AK BLM GFO 2019 (1) Sourdough Campground Bridge
Solicitation number
69056722B000023
Issued by

About this file

This document contains answers to technical questions regarding Federal Solicitation Number 69056722B000023 for the AK BLM GFO 2019 (1) Sourdough Campground Bridge project. The project involves replacing an existing bridge over Sourdough Creek in Alaska. Key details include that as-built plans for the existing bridge are unavailable, the temporary diversion channel is to divert creek flow during construction, and the project does not require an Alaska Fish Habitat Permit. Substantial completion is defined as completion of the new bridge, with final completion including removal of the temporary bridge. The document provides clarification to potential bidders on technical aspects of the project in response to their questions.

View the file

Other files

Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AK BLM GFO 2019(1)

Sourdough Campground Bridge

# General Technical Question Answer Date

1 X Do you have any as builts for the existing bridge?

As‐Builts are not available. See Physical

Data file named

FY20_SourdoughCGBridge_InspRpt

7_22_2020 final.pdf for existing conditions.

12/20/2022

2 X

What is the cable attached to the existing bridge? Electrical? Communications? And who is the owner?

Plan Sheet D.2 shows the existing utility lines in the vicinity of the bridge. See Sheet

A.3 for Plan Symbols and Abbreviations;

and see Subsection 107.02 for specifications regarding the utility relocation requirements for this project.

12/20/2022

3 X

How do the specifications for this project differ from those of the project previously bid on May

4, 2022?

Please submit bids according to the solicitation documents under this project re‐solicitation.

12/20/2022

4 X What is the purpose of the Temporary

Diversion Channel?

See callouts on Sheet E.1. 12/20/2022

5 X Is Sourdough Creek an Anadromous fish creek?

See last sentence under Regional Condition

G on Page H‐31.

12/20/2022

6 X

Will a State of Alaska, ADF&G Habitat Permit be required for this project? And, if so, have you acquired the permit?

The prescribed work does not require an

Alaska Fish Habitat Permit. Comply with the requirements of Subsection 107.01, and please submit bid according to the solicitation documents.

12/20/2022

7 X

There are several references to asphalt concrete in the specifications. Is asphalt concrete anticipated on this project?

No. 12/21/2022

8 X

575.04 Acceptance refers to minor bridge work

on the Gibbon River Bridge. I assume that is left over from another project.

This will be addressed under Amendment

A001.

12/21/2022

9 X

Substantial Completion is November 30, 2023

(though completing the bridge (concrete, grout) after early October will be very difficult with the freezing, sub‐zero temperatures), and final is November 11, 2024. What constitutes substantial completion on this project, completion of the new bridge, or completion of the new bridge and removal of the temporary bridge?

Substantial completion is defined at the top of FP‐14 Page 10.

12/21/2022