Federal Highway Administration Eastern Federal Lands Highway Division

Bid Opening
for

Blue Ridge Parkway

PROJECT: NP-OZAR 10(2)

SOLICITATION NO. 693C73-18-B-000013

May 8, 2018 at 2:00 p.m.

Sterling, VA

FEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

BID OPENING for SOLICITATION NO. 693C73-18-B-000013, Project: NP-OZAR 10(2) May 8, 2018, 2:00 p.m. local time The total calendar days bid to complete all contract work must be completed within 360 Calendar days.

BIDDER’SBID TOTALSDAYSTOTAL PRICE
Emery Sapp & Sons, Inc

. SCHEDULE A (BASE):

$3,402,209.72

SCHEDULE B, GOVT. OPTION 1:

$271,134.00 SCHEDULE A – 320 Days

SCHEDULE B – 80 Days SCHEDULE A + SCHEDULE B $3,673,343.72

Kovilic Construction Company, Inc.
SCHEDULE A (BASE):

$4,027,172.00

SCHEDULE B, GOVT. OPTION 1:

$414,650.00 SCHEDULE A – 320 Days

SCHEDULE B - 80 Days SCHEDULE A + SCHEDULE B $4,441,822.00

Robertson Contractors, Inc.
SCHEDULE A (BASE):

$2,764,174.70

SCHEDULE B, GOVT. OPTION 1:

$284,484.00 SCHEDULE A – 320 Days

SCHEDULE B - 80 Days SCHEDULE A + SCHEDULE B $3,048,658.70

FEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

BID OPENING for SOLICITATION NO. 693C73-18-B-000013, Project: NP-OZAR 10(2) May 8, 2018, 2:00 p.m. local time The total calendar days bid to complete all contract work must be completed within 360 Calendar days.

BIDDER’SBID TOTALSDAYSTOTAL PRICE
Patrick Engineering, INC
SCHEDULE A (BASE):

$3,991,751.58

SCHEDULE B, GOVT. OPTION 1:

$247,914.90 SCHEDULE A – 320 Days

SCHEDULE B – 80 Days

SCHEDULE A + SCHEDULE B

$4,239,666.48 Engineer’s Estimate SCHEDULE A (BASE):

$3,200,000.00

SCHEDULE B, GOVT. OPTION 1:

$230,000.00 SCHEDULE A - 320 Days

SCHEDULE B – 80 Days

SCHEDULE A + SCHEDULE B

$3,430,000.00