SCR_Amendment_2.pdf

PDF 20 KB Posted

Attached to
NP-OZAR 10(2), Ozark National Scenic Riverways
Solicitation number
693C73-18-B-000013
Issued by

About this file

SCR Amended.

View the file

Other files

File Type Posted
ROBO_-NP-OZAR_10(2).ppt PPT presentation
Amendment_0003_5.3.2018.pdf PDF
Plans_Amendment_2.pdf PDF
Questions-Clarifcations_Amendment_2.pdf PDF
Amendment_0002_5.1.2018.pdf PDF
Amendment_0001,_4.26.18.pdf PDF
NP-OZAR_10(2)_Plans.pdf PDF
Bridge_Inspection_Report_STR_6640-005P_Alley_Spring.pdf PDF
NEPA_EA_Big_Spring_Bridge.pdf PDF
Bidder's_Qualifications_Form.doc DOC document
VETS-4212.pdf PDF
FP14_Eng.pdf PDF
Soils_and_Foundations_Report.pdf PDF
NEPA_CE_Alley_Spring_Bridge.pdf PDF
Utility_Investigation_Report.pdf PDF
IFB_Solicitation-NP-OZAR_10(2).pdf PDF
NEPA_CE_SHPO_Concurrence_Alley_Spring_Bridge.pdf PDF
SWPPP_draft.pdf PDF
NEPA_FONSI_Big_Spring_Bridge.pdf PDF
Subcontracting_plan.doc DOC document
Bridge_Inspection_Report_STR_6640-001P_Big_Spring.pdf PDF
Synopsis_02.08.18.pdf PDF
Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Amendment 2

SCR changes Page 1 of 1

Add the following to Subsection 612.03 of the Special Contract Requirements (J Pages), page J- 29:

Use ductile iron pipe for all portions of the sanitary sewer line except that installed by horizontal directional drilling. Use ductile iron pipe or submit high-density polyethylene pipe (HDPE) for approval in the portion of the sanitary sewer line installed by horizontal directional drilling. Submit shop drawings for the proposed connection to transition from ductile iron pipe to HDPE to the CO for approval.