- RTU Replacement at 3rd PCT
- Solicitation number
- 550668
- Issued by
- Wayne County, Detroit City, Michigan
About this file
This is a price proposal template for HVAC replacement services at the Detroit Police Department's 3rd Precinct, prepared for the City of Detroit Office of Contracting and Procurement on behalf of the Construction and Demolition Department. The project involves design-build services for HVAC upgrades at 2875 West Grand Blvd., Detroit, Michigan 48202. The proposal is structured in two phases: Phase 1 covers design services including design and permit drawings and documentation with associated permit costs, plus any applicable awardee markup fees; Phase 2 encompasses construction items including markup fees, general conditions with specified duration, insurance and bond costs, and alternate pricing for three additional minisplits for information technology rooms with associated electrical work. The template requires bidders to provide fully burdened hourly labor rates for construction management personnel including project director, project manager, project superintendent, project engineer, project estimator, accounting, clerical, journeyman general contractor positions, and other specified labor categories.
All line items in Column B are designated as calculated fields that cannot be edited, indicating the template will automatically compute subtotals and totals based on values entered in other columns. Bidders are instructed to provide cost estimates and duration details for each line item, with particular attention to construction duration for general conditions and mobilization requirements. The alternate pricing option for IT room minisplits requires inclusion of electrical construction costs. This proposal template establishes the framework for evaluating and comparing qualified respondents' pricing for the HVAC replacement project.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| DPD 3rd Precinct HVAC Replacement Price Proposal - Attachment E | |||
| DO NOT EDIT ANY OF THE B COLUMNS - THESE ARE CALCULATED FIELDS | |||
| Phase 1: | |||
| Design Services Fee | Anticipated Duration/Hours | Comments | |
| A. Design and Permit Drawings and/or documentation | $ - 0 | - 0 | Include permit costs |
| Awardee Mark up Fee for Phase 1 if applicalbe and/or not included in A | $ - 0 | ||
| Phase 1 Sub Total: | $ - 0 |
| Phase 2: Construction | ||
| Items | Value - Costs | Comments |
| 1. Mark Up Fee | $ - 0 | if construction cost is approx. $400,000 |
| 2. General Conditions - specify duration | $ - 0 | Also, note the constructin duration of the GC's, This is to include mobilization and staffing. |
| 3. Insurance and Bond | $ - 0 | |
| 4. Alternate pricing #1 | $ - 0 | Price for 3 additional minisplits for IT rooms. Including electrical |
| Construction Manager's Project Personnel | *Hourly Rate* | *Provide Fully Burdened Labor Rates* |
| Project Director | $ - 0 | |
| Project Manager | $ - 0 | |
| Project Superintendent | $ - 0 | |
| Project Engineer | $ - 0 | |
| Project Estimator | $ - 0 | |
| Accounting | $ - 0 | |
| Clerical | $ - 0 | |
| Journeyman for General Contractor | $ - 0 | |
| Others: | $ - 0 | |
| Others: | $ - 0 | |
| Others: | $ - 0 | |
| Others: | $ - 0 | |
| Others: | $ - 0 |