UNIT HEATER
UH
TEMPERATURE CONTROL VALVE
GATE MOTORIZED VALVE
GLOBE MOTORIZED VALVE
IN-LINE PUMP
PUMP
FILTER (CHANGEABLE ELEMENT)
LEVEL SWITCH
PRESSURE SWITCH
TRIPLE DUTY (SERVICE) VALVE
AIR PURGER
SUPPLY AIR
RETURN AND EXHAUST AIR
SUPPLY AIR DIFFUSER
(WITH END OF LINE CAP)
RETURN AIR DIFFUSER
(WITH END OF LINE CAP)
A X B DUCTWORK
A X B DUCTWORK
VARIABLE AIR VOLUME BOX
MANUAL DAMPER
FLEXIBLE DUCT
FLOW SENSOR
TEMPERATURE SENSOR
FLEXIBLE HOSE
DIFFERENTIAL PRESSURE SWITCH
TEMPERATURE SWITCH
PIPE CHASE OR LOCATOR WITH
COLUMN GRID INDICATOR
COLUMN DESIGNATOR
SOLENOID VALVE
ELBOW FACING AWAY
ELBOW FACING TOWARD
PIPE TEE SINGLE SWEEP
BOILER
DOUBLE BRANCH ELBOW
90° ELBOW
45° ELBOW
HAND WHEEL STEM VALVE
STRAINER
FLOOR DRAIN
REDUCER
TEST CONNECTION
BUTTERFLY VALVE
RELIEF VALVE
ANGLE DRAIN VALVE WITH
HOSE CONNECTION
PRESSURE REDUCING VALVE
BALL VALVE
DRAIN VALVE WITH HOSE
CONNECTION
PIPE CAP
FLANGE CAP
FLOW SWITCH
UNIDENTIFIED VALVE
CIRCUIT SETTER
AIR SEPARATOR
TEMPERATURE GAUGE
PRESSURE GAUGE
AUTOMATIC VENT VALVE
GLOBE VALVE
GATE VALVE
FLANGE
BACKFLOW PREVENTER
CHECK VALVE
UNION
3-WAY TEMPERATURE REGULATING
VALVE
M
M
AUTOMATIC MOTORIZED 12"
BUTTERFLY VALVE
12" TEE, ELEVATION DROP
AUTOMATIC MOTORIZED
BALANCING VALVE
SHEET LIST TABLE
SHEET NUMBER SHEET TITLE
GENERAL
G-001 COVER SHEET
LG-001 LEGEND
MECHANICAL
MD-100 REMOVAL SUCTION PIPING
MD-101 REMOVAL DISCHARGE PIPING
MD-103 DEMO 3D COOLING TOWER PIPING - INSIDE
MD-104 DEMO 3D COOLING TOWER PIPING - OUTSIDE
MD-105 DEMO 3D COOLING TOWER 2 PIPING - OUTSIDE
M-100 NEW SUCTION PIPING
M-101 NEW DISCHARGE PIPING
M-103 NEW 3D COOLING TOWER PIPING - OUTSIDE
M-104 NEW 3D COOLING TOWER 1 ISO VIEW
M-105 NEW 3D COOLING TOWER 2 ISO VIEW
M-106 NEW PUMP - PIPING - INSIDE
M-107 NEW PUMP - INSIDE
ELEVATIONS
EL-200 TOP VIEW - INSIDE AND OUTSIDE
EL-201 BACK & SIDE - OUTSIDE
EL-202 BACK & INSIDE - NEW PUMP
EL-203 TOP VIEW - DISCHARGE
EL-204 TOP VIEW - SUCTION
DETAILS
M-500 DETAIL SHEET - APPENDIX A
CONNECT TO EXISTING
EQUALIZER LINE
IDENTIFICATION
D
ES
IG
N
B Y:
D R
AW
N
B Y:
SU
BM
IT
TE
D B
Y:
PL
O
T
SC
AL
E:
SI
ZE
AN
SI
D
C H
EC
KE
D B
Y:
PL
O
T D
AT
E:
FI
LE
N
AM
E:
SU
BM
IT
TA
L D
AT
E:
SO
LI
C
IT
AT
IO
N N
O
C O
N
TR
AC
T
N O
FI
LE
N U
M
BE
R
M
AR
K D
ES
C
R
IP
TI
O
N D
AT
E:
AP
PR
M
AR
K
D
ES
C R
IP
TI
O N
D
AT
E:
AP
PR
B
C
D
1 2 3 4 5
1 2 3 4 5
Defense Information Systems Agency A Combat Support Agency
A
B
D
C
P.
O
.B O
X
G
R
EE
N W
O O
D V
IL
LA
G E
SE
L
F
AC
IL
IT
IE
S
EN
G
IN
EE
R
IN
G
C O
.8
234567 14 13 12 11 10 9 8
* FOR OFFICIAL USE ONLY *
* FOR OFFICIAL USE ONLY *
A
MD-100
C O
N D
EN
SE
R W
AT
ER
F
IL
TR
AT
IO
N
A N
D U
PG
R
AD
ES
D
AT
A C
EN
TE
R S
AN
A
N
TO
N
IO
R
EM
O
VA
L
SU
C
TI
O N
P
IP
IN
G
M
EC
H
AN
IC
AL
D
ES
IG
N
R M
F
AK
S
N /A
AS
S
H O
W N
JE
S
1/
/2
M D
-1
.D W
G
N /A
N /A
N /A
1/
/2
REMOVAL SUCTION PIPING - APPENDIX A
SCALE : 1/4" = 1'-0"
N
PLAN
REFERENCE
NORTH
A B
C D
KEY PLAN
SCALE: NONE
0 2' 4' 8'
1. ALL DASHED SECTIONS SHALL BE REMOVED .
2. EXISTING VALVE (BETWEEN BUILDING EXTERIOR AND BASKET
STRAINER) SHALL BE EITHER REUSED OR REPLACED.
3. EXISTING BASKET STRAINERS SHALL BE EITHER REUSED OR
REPLACED.
4. EXISTING EQUALIZER PIPE TO REMAIN BETWEEN COOLING
TOWERS 1 AND 2.
KEYNOTES
GENERAL NOTES
1. CONTRACTOR SHALL PROVIDE DETAILED INSTALLATION SHOP DRAWINGS
FOR ALL NEW INSTALLED PIPE AND EQUIPMENT. SHOP DRAWING SHALL
BE REVIEWED AND APPROVED BY THE GOVERNMENT PRIOR TO
ORDERING PARTS AND EQUIPMENT, IF THE CONTRACTOR WOULD LIKE
TO DEVIATE FROM THIS DRAWING SET, COR APPROVAL MUST BE
REQUESTED AND APPROVED. ANY DEVIATION MAY REQUIRE THAT THE
NEW DEVIATION DRAWING BE STAMPED BY A PROFESSIONAL ENGINEER
IN ORDER TO OBTAIN COR APPROVAL.
2. CONTRACTOR SHALL PROVIDE REDUNDANT TEMPORARY CHILLERS,
PUMPS, PIPING, AND CONDUCTORS TO SUPPLY UNINTERRUPTED
CHILLED WATER TO THE MAIN MECHANICAL PLANT FOR THE ENTIRE
PROJECT. CONTRACTOR SHALL PROVIDE A PLAN FOR ACCOMPLISHING
THIS FOR REVIEW AND APPROVAL BY THE COR 14 DAYS PRIOR TO
ORDERING RENTAL EQUIPMENT OR CUTTING ANY PIPE.
3. ALL CONDENSER WATER PIPE INSTALLED SHALL BE BLACK STEEL PIPE
MEETING ASTM A53, GRADE B, TYPE E. FITTINGS SHALL MEET ANSI B16.9.
4. CONTRACTOR SHALL INSTALL THE CONDENSER WATER PIPING WITH
WELDED SEAMLESS JOINTS WHENEVER POSSIBLE. AT MINIMUM 90% OF
ALL INSTALLED JOINTS SHALL BE WELDED SEAMLESS.
5. CONTRACTOR SHALL PROVIDE ADEQUATE SUPPORTS FOR ALL
INSTALLED PIPE AND COMPONENTS. SUPPORTS SHALL MEET THE
MANUFACTURERS' AND INDUSTRY STANDARD FOR PIPE SUPPORTING.
6. CONTRACTOR SHALL PROVIDE AND INSTALL LONG ELBOWS
WHENEVER POSSIBLE. AT MINIMUM 95% OF ALL INSTALLED ELBOWS
SHALL BE LONG ELBOWS.
7. CONTRACTOR SHALL INSTALL NEW LABELS ON BOTH NEW AND
EXISTING CONDENSER WATER PIPING INSIDE AND OUTSIDE THE
BUILDING PER APPENDIX J.
8. PROVIDE, INSTALL, AND INTEGRATE THE NEW VALVES, SIDE STREAM
FILTERS, PUMPS / MOTORS / VFDS. FAN VFDS, AND SENSORS INTO THE
DELTA AND ICONICS BAS. ALL NEW EQUIPMENT SHALL BE COMPATIBLE
AND CAPABLE OF INTERFACING WITH DELTA CONTROLS AND THE
EXISTING ICONICS PER APPENDIX F.
CT-1 CT-2
CH-1 CWP-1 CWP-2
12"
12"
ST
AI
R S
D O
W N
REMOVE PIPE
REMOVE PIPE
REMOVE PIPE
REMOVE PIPE
EQUALIZER LINE
SHEET
IDENTIFICATION
D
ES
IG
N
B Y:
D R
AW
N
B Y:
SU
BM
IT
TE
D B
Y:
PL
O
T
SC
AL
E:
SI
ZE
AN
SI
D
C H
EC
KE
D B
Y:
PL
O
T D
AT
E:
FI
LE
N
AM
E:
SU
BM
IT
TA
L D
AT
E:
SO
LI
C
IT
AT
IO
N N
O
C O
N
TR
AC
T
N O
FI
LE
N U
M
BE
R
M
AR
K D
ES
C
R
IP
TI
O
N D
AT
E:
AP
PR
M
AR
K
D
ES
C R
IP
TI
O N
D
AT
E:
AP
PR
B
C
D
1 2 3 4 5
1 2 3 4 5
Defense Information Systems Agency A Combat Support Agency
A
B
D
C
P.
O
.B O
X
G
R
EE
N W
O O
D V
IL
LA
G E
SE
L
F
AC
IL
IT
IE
S
EN
G
IN
EE
R
IN
G
C O
.8
234567 14 13 12 11 10 9 8
* FOR OFFICIAL USE ONLY *
* FOR OFFICIAL USE ONLY *
A
MD-101
C O
N D
EN
SE
R W
AT
ER
F
IL
TR
AT
IO
N
A N
D U
PG
R
AD
ES
D
AT
A C
EN
TE
R S
AN
A
N
TO
N
IO
R
EM
O
VA
L D
IS
C
H
AR
G E
PI
PI
N G
M
EC
H
AN
IC
AL
D
ES
IG
N
R M
F
AK
S
N /A
AS
S
H O
W N
JE
S
1/
/2
M D
-1
.D W
G
N /A
N /A
N /A
1/
/2
REMOVAL DISCHARGE PIPING- APPENDIX A
SCALE : 1/4" = 1'-0"
N
PLAN
REFERENCE
NORTH
A B
C D
KEY PLAN
SCALE: NONE
0 2' 4' 8'
1. ALL DASHED SECTIONS SHALL BE REMOVED .
2. EXISTING TRIPLE DUTY VALVE SHALL BE EITHER REUSED OR
REPLACED.
3. EXISTING VALVE SHALL BE EITHER REUSED OR REPLACED.
4. EXISTING EQUALIZER PIPE TO REMAIN BETWEEN COOLING
TOWERS 1 AND 2.
KEYNOTES
GENERAL NOTES
1. CONTRACTOR SHALL PROVIDE DETAILED INSTALLATION SHOP DRAWINGS
FOR ALL NEW INSTALLED PIPE AND EQUIPMENT. SHOP DRAWING SHALL
BE REVIEWED AND APPROVED BY THE GOVERNMENT PRIOR TO
ORDERING PARTS AND EQUIPMENT, IF THE CONTRACTOR WOULD LIKE
TO DEVIATE FROM THIS DRAWING SET, COR APPROVAL MUST BE
REQUESTED AND APPROVED. ANY DEVIATION MAY REQUIRE THAT THE
NEW DEVIATION DRAWING BE STAMPED BY A PROFESSIONAL ENGINEER
IN ORDER TO OBTAIN COR APPROVAL.
2. CONTRACTOR SHALL PROVIDE REDUNDANT TEMPORARY CHILLERS,
PUMPS, PIPING, AND CONDUCTORS TO SUPPLY UNINTERRUPTED
CHILLED WATER TO THE MAIN MECHANICAL PLANT FOR THE ENTIRE
PROJECT. CONTRACTOR SHALL PROVIDE A PLAN FOR ACCOMPLISHING
THIS FOR REVIEW AND APPROVAL BY THE COR 14 DAYS PRIOR TO
ORDERING RENTAL EQUIPMENT OR CUTTING ANY PIPE.
3. ALL CONDENSER WATER PIPE INSTALLED SHALL BE BLACK STEEL PIPE
MEETING ASTM A53, GRADE B, TYPE E. FITTINGS SHALL MEET ANSI B16.9.
4. CONTRACTOR SHALL INSTALL THE CONDENSER WATER PIPING WITH
WELDED SEAMLESS JOINTS WHENEVER POSSIBLE. AT MINIMUM 90% OF
ALL INSTALLED JOINTS SHALL BE WELDED SEAMLESS.
5. CONTRACTOR SHALL PROVIDE ADEQUATE SUPPORTS FOR ALL
INSTALLED PIPE AND COMPONENTS. SUPPORTS SHALL MEET THE
MANUFACTURERS' AND INDUSTRY STANDARD FOR PIPE SUPPORTING.
6. CONTRACTOR SHALL PROVIDE AND INSTALL LONG ELBOWS
WHENEVER POSSIBLE. AT MINIMUM 95% OF ALL INSTALLED ELBOWS
SHALL BE LONG ELBOWS.
7. CONTRACTOR SHALL INSTALL NEW LABELS ON BOTH NEW AND
EXISTING CONDENSER WATER PIPING INSIDE AND OUTSIDE THE
BUILDING PER APPENDIX J.
8. PROVIDE, INSTALL, AND INTEGRATE THE NEW VALVES, SIDE STREAM
FILTERS, PUMPS / MOTORS / VFDS. FAN VFDS, AND SENSORS INTO THE
DELTA AND ICONICS BAS. ALL NEW EQUIPMENT SHALL BE COMPATIBLE
AND CAPABLE OF INTERFACING WITH DELTA CONTROLS AND THE
EXISTING ICONICS PER APPENDIX F.
2 3
DEMO 3D COOLING TOWER PIPING - INSIDE
IDENTIFICATION
D
ES
IG
N
B Y:
D R
AW
N
B Y:
SU
BM
IT
TE
D B
Y:
PL
O
T
SC
AL
E:
SI
ZE
AN
SI
D
C H
EC
KE
D B
Y:
PL
O
T D
AT
E:
FI
LE
N
AM
E:
SU
BM
IT
TA
L D
AT
E:
SO
LI
C
IT
AT
IO
N N
O
C O
N
TR
AC
T
N O
FI
LE
N U
M
BE
R
M
AR
K D
ES
C
R
IP
TI
O
N D
AT
E:
AP
PR
M
AR
K
D
ES
C R
IP
TI
O N
D
AT
E:
AP
PR
B
C
D
1 2 3 4 5
1 2 3 4 5
Defense Information Systems Agency A Combat Support Agency
A
B
D
C
P.
O
.B O
X
G
R
EE
N W
O O
D V
IL
LA
G E
SE
L
F
AC
IL
IT
IE
S
EN
G
IN
EE
R
IN
G
C O
.8
* FOR OFFICIAL USE ONLY *
* FOR OFFICIAL USE ONLY *
A
R M
F
KL
K
AS
S
H O
W N
JE
S
1/
/2
C O
O
LI
N G
T O
W
ER
P
IP
IN
G
EX
IS
TI
N G
1/
/2
MD-103
C O
N D
EN
SE
R W
AT
ER
F
IL
TR
AT
IO
N
A N
D U
PG
R
AD
ES
D
AT
A C
EN
TE
R S
AN
A
N
TO
N
IO
D
EM
O
D C
O O
LI
N
G T
O W
ER
P
IP
IN
G
IN
SI
D E
M
EC
H
AN
IC
AL
3D D
ES
IG
N
0 1' 2' 4'SCALE : 1/2" = 1'-0"
KEY NOTES
1. EXISTING TRIPLE DUTY VALVES SHALL BE EITHER REUSED OR REPLACED.
2. EXISTING VALVE SHALL BE EITHER REUSED OR REPLACED.
GENERAL NOTES
1. CONTRACTOR SHALL PROVIDE DETAILED INSTALLATION SHOP DRAWINGS FOR ALL
NEW INSTALLED PIPE AND EQUIPMENT. SHOP DRAWING SHALL BE REVIEWED AND
APPROVED BY THE GOVERNMENT PRIOR TO ORDERING PARTS AND EQUIPMENT, IF
THE CONTRACTOR WOULD LIKE TO DEVIATE FROM THIS DRAWING SET, COR
APPROVAL MUST BE REQUESTED AND APPROVED. ANY DEVIATION MAY REQUIRE
THAT THE NEW DEVIATION DRAWING BE STAMPED BY A PROFESSIONAL ENGINEER
IN ORDER TO OBTAIN COR APPROVAL.
2. CONTRACTOR SHALL PROVIDE REDUNDANT TEMPORARY CHILLERS, PUMPS,
PIPING, AND CONDUCTORS TO SUPPLY UNINTERRUPTED CHILLED WATER TO THE
MAIN MECHANICAL PLANT FOR THE ENTIRE PROJECT. CONTRACTOR SHALL
PROVIDE A PLAN FOR ACCOMPLISHING THIS FOR REVIEW AND APPROVAL BY THE
COR 14 DAYS PRIOR TO ORDERING RENTAL EQUIPMENT OR CUTTING ANY PIPE.
3. ALL CONDENSER WATER PIPE INSTALLED SHALL BE BLACK STEEL PIPE MEETING
ASTM A53, GRADE B, TYPE E. FITTINGS SHALL MEET ANSI B16.9.
4. CONTRACTOR SHALL INSTALL THE CONDENSER WATER PIPING WITH WELDED
SEAMLESS JOINTS WHENEVER POSSIBLE. AT MINIMUM 90% OF ALL INSTALLED
JOINTS SHALL BE WELDED SEAMLESS.
5. CONTRACTOR SHALL PROVIDE ADEQUATE SUPPORTS FOR ALL INSTALLED PIPE
AND COMPONENTS. SUPPORTS SHALL MEET THE MANUFACTURERS' AND
INDUSTRY STANDARD FOR PIPE SUPPORTING.
6. CONTRACTOR SHALL PROVIDE AND INSTALL LONG ELBOWS WHENEVER POSSIBLE.
AT MINIMUM 95% OF ALL INSTALLED ELBOWS SHALL BE LONG ELBOWS.
7. CONTRACTOR SHALL INSTALL NEW LABELS ON BOTH NEW AND EXISTING
CONDENSER WATER PIPING INSIDE AND OUTSIDE THE BUILDING PER APPENDIX J.
8. PROVIDE, INSTALL, AND INTEGRATE THE NEW VALVES, SIDE STREAM FILTERS,
PUMPS / MOTORS / VFDS. FAN VFDS, AND SENSORS INTO THE DELTA AND ICONICS
BAS. ALL NEW EQUIPMENT SHALL BE COMPATIBLE AND CAPABLE OF INTERFACING
WITH DELTA CONTROLS AND THE EXISTING ICONICS PER APPENDIX F.
CWP-2
CWP-2
DEMO 3D COOLING TOWER PIPING - OUTSIDE
IDENTIFICATION
D
ES
IG
N
B Y:
D R
AW
N
B Y:
SU
BM
IT
TE
D B
Y:
PL
O
T
SC
AL
E:
SI
ZE
AN
SI
D
C H
EC
KE
D B
Y:
PL
O
T D
AT
E:
FI
LE
N
AM
E:
SU
BM
IT
TA
L D
AT
E:
SO
LI
C
IT
AT
IO
N N
O
C O
N
TR
AC
T
N O
FI
LE
N U
M
BE
R
M
AR
K D
ES
C
R
IP
TI
O
N D
AT
E:
AP
PR
M
AR
K
D
ES
C R
IP
TI
O N
D
AT
E:
AP
PR
B
C
D
1 2 3 4 5
1 2 3 4 5
Defense Information Systems Agency A Combat Support Agency
A
B
D
C
P.
O
.B O
X
G
R
EE
N W
O O
D V
IL
LA
G E
SE
L
F
AC
IL
IT
IE
S
EN
G
IN
EE
R
IN
G
C O
.8
* FOR OFFICIAL USE ONLY *
* FOR OFFICIAL USE ONLY *
A
R M
N
KL
K
AS
S
H O
W N
JE
S
1/
/2
C O
O
LI
N G
T O
W
ER
P
IP
IN
G
EX
IS
TI
N G
1/
/2
MD-104
C O
N D
EN
SE
R W
AT
ER
F
IL
TR
AT
IO
N
A N
D U
PG
R
AD
ES
D
AT
A C
EN
TE
R S
AN
A
N
TO
N
IO
D
EM
O
D C
O O
LI
N
G T
O W
ER
P
IP
IN
G
O U
TS
ID
E M
EC
H
AN
IC
AL
3D
D
ES
IG
N
0 1' 2' 4'SCALE : 1/2" = 1'-0"
KEY NOTES
1. EXISTING VALVE (BETWEEN THE BUILDING EXTERIOR AND THE BASKET
STRAINER) SHALL BE EITHER REUSED OR REPLACED.
2. EXISTING BASKET STRAINERS SHALL BE EITHER REUSED OR REPLACED.
3. EXISTING EQUALIZER PIPE TO REMAIN BETWEEN COOLING TOWERS 1 AND 2.
GENERAL NOTES
1. CONTRACTOR SHALL PROVIDE DETAILED INSTALLATION SHOP DRAWINGS FOR ALL
NEW INSTALLED PIPE AND EQUIPMENT. SHOP DRAWING SHALL BE REVIEWED AND
APPROVED BY THE GOVERNMENT PRIOR TO ORDERING PARTS AND EQUIPMENT, IF
THE CONTRACTOR WOULD LIKE TO DEVIATE FROM THIS DRAWING SET, COR
APPROVAL MUST BE REQUESTED AND APPROVED. ANY DEVIATION MAY REQUIRE
THAT THE NEW DEVIATION DRAWING BE STAMPED BY A PROFESSIONAL ENGINEER
IN ORDER TO OBTAIN COR APPROVAL.
2. CONTRACTOR SHALL PROVIDE REDUNDANT TEMPORARY CHILLERS, PUMPS,
PIPING, AND CONDUCTORS TO SUPPLY UNINTERRUPTED CHILLED WATER TO THE
MAIN MECHANICAL PLANT FOR THE ENTIRE PROJECT. CONTRACTOR SHALL
PROVIDE A PLAN FOR ACCOMPLISHING THIS FOR REVIEW AND APPROVAL BY THE
COR 14 DAYS PRIOR TO ORDERING RENTAL EQUIPMENT OR CUTTING ANY PIPE.
3. ALL CONDENSER WATER PIPE INSTALLED SHALL BE BLACK STEEL PIPE MEETING
ASTM A53, GRADE B, TYPE E. FITTINGS SHALL MEET ANSI B16.9.
4. CONTRACTOR SHALL INSTALL THE CONDENSER WATER PIPING WITH WELDED
SEAMLESS JOINTS WHENEVER POSSIBLE. AT MINIMUM 90% OF ALL INSTALLED
JOINTS SHALL BE WELDED SEAMLESS.
5. CONTRACTOR SHALL PROVIDE ADEQUATE SUPPORTS FOR ALL INSTALLED PIPE
AND COMPONENTS. SUPPORTS SHALL MEET THE MANUFACTURERS' AND
INDUSTRY STANDARD FOR PIPE SUPPORTING.
6. CONTRACTOR SHALL PROVIDE AND INSTALL LONG ELBOWS WHENEVER POSSIBLE.
AT MINIMUM 95% OF ALL INSTALLED ELBOWS SHALL BE LONG ELBOWS.
7. CONTRACTOR SHALL INSTALL NEW LABELS ON BOTH NEW AND EXISTING
CONDENSER WATER PIPING INSIDE AND OUTSIDE THE BUILDING PER APPENDIX J.
8. PROVIDE, INSTALL, AND INTEGRATE THE NEW VALVES, SIDE STREAM FILTERS,
PUMPS / MOTORS / VFDS. FAN VFDS, AND SENSORS INTO THE DELTA AND ICONICS
BAS. ALL NEW EQUIPMENT SHALL BE COMPATIBLE AND CAPABLE OF INTERFACING
WITH DELTA CONTROLS AND THE EXISTING ICONICS PER APPENDIX F.
CT-1
CT-2
DEMO 3D COOLING TOWER 2 PIPING - OUTSIDE
IDENTIFICATION
D
ES
IG
N
B Y:
D R
AW
N
B Y:
SU
BM
IT
TE
D B
Y:
PL
O
T
SC
AL
E:
SI
ZE
AN
SI
D
C H
EC
KE
D B
Y:
PL
O
T D
AT
E:
FI
LE
N
AM
E:
SU
BM
IT
TA
L D
AT
E:
SO
LI
C
IT
AT
IO
N N
O
C O
N
TR
AC
T
N O
FI
LE
N U
M
BE
R
M
AR
K D
ES
C
R
IP
TI
O
N D
AT
E:
AP
PR
M
AR
K
D
ES
C R
IP
TI
O N
D
AT
E:
AP
PR
B
C
D
1 2 3 4 5
1 2 3 4 5
Defense Information Systems Agency A Combat Support Agency
A
B
D
C
P.
O
.B O
X
G
R
EE
N W
O O
D V
IL
LA
G E
SE
L
F
AC
IL
IT
IE
S
EN
G
IN
EE
R
IN
G
C O
.8
* FOR OFFICIAL USE ONLY *
* FOR OFFICIAL USE ONLY *
A
R M
F
KL
K
AS
S
H O
W N
JE
S
1/
/2
C O
O
LI
N G
T O
W
ER
EX
IS
TI
N
G
1/
/2
MD-105
C O
N D
EN
SE
R W
AT
ER
F
IL
TR
AT
IO
N
A N
D U
PG
R
AD
ES
D
AT
A C
EN
TE
R S
AN
A
N
TO
N
IO
D
EM
O
D C
O O
LI
N
G T
O W
ER
P
IP
IN
G
O
U
TS
ID
E
M
EC
H
AN
IC
AL
3D D
ES
IG
N
0 1' 2' 4'SCALE : 1/2" = 1'-0"
KEY NOTES
1. EXISTING VALVE (BETWEEN THE BUILDING EXTERIOR AND THE BASKET
STRAINER) SHALL BE EITHER REUSED OR REPLACED.
2. EXISTING BASKET STRAINERS SHALL BE EITHER REUSED OR REPLACED.
3. EXISTING EQUALIZER PIPE TO REMAIN BETWEEN COOLING TOWERS 1 AND 2.
GENERAL NOTES
1. CONTRACTOR SHALL PROVIDE DETAILED INSTALLATION SHOP DRAWINGS FOR ALL
NEW INSTALLED PIPE AND EQUIPMENT. SHOP DRAWING SHALL BE REVIEWED AND
APPROVED BY THE GOVERNMENT PRIOR TO ORDERING PARTS AND EQUIPMENT, IF
THE CONTRACTOR WOULD LIKE TO DEVIATE FROM THIS DRAWING SET, COR
APPROVAL MUST BE REQUESTED AND APPROVED. ANY DEVIATION MAY REQUIRE
THAT THE NEW DEVIATION DRAWING BE STAMPED BY A PROFESSIONAL ENGINEER
IN ORDER TO OBTAIN COR APPROVAL.
2. CONTRACTOR SHALL PROVIDE REDUNDANT TEMPORARY CHILLERS, PUMPS,
PIPING, AND CONDUCTORS TO SUPPLY UNINTERRUPTED CHILLED WATER TO THE
MAIN MECHANICAL PLANT FOR THE ENTIRE PROJECT. CONTRACTOR SHALL
PROVIDE A PLAN FOR ACCOMPLISHING THIS FOR REVIEW AND APPROVAL BY THE
COR 14 DAYS PRIOR TO ORDERING RENTAL EQUIPMENT OR CUTTING ANY PIPE.
3. ALL CONDENSER WATER PIPE INSTALLED SHALL BE BLACK STEEL PIPE MEETING
ASTM A53, GRADE B, TYPE E. FITTINGS SHALL MEET ANSI B16.9.
4. CONTRACTOR SHALL INSTALL THE CONDENSER WATER PIPING WITH WELDED
SEAMLESS JOINTS WHENEVER POSSIBLE. AT MINIMUM 90% OF ALL INSTALLED
JOINTS SHALL BE WELDED SEAMLESS.
5. CONTRACTOR SHALL PROVIDE ADEQUATE SUPPORTS FOR ALL INSTALLED PIPE
AND COMPONENTS. SUPPORTS SHALL MEET THE MANUFACTURERS' AND
INDUSTRY STANDARD FOR PIPE SUPPORTING.
6. CONTRACTOR SHALL PROVIDE AND INSTALL LONG ELBOWS WHENEVER POSSIBLE.
AT MINIMUM 95% OF ALL INSTALLED ELBOWS SHALL BE LONG ELBOWS.
7. CONTRACTOR SHALL INSTALL NEW LABELS ON BOTH NEW AND EXISTING
CONDENSER WATER PIPING INSIDE AND OUTSIDE THE BUILDING PER APPENDIX J.
8. PROVIDE, INSTALL, AND INTEGRATE THE NEW VALVES, SIDE STREAM FILTERS,
PUMPS / MOTORS / VFDS. FAN VFDS, AND SENSORS INTO THE DELTA AND ICONICS
BAS. ALL NEW EQUIPMENT SHALL BE COMPATIBLE AND CAPABLE OF INTERFACING
WITH DELTA CONTROLS AND THE EXISTING ICONICS PER APPENDIX F.
CT2
CT2
M M
MM
M
EQUALIZER LINE
SHEET
IDENTIFICATION
D
ES
IG
N
B Y:
D R
AW
N
B Y:
SU
BM
IT
TE
D B
Y:
PL
O
T
SC
AL
E:
SI
ZE
AN
SI
D
C H
EC
KE
D B
Y:
PL
O
T D
AT
E:
FI
LE
N
AM
E:
SU
BM
IT
TA
L D
AT
E:
SO
LI
C
IT
AT
IO
N N
O
C O
N
TR
AC
T
N O
FI
LE
N U
M
BE
R
M
AR
K D
ES
C
R
IP
TI
O
N D
AT
E:
AP
PR
M
AR
K
D
ES
C R
IP
TI
O N
D
AT
E:
AP
PR
B
C
D
1 2 3 4 5
1 2 3 4 5
Defense Information Systems Agency A Combat Support Agency
A
B
D
C
P.
O
.B O
X
G
R
EE
N W
O O
D V
IL
LA
G E
SE
L
F
AC
IL
IT
IE
S
EN
G
IN
EE
R
IN
G
C O
.8
234567 14 13 12 11 10 9 8
* FOR OFFICIAL USE ONLY *
* FOR OFFICIAL USE ONLY *
A
M-100
C O
N D
EN
SE
R W
AT
ER
F
IL
TR
AT
IO
N
A N
D U
PG
R
AD
ES
D
AT
A C
EN
TE
R S
AN
A
N
TO
N
IO
N
EW
S U
C
TI
O N
P
IP
IN
G
M
EC
H
AN
IC
AL
D
ES
IG
N
R M
F
AK
S
N /A
AS
S
H O
W N
JE
S
1/
/2
M -1
.D
W G
N /A
N /A
N /A
1/
/2
0 2' 4' 8'
NEW SUCTION PIPING - APPENDIX A
SCALE : 1/4" = 1'-0"
N
PLAN
REFERENCE
NORTH
A B
C D
KEY PLAN
SCALE: NONE
1. EXISTING VALVE (BETWEEN BUILDING EXTERIOR AND BASKET
STRAINER) SHALL BE EITHER REUSED OR REPLACED.
2. EXISTING BASKET STRAINERS SHALL BE EITHER REUSED OR
REPLACED.
3. PROVIDE NEW CONDENSER WATER ISOLATION VALVES. THESE
ASSEMBLIES SHALL BE MOTORIZED BUTTERFLY VALVES.
PROVIDE VALVES WITH TWO POSITION ACTUATORS WITH END
SWITCH INDICATION, WITH BACK-UP MANUAL OVERRIDE
HANDLES OR GEAR DRIVEN WHEELS, AND WITH POWER THAT
CAN BE FED FROM EITHER 24 VOLTS OR 120 VOLTS.
4. CONTRACTOR SHALL MINIMIZE THE USE OF 8 INCH DIAMETER
PIPING ON THE SUCTION-SIDE. A MAXIMUM OF 8 FEET OF 8 INCH
DIAMETER PIPE SHALL BE PERMITTED PER COOLING TOWER
UNLESS APPROVED BY THE COR.
5. PIPING FOR COOLING TOWER 1 SHALL BE A MIRROR IMAGE OF
THE PIPING FOR COOLING TOWER 2.
6. CONTRACTOR SHALL INSTALL PROTECTIVE ALUMINUM
JACKETING ON ALL EXTERIOR CONDENSER WATER PIPE THAT IS
BOTH NEW AND EXISTING TO INCLUDE THE CONDENSER WATER
BASIN EQUALIZER PIPE.
7. EXISTING EQUALIZER PIPE TO REMAIN BETWEEN COOLING
TOWERS 1 AND 2.
KEYNOTES
GENERAL NOTES
1. CONTRACTOR SHALL PROVIDE DETAILED INSTALLATION SHOP DRAWINGS
FOR ALL NEW INSTALLED PIPE AND EQUIPMENT. SHOP DRAWING SHALL
BE REVIEWED AND APPROVED BY THE GOVERNMENT PRIOR TO
ORDERING PARTS AND EQUIPMENT, IF THE CONTRACTOR WOULD LIKE
TO DEVIATE FROM THIS DRAWING SET, COR APPROVAL MUST BE
REQUESTED AND APPROVED. ANY DEVIATION MAY REQUIRE THAT THE
NEW DEVIATION DRAWING BE STAMPED BY A PROFESSIONAL ENGINEER
IN ORDER TO OBTAIN COR APPROVAL.
2. CONTRACTOR SHALL PROVIDE REDUNDANT TEMPORARY CHILLERS,
PUMPS, PIPING, AND CONDUCTORS TO SUPPLY UNINTERRUPTED
CHILLED WATER TO THE MAIN MECHANICAL PLANT FOR THE ENTIRE
PROJECT. CONTRACTOR SHALL PROVIDE A PLAN FOR ACCOMPLISHING
THIS FOR REVIEW AND APPROVAL BY THE COR 14 DAYS PRIOR TO
ORDERING RENTAL EQUIPMENT OR CUTTING ANY PIPE.
3. ALL CONDENSER WATER PIPE INSTALLED SHALL BE BLACK STEEL PIPE
MEETING ASTM A53, GRADE B, TYPE E. FITTINGS SHALL MEET ANSI B16.9.
4. CONTRACTOR SHALL INSTALL THE CONDENSER WATER PIPING WITH
WELDED SEAMLESS JOINTS WHENEVER POSSIBLE. AT MINIMUM 90% OF
ALL INSTALLED JOINTS SHALL BE WELDED SEAMLESS.
5. CONTRACTOR SHALL PROVIDE ADEQUATE SUPPORTS FOR ALL
INSTALLED PIPE AND COMPONENTS. SUPPORTS SHALL MEET THE
MANUFACTURERS' AND INDUSTRY STANDARD FOR PIPE SUPPORTING.
6. CONTRACTOR SHALL PROVIDE AND INSTALL LONG ELBOWS
WHENEVER POSSIBLE. AT MINIMUM 95% OF ALL INSTALLED ELBOWS
SHALL BE LONG ELBOWS.
7. CONTRACTOR SHALL INSTALL NEW LABELS ON BOTH NEW AND
EXISTING CONDENSER WATER PIPING INSIDE AND OUTSIDE THE
BUILDING PER APPENDIX J.
8. PROVIDE, INSTALL, AND INTEGRATE THE NEW VALVES, SIDE STREAM
FILTERS, PUMPS / MOTORS / VFDS. FAN VFDS, AND SENSORS INTO THE
DELTA AND ICONICS BAS. ALL NEW EQUIPMENT SHALL BE COMPATIBLE
AND CAPABLE OF INTERFACING WITH DELTA CONTROLS AND THE
EXISTING ICONICS PER APPENDIX F.
COOLING TOWER
FOUNDATION
ABOVE GROUND
ST
AI
R S
D O
W N
M M
MM
M MM
NEW PIPE
BEGINS
NEW PIPE
BEGINS
NEW PIPE
BEGINS
NEW PIPE
BEGINS
EQUALIZER LINE
SHEET
IDENTIFICATION
D
ES
IG
N
B Y:
D R
AW
N
B Y:
SU
BM
IT
TE
D B
Y:
PL
O
T
SC
AL
E:
SI
ZE
AN
SI
D
C H
EC
KE
D B
Y:
PL
O
T D
AT
E:
FI
LE
N
AM
E:
SU
BM
IT
TA
L D
AT
E:
SO
LI
C
IT
AT
IO
N N
O
C O
N
TR
AC
T
N O
FI
LE
N U
M
BE
R
M
AR
K D
ES
C
R
IP
TI
O
N D
AT
E:
AP
PR
M
AR
K
D
ES
C R
IP
TI
O N
D
AT
E:
AP
PR
B
C
D
1 2 3 4 5
1 2 3 4 5
Defense Information Systems Agency A Combat Support Agency
A
B
D
C
P.
O
.B O
X
G
R
EE
N W
O O
D V
IL
LA
G E
SE
L
F
AC
IL
IT
IE
S
EN
G
IN
EE
R
IN
G
C O
.8
234567 14 13 12 11 10 9 8
* FOR OFFICIAL USE ONLY *
* FOR OFFICIAL USE ONLY *
A
M-101
C O
N D
EN
SE
R W
AT
ER
F
IL
TR
AT
IO
N
A N
D U
PG
R
AD
ES
D
AT
A C
EN
TE
R S
AN
A
N
TO
N
IO
N
EW
D
IS
C H
AR
G
E
PI
PI
N
G M
EC
H
AN
IC
AL
D
ES
IG
N
R M
F
AK
S
N /A
AS
S
H O
W N
JE
S
1/
/2
M -1
.D
W G
N /A
N /A
N /A
1/
/2
0 2' 4' 8'
NEW DISCHARGE PIPING - APPENDIX A
SCALE : 1/4" = 1'-0"
N
PLAN
REFERENCE
NORTH
A B
C D
KEY PLAN
SCALE: NONE
1. EXISTING TRIPLE DUTY VALVE SHALL BE EITHER REUSED OR
REPLACED.
2. EXISTING VALVE SHALL BE EITHER REUSED OR REPLACED.
3. PROVIDE A MINIMUM OF ONE FOOT SPOOL PIECE BETWEEN THE
TRIPLE DUTY VALVE AND THE ISOLATION VALVE TO PROVIDE
ISOLATION AND REMOVAL OF THE TRIPLE DUTY VALVE IN THE
FUTURE BY MAINTENANCE.
4. PROVIDE NEW CONDENSER WATER ISOLATION VALVES. THESE
ASSEMBLIES SHALL BE MOTORIZED BUTTERFLY VALVES.
PROVIDE VALVES WITH TWO POSITION ACTUATORS WITH END
SWITCH INDICATION, WITH BACK-UP MANUAL OVERRIDE
HANDLES OR GEAR DRIVEN WHEELS, AND WITH POWER THAT
CAN BE FED FROM EITHER 24 VOLTS OR 120 VOLTS.
5. PROVIDE NEW CONDENSER WATER BALANCING VALVES. THESE
ASSEMBLIES SHALL BE MOTORIZED GLOBE VALVES. PROVIDE
VALVES WITH MULTIPLE POSITION ACTUATORS WITH POSITION
SWITCH INDICATION, WITH BACK-UP MANUAL OVERRIDE
HANDLES OR GEAR DRIVEN WHEELS, AND WITH POWER THAT
CAN BE FED FROM EITHER 24 VOLTS OR 120 VOLTS.
6. CONTRACTOR SHALL MINIMIZE THE USE OF 8 INCH DIAMETER
PIPING ON THE DISCHARGE-SIDE. A MAXIMUM OF 8 FEET OF 8
INCH DIAMETER PIPE SHALL BE PERMITTED PER COOLING
TOWER UNLESS APPROVED BY THE COR.
7. PIPING FOR COOLING TOWER 1 SHALL BE A MIRROR IMAGE OF
THE PIPING FOR COOLING TOWER 2.
8. CONTRACTOR SHALL INSTALL PROTECTIVE ALUMINUM
JACKETING ON ALL EXTERIOR CONDENSER WATER PIPE THAT IS
BOTH NEW AND EXISTING TO INCLUDE THE CONDENSER WATER
BASIN EQUALIZER PIPE.
9. PIPING SHALL HAVE AN ELEVATION CHANGE AS REPRESENTED
TO PROVIDE A WATER LEG OR WATER TRAP DURING LOSS OF
FLOW. ELEVATION CHANGE SHALL BE A MINIMUM OF 5 FEET
UNLESS THE CONTRACTOR REQUESTS AND THE COR APPROVES
DEVIATION.
10.EXISTING EQUALIZER PIPE TO REMAIN BETWEEN COOLING
TOWERS 1 AND 2.
KEYNOTES
GENERAL NOTES
1. CONTRACTOR SHALL PROVIDE DETAILED INSTALLATION SHOP DRAWINGS
FOR ALL NEW INSTALLED PIPE AND EQUIPMENT. SHOP DRAWING SHALL
BE REVIEWED AND APPROVED BY THE GOVERNMENT PRIOR TO
ORDERING PARTS AND EQUIPMENT, IF THE CONTRACTOR WOULD LIKE
TO DEVIATE FROM THIS DRAWING SET, COR APPROVAL MUST BE
REQUESTED AND APPROVED. ANY DEVIATION MAY REQUIRE THAT THE
NEW DEVIATION DRAWING BE STAMPED BY A PROFESSIONAL ENGINEER
IN ORDER TO OBTAIN COR APPROVAL.
2. CONTRACTOR SHALL PROVIDE REDUNDANT TEMPORARY CHILLERS,
PUMPS, PIPING, AND CONDUCTORS TO SUPPLY UNINTERRUPTED
CHILLED WATER TO THE MAIN MECHANICAL PLANT FOR THE ENTIRE
PROJECT. CONTRACTOR SHALL PROVIDE A PLAN FOR ACCOMPLISHING
THIS FOR REVIEW AND APPROVAL BY THE COR 14 DAYS PRIOR TO
ORDERING RENTAL EQUIPMENT OR CUTTING ANY PIPE.
3. ALL CONDENSER WATER PIPE INSTALLED SHALL BE BLACK STEEL PIPE
MEETING ASTM A53, GRADE B, TYPE E. FITTINGS SHALL MEET ANSI B16.9.
4. CONTRACTOR SHALL INSTALL THE CONDENSER WATER PIPING WITH
WELDED SEAMLESS JOINTS WHENEVER POSSIBLE. AT MINIMUM 90% OF
ALL INSTALLED JOINTS SHALL BE WELDED SEAMLESS.
5. CONTRACTOR SHALL PROVIDE ADEQUATE SUPPORTS FOR ALL
INSTALLED PIPE AND COMPONENTS. SUPPORTS SHALL MEET THE
MANUFACTURERS' AND INDUSTRY STANDARD FOR PIPE SUPPORTING.
6. CONTRACTOR SHALL PROVIDE AND INSTALL LONG ELBOWS
WHENEVER POSSIBLE. AT MINIMUM 95% OF ALL INSTALLED ELBOWS
SHALL BE LONG ELBOWS.
7. CONTRACTOR SHALL INSTALL NEW LABELS ON BOTH NEW AND
EXISTING CONDENSER WATER PIPING INSIDE AND OUTSIDE THE
BUILDING PER APPENDIX J.
8. PROVIDE, INSTALL, AND INTEGRATE THE NEW VALVES, SIDE STREAM
FILTERS, PUMPS / MOTORS / VFDS. FAN VFDS, AND SENSORS INTO THE
DELTA AND ICONICS BAS. ALL NEW EQUIPMENT SHALL BE COMPATIBLE
AND CAPABLE OF INTERFACING WITH DELTA CONTROLS AND THE
EXISTING ICONICS PER APPENDIX F.
NEW 3D COOLING TOWER PIPING - OUTSIDE
IDENTIFICATION
D
ES
IG
N
B Y:
D R
AW
N
B Y:
SU
BM
IT
TE
D B
Y:
PL
O
T
SC
AL
E:
SI
ZE
AN
SI
D
C H
EC
KE
D B
Y:
PL
O
T D
AT
E:
FI
LE
N
AM
E:
SU
BM
IT
TA
L D
AT
E:
SO
LI
C
IT
AT
IO
N N
O
C O
N
TR
AC
T
N O
FI
LE
N U
M
BE
R
M
AR
K D
ES
C
R
IP
TI
O
N D
AT
E:
AP
PR
M
AR
K
D
ES
C R
IP
TI
O N
D
AT
E:
AP
PR
B
C
D
1 2 3 4 5
1 2 3 4 5
Defense Information Systems Agency A Combat Support Agency
A
B
D
C
P.
O
.B O
X
G
R
EE
N W
O O
D V
IL
LA
G E
SE
L
F
AC
IL
IT
IE
S
EN
G
IN
EE
R
IN
G
C O
.8
* FOR OFFICIAL USE ONLY *
* FOR OFFICIAL USE ONLY *
A
R M
F
KL
K
AS
S
H O
W N
JE
S
1/
/2
M -3
D
C
T
PI
PI
N
G
N
EW
1/
/2
M-103
C O
N D
EN
SE
R W
AT
ER
F
IL
TR
AT
IO
N
A N
D U
PG
R
AD
ES
D
AT
A C
EN
TE
R S
AN
A
N
TO
N
IO
N
EW
D
C O
O
LI
N G
T O
W
ER
P
IP
IN
G
O
U
TS
ID
E
M
EC
H
AN
IC
AL
3D D
ES
IG
N
0 1' 2' 4'SCALE :1/2" = 1'-0"
GENERAL NOTES
1. CONTRACTOR SHALL PROVIDE DETAILED INSTALLATION SHOP DRAWINGS FOR ALL
NEW INSTALLED PIPE AND EQUIPMENT. SHOP DRAWING SHALL BE REVIEWED AND
APPROVED BY THE GOVERNMENT PRIOR TO ORDERING PARTS AND EQUIPMENT, IF
THE CONTRACTOR WOULD LIKE TO DEVIATE FROM THIS DRAWING SET, COR
APPROVAL MUST BE REQUESTED AND APPROVED. ANY DEVIATION MAY REQUIRE
THAT THE NEW DEVIATION DRAWING BE STAMPED BY A PROFESSIONAL ENGINEER
IN ORDER TO OBTAIN COR APPROVAL.
2. CONTRACTOR SHALL PROVIDE REDUNDANT TEMPORARY CHILLERS, PUMPS,
PIPING, AND CONDUCTORS TO SUPPLY UNINTERRUPTED CHILLED WATER TO THE
MAIN MECHANICAL PLANT FOR THE ENTIRE PROJECT. CONTRACTOR SHALL
PROVIDE A PLAN FOR ACCOMPLISHING THIS FOR REVIEW AND APPROVAL BY THE
COR 14 DAYS PRIOR TO ORDERING RENTAL EQUIPMENT OR CUTTING ANY PIPE.
3. ALL CONDENSER WATER PIPE INSTALLED SHALL BE BLACK STEEL PIPE MEETING
ASTM A53, GRADE B, TYPE E. FITTINGS SHALL MEET ANSI B16.9.
4. CONTRACTOR SHALL INSTALL THE CONDENSER WATER PIPING WITH WELDED
SEAMLESS JOINTS WHENEVER POSSIBLE. AT MINIMUM 90% OF ALL INSTALLED
JOINTS SHALL BE WELDED SEAMLESS.
5. CONTRACTOR SHALL PROVIDE ADEQUATE SUPPORTS FOR ALL INSTALLED PIPE
AND COMPONENTS. SUPPORTS SHALL MEET THE MANUFACTURERS' AND
INDUSTRY STANDARD FOR PIPE SUPPORTING.
6. CONTRACTOR SHALL PROVIDE AND INSTALL LONG ELBOWS WHENEVER POSSIBLE.
AT MINIMUM 95% OF ALL INSTALLED ELBOWS SHALL BE LONG ELBOWS.
7. CONTRACTOR SHALL INSTALL NEW LABELS ON BOTH NEW AND EXISTING
CONDENSER WATER PIPING INSIDE AND OUTSIDE THE BUILDING PER APPENDIX J.
8. PROVIDE, INSTALL, AND INTEGRATE THE NEW VALVES, SIDE STREAM FILTERS,
PUMPS / MOTORS / VFDS. FAN VFDS, AND SENSORS INTO THE DELTA AND ICONICS
BAS. ALL NEW EQUIPMENT SHALL BE COMPATIBLE AND CAPABLE OF INTERFACING
WITH DELTA CONTROLS AND THE EXISTING ICONICS PER APPENDIX F.
KEY NOTES
1. EXISTING VALVE (BETWEEN THE BUILDING EXTERIOR AND THE BASKET
STRAINER) SHALL BE EITHER REUSED OR REPLACED.
2. EXISTING BASKET STRAINERS SHALL BE EITHER REUSED OR REPLACED.
3. CONTRACTOR SHALL MINIMIZE THE USE OF 8 INCH DIAMETER PIPING ON THE
SUCTION-SIDE. A MAXIMUM OF 8 FEET OF 8 INCH DIAMETER PIPE SHALL BE
PERMITTED PER COOLING TOWER UNLESS APPROVED BY THE COR.
4. CONTRACTOR SHALL MINIMIZE THE USE OF 8 INCH DIAMETER PIPING ON THE
DISCHARGE-SIDE. A MAXIMUM OF 8 FEET OF 8 INCH DIAMETER PIPE SHALL BE
PERMITTED PER COOLING TOWER UNLESS APPROVED BY THE COR.
5. PIPING SHALL HAVE AN ELEVATION CHANGE AS REPRESENTED TO PROVIDE A
WATER LEG OR WATER TRAP DURING LOSS OF FLOW.
6. PROVIDE NEW CONDENSER WATER ISOLATION VALVES. THESE ASSEMBLIES
SHALL BE MOTORIZED BUTTERFLY VALVES. PROVIDE VALVES WITH TWO
POSITION ACTUATORS WITH END SWITCH INDICATION, WITH BACK-UP MANUAL
OVERRIDE HANDLES OR GEAR DRIVEN WHEELS, AND WITH POWER THAT CAN BE
FED FROM EITHER 24 VOLT OR 120 VOLTS.
7. PROVIDE NEW CONDENSER WATER BALANCING VALVES. THESE ASSEMBLIES
SHALL BE MOTORIZED GLOBE VALVES. PROVIDE VALVES WITH MULTIPLE
POSITION ACTUATORS WITH POSITION SWITCH INDICATION, WITH BACK-UP
MANUAL OVERRIDE HANDLES OR GEAR DRIVEN WHEELS, AND WITH POWER
THAT CAN BE FED FROM EITHER 24 VOLT OR 120 VOLTS.
8. CONTRACTOR SHALL INSTALL PROTECTIVE ALUMINUM JACKETING ON ALL
EXTERIOR CONDENSER WATER PIPE THAT IS BOTH NEW AND EXISTING TO
INCLUDE THE CONDENSER WATER BASIN EQUALIZER PIPE.
9. EXISTING EQUALIZER PIPE TO REMAIN BETWEEN COOLING TOWERS 1 AND 2.
NEW 3D COOLING TOWER 1 ISO VIEW
IDENTIFICATION
D
ES
IG
N
B Y:
D R
AW
N
B Y:
SU
BM
IT
TE
D B
Y:
PL
O
T
SC
AL
E:
SI
ZE
AN
SI
D
C H
EC
KE
D B
Y:
PL
O
T D
AT
E:
FI
LE
N
AM
E:
SU
BM
IT
TA
L D
AT
E:
SO
LI
C
IT
AT
IO
N N
O
C O
N
TR
AC
T
N O
FI
LE
N U
M
BE
R
M
AR
K D
ES
C
R
IP
TI
O
N D
AT
E:
AP
PR
M
AR
K
D
ES
C R
IP
TI
O N
D
AT
E:
AP
PR
B
C
D
1 2 3 4 5
1 2 3 4 5
Defense Information Systems Agency A Combat Support Agency
A
B
D
C
P.
O
.B O
X
G
R
EE
N W
O O
D V
IL
LA
G E
SE
L
F
AC
IL
IT
IE
S
EN
G
IN
EE
R
IN
G
C O
.8
* FOR OFFICIAL USE ONLY *
* FOR OFFICIAL USE ONLY *
A
R M
F
KL
K
AS
S
H O
W N
JE
S
1/
/2
M -3
D
C
T1
PI
PI
N G
-N
EW
1/
/2
M-104
C O
N D
EN
SE
R W
AT
ER
F
IL
TR
AT
IO
N
A N
D U
PG
R
AD
ES
D
AT
A C
EN
TE
R S
AN
A
N
TO
N
IO
N
EW
D
C O
O
LI
N G
T O
W
ER
IS
O V
IE
W
M
EC
H
AN
IC
AL
3D D
ES
IG
N
0 1' 2' 4'SCALE : 1/2" = 1'-0"
GENERAL NOTES
1. CONTRACTOR SHALL PROVIDE DETAILED INSTALLATION SHOP DRAWINGS FOR ALL
NEW INSTALLED PIPE AND EQUIPMENT. SHOP DRAWING SHALL BE REVIEWED AND
APPROVED BY THE GOVERNMENT PRIOR TO ORDERING PARTS AND EQUIPMENT, IF
THE CONTRACTOR WOULD LIKE TO DEVIATE FROM THIS DRAWING SET, COR
APPROVAL MUST BE REQUESTED AND APPROVED. ANY DEVIATION MAY REQUIRE
THAT THE NEW DEVIATION DRAWING BE STAMPED BY A PROFESSIONAL ENGINEER
IN ORDER TO OBTAIN COR APPROVAL.
2. CONTRACTOR SHALL PROVIDE REDUNDANT TEMPORARY CHILLERS, PUMPS,
PIPING, AND CONDUCTORS TO SUPPLY UNINTERRUPTED CHILLED WATER TO THE
MAIN MECHANICAL PLANT FOR THE ENTIRE PROJECT. CONTRACTOR SHALL
PROVIDE A PLAN FOR ACCOMPLISHING THIS FOR REVIEW AND APPROVAL BY THE
COR 14 DAYS PRIOR TO ORDERING RENTAL EQUIPMENT OR CUTTING ANY PIPE.
3. ALL CONDENSER WATER PIPE INSTALLED SHALL BE BLACK STEEL PIPE MEETING
ASTM A53, GRADE B, TYPE E. FITTINGS SHALL MEET ANSI B16.9.
4. CONTRACTOR SHALL INSTALL THE CONDENSER WATER PIPING WITH WELDED
SEAMLESS JOINTS WHENEVER POSSIBLE. AT MINIMUM 90% OF ALL INSTALLED
JOINTS SHALL BE WELDED SEAMLESS.
5. CONTRACTOR SHALL PROVIDE ADEQUATE SUPPORTS FOR ALL INSTALLED PIPE
AND COMPONENTS. SUPPORTS SHALL MEET THE MANUFACTURERS' AND
INDUSTRY STANDARD FOR PIPE SUPPORTING.
6. CONTRACTOR SHALL PROVIDE AND INSTALL LONG ELBOWS WHENEVER POSSIBLE.
AT MINIMUM 95% OF ALL INSTALLED ELBOWS SHALL BE LONG ELBOWS.
7. CONTRACTOR SHALL INSTALL NEW LABELS ON BOTH NEW AND EXISTING
CONDENSER WATER PIPING INSIDE AND OUTSIDE THE BUILDING PER APPENDIX J.
8. PROVIDE, INSTALL, AND INTEGRATE THE NEW VALVES, SIDE STREAM FILTERS,
PUMPS / MOTORS / VFDS. FAN VFDS, AND SENSORS INTO THE DELTA AND ICONICS
BAS. ALL NEW EQUIPMENT SHALL BE COMPATIBLE AND CAPABLE OF INTERFACING
WITH DELTA CONTROLS AND THE EXISTING ICONICS PER APPENDIX F.
KEY NOTES
1. EXISTING VALVE (BETWEEN THE BUILDING EXTERIOR AND THE BASKET
STRAINER) SHALL BE EITHER REUSED OR REPLACED.
2. EXISTING BASKET STRAINERS SHALL BE EITHER REUSED OR REPLACED.
3. CONTRACTOR SHALL MINIMIZE THE USE OF 8 INCH DIAMETER PIPING ON THE
SUCTION-SIDE. A MAXIMUM OF 8 FEET OF 8 INCH DIAMETER PIPE SHALL BE
PERMITTED PER COOLING TOWER UNLESS APPROVED BY THE COR.
4. CONTRACTOR SHALL MINIMIZE THE USE OF 8 INCH DIAMETER PIPING ON THE
DISCHARGE-SIDE. A MAXIMUM OF 8 FEET OF 8 INCH DIAMETER PIPE SHALL BE
PERMITTED PER COOLING TOWER UNLESS APPROVED BY THE COR.
5. PIPING SHALL HAVE AN ELEVATION CHANGE AS REPRESENTED TO PROVIDE A
WATER LEG OR WATER TRAP DURING LOSS OF FLOW.
6. PROVIDE NEW CONDENSER WATER ISOLATION VALVES. THESE ASSEMBLIES
SHALL BE MOTORIZED BUTTERFLY VALVES. PROVIDE VALVES WITH TWO
POSITION ACTUATORS WITH END SWITCH INDICATION, WITH BACK-UP MANUAL
OVERRIDE HANDLES OR GEAR DRIVEN WHEELS, AND WITH POWER THAT CAN BE
FED FROM EITHER 24 VOLT OR 120 VOLTS.
7. PROVIDE NEW CONDENSER WATER BALANCING VALVES. THESE ASSEMBLIES
SHALL BE MOTORIZED GLOBE VALVES. PROVIDE VALVES WITH MULTIPLE
POSITION ACTUATORS WITH POSITION SWITCH INDICATION, WITH BACK-UP
MANUAL OVERRIDE HANDLES OR GEAR DRIVEN WHEELS, AND WITH POWER
THAT CAN BE FED FROM EITHER 24 VOLT OR 120 VOLTS.
8. CONTRACTOR SHALL INSTALL PROTECTIVE ALUMINUM JACKETING ON ALL
EXTERIOR CONDENSER WATER PIPE THAT IS BOTH NEW AND EXISTING TO
INCLUDE THE CONDENSER WATER BASIN EQUALIZER PIPE.
9. EXISTING EQUALIZER PIPE TO REMAIN BETWEEN COOLING TOWERS 1 AND 2.
NEW 3D COOLING TOWER 2 ISO VIEW
IDENTIFICATION
D
ES
IG
N
B Y:
D R
AW
N
B Y:
SU
BM
IT
TE
D B
Y:
PL
O
T
SC
AL
E:
SI
ZE
AN
SI
D
C H
EC
KE
D B
Y:
PL
O
T D
AT
E:
FI
LE
N
AM
E:
SU
BM
IT
TA
L D
AT
E:
SO
LI
C
IT
AT
IO
N N
O
C O
N
TR
AC
T
N O
FI
LE
N U
M
BE
R
M
AR
K D
ES
C
R
IP
TI
O
N D
AT
E:
AP
PR
M
AR
K
D
ES
C R
IP
TI
O N
D
AT
E:
AP
PR
B
C
D
1 2 3 4 5
1 2 3 4 5
Defense Information Systems Agency A Combat Support Agency
A
B
D
C
P.
O
.B O
X
G
R
EE
N W
O O
D V
IL
LA
G E
SE
L
F
AC
IL
IT
IE
S
EN
G
IN
EE
R
IN
G
C O
.8
* FOR OFFICIAL USE ONLY *
* FOR OFFICIAL USE ONLY *
A
R M
F
KL
K
AS
S
H O
W N
JE
S
1/
/2
M -3
D
C
T2
PI
PI
N G
-N
EW
1/
/2
M-105
C O
N D
EN
SE
R W
AT
ER
F
IL
TR
AT
IO
N
A N
D U
PG
R
AD
ES
D
AT
A C
EN
TE
R S
AN
A
N
TO
N
IO
N
EW
D
C O
O
LI
N G
T O
W
ER
IS
O V
IE
W
M
EC
H
AN
IC
AL
3D D
ES
IG
N
0 1' 2' 4'SCALE : 1/2" = 1'-0"
GENERAL NOTES
1. CONTRACTOR SHALL PROVIDE DETAILED INSTALLATION SHOP DRAWINGS FOR ALL
NEW INSTALLED PIPE AND EQUIPMENT. SHOP DRAWING SHALL BE REVIEWED AND
APPROVED BY THE GOVERNMENT PRIOR TO ORDERING PARTS AND EQUIPMENT, IF
THE CONTRACTOR WOULD LIKE TO DEVIATE FROM THIS DRAWING SET, COR
APPROVAL MUST BE REQUESTED AND APPROVED. ANY DEVIATION MAY REQUIRE
THAT THE NEW DEVIATION DRAWING BE STAMPED BY A PROFESSIONAL ENGINEER
IN ORDER TO OBTAIN COR APPROVAL.
2. CONTRACTOR SHALL PROVIDE REDUNDANT TEMPORARY CHILLERS, PUMPS,
PIPING, AND CONDUCTORS TO SUPPLY UNINTERRUPTED CHILLED WATER TO THE
MAIN MECHANICAL PLANT FOR THE ENTIRE PROJECT. CONTRACTOR SHALL
PROVIDE A PLAN FOR ACCOMPLISHING THIS FOR REVIEW AND APPROVAL BY THE
COR 14 DAYS PRIOR TO ORDERING RENTAL EQUIPMENT OR CUTTING ANY PIPE.
3. ALL CONDENSER WATER PIPE INSTALLED SHALL BE BLACK STEEL PIPE MEETING
ASTM A53, GRADE B, TYPE E. FITTINGS SHALL MEET ANSI B16.9.
4. CONTRACTOR SHALL INSTALL THE CONDENSER WATER PIPING WITH WELDED
SEAMLESS JOINTS WHENEVER POSSIBLE. AT MINIMUM 90% OF ALL INSTALLED
JOINTS SHALL BE WELDED SEAMLESS.
5. CONTRACTOR SHALL PROVIDE ADEQUATE SUPPORTS FOR ALL INSTALLED PIPE
AND COMPONENTS. SUPPORTS SHALL MEET THE MANUFACTURERS' AND
INDUSTRY STANDARD FOR PIPE SUPPORTING.
6. CONTRACTOR SHALL PROVIDE AND INSTALL LONG ELBOWS WHENEVER POSSIBLE.
AT MINIMUM 95% OF ALL INSTALLED ELBOWS SHALL BE LONG ELBOWS.
7. CONTRACTOR SHALL INSTALL NEW LABELS ON BOTH NEW AND EXISTING
CONDENSER WATER PIPING INSIDE AND OUTSIDE THE BUILDING PER APPENDIX J.
8. PROVIDE, INSTALL, AND INTEGRATE THE NEW VALVES, SIDE STREAM FILTERS,
PUMPS / MOTORS / VFDS. FAN VFDS, AND SENSORS INTO THE DELTA AND ICONICS
BAS. ALL NEW EQUIPMENT SHALL BE COMPATIBLE AND CAPABLE OF INTERFACING
WITH DELTA CONTROLS AND THE EXISTING ICONICS PER APPENDIX F.
KEY NOTES
1. EXISTING VALVE (BETWEEN THE BUILDING EXTERIOR AND THE BASKET
STRAINER) SHALL BE EITHER REUSED OR REPLACED.
2. EXISTING BASKET STRAINERS SHALL BE EITHER REUSED OR REPLACED.
3. CONTRACTOR SHALL MINIMIZE THE USE OF 8 INCH DIAMETER PIPING ON THE
SUCTION-SIDE. A MAXIMUM OF 8 FEET OF 8 INCH DIAMETER PIPE SHALL BE
PERMITTED PER COOLING TOWER UNLESS APPROVED BY THE COR.
4. CONTRACTOR SHALL MINIMIZE THE USE OF 8 INCH DIAMETER PIPING ON THE
DISCHARGE-SIDE. A MAXIMUM OF 8 FEET OF 8 INCH DIAMETER PIPE SHALL BE
PERMITTED PER COOLING TOWER UNLESS APPROVED BY THE COR.
5. PIPING SHALL HAVE AN ELEVATION CHANGE AS REPRESENTED TO PROVIDE A
WATER LEG OR WATER TRAP DURING LOSS OF FLOW.
6. PROVIDE NEW CONDENSER WATER ISOLATION VALVES. THESE ASSEMBLIES
SHALL BE MOTORIZED BUTTERFLY VALVES. PROVIDE VALVES WITH TWO
POSITION ACTUATORS WITH END SWITCH INDICATION, WITH BACK-UP MANUAL
OVERRIDE HANDLES OR GEAR DRIVEN WHEELS, AND WITH POWER THAT CAN BE
FED FROM EITHER 24 VOLT OR 120 VOLTS.
7. PROVIDE NEW CONDENSER WATER BALANCING VALVES. THESE ASSEMBLIES
SHALL BE MOTORIZED GLOBE VALVES. PROVIDE VALVES WITH MULTIPLE
POSITION ACTUATORS WITH POSITION SWITCH INDICATION, WITH BACK-UP
MANUAL OVERRIDE HANDLES OR GEAR DRIVEN WHEELS, AND WITH POWER
THAT CAN BE FED FROM EITHER 24 VOLT OR 120 VOLTS.
8. CONTRACTOR SHALL INSTALL PROTECTIVE ALUMINUM JACKETING ON ALL
EXTERIOR CONDENSER WATER PIPE THAT IS BOTH NEW AND EXISTING TO
INCLUDE THE CONDENSER WATER BASIN EQUALIZER PIPE.
9. EXISTING EQUALIZER PIPE TO REMAIN BETWEEN COOLING TOWERS 1 AND 2.
NEW PUMP - PIPING - INSIDE
IDENTIFICATION
D
ES
IG
N
B Y:
D R
AW
N
B Y:
SU
BM
IT
TE
D B
Y:
PL
O
T
SC
AL
E:
SI
ZE
AN
SI
D
C H
EC
KE
D B
Y:
PL
O
T D
AT
E:
FI
LE
N
AM
E:
SU
BM
IT
TA
L D
AT
E:
SO
LI
C
IT
AT
IO
N N
O
C O
N
TR
AC
T
N O
FI
LE
N U
M
BE
R
M
AR
K D
ES
C
R
IP
TI
O
N D
AT
E:
AP
PR
M
AR
K
D
ES
C R
IP
TI
O N
D
AT
E:
AP
PR
B
C
D
1 2 3 4 5
1 2 3 4 5
Defense Information Systems Agency A Combat Support Agency
A
B
D
C
P.
O
.B O
X
G
R
EE
N W
O O
D V
IL
LA
G E
SE
L
F
AC
IL
IT
IE
S
EN
G
IN
EE
R
IN
G
C O
.8
* FOR OFFICIAL USE ONLY *
* FOR OFFICIAL USE ONLY *
A
R M
F
KL
K
AS
S
H O
W N
JE
S
1/
/2
M -3
D
N
EW
P
U M
P
1/
/2
M-106
C O
N D
EN
SE
R W
AT
ER
F
IL
TR
AT
IO
N
A N
D U
PG
R
AD
ES
D
AT
A C
EN
TE
R S
AN
A
N
TO
N
IO
N
EW
P U
M P
- P
IP
IN
G
IN
SI
D
E M
EC
H
AN
IC
AL
3D
D
ES
IG
N
0 1' 2' 3'SCALE : 3/4" = 1'-0"
KEY NOTES
1. EXISTING TRIPLE DUTY VALVES SHALL BE EITHER REUSED OR REPLACED.
2. EXISTING VALVE SHALL BE EITHER REUSED OR REPLACED.
3. PROVIDE A MINIMUM OF A 1 FOOT SPOOL PIECE BETWEEN THE TRIPLE DUTY
VALVE AND THE ISOLATION AND REMOVAL OF THE TRIPLE DUTY VALVE IN THE
FUTURE BY MAINTENANCE.
4. PROVIDE AND INSTALL BOTH A DIFFERENTIAL PRESSURE SENSOR TO BE USED
BY THE PUMP/BAS AND A DIFFERENTIAL PRESSURE GAUGE PER DETAIL SHEET
M-500.
5. REDUCER SHALL BE INSTALLED WITH THE SMALL DIAMETER AXIS HIGHER THAN
THE LARGE DIAMETER AXIS.
GENERAL NOTES
1. CONTRACTOR SHALL PROVIDE DETAILED INSTALLATION SHOP DRAWINGS FOR ALL
NEW INSTALLED PIPE AND EQUIPMENT. SHOP DRAWING SHALL BE REVIEWED AND
APPROVED BY THE GOVERNMENT PRIOR TO ORDERING PARTS AND EQUIPMENT, IF
THE CONTRACTOR WOULD LIKE TO DEVIATE FROM THIS DRAWING SET, COR
APPROVAL MUST BE REQUESTED AND APPROVED. ANY DEVIATION MAY REQUIRE
THAT THE NEW DEVIATION DRAWING BE STAMPED BY A PROFESSIONAL ENGINEER
IN ORDER TO OBTAIN COR APPROVAL.
2. CONTRACTOR SHALL PROVIDE REDUNDANT TEMPORARY CHILLERS, PUMPS,
PIPING, AND CONDUCTORS TO SUPPLY UNINTERRUPTED CHILLED WATER TO THE
MAIN MECHANICAL PLANT FOR THE ENTIRE PROJECT. CONTRACTOR SHALL
PROVIDE A PLAN FOR ACCOMPLISHING THIS FOR REVIEW AND APPROVAL BY THE
COR 14 DAYS PRIOR TO ORDERING RENTAL EQUIPMENT OR CUTTING ANY PIPE.
3. ALL CONDENSER WATER PIPE INSTALLED SHALL BE BLACK STEEL PIPE MEETING
ASTM A53, GRADE B, TYPE E. FITTINGS SHALL MEET ANSI B16.9.
4. CONTRACTOR SHALL INSTALL THE CONDENSER WATER PIPING WITH WELDED
SEAMLESS JOINTS WHENEVER POSSIBLE. AT MINIMUM 90% OF ALL INSTALLED
JOINTS SHALL BE WELDED SEAMLESS.
5. CONTRACTOR SHALL PROVIDE ADEQUATE SUPPORTS FOR ALL INSTALLED PIPE
AND COMPONENTS. SUPPORTS SHALL MEET THE MANUFACTURERS' AND
INDUSTRY STANDARD FOR PIPE SUPPORTING.
6. CONTRACTOR SHALL PROVIDE AND INSTALL LONG ELBOWS WHENEVER POSSIBLE.
AT MINIMUM 95% OF ALL INSTALLED ELBOWS SHALL BE LONG ELBOWS.
7. CONTRACTOR SHALL INSTALL NEW LABELS ON BOTH NEW AND EXISTING
CONDENSER WATER PIPING INSIDE AND OUTSIDE THE BUILDING PER APPENDIX J.
8. PROVIDE, INSTALL, AND INTEGRATE THE NEW VALVES, SIDE STREAM FILTERS,
PUMPS / MOTORS / VFDS. FAN VFDS, AND SENSORS INTO THE DELTA AND ICONICS
BAS. ALL NEW EQUIPMENT SHALL BE COMPATIBLE AND CAPABLE OF INTERFACING
WITH DELTA CONTROLS AND THE EXISTING ICONICS PER APPENDIX F.
CWP-2 CWP-1
CWP-1
NEW PUMP - INSIDE
IDENTIFICATION
D
ES
IG
N
B Y:
D R
AW
N
B Y:
SU
BM
IT
TE
D B
Y:
PL
O
T
SC
AL
E:
SI
ZE
AN
SI
D
C H
EC
KE
D B
Y:
PL
O
T D
AT
E:
FI
LE
N
AM
E:
SU
BM
IT
TA
L D
AT
E:
SO
LI
C
IT
AT
IO
N N
O
C O
N
TR
AC
T
N O
FI
LE
N U
M
BE
R
M
AR
K D
ES
C
R
IP
TI
O
N D
AT
E:
AP
PR
M
AR
K
D
ES
C R
IP
TI
O N
D
AT
E:
AP
PR
B
C
D
1 2 3 4 5
1 2 3 4 5
Defense Information Systems Agency A Combat Support Agency
A
B
D
C
P.
O
.B O
X
G
R
EE
N W
O O
D V
IL
LA
G E
SE
L
F
AC
IL
IT
IE
S
EN
G
IN
EE
R
IN
G
C O
.8
* FOR OFFICIAL USE ONLY *
* FOR OFFICIAL USE ONLY *
A
R M
F
KL
K
AS
S
H O
W N
JE
S
1/
/2
M -3
D
N
EW
P
U M
P
1/
/2
M-107
C O
N D
EN
SE
R W
AT
ER
F
IL
TR
AT
IO
N
A N
D U
PG
R
AD
ES
D
AT
A C
EN
TE
R S
AN
A
N
TO
N
IO
N
EW
P U
M P
- I N
SI
D
E M
EC
H
AN
IC
AL
3D
D
ES
IG
N
0 1' 2' 4'SCALE : 1/2" = 1'-0"
KEY NOTES
1. EXISTING TRIPLE DUTY VALVES SHALL BE EITHER REUSED OR REPLACED.
2. EXISTING VALVE SHALL BE EITHER REUSED OR REPLACED.
3. PROVIDE A MINIMUM OF A 1 FOOT SPOOL PIECE BETWEEN THE TRIPLE DUTY
VALVE AND THE ISOLATION AND REMOVAL OF THE TRIPLE DUTY VALVE IN THE
FUTURE BY MAINTENANCE.
4. PROVIDE AND INSTALL BOTH A DIFFERENTIAL PRESSURE SENSOR TO BE USED
BY THE PUMP/BAS AND A DIFFERENTIAL PRESSURE GAUGE PER DETAIL SHEET
M-500.
5. REDUCER SHALL BE INSTALLED WITH THE SMALL DIAMETER AXIS HIGHER THAN
THE LARGE DIAMETER AXIS.
GENERAL NOTES
1. CONTRACTOR SHALL PROVIDE DETAILED INSTALLATION SHOP DRAWINGS FOR ALL
NEW INSTALLED PIPE AND EQUIPMENT. SHOP DRAWING SHALL BE REVIEWED AND
APPROVED BY THE GOVERNMENT PRIOR TO ORDERING PARTS AND EQUIPMENT, IF
THE CONTRACTOR WOULD LIKE TO DEVIATE FROM THIS DRAWING SET, COR
APPROVAL MUST BE REQUESTED AND APPROVED. ANY DEVIATION MAY REQUIRE
THAT THE NEW DEVIATION DRAWING BE STAMPED BY A PROFESSIONAL ENGINEER
IN ORDER TO OBTAIN COR APPROVAL.
2. CONTRACTOR SHALL PROVIDE REDUNDANT TEMPORARY CHILLERS, PUMPS,
PIPING, AND CONDUCTORS TO SUPPLY UNINTERRUPTED CHILLED WATER TO THE
MAIN MECHANICAL PLANT FOR THE ENTIRE PROJECT. CONTRACTOR SHALL
PROVIDE A PLAN FOR ACCOMPLISHING THIS FOR REVIEW AND APPROVAL BY THE
COR 14 DAYS PRIOR TO ORDERING RENTAL EQUIPMENT OR CUTTING ANY PIPE.
3. ALL CONDENSER WATER PIPE INSTALLED SHALL BE BLACK STEEL PIPE MEETING
ASTM A53, GRADE B, TYPE E. FITTINGS SHALL MEET ANSI B16.9.
4. CONTRACTOR SHALL INSTALL THE CONDENSER WATER PIPING WITH WELDED
SEAMLESS JOINTS WHENEVER POSSIBLE. AT MINIMUM 90% OF ALL INSTALLED
JOINTS SHALL BE WELDED SEAMLESS.
5. CONTRACTOR SHALL PROVIDE ADEQUATE SUPPORTS FOR ALL INSTALLED PIPE
AND COMPONENTS. SUPPORTS SHALL MEET THE MANUFACTURERS' AND
INDUSTRY STANDARD FOR PIPE SUPPORTING.
6. CONTRACTOR SHALL PROVIDE AND INSTALL LONG ELBOWS WHENEVER POSSIBLE.
AT MINIMUM 95% OF ALL INSTALLED ELBOWS SHALL BE LONG ELBOWS.
7. CONTRACTOR SHALL INSTALL NEW LABELS ON BOTH NEW AND EXISTING
CONDENSER WATER PIPING INSIDE AND OUTSIDE THE BUILDING PER APPENDIX J.
8. PROVIDE, INSTALL, AND INTEGRATE THE NEW VALVES, SIDE STREAM FILTERS,
PUMPS / MOTORS / VFDS. FAN VFDS, AND SENSORS INTO THE DELTA AND ICONICS
BAS. ALL NEW EQUIPMENT SHALL BE COMPATIBLE AND CAPABLE OF INTERFACING
WITH DELTA CONTROLS AND THE EXISTING ICONICS PER APPENDIX F.
CWP-1
TOP VIEW - INSIDE AND OUTSIDE
IDENTIFICATION
D
ES
IG
N
B Y:
D R
AW
N
B Y:
SU
BM
IT
TE
D B
Y:
PL
O
T
SC
AL
E:
SI
ZE
AN
SI
D
C H
EC
KE
D B
Y:
PL
O
T D
AT
E:
FI
LE
N
AM
E:
SU
BM
IT
TA
L D
AT
E:
SO
LI
C
IT
AT
IO
N N
O
C O
N
TR
AC
T
N O
FI
LE
N U
M
BE
R
M
AR
K D
ES
C
R
IP
TI
O
N D
AT
E:
AP
PR
M
AR
K
D
ES
C R
IP
TI
O N
D
AT
E:
AP
PR
B
C
D
1 2 3 4 5
1 2 3 4 5
Defense Information Systems Agency A Combat Support Agency
A
B
D
C
P.
O
.B O
X
G
R
EE
N W
O O
D V
IL
LA
G E
SE
L
F
AC
IL
IT
IE
S
EN
G
IN
EE
R
IN
G
C O
.8
* FOR OFFICIAL USE ONLY *
* FOR OFFICIAL USE ONLY *
A
R M
F
KL
K
AS
S
H O
W N
JE
S
1/
/2
M -E
L2
T O
P
1/
/2
EL-200
C O
N D
EN
SE
R W
AT
ER
F
IL
TR
AT
IO
N
A N
D U
PG
R
AD
ES
D
AT
A C
EN
TE
R S
AN
A
N
TO
N
IO
TO
P
VI
EW
IN
SI
D
E
AN
D O
U
TS
ID
E
EL
EV
AT
IO
N S
D
ES
IG
N
0 2' 4' 6'SCALE 3/8" = 1'-0"
TOP VIEW
CT-1
CT-2
8'-05 8"
12'-03 4"
15'-43 4"
2'-4"
1'-117 8"
8"
5'-01 2"
24'-01 2"
8'-8"
2'-7 1 16"
CWP-1
5'-113 4"
CWP-2
6"
12"
8"
8" 8"
12"
12"
GENERAL NOTES
6 5
6 6
1. CONTRACTOR SHALL PROVIDE DETAILED INSTALLATION SHOP DRAWINGS FOR ALL
NEW INSTALLED PIPE AND EQUIPMENT. SHOP DRAWING SHALL BE REVIEWED AND
APPROVED BY THE GOVERNMENT PRIOR TO ORDERING PARTS AND EQUIPMENT, IF
THE CONTRACTOR WOULD LIKE TO DEVIATE FROM THIS DRAWING SET, COR
APPROVAL MUST BE REQUESTED AND APPROVED. ANY DEVIATION MAY REQUIRE
THAT THE NEW DEVIATION DRAWING BE STAMPED BY A PROFESSIONAL ENGINEER
IN ORDER TO OBTAIN COR APPROVAL.
2. CONTRACTOR SHALL PROVIDE REDUNDANT TEMPORARY CHILLERS, PUMPS,
PIPING, AND CONDUCTORS TO SUPPLY UNINTERRUPTED CHILLED WATER TO THE
MAIN MECHANICAL PLANT FOR THE ENTIRE PROJECT. CONTRACTOR SHALL
PROVIDE A PLAN FOR ACCOMPLISHING THIS FOR REVIEW AND APPROVAL BY THE
COR 14 DAYS PRIOR TO ORDERING RENTAL EQUIPMENT OR CUTTING ANY PIPE.
3. ALL CONDENSER WATER PIPE INSTALLED SHALL BE BLACK STEEL PIPE MEETING
ASTM A53, GRADE B, TYPE E. FITTINGS SHALL MEET ANSI B16.9.
4. CONTRACTOR SHALL INSTALL THE CONDENSER WATER PIPING WITH WELDED
SEAMLESS JOINTS WHENEVER POSSIBLE. AT MINIMUM 90% OF ALL INSTALLED
JOINTS SHALL BE WELDED SEAMLESS.
5. CONTRACTOR SHALL PROVIDE ADEQUATE SUPPORTS FOR ALL INSTALLED PIPE
AND COMPONENTS. SUPPORTS SHALL MEET THE MANUFACTURERS' AND
INDUSTRY STANDARD FOR PIPE SUPPORTING.
6. CONTRACTOR SHALL PROVIDE AND INSTALL LONG ELBOWS WHENEVER POSSIBLE.
AT MINIMUM 95% OF ALL INSTALLED ELBOWS SHALL BE LONG ELBOWS.
7. CONTRACTOR SHALL INSTALL NEW LABELS ON BOTH NEW AND EXISTING
CONDENSER WATER PIPING INSIDE AND OUTSIDE THE BUILDING PER APPENDIX J.
8. PROVIDE, INSTALL, AND INTEGRATE THE NEW VALVES, SIDE STREAM FILTERS,
PUMPS / MOTORS / VFDS. FAN VFDS, AND SENSORS INTO THE DELTA AND ICONICS
BAS. ALL NEW EQUIPMENT SHALL BE COMPATIBLE AND CAPABLE OF INTERFACING
WITH DELTA CONTROLS AND THE EXISTING ICONICS PER APPENDIX F.
KEY NOTES
1. EXISTING VALVE (BETWEEN THE BUILDING EXTERIOR AND THE BASKET
STRAINER) SHALL BE EITHER REUSED OR REPLACED.
2. EXISTING BASKET STRAINERS SHALL BE EITHER REUSED OR REPLACED.
3. EXISTING TRIPLE DUTY VALVES SHALL BE EITHER REUSED OR REPLACED.
4. EXISTING VALVES SHALL BE EITHER REUSED OR REPLACED.
5. CONTRACTOR SHALL MINIMIZE THE USE OF 8 INCH DIAMETER PIPING ON THE
SUCTION-SIDE. A MAXIMUM OF 8 FEET OF 8 INCH DIAMETER PIPE SHALL BE
PERMITTED PER COOLING TOWER UNLESS APPROVED BY THE COR.
6. CONTRACTOR SHALL MINIMIZE THE USE OF 8 INCH DIAMETER PIPING ON THE
DISCHARGE-SIDE. A MAXIMUM OF 8 FEET OF 8 INCH DIAMETER PIPE SHALL BE
PERMITTED PER COOLING TOWER UNLESS APPROVED BY THE COR.
7. PIPING SHALL HAVE AN ELEVATION CHANGE AS REPRESENTED TO PROVIDE A
WATER LEG OR WATER TRAP DURING LOSS OF FLOW.
8. PROVIDE NEW CONDENSER WATER ISOLATION VALVES. THESE ASSEMBLIES
SHALL BE MOTORIZED BUTTERFLY VALVES. PROVIDE VALVES WITH TWO
POSITION ACTUATORS WITH END SWITCH INDICATION, WITH BACK-UP MANUAL
OVERRIDE HANDLES OR GEAR DRIVEN WHEELS, AND WITH POWER THAT CAN BE
FED FROM EITHER 24 VOLT OR 120 VOLTS.
9. PROVIDE NEW CONDENSER WATER BALANCING VALVES. THESE ASSEMBLIES
SHALL BE MOTORIZED GLOBE VALVES. PROVIDE VALVES WITH MULTIPLE
POSITION ACTUATORS WITH POSITION SWITCH INDICATION, WITH BACK-UP
MANUAL OVERRIDE HANDLES OR GEAR DRIVEN WHEELS, AND WITH POWER
THAT CAN BE FED FROM EITHER 24 VOLT OR 120 VOLTS.
10. CONTRACTOR SHALL INSTALL PROTECTIVE ALUMINUM JACKETING ON ALL
EXTERIOR CONDENSER WATER PIPE THAT IS BOTH NEW AND EXISTING TO
INCLUDE THE CONDENSER WATER BASIN EQUALIZER PIPE.
11. EXISTING EQUALIZER PIPE TO REMAIN BETWEEN COOLING TOWERS 1 AND 2.
BACK & SIDE - OUTSIDE
IDENTIFICATION
D
ES
IG
N
B Y:
D R
AW
N
B Y:
SU
BM
IT
TE
D B
Y:
PL
O
T
SC
AL
E:
SI
ZE
AN
SI
D
C H
EC
KE
D B
Y:
PL
O
T D
AT
E:
FI
LE
N
AM
E:
SU
BM
IT
TA
L D
AT
E:
SO
LI
C
IT
AT
IO
N N
O
C O
N
TR
AC
T
N O
FI
LE
N U
M
BE
R
M
AR
K D
ES
C
R
IP
TI
O
N D
AT
E:
AP
PR
M
AR
K
D
ES
C R
IP
TI
O N
D
AT
E:
AP
PR
B
C
D
1 2 3 4 5
1 2 3 4 5
Defense Information Systems Agency A Combat Support Agency
A
B
D
C
P.
O
.B O
X
G
R
EE
N W
O O
D V
IL
LA
G E
SE
L
F
AC
IL
IT
IE
S
EN
G
IN
EE
R
IN
G
C O
.8
* FOR OFFICIAL USE ONLY *
* FOR OFFICIAL USE ONLY *
A
R M
F
KL
K
AS
S
H O
W N
JE
S
1/
/2
M -E
L2
O U
TS
ID
E
- B
AC
K
SI
D E
1/
/2
EL-201
C O
N D
EN
SE
R W
AT
ER
F
IL
TR
AT
IO
N
A N
D U
PG
R
AD
ES
D
AT
A C
EN
TE
R S
AN
A
N
TO
N
IO
BA
C
K
SI
D
E
- O
U
TS
ID
E
EL
EV
AT
IO
N S
D
ES
IG
N
0 2' 4' 6'SCALE : 3/8" = 1'-0"
19'-111 2"
11'-51 2"
2'-91 2"
6'-8 3 16"
12'-03 4"
3'-81 8"
8'-6"
15'-43 4"
2'-4"
9'-71 4"
6'-8 3 16"
5'-01 2"
9'-2 1 16"
12'-01 2"
8"
12"
12"
SIDE VIEW BACK VIEW
12"
CT-1CT-2
12"
8"
6'-0 3 16"
KEY NOTES
1. EXISTING VALVE (BETWEEN THE BUILDING EXTERIOR AND THE BASKET
STRAINER) SHALL BE EITHER REUSED OR REPLACED.
2. EXISTING BASKET STRAINERS SHALL BE EITHER REUSED OR REPLACED.
3. CONTRACTOR SHALL MINIMIZE THE USE OF 8 INCH DIAMETER PIPING ON THE
SUCTION-SIDE. A MAXIMUM OF 8 FEET OF 8 INCH DIAMETER PIPE SHALL BE
PERMITTED PER COOLING TOWER UNLESS APPROVED BY THE COR.
4. CONTRACTOR SHALL MINIMIZE THE USE OF 8 INCH DIAMETER PIPING ON THE
DISCHARGE-SIDE. A MAXIMUM OF 8 FEET OF 8 INCH DIAMETER PIPE SHALL BE
PERMITTED PER COOLING TOWER UNLESS APPROVED BY THE COR.
5. PIPING SHALL HAVE AN ELEVATION CHANGE AS REPRESENTED TO PROVIDE A
WATER LEG OR WATER TRAP DURING LOSS OF FLOW.
6. PROVIDE NEW CONDENSER WATER ISOLATION VALVES. THESE ASSEMBLIES
SHALL BE MOTORIZED BUTTERFLY VALVES. PROVIDE VALVES WITH TWO
POSITION ACTUATORS WITH END SWITCH INDICATION, WITH BACK-UP MANUAL
OVERRIDE HANDLES OR GEAR DRIVEN WHEELS, AND WITH POWER THAT CAN BE
FED FROM EITHER 24 VOLT OR 120 VOLTS.
7. PROVIDE NEW CONDENSER WATER BALANCING VALVES. THESE ASSEMBLIES
SHALL BE MOTORIZED GLOBE VALVES. PROVIDE VALVES WITH MULTIPLE
POSITION ACTUATORS WITH POSITION SWITCH INDICATION, WITH BACK-UP
MANUAL OVERRIDE HANDLES OR GEAR DRIVEN WHEELS, AND WITH POWER
THAT CAN BE FED FROM EITHER 24 VOLT OR 120 VOLTS.
8. CONTRACTOR SHALL INSTALL PROTECTIVE ALUMINUM JACKETING ON ALL
EXTERIOR CONDENSER WATER PIPE THAT IS BOTH NEW AND EXISTING TO
INCLUDE THE CONDENSER WATER BASIN EQUALIZER PIPE.
9. EXISTING EQUALIZER PIPE TO REMAIN BETWEEN COOLING TOWERS 1 AND 2.
GENERAL NOTES
1. CONTRACTOR SHALL PROVIDE DETAILED INSTALLATION SHOP DRAWINGS FOR ALL
NEW INSTALLED PIPE AND EQUIPMENT. SHOP DRAWING SHALL BE REVIEWED AND
APPROVED BY THE GOVERNMENT PRIOR TO ORDERING PARTS AND EQUIPMENT, IF
THE CONTRACTOR WOULD LIKE TO DEVIATE FROM THIS DRAWING SET,…
This is the start of the file's text. The full file is on GovTribe.