This is a Request for Substitution Form for the Bidding Phase related to the Keystone Human Services Homes Remodel project in Pennsylvania, involving the Owner Keystone Service Systems and Architect Martina Bacarella Architect (Project Number 25020). The project encompasses the remodeling of three single-family houses located at 594 Warren Ave in Kingston, PA; 6 Valleyview Drive in Swoyersville, PA; and 137 Stucker Ave in Wilkes-Barre, PA to achieve ADA accessibility compliance. Prime bidders are permitted to request consideration of unnamed manufacturers, unnamed products, or alternative fabrication methods prior to bid submission through this formal substitution process. Substitution requests must be submitted electronically no later than 10 days prior to the bid opening date of June 16, 2026 at 10:00 a.m. A mandatory prebid meeting and site walkthrough is scheduled for May 26, 2026 at 10:00 a.m., beginning at 6 Valleyview Drive. The Architect will respond to bidder questions received until June 9, 2026.
Bidders requesting product or method substitutions must provide comprehensive documentation including point-by-point comparisons of specified versus proposed products, current independent third-party test data, product samples where applicable, material test reports from qualified testing agencies, ICC-ES research reports demonstrating building code compliance, and manufacturer certification that the substitute is equal to or superior to the specified product. The Architect will notify all bidders of approval of any proposed substitute through an Addendum to the Procurement and Contracting Documents. By submitting a substitution request, the bidder certifies that the proposed substitute meets or exceeds specified product performance, maintains equivalent warranties and maintenance service availability, does not affect contract time or the work of other trades, and provides comparable sustainable design properties. Bidders waive the right to additional payment or time extensions due to failure of the substitute to perform as represented.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
04/20/2026 Construction Documents Set
KHS Homes Remodel
REQUEST FOR SUBSTITUTION FORM,
BIDDING PHASE
002601 - 1
DOCUMENT 002601 - REQUEST FOR SUBSTITUTION FORM, BIDDING PHASE
PART 1 - GENERAL
1.1 SUMMARY
A. Prime Bidders: Use this form to request consideration of an unnamed manufacturer, an unnamed product, or an alternative fabrication method prior to submittal of bids when use of specific manufacturers, products, or fabrications methods are required by the Specifications.
B. This form is not required to be submitted when named products are introduced by the phrase "Available products include…" unless the intended product differs substantially from the requirements of the Contract Documents.
C. Response to this request by Architect will be in the form of a written response to the Bidder and, if approved, by Addendum issued to all Bidders.
D. Procurement Substitution Requests: Requests for changes in products, materials, equipment, and methods of construction from those indicated in the Procurement and Contracting Documents, submitted prior to receipt of bids in accordance with Instructions to Bidders.
E. Procurement Prior Approval Requests: Requests for approval of products or manufacturers from those required by the Contract Documents as defined by product selection procedures in Section 016000 "Product Requirements."
1. Procurement prior approval is required when products or manufacturers are listed in specifications under "Sole Product," "Sole Manufacturer," "Limited List of Products," or "Limited List of Manufacturers" introductory paragraphs.
2. Where use of "Sole Product," "Sole Manufacturer," "Limited List of Products," or "Limited List of Manufacturers" introductory paragraphs is not allowed by statute, procurement prior approval request is not required.
1.2 QUALITY ASSURANCE
A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage a qualified testing agency to perform compatibility tests recommended by manufacturers.
1.3 PROCUREMENT SUBSTITUTIONS
A. Procurement Substitutions, General: By submitting a bid, the Bidder represents that its bid is based on materials and equipment described in the Procurement and Contracting Documents, including Addenda. Bidders are encouraged to request approval of qualifying substitute materials and equipment when the Specifications Sections list materials and equipment by product or manufacturer name.
002601 - 2
B. Procurement Substitution Requests will be received and considered by Owner when the following conditions are satisfied, as determined by Architect; otherwise requests will be returned without action:
1. Extensive revisions to the Contract Documents are not required.
2. Proposed changes are in keeping with general intent of the Contract Documents, including level of quality of the Work represented by requirements therein.
3. Request is fully documented and properly submitted.
1.4 SUBMITTALS
A. Procurement Substitution Request: Submit to Architect. Procurement Substitution Request must be made in writing by prime contract Bidder only in compliance with the following requirements:
1. Requests for substitution of materials and equipment will be considered if received no later than 10 days prior to date of bid opening.
2. Submittal Format, Electronic: Submit Procurement Substitution Request, using format provided on Project web-based bidding management software site.
a. Identify the product or the fabrication or installation method to be replaced in each request. Include related Specifications Sections and Drawing numbers.
b. Provide complete documentation on both the product specified and the proposed substitute, including the following information as appropriate:
1) List of similar installations for completed projects, with project names and addresses as well as names and addresses of architects and owners.
2) Product data, including drawings and descriptions of products and fabrication and installation procedures.
3) Point-by-point comparison of specified and proposed substitute product data, fabrication drawings, and installation procedures.
4) Copies of current, independent third-party test data of salient product or system characteristics.
5) Samples where applicable or when requested by Architect.
6) Detailed comparison of significant qualities of proposed substitute with those of the Work specified. Significant qualities may include attributes such as performance, weight, size, durability, visual effect, sustainable design characteristics, warranties, and specific features and requirements indicated. Indicate deviations, if any, from the Work specified.
7) Material test reports from a qualified testing agency indicating and interpreting test results for compliance with requirements indicated.
8) Research reports, where applicable, evidencing compliance with building code in effect for Project, from ICC-ES.
9) Coordination information, including a list of changes or modifications needed to other parts of the Work and to construction performed by Owner and separate contractors, which will become necessary to accommodate proposed substitute.
002601 - 3
c. Provide certification by manufacturer that proposed substitute is equal to or superior to that required by the Procurement and Contracting Documents, and that its in-place performance will be equal to or superior to product or equipment specified in the application indicated.
d. Bidder, in submitting the Procurement Substitution Request, waives the right to additional payment or an extension of Contract Time because of the failure of substitute to perform as represented in the Procurement Substitution Request.
B. Architect's Action:
1. Architect may request additional information or documentation necessary for evaluation of the Procurement Substitution Request. Architect will notify all Bidders of acceptance of proposed substitute by means of an Addendum to the Procurement and Contracting Documents.
C. Architect's approval of substitute during bidding does not relieve Contractor of the responsibility to submit required Shop Drawings and to comply with all other requirements of the Contract Documents.
1.5 PROJECT INFORMATION
A. Project Name: KHS Homes Remodel.
B. Project Locations:
1. 594 Warren Ave, Kingston, PA.
2. 6 Valleyview Drive, Swoyersville, PA
3. 137 Stucker Ave, Wilkes-Barre, PA.
C. Owner: Keystone Service Systems.
D. Architect: Martina Bacarella Architect.
E. Architect Project Number: 25020.
1.6 BIDDING REQUEST INFORMATION
A. Bidder: ____________________________. Email: ____________________________.
B. Specification Section No.:
1.7 SPECIFIED PRODUCT
A. Specified Product/Fabrication Method (List Name, Description, Model Number, and Manufacturer):
002601 - 4
B. Specified Product Information (Attach Point-by-Point Data to This Form):
1. ▢ Point-by-point comparative product data.
2. ▢ Test reports.
3. ▢ Fabrication drawings.
4. ▢ Samples (where applicable).
1.8 PROPOSED PRODUCT
A. Specified Product/Fabrication Method (List Name, Description, Model Number, and Manufacturer):
B. Proposed Product Information (Attach Point-by-Point Data to This Form):
1. ▢ Point-by-point comparative product data.
2. ▢ Test reports.
3. ▢ Fabrication drawings.
4. ▢ Samples (where applicable).
1.9 IMPACT OF PROPOSED SUBSTITUTION
A. List of Related Changes Required by Substitution: ▢ None. Explain:
B. Differences between Specified Product and Proposed Substitution: ▢ None. Explain:
C. Proposed Product/Fabrication Method Effects on Other Parts of the Work: ▢ None.
Explain:
D. Proposed Product/Fabrication Method Effects on the Contract Time: ▢ None. Explain:
1.10 CERTIFICATION
A. Undersigned certifies the following:
1. Proposed substitution has been investigated by the Bidder and determined to be equal or superior to specified product as used for this Project, except as noted herein.
2. Qualifications of manufacturer, Installer, and other specified parties meet the specified qualifications.
3. Same warranty will be furnished for proposed substitution as for specified product, if applicable.
4. Same maintenance service and availability of replacement parts as for specified product, if applicable.
002601 - 5
5. Proposed substitution does not affect dimensions and functional clearances, except as noted herein.
6. Proposed substitution will not affect the Contract Time.
7. Proposed substitution will not affect work of other trades.
8. Proposed substitution provides comparable sustainable design properties as specified product, if applicable.
1.11 SUBMISSION OF REQUEST FOR SUBSTITUTION
A. For the Bidder:
1. Submittal Date:
2. Firm Name:
3. Submitted by:
4. Email:
B. For Manufacturer:
1. Submittal Date:
2. Firm Name:
3. Submitted by:
4. Email:
PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION (Not Used)
END OF DOCUMENT 002601