J-1 DRFP PWS.pdf
PDF 484 KB Posted
- Attached to
- Orion Main Engine Federal contract opportunity
- Solicitation number
- 80JSC020OME
About this file
This is a draft request for proposal issued by NASA's Johnson Space Center to develop the Orion Main Engine to replace the repurposed Orbital Maneuvering System-Engine for Artemis missions. The contractor will be responsible for design, development, certification, production, and sustaining engineering of the engine. Key requirements include integrating the engine into the European Service Module, meeting performance and interface specifications, and following NASA and MPCV program standards for design, workmanship, qualification, and other technical and programmatic requirements associated with human rating. The contractor must allow NASA participation in technical reviews and provide data packages. Comments on the draft RFP are due by January 21, 2020.
View the file
Other files for this federal contract opportunity
Show all 20
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT J-1
December 19, 2019
PERFORMANCE WORK
STATEMENT
80JSC020OME
Draft Performance Work Statement
Table of Contents
1. INTRODUCTION
2. CONTRACT STRUCTURE
2.1. OME CERTIFICATION (CONTRACT LINE ITEM NUMBER (CLIN) 0001)
2.2. OME PRODUCTION PER UNIT (CLIN 0002)
2.3. SPECIAL TASKS AND STUDIES (CLIN 0003)
2.3.1. OME REQUIREMENTS CHANGE EVALUATION (SUB-CLIN 0003A)
3. RESERVED
4. PROJECT MANAGEMENT, SYSTEMS, PLANNING AND REPORTING
4.1. PROJECT MANAGEMENT PLAN
4.2. EXTERNAL RELATIONSHIPS: ESA AND ESA RELATED ENTITIES
4.3. INSIGHT/OVERSIGHT IMPLEMENTATION
4.4. INTEGRATED SCHEDULE MANAGEMENT
4.5. PROPERTY MANAGEMENT
4.6. INFORMATION TECHNOLOGY SECURITY MANAGEMENT
4.6.1. INFORMATION TECHNOLOGY MANAGEMENT
4.6.2. INFORMATION TECHNOLOGY (IT) SECURITY MANAGEMENT PROJECT COMPLIANCE
4.6.2.1. IT SECURITY PROJECT MANAGEMENT PLAN
4.6.2.2. IT SECURITY PLAN
4.6.2.3. EMPLOYEE IT SECURITY AWARENESS TRAINING
4.6.2.4. IT SECURITY ROLE BASED TRAINING
4.6.2.5. INFORMATION ON EMPLOYEES IN SENSITIVE POSITIONS/ASSIGNMENTS REPORTS
4.6.2.6. INTERNAL IT SECURITY PLAN AUDITS
4.6.2.7. IT SECURITY POINT-OF-CONTACT
4.6.2.8. IT CERTIFICATION AND ACCREDITATION
4.6.2.9. WIRELESS LOCAL AREA NETWORKS
4.7. RESERVED
4.8. RESERVED
4.9. CONFIGURATION MANAGEMENT
4.10. DATA MANAGEMENT
4.11. RISK MANAGEMENT
4.12. BUSINESS MANAGEMENT
5. OME INTEGRATION MANAGEMENT
5.1. MASTER VERIFICATION PLAN
5.2. FRACTURE CONTROL
5.3. ELECTRICAL, ELECTRONIC, AND ELECTROMECHANICAL PARTS MANAGEMENT
5.4. OME DESIGN DATABOOK
5.5. MODELS, SIMULATIONS, AND INTEGRATED SUPPORT PLAN
5.6. OME STRESS ANALYSIS REPORTS
5.7. ALTERNATE STANDARDS
6. ENGINE INTEGRATION SERVICES
7. OME CERTIFICATION AND ENGINE PRODUCTION MANAGEMENT
8. FORMAL MEETINGS AND REVIEWS
8.1. MEETINGS
8.1.1. OME QUARTERLY PROJECT MEETINGS
8.1.2. OME WEEKLY WORKING MEETINGS
8.1.3. OME WEEKLY INTEGRATION WORKING GROUP MEETINGS
8.2. TECHNICAL MILESTONE REVIEWS (OME CERTIFICATION)
8.2.1. CERTIFICATION MILESTONE 1 - SRR
8.2.2. CERTIFCATION MILESTONE 2 - PDR
8.2.3. CERTIFICATION MILESTONE 3 - CDR
8.2.4. CERTIFICATION MILESTONE 4 - DCR
8.3. TECHNICAL MILESTONE REVIEWS (OME PRODUCTION - DELIVERY)
8.3.1. PRODUCTION MILESTONE 1A – PRR #1
8.3.2. PRODUCTION MILESTONE 1B – PRR #2
8.3.3. PRODUCTION MILESTONE 2 – PRE-SHIP HAR
8.3.4. PRODUCTION MILESTONE 3 – POST-SHIP HAR
8.3.5. PRODUCTION MILESTONE 4 – PFAR
9. OME SYSTEMS ENGINEERING AND INTEGRATION
9.1. SYSTEM ENGINEERING & INTEGRATION MANAGEMENT AND ADMINISTRATION
9.2. REQUIREMENTS DEFINITION AND MANAGEMENT
9.3. INTEGRATION AND INTERFACES MANAGEMENT
9.4. OME INTEGRATED ANALYSIS
9.5. SPECIALTY ENGINEERING
9.5.1. NATURAL AND INDUCED ENVIRONMENTS
9.5.2. MICROMETEOROID AND ORBITAL DEBRIS ENVIRONMENTS
9.5.3. MATERIALS AND PROCESSES
9.5.4. ELECTRO-MAGNETIC INTERFERENCE/ELECTRO-MAGNETIC INTERFERENCE
9.5.5. EEE PARTS
10. SAFETY AND MISSION ASSURANCE
10.1. S&MA MANAGEMENT AND ADMINISTRATION
10.2. SYSTEM SAFETY
10.3. SAFETY AND HEALTH
10.4. RELIABILITY AND MAINTAINABILITY
10.5. HARDWARE QUALITY ASSURANCE
11. ORION MAIN ENGINE DESIGN, DEVELOPMENT, PRODUCTION AND SUSTAINING ENGINEERING
11.1. ENGINE DEVELOPMENT, ASSEMBLY, AND TEST
11.2. OME TEST AND VERIFICATION
11.2.1. OME VERIFICATION MANAGEMENT
11.2.2. OME HARDWARE CERTIFICATION TESTING
11.2.3. OME INTEGRATED TESTING WITH AVIONICS, POWER AND SOFTWARE
11.3. OME ASSEMBLY INTEGRATION AND PRODUCTION
11.4. OME SUSTAINING ENGINEERING
12. OME OPERATIONS
12.1. FLIGHT OPERATIONS
12.1.1. FLIGHT OPERATIONS PREPARATION AND EXECUTION
12.1.2. TRAINING
12.2. OME GROUND OPERATIONS
12.2.1. GROUND OPERATIONS PREPARATION AND EXECUTION
12.2.2. GROUND STORAGE
12.2.3. HANDLING AND TRANSPORTATION
12.2.4. FACILITIES AND FACILITY SYSTEMS
13. OME GROUND SYSTEMS SUPPORT EQUIPMENT
1. INTRODUCTION
This Performance Work Statement (PWS) and all exhibits and documents attached or referenced herein define the National Aeronautics and Space Administration (NASA) requirements for the Contractor to provide the Orion Main Engine (OME) that will replace the Orion Multi-Purpose Crew Vehicle (MPCV) Orbital Maneuvering System-Engine that was repurposed to support the Orion spacecraft on Artemis I through Artemis V. The contractor shall integrate the OME into the Orion primary power and propulsion component, the European Service Module (ESM).
The OME shall be integrated into the European Space Agency (ESA) supplied ESMs, which will constrain the OME within the existing ESM interface, performance, and functional requirements. The OME will be disposed of after each mission and will be designed, developed, built, and certified for flight consistent with NASA and MPCV/ESM program design, construction, workmanship, qualification standards, and other technical and programmatic requirements associated with human rating considerations. This includes configuration management, reliability analysis, and safety assessment processes. NASA will consider use of the OME Contractor company and/or industry standards so long a NASA agrees that these company and/or industry standards meet the intent of the standards contained in Attachment J-3, Applicable, Meet the Intent, Informational, and Tailored Documents List, as meet-the-intent documents.
NASA will provide access to detailed design information for components associated with OME to fulfill this PWS as defined in the clause entitled Government Furnished Services and Data. This includes hardware drawings, acceptance test procedures, test equipment designs and data for the contractor’s use in procuring these items. The Contractor shall perform all tasks necessary to ensure the delivery of safe reliable engines.
The Contractor shall provide the necessary services, test hardware and software, and engine specific elements required to certify, produce, and deliver the OME.
2. CONTRACT STRUCTURE
2.1. OME CERTIFICATION (CONTRACT LINE ITEM NUMBER (CLIN) 0001)
The Contractor shall perform design, development, test, and evaluation (DDT&E) activities and provide the required data for certification of the OME. The Contractor shall be responsible for the following four aspects of OME certification:
a. Design – The design activities will consist of a series of technical reviews to include a System Requirements Review (SRR), a Preliminary Design Review (PDR), a Critical Design Review (CDR), and a Design Certification Review (DCR). Design Analysis Cycles and a Verification Analysis Cycle should be aligned to support these technical reviews.
b. Engineering Development Unit (EDU) components that will ultimately be assembled into an EDU OME that will be hot fired to validate the functional and performance requirements of the engine. As a risk mitigation for the OME qualification test, qualification level environmental testing on the EDU components should be conducted to inform the development of the qualification engine.
c. Qualification – Qualification activities will consist of the procurement, buildup, and testing of the qualification engine components and fully assemble engine. Engine level environmental testing to qualification levels and a hot-fire test will be performed.
d. Certification – Certification activities will consist of the DCR and will lead to final certification of the engine design and associated support equipment.
Work associated with the OME Certification CLIN includes the work required to support the technical reviews (SRR, PDR, CDR, and DCR) as well as the associated data deliverables defined in Attachment J-2, Data Procurement Document, and delivered per Attachment J-2-A, DRD Submission Matrix, for the Submission Events of SRR, PDR, CDR, DCR, and any required Updates.
2.2. OME Production Per Unit (CLIN 0002)
The Contractor shall perform production activities and provide the required data for Government review and subsequent transfer of property accountability to NASA. The Contractor shall be responsible for the following four aspects of OME production:
a. Production Reviews - After authority to proceed for the production engines, a Production Readiness Review (PRR) will be held to ensure any changes to the OME design are incorporated and that the OME Contractor is ready to proceed with production. It is likely that DDT&E will run concurrent with production which will require the start of the first production lot shortly after PDR. In this eventuality, an initial PRR (PRR#1) should be held concurrent with PDR to give an authority to proceed with production long-lead procurements and then a final PRR (PRR#2) should be held concurrent with CDR to give an authority to proceed with full production. For future buys, only a single PRR will be held that combines the entrance and accomplishment criteria of PRR#1 and PRR#2.
b. Acceptance Test – An acceptance test will be performed on each engine. Engine level environmental testing to acceptance levels and a hot-fire test will be performed, then the engine will be decontaminated in preparation for shipment to the ESM integration site.
c. Pre-Ship Hardware Acceptance Review – Shortly after successful acceptance testing, a Hardware Acceptance Review (HAR) will be conducted. This Pre-Ship HAR will act as preliminary HAR in order for the Government to understand the scope of any open work both prior to shipment and leading up to the Post-Ship Hardware Acceptance Review. This Pre-Ship HAR will also serve as a Pre-Ship or Storage Review for the engine depending whether it will be shipped right away or will be stored for later shipment.
d. Post-Ship HAR – The scope of this review is twofold, disposition any and all open work documented in the Pre-Ship HAR and any new open work documented since the Pre-Ship HAR, and review the OME receiving inspection results after the hardware is received at the ESM integration. If the engine was in storage, then the Post-Ship HAR could also serve as a Pre-Ship Review. After successful completion of the Post-Ship HAR, the OME and associated property will be transferred to NASA via a DD Form 250.
For the first two flown missions, a Post-Flight Assessment Report (PFAR) shall be submitted per Attachment J-2, Data Procurement Document, and delivered per Attachment J-2-A, DRD Submission Matrix.
Work associated with the OME Production per Unit CLIN includes the work required to support the production reviews and reports (PRRs #1, PRRs #2, Pre-Ship HARs, Post-Ship HARs, and PFARs) as well as the associated data deliverables defined in Attachment J-2, Data Procurement Document, and delivered per Attachment J-2-A, DRD Submission Matrix, for the Submission Events of PRR #1, PRR #2, Pre-Ship HAR, Post-Ship HAR, PFAR, and any required Updates.
2.3. SPECIAL TASKS AND STUDIES (CLIN 0003)
The Contractor shall perform special studies and analyses, provide materials, fabricate incidental hardware in support of this contract, and/or store hardware as required. These tasks include advance planning and feasibility studies in support of future contemplated engines; development, fabrication, and test of hardware/software to support planning studies or special tests;
engine unique studies; material provision; and implementation of changes required due to changes in requirements as evaluated in sub-CLIN 0003A.
2.3.1. OME REQUIREMENTS CHANGE EVALUATION (SUB-CLIN 0003A)
The Contractor shall evaluate proposed requirement changes per the MPCV Change Request (CR) process as defined in MPCV 72523, Orion MPCV Program Configuration and Data Management Plan when reviewing CRs to the MPCV 72634, Orion MPCV Program OME PTRS. The OME Contractor shall only participate in the CR process for CRs that may impact the OME. The Contractor’s initial assessment shall be completed and returned within two (2) weeks from notification of the change and shall result in a determination of whether the change falls into Category A (no impact or administrative change only) or Category B (impact, further evaluation required). There are no further actions required from the Contractor for changes in Category A. For Category B changes, within four (4) weeks from change notification, the Contractor shall evaluate and respond with an impact of:
a. Whether the change can be implemented;
b. When the change can be implemented (at which OME the change goes into effect);
c. An impact assessment for which products would be affected; and
d. A qualitative Rough Order of Magnitude for implementation (minor, medium, major impact).
OME Storage (Sub-CLIN 0003C) In the event NASA delays the OME on-dock delivery date to the ESM integration site beyond the standard delivery window (60 days) in accordance with the clause entitled Adjustments to Engine Delivery Schedule, or the engine is ready to ship prior to the delivery date, the contractor shall arrange a bonded storage facility in accordance with SAE AS9100, Quality Management Systems – Requirements for Aviation, Space, and Defense Organizations. This effort shall include both electronic and paper document control, maintenance of OME, and control of secure physical access. The contractor shall perform inventory control validation and record keeping for OME certified hardware in accordance with SAE AS9100 standards, and assure all OME procedures for quality control testing are adhered to.
The Contracting Officer shall notify the Contractor in writing 60 days in advance of planned on-dock delivery date with an updated delivery date as required. The OME storage requirements will be procured via FFP task order. NASA reserves the right to determine, on an as needed basis, if there is a need to procure storage facilities using Sub-CLIN 0003C. If it is determined that the on-dock delivery date will be extended, the appropriate tier will be selected and both parties agree, a subsequent amendment to the FFP task order will be executed.
3. RESERVED
4. PROJECT MANAGEMENT, SYSTEMS, PLANNING AND REPORTING
Project Management includes development, implementation and maintenance of common Project management processes, systems and data deliverables to be utilized throughout the life of the contract.
4.1. PROJECT MANAGEMENT PLAN
The Contractor shall establish an organizational structure for the management, coordination, and control of contract activities including the Project’s cost, schedule, performance, risks, contracts, and subcontracts using as guidance ISO 14300-1, Space Systems - Project Management - Part 1: Structuring of a Project.
The Contractor shall develop and implement the Orion Main Engine Project Management Plan, DRD OME-M-001, which covers all aspects of Project management for the Orion OME Project including approaches for Government insight/oversight and integrated logistics. The MPCV 72008, Orion Multi-Purpose Crew Vehicle (MPCV) Program Plan provides information to help the contractor formulate the Project Management Plan.
The Contractor shall provide all program management functions required to deliver the OME to satisfy the engine requirements for each Artemis mission. The program management function of this contract shall provide insight to NASA for technical and programmatic activities performed under this contract.
The Contractor shall develop, maintain and implement a process to verify engine readiness. This auditable approach shall verify that all engine preparation responsibilities and requirements have been met and that all problems have been dispositioned prior to delivery. Prior to each property transfer of accountability to the Government via a DD Form 250, the Contractor shall certify engine readiness per the Pre-Ship and Post-Ship HARs.
Deliverables OME-M-001, Orion Main Engine Project Management Plan
4.2. EXTERNAL RELATIONSHIPS: ESA AND ESA RELATED ENTITIES
The Contractor shall establish cooperative relationships with ESA and ESA related entities to support the implementing arrangement between NASA and ESA for the development of the ESM.
The Contractor shall perform technical interactions with ESA and ESA related entities that are necessary for exchange of data, hardware, and software.
For the export of hardware, software, and data, the contractor shall comply with the United States export control regulations:
International Traffic in Arms Regulations, Title 22 Foreign Relations, Volume 1, Chapter 1, Parts 120-130, and
Export Administration Regulations, Title 15 Commerce and Foreign Trade, Volume 1, Subtitle B, Chapter VII, Subchapter C, Part 730-774.
It shall be the responsibility of the Contractor to seek and obtain Technical Assistance Agreements (TAAs) for technical interactions with any international partners as required.
These Contractor TAAs shall be approved by the State Department Directorate of Defense Trade Controls prior to contract award in accordance with the International Traffic in Arms Regulations.
For the export of hardware, NASA will be responsible for obtaining the export licenses for OME shipments.
4.3. INSIGHT/OVERSIGHT IMPLEMENTATION
The Contractor shall establish a partnership and working relationship between the Government and the Contractor, and the level of insight/oversight the Government will have into the Contractor activities in accordance with OME-M-001, Orion Main Engine Project Management Plan.
Deliverable OME-M-001, Orion Main Engine Project Management Plan
4.4. INTEGRATED SCHEDULE MANAGEMENT
The Contractor shall develop, maintain, and provide NASA access to an OME Integrated Master Schedule (IMS) in accordance with DRD OME-M-002, Integrated Master Schedule (IMS) and Schedule Deliverables.
Deliverable OME-M-002, Integrated Master Schedule (IMS) and Schedule Deliverables
4.5. PROPERTY MANAGEMENT
The Contractor shall manage the use, maintenance, repair, protection, and preservation of Government personal property, including initiating and maintaining the processes, systems, procedures, records, and methodologies necessary for effective and efficient control of government property.
The Contractor shall develop and implement a property management plan that covers all aspects of government property management in accordance with DRD OME-M-009, Government Property Management Plan.
Deliverables OME-M-009, Government Property Management Plan
4.6. INFORMATION TECHNOLOGY SECURITY MANAGEMENT
The Contractor shall protect the integrity, availability, and, confidentiality of the information resources transiting the interface between the Contractor, NASA, ESA, and ESA’s Contractor. The Contractor shall perform the following aspects of Information Technology (IT) Security Management.
4.6.1. INFORMATION TECHNOLOGY MANAGEMENT
The NASA Integrated Collaborative Environment (ICE) is the primary means of sharing, reporting, collecting, recording, and accessing Project information between NASA, the OME Contractor, subcontractors and authorized Government personnel connected with the Orion Program. ICE provides secure, real-time collaborative access to a single source of management information, product information, and technical data. ICE is the principal mechanism for integrating a project's digital information management environment.
The Contractor shall use ICE for delivery of all data unless data is defined as make-available.
The Contractor shall use the interactive collaborative configuration management and document management environments of ICE for configuration management of Orion MPCV Program directives and change control activities.
The Contractor shall comply with Attachment J-14, ICE Operating Environment.
The Contractor’s collaborative environment shall be available within 30 days of contract award.
The Contractor’s collaborative environment shall be updated with the Type 4 data requirement deliverables per Attachment J-2, Data Procurement Document and any other data required to be made available in this PWS.
The Contractor shall transmit non-data requirement deliverable information, such as week-to-week coordination, working level analysis, action item responses, etc., via a contractor-established data sharing system.
4.6.2. INFORMATION TECHNOLOGY (IT) SECURITY MANAGEMENT PROJECT COMPLIANCE
Contractors who purchase, lease, network to, or otherwise utilize Government-funded IT (Clinger-Cohen Act of 1996 and referenced by Office of Management and Budget (OMB) Circular A-130, Managing Information as a Strategic Resource) shall comply with NPR 2810.1A, Security of Information Technology.
4.6.2.1. IT SECURITY PROJECT MANAGEMENT PLAN
The Contractor shall submit DRD OME-M-004, Information Technology Security Management Project Plan for its unclassified IT resources. The Contractor’s IT Security Management Project Plan shall be compliant with Federal and NASA policies as referenced in OMB Circular A-130, Managing Information as a Strategic Resource and NPR 2810.1, Security of Information Technology.
4.6.2.2. IT SECURITY PLAN
The Contractor shall have an Information Systems Security Officer (ISSO) who is responsible for the Contractor’s system(s) in accordance with the definitions set forth in NPR 2810.1A, Security of Information Technology.
4.6.2.3. EMPLOYEE IT SECURITY AWARENESS TRAINING
Contractor employees performing work under this contract shall complete the NASA-provided IT Security Awareness Training annually. The Government shall track completion within Systems for Administration, Training, and Education Resources for NASA SATERN. Completion dates are issued annually by the Government with access repeal for non-completion. The IT Security Awareness Training is delivered via desktop workstation and takes approximately 1 hour to complete.
4.6.2.4. IT SECURITY ROLE-BASED TRAINING
Contractor employees performing work under this contract shall complete NASA role-based training in accordance with the NASA Information Technology Security Handbook, IT Security Awareness Training, ITS-HBK-2810.06-2B for the following roles: IT Security Manager, Information Security Officer, ISSO, and Organizational Computer Security Official Representative.
4.6.2.5. INFORMATION ON EMPLOYEES IN SENSITIVE POSITIONS/ASSIGNMENTS REPORTS
The Contractor shall provide information reporting annually for personnel screening as required by NPR 2810.1A, Security of Information Technology, and NPR 1600.1, NASA Security Project Procedural Requirements on position risk.
4.6.2.6. INTERNAL IT SECURITY PLAN AUDITS
The Contractor shall proactively protect sensitive data as defined by system IT Security Plans in accordance with DRD OME-M-004, Information Technology Security Management Project Plan.
4.6.2.7. IT SECURITY POINT-OF-CONTACT
The Contractor shall identify a point-of-contact that NASA may reach in its attempt to address IT and IT security issues. The point-of-contact shall have the authority to ensure appropriate actions occur.
4.6.2.8. IT CERTIFICATION AND ACCREDITATION
For IT systems delivered to NASA, the contractor shall develop and deliver systems following NFS 1852.204-76, Security Requirements for Unclassified Information Technology Resources.
4.6.2.9. WIRELESS LOCAL AREA NETWORKS
Wireless Local Area Networks (WLAN) requirements shall be applicable for systems on NASA facilities utilizing NASA wireless networks. The contractor shall meet the hosting Center’s requirements for WLAN implementation.
WLAN requirements shall meet the intent of the hosting Center’s WLAN requirements for wireless systems located on a NASA facility and utilizing the Contractor’s wireless network. WLAN requirements for wireless implementations on a contractor’s facility shall be based on the contractor’s existing policies and procedures to meet the intent of NPR 2810.1A, Security of Information Technology.
Deliverables DRD OME-M-004, Information Technology Security Project Plan
4.7. RESERVED
4.8. RESERVED
4.9. CONFIGURATION MANAGEMENT
The Contractor shall develop and implement Configuration Management (CM) processes and systems in accordance with DRD OME-M-001, Orion Main Engine Project Management Plan.
The Contractor CM process and system shall use SAE EIA-649-2, Technical Report, Configuration Management Requirements for NASA Enterprises.
The Contractor shall integrate the CM system across the OME Project, including modeling and simulation, engineering drawing development and release, manufacturing, test equipment and test articles, operations, and quality, as well as acquisition organizations, including customer and vendor CM systems.
The Contractor shall implement and maintain a configuration status accounting system that provides information defining, maintaining, and reconciling the As-Designed versus As-Built configuration of the hardware and software, including the status of changes to this configuration.
Deliverables DRD OME-M-001, Orion Main Engine Project Management Plan
4.10. DATA MANAGEMENT
The Contractor shall develop and implement Data Management (DM) processes and systems in accordance with DRD OME- M-001, Orion Main Engine Project Management Plan.
The Contractor DM process and systems shall use SAE GEIA859, Technical Report, Data Management as guidance.
The Contractor’s DM process and system shall implement the following functions: (1) data identification and definition, (2) data acquisition and preparation, (3) data control, (4) data status accounting and disposition, (5) data management verification and audits, and (6) data archiving.
The Contractor shall use the MPCV deliverables process for acceptance and release of contractor data, defined in MPCV 72523 Orion MPCV Program Configuration and Data Management Plan.
The Contractor shall integrate the DM system across the OME Project such as modeling and simulation, engineering drawing development, manufacturing, test equipment and test articles, operations, and quality, as well as acquisition organizations including customer and vendor DM systems to successfully complete Project acceptance and Certification of Flight.
Deliverables DRD OME-M-001, Orion Main Engine Project Management Plan
4.11. RISK MANAGEMENT
The Contractor shall identify, evaluate, manage, and control the safety, technical, cost, and schedule-related risks associated with all aspects of the OME Project in accordance with MPCV 72091, Orion MPCV Project Integrated Risk Management Plan.
Project risks will be reviewed at the OME Monthly Project Meeting. Due to the limited Government oversight, the contractor shall also status candidate risks starting at the first OME Monthly Project Meeting. These candidate risks are risks that if accepted will impact requirements or design and test of a safe and reliable engine.
4.12. BUSINESS MANAGEMENT
The Contractor shall provide their planned approach to small business subcontracting and their reporting against this plan per DRD OME-B-001, Small Business Subcontracting Plan.
The contractor shall provide an Organizational Conflicts of Interest Plan in accordance with DRD OME-M-012, Organizational Conflicts of Interest (OCI) Plan.
The Contractor shall identify all third-party proprietary information per Attachment J-25, Limited Right in Data and Restricted Computer Software.
Deliverables DRD OME-B-001, Small Business Subcontracting Plan DRD OME-M-012, Organizational Conflicts of Interest (OCI) Plan
5. OME INTEGRATION MANAGEMENT
5.1. MASTER VERIFICATION PLAN
The Contractor shall specify, produce and deliver integration testing assemblies and flight test articles necessary to develop the OME Master Test Plan in accordance with DRD OME-T-015, Master Verification Plan (MVP).
Deliverables DRD OME-T-015, Master Verification Plan (MVP)
5.2. FRACTURE CONTROL
The Contractor shall implement a fracture control program and identify fracture critical parts to protect against catastrophic structural hazards associated with flaw presence, fatigue crack propagation, and fracture. The Contractor shall develop, implement, and maintain the Fracture Control Plan, DRD OME-T-069, and deliver DRD OME-T-070, Fracture Control Summary Report.
Deliverables DRD OME-T-069, Fracture Control Plan DRD OME-T-070, Fracture Control Summary Report
5.3. ELECTRICAL, ELECTRONIC, AND ELECTROMECHANICAL PARTS MANAGEMENT
The Contractor shall develop and implement an Electrical, Electronic, and Electromechanical (EEE) parts plan that is required by MPCV 72634, Orion MPCV Program OME PTRS.
The Contractor shall develop, implement, and maintain DRD OME-T-027, Electrical, Electronic, and Electromechanical Management and Implementation Plan, and deliver DRD OME-T-028, As-Built EEE Parts List.
Deliverables DRD OME-T-027, Electrical, Electronic, and Electromechanical Management and Implementation Plan DRD OME-T-028, As-Built EEE Parts List
5.4. OME DESIGN DATABOOK
The Contractor shall document the engine and component design, operational limits, significant analyses, trade studies, and developmental testing performed to determine the engine and component design in the OME Design Databook, per DRD OME- T-071.
The Contractor shall document the engine passive thermal design details, analysis, operational limits, trade studies, developmental testing, and data to determine the engine and component design in the OME Design Databook, per DRD OME- T-071.
The Contractor shall collaborate with NASA and ESA, their suppliers, and their affiliated stakeholders to ensure successful coordination of the highly integrated ESM system on interface requirements, design, verification, testing, integration, and delivery logistics.
The Contractor shall provide analysis of OME performance for transient and steady-state conditions using a suitably anchored engine performance model, for the full range of operating conditions defined in MPCV 72634, Orion MPCV Program OME
PTRS.
Deliverables DRD OME-T-071, OME Design Databook
5.5. MODELS, SIMULATIONS, AND INTEGRATED SUPPORT PLAN
The Contractor shall develop and deliver thermal analytical models to support integrated Orion vehicle analyses per DRD OME-T-001, Models, Emulators/Simulators, Simulations.
The Contractor shall develop models to support integrated Orion loads and stress analyses. The Contractor shall deliver DRD OME-T-001, Models, Emulators/Simulators, Simulations, which will deliver and describe the mathematical models used in the engine and component loads and stress analyses.
Deliverables DRD OME-T-001, Models, Emulators/Simulators, Simulations
5.6. OME STRESS ANALYSIS REPORTS
The Contractor shall perform stress and fatigue analyses and document the results in DRD OME-T-062, Stress Analysis Report.
Deliverables DRD OME-T-062, Stress Analysis Report
5.7. ALTERNATE STANDARDS
The Contractor shall provide any alternate standard that will be implemented to meet the intent of the NASA standards listed in the Meet the Intent section of Attachment J-3, Applicable, Meet the Intent, Informational and Tailored Documents, and document the details in DRD OME-T-094, Alternate Standards.
Deliverables DRD OME-T-094, Alternate Standards
6. ENGINE INTEGRATION SERVICES
The Contractor shall ensure the safe integration and transport of the OME to the ESM integration site. The Contractor shall put in place and support an Integration and Operations process for all OME deliveries. The Contractor shall provide integration support for OME/ESM and perform analysis.
7. OME CERTIFICATION AND ENGINE PRODUCTION MANAGEMENT
The Contractor shall perform OME certification and engine production tasks in accordance with DRD OME-M-003, OME Work Plan.
Deliverables DRD OME-M-003, OME Work Plan
8. FORMAL MEETINGS AND REVIEWS
The intent of the formal reviews is to provide a forum for open dialog between NASA and the OME Contractor with respect to OME certification and production.
The Contractor shall send a review invitation to the NASA OME Project Manager, who will forward to the NASA OME team as required.
The Contractor shall make available to NASA the Review Item Description/Request for Action (RID/RFA) process at least 30 days prior to the SRR.
The Contractor shall submit a final electronic copy of the presentation material to NASA at least one (1) week before the review is held.
The Contractor shall provide minutes that include a list of attendees, agreements and action items resulting from each review to NASA within one week after the review; the payment milestone will not be considered complete until the minutes are provided and any actions identified as required to be completed for completion of the milestone are accomplished.
The Contractor shall maintain and update the action item developed during the review. The list shall include:
a. Closure Date
b. Action item description
c. Closure Plan
d. Assigned tracking number for each action item,
e. Person or organization responsible for completing the action,
f. Status of action (i.e., open, closed, or deleted).
8.1. MEETINGS
8.1.1. OME QUARTERLY PROJECT MEETINGS
During the task order performance period, the Contractor shall conduct OME Quarterly Project Meetings (OQPMs) with NASA, beginning at task order start, to report on the topics listed below:
a. The status, closure plan and schedule for remaining OME certification and production compliance tasks, or tasks to be repeated in the event of changes to the design baseline. This shall be the focus of the meeting when tasks are open.
b. The integrated schedule and status for all engines given authority to proceed.
c. Key schedule items from other contractor or international partners activities that may affect the technical, cost and schedule risk to NASA missions, such as, but not limited to, other program milestones, mission dates of other contractors utilizing test site, etc.
d. Schedule and technical risks, including risk statements, mitigation plans and mitigation schedules.
e. Summary status of the special task assignments (under CLIN003) that were started, in-work, or completed since previous review.
f. Action items from previous meetings and technical reviews, including their status, closure plan, and closure rationale.
The contractor shall publish minutes within one week of the meeting and make them available on the Contractor collaborative environment.
NASA will provide status of program direction at the meetings.
These meetings are expected to last no longer than 2.0 hours.
8.1.2. OME WEEKLY WORKING MEETINGS
The contractor shall provide input to the weekly NASA OME certification and engine production working meetings through delivery of the first two engines. For subsequent engine orders, the contractor shall provide input to the bi-weekly working meeting through the life of the contract, with a focus on working technical issues, forward planning, and contractual modifications, if applicable. The frequency of the meetings may increase if time-critical issues are identified and require expedited resolution. The meeting is intended to be a technical status and not a design review or additional technical panel.
The objective is to provide technical insight to engine activities and allow for early identification of risk items or changes required. These meetings are expected to last no longer than 1.5 hours per week and shall cover the following topics:
a. Requirements
1. At risk requirements – a listing of the requirements that are believed to be at risk of having a negative margin to its requirement. The expected values are to be derived from the best analysis/test data at the time and could change as new data is obtained.
2. Standards Baselining Status – a status progress made to obtain mutual agreement on alternate standards.
3. Open CRs – status of requirements CR under review. These CR could be either applicable to OME requirements or CRs against other program level requirements that OME is reviewing for impacts.
b. Design/Analysis
1. Completed design/analysis activities/results
2. Status of in-work design/analysis activities
3. Review of upcoming scheduled analysis
c. Test
1. Completed test activities/results (test activities are all test processes such as planning, testing, reporting, issue resolution)
2. Status of in-work test activities
3. Review of upcoming scheduled test activities
d. Issues
1. Open non-conformances
2. Hardware failures or test issues
3. Contractor approved changes to baselined standards/plans. Any changes to the baselined standards or plans baselined on the contract, made at a contractor review board (such as Fracture Control Board, Contractor Material Control Board, or EEE Parts Control Board) shall be listed along with any dissenting opinions. Any changes after baselining may require equitable adjustment of contract value.
4. Upcoming OME Safety Panel Reviews (either contractor Safety Review or NASA Safety Panel reviews).
e. Schedule
1. Impacts to near term schedule from above topics
f. Actions Item Review
1. Review of new actions
2. Status of in-work actions
Meeting minutes shall be assembled by the contractor covering items discussed, a brief discussion of topic discussions, decisions/agreements made, links to meeting presentation(s), and a link to the action item list. The Contractor shall post the minutes electronically no later than three working days after the meeting is held.
8.1.3. OME WEEKLY INTEGRATION WORKING GROUP MEETINGS
The contractor shall provide input to the weekly Integration Working Group that focuses on integration of the OME with the rest of the Orion vehicle. As the engine development proceeds, and actual engine performance is established, this forum will be used as an avenue to communicate topics pertinent to the propulsion sub-system, the ESM Integration Office, the Vehicle Integration Office, and the Safety community. The objective is to provide a forum to discuss technical subjects having potential impacts that span the engine interfaces to the rest of the spacecraft, determine actions needed to address the issues, and track those actions with the respective organization. These meetings are expected to average no longer than 2 hours per meeting, however, individual meeting lengths may vary due to the nature of the topic.
8.2. TECHNICAL MILESTONE REVIEWS (OME CERTIFICATION)
The certification and production milestone entrance criteria, accomplishment criteria, and applicable products are defined in the tables below. The entrance criteria are the minimum accomplishments that the OME Contractor shall fulfill prior to the respective technical milestone review. The accomplishment criteria are the specific accomplishments that the OME Contractor shall satisfactorily demonstrate to meet the objectives of the review so that the technical effort can progress further in the life cycle. The applicable products are the deliverables that the OME Contractor shall use to verify the accomplishment criteria was met.
The Contractor shall conduct technical reviews to status the end-to-end certification of the OME. The Contractor shall allow NASA to participate in reviews to allow NASA to assess the progress towards meeting the OME certification requirements.
The Contractor shall deliver review data packages to NASA for review per Attachment J-2-A, DRD Submission Matrix.
Data Requirement Documents (DRDs) delivered for technical milestones reviews (SRR, PDR, CDR, and DCR) identified in Attachment J-2, Data Procurement Document, shall be reviewable documents as part of the review data package at the associated review.
8.2.1. CERTIFICATION MILESTONE 1 - SRR
The OME SRR evaluates whether the functional and performance requirements defined for the engine are responsive to the project’s requirements and ensures the preliminary project plan and requirements will satisfy the end item deliverables. The SRR shall be completed before PDR and PRR#1. Table 1 shows the entrance criteria, accomplishment criteria, and applicable products for the SRR.
Table 1 SRR ENTRANCE AND ACCOMPLISHMENT CRITERIA AND PRODUCTS Entrance Criteria Accomplishment Criteria Applicable Products
1. A preliminary SRR agenda, success criteria, and instructions to the review board have been agreed to by the technical team, project manager, and review chair prior to the SRR.
2. OME products are ready for review at
The functional and performance requirements defined for the engine are responsive to the parent requirements and represent achievable capabilities
OME <Level> Requirements OME Specification and Drawing Trees OME Ground Support Equipment Requirements and Plans
The maturity of the requirements OME <Level> Requirements the maturity levels stated in the definition and associated plans is OME Data Specification and Drawing governing J2 submission matrix.
3. OME requirements are available to the cognizant participants prior to the review and are ready to be baselined after the review. Preliminary requirements allocation to the next lower level has been performed.
4. Other SRR work products have been made available to the cognizant participants:
a. Updated parent requirements (if required to be provided by NASA)
b. Risk management plan ready to be baselined after review comments are incorporated.
sufficient to begin the next phase. Trees OME Ground Operations and Logistics Requirements Document OME Ground Support Equipment Requirements and Plans
The project utilizes a sound process for the allocation and control of requirements throughout all levels, and a plan has been defined to complete the requirements definition at lower levels within schedule constraints
OME <Level> Requirements OME Specification and Drawing Trees OME Ground Operations and Logistics Requirements Document OME Ground Support Equipment Requirements and Plans Integrated Master Schedule
The interface requirements defined for the engine are responsive to the parent requirements and represent achievable capabilities.
OME <Level> Requirements OME Ground Operations and Logistics Requirements Document OME CAD models c.
d.
e.
f.
g.
h.
i.
j.
k.
l.
Updated risk assessment and mitigations.
Initial document tree and model structure.
Initial verification and validation method identified for each requirement.
Initial system safety analysis.
Other specialty discipline analyses, as required.
Updated schedule for the OME project implementation.
Initial Updated OME Ground Operations and Logistics Requirements Document and OME Ground Support Equipment Requirements and Plans System safety and mission assurance plan ready to be baselined after review comments are incorporated.
Preliminary engineering development assessment and technical plans to achieve what needs to be accomplished in the next phase.
Design and Construction standards have been identified and agreed upon by the NASA customer.
OME Interface Simulator Plan (Models, Simulations, and Integrated Support Plan)
Preliminary approaches have been determined for how requirements will be verified and validated.
Master Verification Plan
Major risks have been identified and technically assessed, and viable mitigation strategies have been defined
Risk Plan
TBD and TBR items are clearly identified with acceptable plans and schedule for their disposition
All items
Design and Construction standards have been agreed upon by the NASA customer.
Alternate Standards
8.2.2. CERTIFCATION MILESTONE 2 - PDR
The OME PDR demonstrates that the preliminary design meets all engine level requirements with a risk score of 1-10, based on the ESD Risk Scorecard found in Appendix C of ESD 10003, Exploration System Development Risk Management Plan, and within schedule constraints and establishes the basis for proceeding with detailed design. The PDR shall be completed between SRR and CDR and before PRR #1. Table 2 shows the entrance criteria, accomplishment criteria, and applicable products for the PDR.
Table 2 PDR ENTRANCE AND ACCOMPLISHMENT CRITERIA AND PRODUCTS Entrance Criteria Accomplishment Criteria Applicable Products
1. The project has successfully completed the previous planned milestone reviews, and responses and have been made to all RFAs and RIDs or a timely closure plan exists for those remaining open.
2. A preliminary PDR agenda, success criteria, and instructions to the review board have been agreed to by the technical team, project manager, and review chair prior to the PDR.
3. All planned lower level PDRs and peer reviews have been successfully conducted, and RID/RFA/Action Items have been addressed with the concurrence of the originators.
4. Programmatic products are ready for review at the maturity levels stated in the governing PWS/DRDs.
5. The following primary products are ready for review:
a. A preliminary detailed design that can be shown to meet requirements.
The top-level requirements—and any sponsor-imposed constraints—are agreed upon, finalized, stated clearly, and consistent with the preliminary design.
OME <Level> Requirements
The flow down of verifiable requirements is complete and proper or, if not, an adequate plan exists for timely resolution of open items.
OME <Level> Requirements OME Data Specification and Drawing Trees OME Ground Operations and Logistics Requirements Document OME Ground Support Equipment Requirements and Plans
The project schedule is credible and within project constraints
Integrated Master Schedule Schedule Risk Assessment
The preliminary design is expected to meet the MPCV 72634, Orion MPCV Program OME PTRS requirements (including interface requirements) with adequate margins at an acceptable level of risk to proceed with CDR.
OME Design Databook Risk Report Stress Analysis Report Models, Simulations, and integrated Support Plan
Definition of the technical interfaces (both external entities and between internal elements) is consistent with
OME <Level> Requirements OME Data Specification and Drawing Trees
b. Updated trending information from the OME Design Databook.
6. Other PDR technical work have been made available to the cognizant the overall technical maturity and provides an acceptable level of risk.
OME Ground Operations and Logistics Requirements Document OME Ground Support Equipment Requirements and Plans participants prior to the review: The project risks are understood and Risk Report
a. Component design specifications, have been credibly assessed, and Integrated Master Schedule with supporting trade-off analyses plans, a process, and resources exist Schedule Risk Assessment (SRA) and data, as required, that are ready to effectively manage them to be baselined after review S&MA (e.g.,, safety, reliability, S&MA Plan comments are incorporated. maintainability, quality, and EEE parts) FMEA/CIL
b. Updated risk assessment and have been adequately addressed in mitigation. preliminary designs and any applicable
c. Integrated Master Schedule (IMS) is ready to be baselined after review comments are incorporated.
d. Final OME Ground Operations and Logistics Requirements Document and updated OME Ground Support Equipment Requirements and Plans
e. Applicable technical plans that are ready to be baselined after review comments are incorporated (e.g., technical performance measurement plan, contamination control plan, parts management plan, Electromagnetic Interference/ Electromagnetic Compatibility (EMI/EMC) control plan, producibility/manufacturability program plan, quality assurance plan).
S&MA products (e.g., system safety analysis and failure modes and effects analysis) meet requirements, are at the appropriate maturity level for this phase of the program’s life-cycle, and indicate that the program safety/reliability residual risks will be at an acceptable level.
Technical trade studies are mostly complete to sufficient detail and remaining trade studies are identified, plans exist for their closure, and potential impacts are understood.
Presentation on Trade Study Results Status of Open Trades
TBD and TBR items are clearly identified with acceptable plans and schedule for their disposition.
Applicable to all Products
Preliminary analysis of the primary subsystems has been completed and summarized, highlighting performance and design margin challenges.
OME Design Databook Stress Analysis Report
f. Any new applicable standards that have been identified and all standards have been flowed to components and incorporated.
g. Updated safety plans.
h. Presentation of Phase I safety analyses
i. Initial engineering drawing tree.
j. Interface control documents that are ready to be baselined after review comments are incorporated.
k. Verification/validation plan that is ready to be baselined after review comments are incorporated.
l. Plans to respond to regulatory requirements, as required, that are ready to be baselined after review comments are incorporated.
m. Updated technical resource utilization estimates and margins.
n. Preliminary OME fit check with ESM performed.
o. Decontamination Plan, for removing hazardous material from the OME after ATP hot fire and prior to shipping to Bremen, Germany, has been negotiated and accepted by ESA and its prime contractor and ready to be baselined after review comments are incorporated.
Appropriate modeling and analytical results are available and have been considered in the design
Stress Analysis Report Models Simulations and Integrated Support Plan OME Vehicle Wiring Configuration, Identification, and Definitions Reports
Manufacturability has been adequately included in design.
OME Design Databook Manufacturing and Assembly Plan Fracture Control Plan
Forward work plan for physical interface compliance has been agreed upon.
8.2.3. CERTIFICATION MILESTONE 3 - CDR
The OME CDR demonstrates that the maturity of the design is appropriate to support proceeding with full-scale fabrication, assembly, integration, and test. CDR determines that the technical effort is on track to complete the flight and ground end item development and operations support to meet OME requirements within the identified schedule constraints. The CDR shall be completed between the PDR and CDR and before the PRR #2. Table 3 shows the entrance criteria, accomplishment criteria, and applicable products for the CDR.
Table 3 CDR ENTRANCE AND ACCOMPLISHMENT CRITERIA AND PRODUCTS Entrance Criteria Accomplishment Criteria Applicable Products
1. EDU hot-fire testing completed and test results analyzed and ready to be presented at review
2. The project has successfully completed the previous planned milestone reviews, and responses and have been made to all RFAs and RIDs or a timely closure plan exists for those remaining open.
3. A preliminary CDR agenda, success criteria, and instructions to the review board have been agreed to by the technical team, project manager, and review chair prior to the CDR.
4. All planned lower level CDRs and peer reviews have been successfully conducted, and RID/RFA/Action Items have been addressed with the concurrence of the originators.
5.…
This is the start of the file's text. The full file is on GovTribe.