This is an addendum (No. 001) to Request for Quotation 5-B176-Q-00304-00 issued by Argonne National Laboratory's Procurement Department on February 21, 2025, providing answers to technical questions about the required Plasma Enhanced Chemical Vapor Deposition (PECVD) System.
The addendum clarifies mandatory requirements including: the system must have a pressurized reactor design with an exterior chamber at a lower pressure than the process chamber; a hot wall PECVD reactor is required; dual frequency capability is mandatory; and the system must be capable of depositing various materials including SiO2, Si3N4, SiOCH, SiOF, SiC and aSi-H films. The document defines "maintenance-free" components as those without mechanical parts prone to clogging and requiring a hot wall for high-efficiency in-situ plasma cleaning to avoid manual cleaning. Offers must include signed acknowledgment of this addendum when submitting proposals.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Addendum and Acknowledgement 2.doc | DOC document | |
| ANL-70A Reps and Certs Short-04-FEB-2025.PDF | ||
| ANL-70 Request for Quotation.doc | DOC document | |
| Appendix D8C-12-DEC-2023.PDF | ||
| Appendix A-71COM-13-FEB-2023.PDF | ||
| PECVD SOW 2.13.25.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MOLLY MURTAUGH
Procurement Specialist 3 Office of the Chief Financial Officer
Procurement Department
Argonne National Laboratory
9700 South Cass Avenue, Bldg. 201
Lemont, IL 60439
(630)252-3094 mmurtaugh@anl.gov
02/21/2025
TO ALL OFFERORS:
Subject:
Request for 5-B176-Q-00304-00 No.
Addendum No. 001 Attached herewith for your information and use in preparing your proposal for subject project is one (1) copy of Addendum No.001.
Kindly acknowledge receipt of this Addendum by signing and returning one (1) copy of this letter and including this signed document with the completed Request for Quotation by the offer deadline.
Sincerely, MOLLY MURTAUGH
Procurement Specialist 3
Procurement Department
Receipt Acknowledged:
Company:
By:
cc:
File
CF
Addendum No.
TO
REQUEST FOR 5-B176-Q-00304-00
FOR
Argonne National Laboratory
BLDG. 201 OCF
9700 S. Cass Ave.
Lemont, IL 60439
02/21/2025 This addendum is being issued to incorporate the addition of questions and responses as follows:
1. Will a parallel-plate type PECVD system equipped with a vacuum loadlock chamber be acceptable? Would a loadlock system be acceptable because the reaction chamber has a much lower pressure than the loadlock due to a turbomolecular pump lowering the pressure?
A loadlock system alone is not sufficient. The system must have a pressurized reactor design with an exterior chamber at a much lower pressure than the process chamber to prevent contamination from entering the deposition zone.
2. Is hot wall PECVD reactor mandatory?
Yes.
3. Is pressurized reactor mandatory? Our reaction chamber is always under vacuum. The loadlock chamber is cycled between atmospheric pressure and vacuum for loading/unloading and transfer of wafer.
Yes, a pressurized reactor is mandatory.
4. Could you please specify what kind of film (materials) does your End-User wants to deposit using this system?
A wide range of materials including SiO2, Si3N4, SiOCH, SiOF, SiC and aSi-H films.
5. The RFQ states, “Maintenance-free pressure control system and maintenance-free PECVD reactor”. Can you please elaborate what this means?
"Maintenance-free pressure control system" means the system doesn't have mechanical components prone to clogging by deposits. "Maintenance-free PECVD reactor" means the reactor should have hot wall to enable high-efficiency of in-situ plasma cleaning so that the reactor does not require for manual cleaning.
6. For the acceptance criteria, is dual frequency required or optional for the depositions themselves?
Dual frequency is required.
7. Is uniformity within wafer (%) <+/- 3 measured by using the formula (max-min)/2/average?
Uniformity = ±[(max-min)/(max+min)]*100% over 5 points per wafer. Characteristics are measured on wafers with edge exclusion of 7 mm. Locations of measurement points are center, top, bottom, left right.
8. What are the deposition temperature requirements?
150 - 320 degree C.
U. S. Department of Energy laboratory managed by UChicago Argonne, LLC