BidSum_AK BLM GFO 2019(1).pdf

PDF 95 KB Posted

Attached to
AK BLM GFO 2019 (1) Sourdough Campground Bridge
Solicitation number
69056722B000023
Issued by

About this file

This bid opening summary outlines the bids received in response to solicitation number 69056722B000023 issued by the Bureau of Land Management Alaska State Office. Five contractors submitted bids for the AK BLM GFO 2019(1) Sourdough Campground Bridge project, with prices ranging from $3,251,212 to $5,587,647.10. D&L Construction Inc. provided the lowest bid at $3,251,212, while the engineer's estimate was $2,468,448.25. The solicitation sought full and open competition for construction of a bridge as part of the Sourdough Campground located on federal land managed by the Department of Transportation Federal Highway Administration. Bids were due between January 9-13, 2023 and were publicly opened on the latter date with representatives from five contractors attending.

View the file

Other files

Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BID OPENING SUMMARY

Solicitation No. 69056722B000023 Bid Opening Date 01/13/2023 Time 2:00 p.m.

Project Name/Number: AK BLM GFO 2019(1), Sourdough Campground Bridge

OFFER RECEIVED

REC'D

BY

CONTRACTOR

DATE

TIME

Schedule A

1.

1/9/23 Mod

1/13/2023

7:42am Mod

1:23pm

AA

Mod

RW

Brice Civil Constructors

$5,587,647.10

2.

1/10/23 Mod

1/13/2023

12:15pm Mod

8:55am

AA

Mod

RW

D&L Construction Inc.

$3,251,212.00

3.

1/11/23 2:45 pm AA

Drennon Construction & Consulting, Inc.

$3,545,784.25

4.

11/12/23 9:59am AA HC Contractors, LLC $3,348,653.00

5.

6.

7.

8.

9.

Engineer’s Estimate

$2,468,448.25

LOW BIDDER'S

PHONE NUMBER: 907-262-6160

Attendance: 0

Bid Opening Officer: Andres Arredondo Assistant: Rebekah Webb