About this file

This is an Addendum #3 Questions and Answers document related to a wayfinding sign installation project for the City of Griffin and Spalding County, Georgia. The project involves the procurement and installation of 39 directional signs to be placed throughout Spalding County and the City of Griffin to direct tourists and visitors to key points of interest. The addendum clarifies that value engineering options are acceptable for pricing consideration, installation pricing should not be included in proposals, the quantity of 39 signs is confirmed, and signs vary in size with differing panel layouts and arrow configurations (ranging from 2 to 6 arrows per sign). Height restrictions from grade to the lower point of each sign must remain constant due to sidewalk placement requirements, which will result in posts of varying heights. The document confirms that delivery must be arranged to prevent sign damage, with the owner's facility capable of accommodating forklift unloading if necessary.

Breakaway hardware is required as a separate line item to allow the owner flexibility in potentially sourcing this component at a lower cost independently. The varying sign sizes necessitate different post heights to maintain consistent clearance from grade, a critical consideration for signs positioned on sidewalks subject to height restrictions. Bidders should structure their proposals to clearly delineate hardware costs from other project components to facilitate the owner's procurement options and cost management strategy.

Text of this file

Addendum #3 Questions / Answers

1. We have heard that you may be open to VE options on this project. Can we provide value engineering options as an option for pricing?

Answer: Yes

1. Should we include installation pricing as part of the proposal?

Answer: No

1. Can you confirm the quantity for the signs at QTY - 39?

Answer: Yes

1) Does the breakaway hardware that is required for the base… need to be included in the bid price?

Answer: 1.) Breakaway hardware needs to be a separate line item, so that depending on the cost, we may be able to get it cheaper directly.

2) Some locations have 2 arrows and others have 6 arrows, Are the signs all the same size?

Answer: 2.) No, not all signs are the same size.

3) In reference to question 2/ If some panel layouts are larger, will the height from grade need to change? This will also causing the height of the post to be taller.

Answer: 3.) From grade to lower point of sign cannot change as many of these signs will be on sidewalks and height restrictions must be maintained; yes some posts will be taller than others.

4) How do you want the sign delivered? On multiple pallets? Do you have the facility and equipment to off load large pallets?

Answer: 4.) Delivery so that no sign is damaged from your company to our unloading area. We can accommodate fork lift unloading if needed.

Other files

File Type Posted
Award Information —
22-003 Addendum #2 —
Cancellation Notice —
22-003 Addendum #1 —
Supplier Q&A —
22-003 RFP document —
Wayfinding Signage List Final —
EV- Vendor Affidavit —
Questions and Answers —
Addendum #2 Questions-Answers —
Addendum #1 —
Wayfinding Signage Project —
Signage Drawing Package —
W-9 —
22-003 Notice of Cancellation —
Signage Drawings Update —
Addendum #5 Extension —
Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .