About this file

This is Amendment 3 to an advertised contract issued by Paulding County for the FY2026 Asphalt Resurfacing Project (Project Number 2026-ASPH-1, Bid #26015-1508). The amendment addresses clarifications regarding work specifications for center turn lanes and establishes a deadline for bidder questions. The project has a letting date of March 27, 2026. Center turn lanes will typically require 1.5 inches of milling and inlay work unless field conditions warrant additional deep patching, which will be marked by the project engineer. Bidders must submit questions by Friday, March 20th at 5:00 p.m. to allow adequate time for responses prior to bid opening.

No additional pricing terms, set-asides, funding sources, or other salient contract details are provided in this amendment document.

View the file

Other files

File Type Posted
Amendment 2.pdf PDF
Amendment No_ 1.pdf PDF
Advertisement.pdf PDF
FY2026 Asphalt Resurfacing Project Contract I.pdf PDF
Amendment 4.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

3/18/2026

AMENDMENT TO ADVERTISED CONTRACT

PROJECT NAME: FY2026 Asphalt Resurfacing Project Contract I

PROJECT NUMBER: 2026 - ASPH - 1

BID # 26015-1508

COUNTY: PAULDING

AMENDMENT NUMBER: 3

LETTING DATE: March 27, 2026

THE FOLLOWING AMENDMENTS ARE HEREBY MADE TO THIS CONTRACT.

THE BIDDER IS RESPONSIBLE FOR MAKING ANY NECESSARY CHANGES IN

INK IN THE PROPOSAL. BIDDER SHALL ACKNOWLEDGE THIS AMENDMENT

BY CHECKING THE APPROPRIATE SPACE ON THE AMENDMENT

CERTIFICATION PAGE.

ITEMS INCLUDED IN THIS AMENDMENT:

Questions received by bidders. Responses shown in RED.

1. Will the center turn lanes require 2” patching or will these fall under the 1.5” milling areas?

The typical for center turn lanes will be the 1.5” of mill and inlay unless there is a significant need for deep patching. Any additional deep patching areas will be marked by the project engineer in the field.

2. Note: Deadline to submit questions is Friday March 20th by 5:00pm. To provide adequate time to answer prior to the bid opening.