SF 30_Amd_0001.pdf

PDF 167 KB Posted

Attached to
Folsom Substation Upgrade
Solicitation number
89503321BWA000001
Issued by

About this file

This solicitation is for a competitive small business set-aside invitation for bid to upgrade equipment at the Folsom and Roseville substations near Sacramento, California. Work includes replacing and upgrading line jumpers, disconnect switches, fittings, hardware, and expansion tubes. The project value is estimated between $500,000 and $1,000,000. The performance period is near Sacramento with the Department of Energy listed as the agency. Interested parties must RSVP by July 14th to attend an optional site visit on July 21st. Questions are due by July 26th with bids due on August 9th. The successful bidder must be registered in the System for Award Management and have a current Online Representations and Certifications. The solicitation and drawings are only available electronically with no hard copies distributed.

View the file

Other files

File Type Posted
Updated Drawings_07_29_21.pdf PDF
Site Visit Attendance.pdf PDF
Attachment A-Bid Schedule.xlsx XLSX spreadsheet
Attachment D-SubmittalLog.pdf PDF
Attachment B-Specifications.pdf PDF
1442.pdf PDF
Attachment E- Wage Determination.pdf PDF
Attachment C-Drawings.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

89503321BWA000001

x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

FOLSOM CA 95630-4710

SNR

114 PARKSHORE DRIVE

SIERRA NEVADA CSR

US DOE/WESTERN AREA POWER

WAPA (SNR)

07/07/20210001

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

07/07/2021

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Brittaniya J. Poirier

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

07/07/2021 Signature on File

89503321BWA00001

Amendment 0001

The purpose of this amendment is to add WebEx meeting information for the bid opening, publish site visit attendance (separate attachment), and to publish answers to questions received.

A. The bid opening date remains unchanged. Due to the bid opening being closed to the public for safety reasons. Please see the below WebEx attendance information:

Folsom Substation Upgrade Bid Opening

When: Monday, August 9, 2021 12:00 PM Pacific Time (UTC-07:00)

Audio Connection:

Meeting number (access code): 199 668 8455

+1-415-527-5035 US Toll +1-929-251-9612 USA Toll 2

89503321BWA00001

Amendment 0001

Questions and Answers

Question 1: Attachment C, Drawings- Sheet 6 of 32, FOL 0001: YY4M/481 is clouded as work to be completed for this project. WY4T/485 is not clouded. Please confirm.

Answer: WY4T/485 should be clouded and YY4M/481 should be unclouded (same goes for sheet 4—no work on 481).

Question 2: Attachment C, Drawings - Sheet 11 of 32, FOL 1010-2: Switch in Bay Y4 is labeled WY4M. There are 2 switches labeled as WY4M on that plan sheet. Please confirm this is correct.

Answer: Yes, switch 485 should be labeled WY4T (existing installation, pg. 9).

Question 3: Whom is to supply connecting hardware (nuts and Bolts)?

Answer: Contractor shall supply connecting hardware (Nuts & Bolts).

Question 4: Why are there are no LD’s Listed?

Answer: The Contracting Officer determined that Liquidated Damages Rates will not be included in the project after considering the requirements.

Question 5: There is no mention of an Inspectors trailer-- will one be required?

Answer: No construction trailer required.

File details come from the government source that posted it. Updated .