Amendment 000001 AG-82X9-S-12-0051

Pike & San Isabel National Forests

Roads Construction IDIQ

SUMMARY OF CHANGES:

SECTION B

Page 7 the following Pay Items for the base year unit has been changed from “Man Hour” to Hour.

622(01) Motor Grader, Cat 140, JD770D, or equivalent; with operator 50 AQ Hour

622(02)

Backhoe/Loader, Cat 416E, JD 310G, or equivalent, 4-wheel drive, w/ extendable stick; with operator 50 AQ Hour

622(03) Crawler Dozer, Cat D-4, Case 550, or equivalent, w/ tilt blade; with operator 50 AQ Hour

Page 15 Note 22 now reads as follows

22) Pay Items 602(01) and 602(02) assume excavation achievable with a backhoe or trackhoe. Solid material requiring the use of hydraulic hammers or blasting shall be covered separately. Imported backfill material will also be covered separately under an applicable pay item as determined by the

Contracting Officer. Bid prices should assume a maximum burial depth of 5 feet below existing road surface. Depths exceeding this amount shall be negotiated and covered separately, as needed. Bid prices should assume a dry installation method. If a wet installation method is needed then this unit price shall be negotiated and covered separately. Bid prices should assume using annular corrugated metal pipe.

SECTION J

Page 31 Wage Determinations have been updated to 06/0102012 version.

Attachment J.4 General Decision CO120013 Dated 06/01/2012 CO13

Attachment J.5 General Decision CO120012, Dated 06/01/2012 CO12

SECTION K

Page 32 FAR Clause updated to May Version, NAICS and Size standard corrected.

FAR 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAY 2012)

a)

(1) The North American Industry classification System (NAICS) code for this acquisition is 237310.

(2) The small business size standard is 33.5 million.

SECTION L

Page 4 paragraph L. 1 last sentence should be edited to read as follows:

Email submission of proposals is acceptable as long as all required information is submitted, including required signatures. FAXED RESPONSES WILL NOT BE ACCEPTED.

Page 4 Paragraph L.1. L.1.1 block 10 has been added.

(a) Business Proposal - 1 copy of the Completed, Signed Offer (Section A and B) and complete blocks

10, 14, 15, 16, 20a, b, and c on the SF 1442. If amendment(s) are issued acknowledge amendments or complete blocks 19, 20a, 20b and 20c. Complete Section K (Clauses FAR & 52.209-7, 52.219-1 &

AGAR 452.209 – 70). (b) Technical Proposal - 1 original and 1 copy.

Amendment 000001 AG-82X9-S-12-0051

Pike & San Isabel National Forests

Roads Construction IDIQ

Pike & San Isabel National Forests Road’s Construction IDIQ

Pre-Bid Meeting Notes

Solicitation: AG-82X9-S-12-0051

Forest Service officials present: Toniette Aranda – CO

James Statezny – COR Designate

Mark Varhus – COR Designate

Gifford Martinez – COR Designate

Questions/comments are from the Pre-Bid Meeting held May 31, 2012 @ 10:00 a.m. @ the Pike

& San Isabel National Forests Supervisor’s Office in Pueblo, Colorado:

1. Is it assumed that the culvert installations will be a dry application method?

-This question will be answered in Section B Note #22.

2. What type of culvert materials are allowed, annular or spiral?

-This question will be answered in Section B Note #22.

3. Is there an Item for actual road reconstruction?

-No separate Pay Item for road reconstruction will be established but multiple items in the schedule of items can be used in conjunction if road reconstruction is needed.

4. My questions are directed to line items 622(05) & 622(07). Unit pricing for those two line items are by the hour and the 3 line items above those are for man hours. Is there a difference in how we should be bidding those 5 lines? Or are they all the same?

-Pay items have been corrected to “Hour”.