Summary of Work
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Summary of Work – Coburn Gore LPOE – Buildings Exterior and Site Improvements Page | 1
SUMMARY OF WORK
Coburn Gore Land Port of Entry
Miscellaneous Work at Coburn Gore LPOE and Residences 1, 2, 3 & 4
Coburn Gore LPOE – DHS/U.S. Customs and Immigration
Route 27, Coburn Gore Franklin County Maine
PART 1. PROJECT DESCRIPTION:
a. Residences 1,2,3,4 Asphalt Roofing Shingle Replacement (Base Bid)
b. Residences 1,2,3,4 Windows Replacement (Base Bid)
c. Residences 1,2,3,4 Exterior Doors Replacement (Base Bid)
d. Residences 2,3,4 Kitchen and Bathroom Renovations (Base Bid)
e. Main Port Facility Asphalt Roofing Replacement (Option 1)
f. Residences 1-2 Subsurface Wastewater Disposal System (Option 2)
g. Main Port Facility Embankment Stabilization (Option 3)
REMOVALS:
THE FOLLOWING ITEMS SHALL BE REMOVED FROM THE PROJECT SITE:
Unless specified otherwise, all removals and construction waste to be removed from the site and properly disposed of by the Contractor.
NEW WORK:
New Work is as indicated in this Statement of Work, Appendages, and Drawings.
1.02 QUALITY ASSURANCE:
All new materials and installations provided shall conform to the division one definitions. The quality of materials and finishes shall be new and without deficiency.
1.03 SUBMITTALS:
Prior to contract award, the contractor must submit to the Contracting Officer for approval, manufacturer data for all products and materials proposed for this project.
See requirements for access to site
Submittals required for:
a. Personnel requiring site access (all General Contractor and Subcontractor workforce)
b. Roofing (asphalt roofing shingles; ice and water membrane; roofing felt; drip edge)
c. Windows (including window size schedule showing type, dimensions, and location)
d. Exterior Doors (including door schedule showing type, dimensions, and location)
e. Kitchen Casework and Bathroom Vanity (including interior elevations, dimensions, and location)
f. Kitchen and Bathroom Plumbing Fixtures (including fixture schedule, make and model, and location)
g. As indicated in the specifications for Residence 1 Complete Renovation
h. Subsurface Wastewater Disposal System for design and system components ePM 45270 Miscellaneous Work at Coburn Gore LPOE and Residences 1,2,3, and 4 Page | 2
i. Embankment Stabilization for granite block handling and materials used
j. Asbestos Containing Materials (ACMs) remediation (including ACM remediation plan, disposal, testing)
1.04 WARRANTY:
In addition to any manufacturer’s warranty, all materials and equipment provided shall be warranted against defect in material and workmanship for a period of one (1) year from the date of final acceptance by the government.
PART 2. PRODUCTS:
All products and materials proposed for this project shall be commercially available first line products of a reputable manufacturer acceptable to the contracting officer (C.O.).
PART 3. HOURS OF WORK:
All work must be conducted between 7:00 am and 5:00 pm excluding weekends unless noted otherwise. All work, which may affect normal building operations including power interruptions, must be closely coordinated with the GSA Property Manager Access to secured areas must be coordinated with the GSA Property Manager. Security clearance will be required for all personnel working on this project. The GSA Property Manager contact information is as follows:
Chris Evans
Property Manager
U.S. General Services Administration
202 Harlow Street
Bangor, ME 04401
207-217-7518 christopherc.evans@gsa.gov
PART 4. CLEAN UP AND DEBRIS REMOVAL:
The contractor shall be responsible for the removal of all trash and debris generated during this project on a daily basis. Areas of the work will be swept, vacuumed, and policed. The contractor shall be responsible for the thorough cleaning of the space prior to final acceptance by the government. All areas of the work including traffic areas shall be protected from dirt, dust, debris, spills, and splatters during the project.
PART 5, BASE BID, OPTIONS, ALLOWANCES:
The Project consists of identified BASE BID Items, and, if accepted, OPTION Items Nos 1, 2, 3, 4. This bidding structure is devised to allow for the full potential of available funding while maximizing the fullest extent of Work.
BASE BID WORK SCHEDULE
Project ID Items a, b, c, d shown below represents the BASE BID for this Project. BASE BID Items pertain to Work Items indicated below for Project Items a, b, c for indicated new Roofing, Windows, and Exterior
Doors Work at Residences 1, 2, 3, 4; and Project Item d for indicated new Kitchen and Bathroom Renovations
Work at Residences 2, 3, 4:
ePM 45270 Miscellaneous Work at Coburn Gore LPOE and Residences 1,2,3, and 4 Page | 3
Project
Item Base Bid Work Item Description a Roofing – Residences 1,2,3,4 Asphalt Roof Shingle Replacement b Windows – Residences 1,2,3,4 Windows Replacement c Exterior Doors – Residences 1,2,3,4 Exterior Doors Replacement d Kitchen and Bathrooms
Renovations – Residences 2,3,4
Kitchen and Bathroom Renovations
SCHEDULE OF OPTIONS
Project Identification items e, f, g shown below represent BID OPTION Items for this Project. **See appended Specification Section 010350 - Options
Item Bid Option Work Item Description e Option 1 LPOE Main Port Facility Asphalt Roofing Shingle Replacement f Option 2 Residences 1-2 Subsurface Wastewater Disposal System Replacement g Option 3 LPOE Main Port Facility Embankment Stabilization
**It is the intent to select Options based on available funding.
ALLOWANCES
Allowances indicated in the Allowance Schedule below pertain to Project Items a and e and will be included in the Base Bid as they are related to Asphalt Roofing Shingle Replacement Work:
Unit of Base Bid
Quantity
Allowance No. and Description Work Intent Measurement Incl in Contract
1. Asphalt Roof Sheathing
Replacement
Replace existing deficient/rotted roof sheathing with new oriented strand board (OSB) roof sheathing of same thickness. Per sheet replacement.
Measured per roofing sheet
Each (32 SF) -
EA
(12) sheets
2. Asphalt Roof Sheathing
Replacement
Replace existing deficient/rotted
3/4"x 7" WP fascia/rake trim board with new in-kind to include (1) ct primer all sides,
(2) cts finish ext paint on exposed sides.
Measured per linear foot fascia/rake trim replaced - LF
(100) LF
** Bidders are note that there is no Government-furnished Labor, Materials, or Equipment on this Project.
PART 6, ACCESS TO SITE
For work at a Land Port of Entry (LPOE), the Contractor shall provide a list of all personnel requiring access to the site for a Fitness Determination (security check) at least 14 calendar days prior to their arrival at the site.
Information shall be sent directly to the Port Director via encrypted email. (do not send to the COR).
Information required shall be determined by the Port Director. Workers not acceptable to the Port Director will not be allowed on site.
ePM 45270 Miscellaneous Work at Coburn Gore LPOE and Residences 1,2,3, and 4 Page | 4
For all work, Workers (including LPOEs)
All personnel accessing the site (for work, delivery, inspection…) shall have “Real ID” such as a passport. A
State of Maine Driver’s License is NOT a Real ID.
Special Agreement Check (SAC) or Short‐Term Investigations:
The Contractor shall obtain fitness clearances from the Zone A
Non‐HSPD‐12 SACs are good for 6 months from the date of the SAC determination. Short‐term contractors must submit a completed CIW (Form 850) and OF 306 to Zonal Help Desk, then complete fingerprint enrollment. The CIW and OF 306 must be submitted together to the Zonal Help Desk via encrypted email.
Upon completion of a SAC, a contractor may work up to 6 months only. If additional work is required after the expiration date, a new investigation is required.
1. Contractor’s POC
a. Shall attend training provided by the Zonal Help Desk regarding the investigation process.
b. Initiate Requesting Official Approval List to include full legal names and associated information for all contractors who will be working on contract/project and sends it to requesting official for approval.
c. Assist contractors and subcontractors in completing all investigation requirements within time constraints.
d. Notify requesting official (via an updated RO Contractor Approval List) of anyone being added to contract/project and anyone leaving the contract/project. Ensures all GSA credentials are returned to the RO for those leaving the project or at the end of the project.
2. Vendor Applicant
a. Completes section 1 of the CIW.
b. Schedules and enrolls at Managed Service Office (MSO) station for fingerprints per enrollment email.
c. Completes OF 306, GSA 3665, and/or e‐QIP as applicable for the type of investigation requested.
Applicants are not allowed to work on the project until they receive a favorable SAC determination. They are not authorized to work past 6 months from the date of the SAC determination without completing an additional background check.
PART 7, NATIONAL REGISTER OF HISTORIC PLACES
The U.S. Customs Inspection Station (Coburn Gore LPOE), to include the Port Facility, the Residences, and property site, was published on the National Register of Historic Places on 9/10/2014. All work for this
Project will be done in accordance with National Park Service (NPS), Maine State Historic Preservation Office
(MeSHPO), and GSA historical standards. The selected Contractor will work with these offices and their representatives during the construction phase to achieve the standards outlined in this summary. The design and construction will be done in a manner that complies at all times with those standards. Where relevant within the Summary of Work and indicated in the notes on the drawings a specific type of material or product may be noted or called out in order to comply with the historical nature of this work for that particular architectural or site system. Replacement of failed or deficient building components will be done in manner where an acceptable product will be specified for use that complies with NPS, MeSHPO, and GSA standards to meet this purpose and any deviation from the standards is not permitted.
The GSA Regional Historic Preservation Officer (RHPO) contact information is as follows:
Liz Mees, RHPO
Architect
General Services Administration
Design and Construction Division
10 Causeway Street
Boston, MA 02222-1048
(617) 565-7282 elizabeth.mees@gsa.gov ePM 45270 Miscellaneous Work at Coburn Gore LPOE and Residences 1,2,3, and 4 Page | 5
PART 8, CBP OPERATIONS AND WORK COORDINATION REQUIREMENTS
The Coburn Gore LPOE is a compact site and construction activity will need to be coordinated with U.S.
Customs and Border Patrol (CBP) operational requirements during the construction duration. The Contractor will anticipate that Residences 2, 3, 4 will be occupied which will require that the work to be done in a manner that will pose the least impact on the Port operations and the CBP Staff. The Contractor will anticipate that
Residence 1 will not be occupied. Bid Option 1 - LPOE Main Facility Asphalt Roofing Replacement Work, if accepted, will require coordination of the selected Contractor of the work arrangement as to minimize impact on ongoing Land Port operations. Bid Option 2 - Replace Residences 1-2 Subsurface Wastewater Disposal
System Work, if accepted, will require coordination of the selected Contractor for temporary collection of wastewater from Residence 2 as the Residence is occupied. All temporary work required to accommodate the successful completion of Bid Option 2 work, including pumping and connection work, if accepted, will be included in the Option Price for the Bid Option 2 work. Given the nature of the proposed new work at occupied Residences 2, 3, and 4, it will be the intent of the Government to have available at least one (1) single
Residence with which all work can be done at one time prior to another Residence becoming available to the
Contractor for work.
PART 9, ASBESTOS CONTAINING MATERIALS (ACMs) SURVEY REPORT
An Asbestos Survey Report was conducted of Residences 1,2,3,4 in March, 2012. The findings were documented by the Federal Occupational Health Agency. A copy of the Federal Occupational Health
Agency’s Asbestos Survey is appended as Appendix A. For the purpose of this Project, under the BASE BID portion of the Work, anticipated encounter with asbestos containing materials (ACMs) will be in the window replacement portion of the work, specifically having to do with ACMs in certain locations of the 1/2” gypsum wall board that will be encountered with the replacement of the 3-1/2” wide interior trim around the windows
(Project Item b); ACMs in certain locations of the 1/2” gypsum wallboard that will be encountered with the replacement of the door trim (Project Item c). The ACM locations effected by the window and exterior door replacement work are indicated in ACM schedules found in their respective Project Items b, c. Project Item d involving Residences 2,3,4 Kitchen and Bathroom Renovations will have limited ACMs removal work mainly confined to those spaces and having to do with finish flooring in the Kitchens. The eventual selected
Contractor will be expected to procure the services of an asbestos abatement contractor licensed in the State of
Maine for ACM remediation for all ACMs identified in the FOH Survey Report that are impacted by new
Work. All costs relating to ACMs remediation will be included in their respective work task in the Base Bid
(Project IDs b, c, d).
PART 10, LIST OF DOCUMENTS AND APPENDIXES
The following documents comprise the Summary of Work for the Project:
Part 1 General
Part 2 Products
Part 3 Hours of Work
Part 4 Clean-up and Debris Removal
Part 5 Base Bid, Options, Allowances
Part 6 Access to Site
Part 7 National Register of Historic Places
Part 8 CBP Operations and Work Coordination Requirements
Part 9 Asbestos Containing Materials (ACMs) Survey Report
Part 10 List of Documents and Appendages: As indicated below and in Documents Enumeration this section:
- Project Items a, e Roofing Replacement Work: Base Bid (a) and Option 1 (e) a Residences 1,2,3,4 Asphalt Roofing Shingle Replacement scope of work (Base Bid) ePM 45270 Miscellaneous Work at Coburn Gore LPOE and Residences 1,2,3, and 4 Page | 6 e LPOE Main Port Facility Asphalt Roofing Shingle Replacement scope of work
Specification Section 07 31 13 Asphalt Roofing Specification
Drawings A401, A402, A403
- Project Item b Windows Replacement Work: Base Bid b Residences 1,2,3,4 Window Replacement scope of work (Base Bid)
Specification Section 08 52 13 Custom Epic Wood Window specification
Drawings A301, A302
- Project Item c Exterior Doors Replacement Work: Base Bid c Residences 1,2,3,4 Exterior Doors Replacement scope of work (Base Bid)
Specification Section 08 14 33 Stile and Rail Wood Doors
Drawings A301, A302
- Project Item d Kitchen and Bathroom Renovations Work: Base Bid d Residences 2,3,4 Kitchen and Bathroom Renovations scope of work with itemized products specifications (Base Bid)
Drawings A101, A102, A201, A202, A203
- Project Item f Residence 1-2 Wastewater System Work: Option 2 f Residence 1-2 combined subsurface wastewater disposal system scope of work
Drawing Coburn Gore LPOE Boundary and Utility Site Survey Drawing (location)
- Project Item g East-West Embankment Stabilization Work: Option 3 g LPOE Main Facility East and West Embankment Stabilization scope of work
- Appendixes:
Appendix A - Asbestos Survey Report, USBS Coburn Gore, Federal Occupational
Health Agency, March 26, 2012
Appendix B - Coburn Gore LPOE Residences 1,2,3,4; LPOE Main Facility; and Site combined Image Binder, Image Plates 1-10, Images 1-31, April, 2018.
Coburn Gore LPOE ME – Miscellaneous Buildings and Site Improvements
Documents Enumeration
Item Document Content
1 Summary of Work Pages 1-42
2 Base Bid Drawings: G001 Title Drawing (Base Bid and Options)
3 A101 Residences 1-2 Building Type Layouts
4 A102 Residences 3-4 Building Type Layouts
5 A201 Residence 2 Kitchen and Bath Plan and Interior Elevations
6 A202 Residences 3-4 Kitchen Enlarger Plan and Interior Elevations
7 A203 Residences 3-4 Bath Enlarged Plan and Interior Elevations
8 A301 Residences 1-2 Windows and Exterior Doors Plan and Schedules
9 A302 Residences 3-4 Windows and Exterior Doors Plan and Schedules
10 A401 Residences 1-2 Building Type Roof Plan
11 A402 Residences 3-4 Building Type Roof Plan
12 Option Drawings: A403 LPOE Main Port Facility Roof Plan (Option No. 1)
13 Site Boundary Drawing LPOE Boundary Survey Drawing (Option No. 2)
14 C101 Existing Conditions Plan (option No. 3)
15 C120 Existing Conditions West Embankment Enlarger Plan (Option No. 3)
16 C121 Existing Conditions East Embankment Enlarged Plan (Option No. 3)
17 C201 Proposed Plan (Option No. 3) ePM 45270 Miscellaneous Work at Coburn Gore LPOE and Residences 1,2,3, and 4 Page | 7
18 C221 Proposed West Embankment Enlarged Plan (Option No. 3)
19 C222 Proposed East Embankment Enlarged Plan (Option No. 3)
20 C501 Details, Schedules (Option No. 3)
21 Appendix A - FOH Asbestos Survey Report
Pages 1-57 including Title, Contents, Report, Attachment
22 Appendix B - Image Binder Pages 1-10, Images 1-31 ePM 45270 Miscellaneous Work at Coburn Gore LPOE and Residences 1,2,3, and 4 Page | 8
SECTION 010350 - OPTIONS
PART 1 - GENERAL
1.1 DESCRIPTION OF REQUIREMENTS
A. Definition: An option is an amount proposed by Bidders and stated on the Bid Form that will be added to Base Bid amount if the Government decides to accept a corresponding change in either scope of work or in products, materials, equipment, systems or installation methods described in
Contract documents.
1. Government acceptance of the change shall constitute the “exercise” of the option.
2. The Government shall have sole discretion as to whether to exercise the option or not and shall bear no liability to the bidder for the exercise or non-exercise of the option so long as the decision is made on or before the “Deadline for Acceptance.”
B. Deadline for Acceptance: The options, if exercised, shall be exercised in writing not later than the number of calendar days specified for each Option Period.
C. Performance Period: Should the Government exercise any or all of the options, the work included in each option shall be performed concurrently with the base contract work. There shall be no extension in contact performance time with the exercise of any or all of the options.
D. Coordination:
1. Coordinate related work and modify or adjust adjacent work as required to ensure that work affected by each option is complete and fully integrated into the project.
2. All bidders shall provide a price for each option in the place provided on the Bid form.
3. Include as part of each option, miscellaneous devices, appurtenances and similar items incidental to or required for a complete installation whether or not mentioned as part of the option.
4. Include as part of the price of each option all costs attributable to project Contract Clauses, Division 1 requirements, overhead and profit. No additional payments will be made by the
Government for the work of any Option which is exercised beyond the option Price listed, except in accordance with contract provisions related to Changes in the Work.
1.2 SCHEDULE OF OPTIONS:
Project Identification items e, f, g shown below represent BID OPTION Items for this Project.
ID Bid Option No. Item Description e Option No. 1 Main Port Facility Asphalt Roofing Replacement f Option No. 2 Residence 1-2 Subsurface Wastewater Disposal System Replacement g Option No. 3 Main Port Facility East and West Embankment Stabilization ePM 45270 Miscellaneous Work at Coburn Gore LPOE and Residences 1,2,3, and 4 Page | 9
Option No. 1 – Main Port Facility Asphalt Roofing Replacement
A. Main Port Facility asphalt roofing shingle replacement to include all roof sections on the Main
Building, and connected Garage and Inspection Bay. Option No. 1 Work will involve the removal of existing asphalt roofing shingles and felt paper down to the roof deck, installation of an ice and water membrane, a new single layer of asphalt roofing shingles, starter course shingles, ridgevent and shingle cap, new vent piping boots, sealant, disposal and removal of removed materials, and any and all work necessary for a complete finished product to include administrative and other requirements considering safety requirements, coordination, and quality assurance. See pertinent Summary of
Work Section e. and Drawings for Work specifications and requirements.
B. Option Period: The Government shall have 30 calendar days to exercise this option after the Notice to Proceed for the base contract is received by the Contractor.
C. The work of this option shall be started no later than 3 calendar days after the receipt by the
Contractor of the Government’s exercise of the Option.
1. The Contractor shall coordinate all work of the base bid with the work of the Option so as to expedite the work of the project.
2. An extension of the contract period will be negotiated with the Contractor upon Government acceptance of the Bid Option.
ePM 45270 Miscellaneous Work at Coburn Gore LPOE and Residences 1,2,3, and 4 Page | 10
Option No. 2 – Residence 1-2 Subsurface Wastewater Disposal Field Replacement
A. Residences 1 and 2 have a combined surbsurface wastewater disposal system located on site behind the two Residences. The location of existing subsurface wastewater disposal field is located approximately as shown on the LOE Boundary Survey Drawing that is made part of these documents.
Option No. 2 Work will involve the temporary pumping of the existing septic tank through the construction period, permanent separation and effective decommissioning from and of the existing holding structures, the design and installation of a new pumped subsurface wastewater disposal system for combined Residences 1 and 2, new system structures with pumping systems complete to include structures (wet well, velocity reducing structure, flow disbution), duplex pumps, hardware, electrical, instrumentation, alarms, and sanitary piping connections to the new system, disposal and removal of removed materials, and any and all work necessary for a complete finished product to include administrative and other requirements considering safety requirements, coordination, State of
Maine reporting requirements, and quality assurance. See Summary of Work Section f. and referenced boundary survey drawing for Work specifications and requirements.
B. Option Period: The Government shall have 30 calendar days to exercise this option after the Notice ePM 45270 Miscellaneous Work at Coburn Gore LPOE and Residences 1,2,3, and 4 Page | 11
Option No. 3 – Main Port Facility East and West Embankment Stabilization
A. Option No. 3 Work will involve any and all new work as outlined in the Appendix B as made of these dcuments entitiled East and West Embankment Stabilization. The intent of the Work under this
Option involves new stormwater drainage, existing granite block repositioning, granite curbing and bituminous pavement, and associated rock and stone installations necessary for a complete finished product to include administrative and other requirements considering safety requirements, coordination, State of Maine reporting requirements, and quality assurance. See Summary of Work
Section g. and Drawings for Work specifications and requirements.
B. Option Period: The Government shall have 30 calendar days to exercise this option after the Notice
END SECTION
ePM 45270 Miscellaneous Work at Coburn Gore LPOE and Residences 1,2,3, and 4 Page | 12
a. Residences 1,2,3,4 Asphalt Roof Shingle Replacement (Base Bid)
e. Main Port Facility Asphalt Roofing Replacement (Option 1)
1. Scope of Work for this portion of the Project is for the replacement of existing asphalt roofing shingles at locations as indicated in the Base and Option Work Schedules. The Base Bid Work locations are
Residences 1,2,3,4; and Bid Option 2 pertains to asphalt roofing replacement at the Main Port Facility
Building. The Scope will include the removal and disposal of existing roofing shingles and other roofing materials being replaced; refastening of loose existing roof sheathing as required; installation of new drip edge flashing; installation of new ice and water membrane (bitumastic membrane) at locations of the roof as indicated on the drawings; install 15# roofing felt; new rubber boots (for sanitary and vent piping penetrations); new 3-tab asphalt roofing shingles; new ridge vent; and new shingled ridge vent cap. It is felt that condition of the existing roofing, fascia and rake trim boards are in fair condition, however, where necessary, the replacement of any deficient roof sheathing, fascia, or rake trim, will be done with approval using the Allowances set forth in the Allowance Schedule in Part
5 of this Statement of Work.
2. Specification. See appended Section 07310 Asphalt Shingles.
3. Removal and Disposal: Removal and disposal of existing asphalt roofing shingles along with existing felt paper, plumbing vent boots, ridge cap and ridge vent. Dispose of any and all construction debris and removed materials in a proper manner. **The Bidder must anticipate that there (2) courses of existing roofing shingles on Residences 1,2,3,4 and the Main Port Facility. The intent of the roofing shingles removals work is to remove all existing roofing shingles and roofing felt down to the roof sheathing (existing roof deck).
4. Protect or temporarily remove and reinstall existing gutters as required for new Work.
5. Contractor to verify all roof dimensions, penetrations, existing roof sheathing thickness, and existing conditions relevant to the scope of the roofing work prior to bidding for all conditions where it can be reasonably determined prior to the bid.
6. Contractor to be responsible for temporary roof covering as required for the protection of the structure against any roof leaks during the construction period.
7. Replace any deficient roof sheathing as required. This work will be paid for in accordance with the
Allowance Price stated by the Contractor. The basis of the work will be to replace (if required) any deficient roof sheathing on an entire sheet basis (32 SF) with new OSB roof sheathing to match existing thickness, “H”-clips at all unsupported edges, and sheathing manufacturer approved fasteners.
8. Replace any deficient or rotted fascia or rake trim as required. This work will be paid for in accordance with the Allowance Price stated by the Contractor. The basis of the work will be to replace (if required) existing rotted fascia, 3/4”x 7”, western pine, primed all sides with exterior primer, (2) coats exterior finish paint to match existing on exposed sides.
9. Install new ice and water shield equal to Grace Ice and Water Shield, 40-mil thickness, at eaves, rakes, ridge, and at all roofing penetrations as shown on the drawings. Do not install around chimney. (2)-courses at each eave with a 6” overlap, and a single course at the rakes and on each side of ridge. At roof penetrations install a 24”x 24” piece of the specified ice and water membrane with circular section removed representing the diameter of the penetrating object and apply directly to the roof sheathing.
10. Install new galvanized drip edge 1-1/2”x 2-1/4”, 26 ga., min. 10’ long sections, equal to product as manufactured by Union Corrugating Company.
11. Refasten loose existing sheathing to remain with sheathing manufacturer recommended fasteners.
12. Install asphaltic saturated 15# roofing felt equal to GAF 15 Felt.
13. Install new plumbing vent stack rubber boots, of counter flash design, with stainless steel strap.
14. Install new 3-Tab fiberglass asphalt roofing shingles equal to Certainteed, XT30 IR, Class A, meeting
ASTM D3462, 30-year warranty, 230#/SQ, and full wind rating for Project area that conforms to code.
Shingle color to be selected from manufacturer’s full selection.
15. Install new ridgevent equal to AirVent Shinglevent II, min 18.0 sq in/LF NFA, baffle design, maximum lengths, Class A FR.
ePM 45270 Miscellaneous Work at Coburn Gore LPOE and Residences 1,2,3, and 4 Page | 13
16. Install ridge cap with shingles matching the make and manufacturer of the new roofing shingles.
17. As part of this Roofing Replacement Work existing metal exhaust fan vents mounted on the roof at each Residence 1, 2, 3, 4, will be removed, the penetration opening infilled, the metal exhaust duct rerouted to the exterior soffit under the attic space insulation, and vented to a new aluminum soffit vent grille. There is one (1) existing metal duct per Residence roof.
18. Temporarily support satellite dish(s) (typical) during new roofing work and coordinate its repositioning with the Satellite Dish Company. Satellite dish company site visit cost for dish repositioning to be made incidental to new roofing work and Base Bid.
Existing metal exhaust vent that will be relocated to the soffit (see Item 18 this section). The vent exhausts air from the Bathroom.
Temporarily remove and support existing satellite dish. Coordinate with satellite dish company. (see Item 19 this section)
Existing metal eave flashing to be removed.
New metal eave flashing shall comply with part
2.10, A., of the roofing specifications, 07310.
Residence 3 rear elevation view of existing roofing shingles, exterior windows, and exterior door. Temporarily remove and reinstall existing gutter system to include downspout, and reseal gutter seams with approved silicone or copolymer sealant (typical)
Residence 3 front elevation view of existing roofing shingles, exterior windows, and exterior door. Residence 4 end elevation can be seen in the background.
ePM 45270 Miscellaneous Work at Coburn Gore LPOE and Residences 1,2,3, and 4 Page | 14
SECTION 07 31 13
ASPHALT ROOFING SHINGLES
PART 1 GENERAL
1.1 SECTION INCLUDES
A. Removal of existing roofing.
B. Ventilated roof insulation panels.
C. Asphalt roofing shingles.
D. Leak barrier and moisture shedding roof deck protection.
E. Underlayment.
F. Metal flashing associated with shingle roofing.
G. Attic ventilation and ventilation accessories.
1.2 REFERENCES
A. AC438-1011-R1 - New Acceptance Criteria for Alternative Asphalt Roofing Shingles
B. American Society of Civil Engineers (ASCE): ASCE 7 - Minimum Design Loads for Buildings and Other Structures.
C. Asphalt Roofing Manufacturers Association (ARMA).
D. ASTM International (ASTM):
1. ASTM D 3018 - Standard Specification for Class A Asphalt Shingles Surfaced with Mineral
Granules.
2. ASTM D 3161 - Standard Test Method for Wind-Resistance of Asphalt Shingles (Fan-Induced
Method).
3. ASTM D 3462 - Standard Specification for Asphalt Shingles Made from Glass Felt and
Surfaced with Mineral Granules.
E. ENERGYSTAR.
F. National Roofing Contractors Association (NRCA).
G. Underwriters Laboratory (UL)
1. UL 790 - Tests for Fire Resistance of Roof Covering Materials.
2. UL 997 - Wind Resistance of Prepared Roof Covering Materials.
1.3 DEFINITIONS
A. Roofing Terminology: Refer to ASTM D1079 and the glossary of the National Roofing Contractors Association (NRCA) Roofing and Waterproofing Manual for definitions of roofing terms related to this section.
1.4 SUBMITTALS
A. Submit under provisions as outlined in the Summary of Work, Part 1, Section 1.03 Submittals.
B. Product Data: Manufacturer's data sheets on each product to be used, showing compliance with ePM 45270 Miscellaneous Work at Coburn Gore LPOE and Residences 1,2,3, and 4 Page | 15 requirements.
C. Installation Instructions: Manufacturer's installation instructions, showing required preparation and installation procedures.
1.5 QUALITY ASSURANCE
A. Installer Qualifications: Installer must be approved by manufacturer for installation of all roofing products to be installed under this section.
1.6 REGULATORY REQUIREMENTS
A. Provide a roofing system achieving an Underwriters Laboratories (UL) Class A fire classification.
B. Provide a roofing system achieving an ENERGYSTAR rating.
C. Install all roofing products in accordance with all federal, state and local building codes.
D. All work shall be performed in a manner consistent with current OSHA guidelines.
1.7 DELIVERY, STORAGE, AND HANDLING
A. Store products in manufacturer's unopened labeled packaging until ready for installation.
B. Store products in a covered, ventilated area, at temperature not more than 110 degrees F (43 degrees C); do not store near steam pipes, radiators, or in sunlight.
C. Store bundles on flat surface to maximum height recommended by manufacturer; store rolls on end.
D. Store and dispose of solvent-based materials, in accordance with requirements of local authorities having jurisdiction.
1.8 WEATHER CONDITIONS
A. Proceed with work only when existing and forecasted weather conditions will permit work to be performed in accordance with roofing shingle manufacturer's recommendations.
1.9 WARRANTY
A. Provide manufacturer's standard limited warranty:
1. Provide to GSA a shingle life duration Warranty.
a. Warranty Duration: 30 years.
PART 2 PRODUCTS
2.1 MANUFACTURERS
A. Acceptable Manufacturer: Certainteed or equal.
2.2 SHINGLES
A. Certainteed. XT30 IR, or equal:
1. 3-tab asphalt shingle with back surface reinforcement meeting UL 2218 Class 4 IR rating.
ASTM D3018, Type I. ASTM D3462.
2. UL 790 Class A rated with ASTM E108 Class A Fire Resistance. UL 997 with ASTM D 3161
Class F Wind Resistance and D 7158 Class H Wind Resistance, and UL 2390/ASTM D6381 Class H Wind Resistance. TDI Windstorm Resistance.
3. ICC-ES Evaluation Report ESR-1389.
ePM 45270 Miscellaneous Work at Coburn Gore LPOE and Residences 1,2,3, and 4 Page | 16
2.3 RIDGE CAP SHINGLES
A. High profile self-sealing hip and ridge cap shingle matching the color of selected roof shingle.
B. Ridge cap shingles must be compatible dimensionally with the approved ridge vent.
2.4 STARTER STRIPS
A. Install self-sealing starter shingles in accordance with the manufacturer’s instructions.
2.5 ICE AND WATER BARRIER
A. Self-adhering, self-sealing, high density, cross laminated polyethylene film coated with rubberized asphalt adhesive layer, bituminous ice and water barrier (membrane) equal to Grace Ice and Water Shield as manufactured by WR Grace.
B. 40-mil thickness.
C. Tensile strength: 250 psi.
D. Elongation: 250%.
E. Permeance: 0.05 perms.
2.6 UNDERLAYMENT
A. #15 Roofing Underlayment: Water repellent breather type cellulose fiber building paper. Meets or exceeds the requirements of ASTM D 4869 Type I.
B. Synthetic, interwoven, non-asphaltic, equal to Tri-Flex XT as manufactured by GCP.
2.7 ROOFING CEMENT AND SEALANT
A. Asphalt Plastic Roofing Cement meeting the requirements of ASTM D 4586, Type I or II.
B. Roofing cement equal to Geocell 2300 Tripolymer roofing sealant.
2.8 ATTIC VENTILATION
A. Ridge Vents:
1. Flexible rigid plastic ridge ventilator designed to allow the passage of hot air from attics, while resisting snow infiltration, baffle-type design, minimum 18.0 square inches net free air (NFA) per linear foot, and equal to Shinglevent II FR as manufactured by Air Vent Inc.
2.9 FASTENERS
A. Nails: Standard round wire, zinc-coated steel or aluminum; 10 to 12 gauge, smooth, barbed or deformed shank, with heads 3/8 inch (9mm) to 7/16 inch (11mm) in diameter. Length must be sufficient to penetrate into solid wood at least 3/4 inch (19mm) or through plywood or oriented strand board by at least 1/8 inch (3.18mm).
B. Screws: Equal to Simpson Strong-Tie (strong drive wood screws), or SPAX.
2.10 METAL FLASHING
A. Galvanized Steel: 24 gauge hot-dip galvanized steel sheet, complying with ASTM A 653/A 653M, G90/Z275.
B. Copper: 16-oz/sq ft (0.56mm) copper sheet, complying with ASTM B 370.
C. Aluminum: 0.032-inch (0.8mm) aluminum sheet, complying with ASTM B 209.
ePM 45270 Miscellaneous Work at Coburn Gore LPOE and Residences 1,2,3, and 4 Page | 17
PART 3 EXECUTION
3.1 EXAMINATION
A. Do not begin installation until roof deck has been properly prepared.
B. If roof deck preparation is the responsibility of another installer, notify Architect or building owner of unsatisfactory preparation before proceeding.
3.2 REMOVAL OF EXISTING ROOFING
A. Remove all existing roofing down to the roof deck.
B. Verify that deck is dry, sound, clean and smooth, free of depressions, waves and projections.
C. Replace damaged roof sheathing with new materials as outlined in the Summary of Work.
D. Clean deck surfaces thoroughly prior to installation of eaves protection membrane and underlayment.
3.3 PREPARATION OF SUBSTRATE
A. Clean deck surfaces thoroughly prior to installation of leak barrier and roof deck protection.
B. At areas to receive leak barrier, fill knot holes and cracks with silicone filler (roofing cement) equal to the product specified.
3.4 INSTALLATION OF UNDERLAYMENT
A. Install using methods recommended by manufacturer in accordance with local building code.
When local codes and application instructions are in conflict, the more stringent requirements shall take precedence.
B. Materials per Part 2.6 of this section.
3.5 INSTALLATION OF SHINGLES
A. Install in accordance with manufacturer's instructions and requirements of local building code.
1. Avoid breakage of shingles by avoiding dropping bundles on edge, by separating shingles carefully (not by "breaking" over ridge or bundles), and by taking extra precautions in temperatures below 40 degrees F (4 degrees C).
2. Handle carefully in hot weather to avoid damaging shingle edges.
3. Secure with 4 to 6 nails per shingle; use number of nails required by manufacturer or by code, whichever is greater. Nails must be long enough to penetrate through plywood or OSB, or 3/4 inch (19 mm) into dimensional lumber.
B. At ridges, install ridge shingles over ridge vent material.
C. All penetrations are to be flashed according to ARMA and NRCA application instructions and construction details.
3.6 PROTECTION
A. Stage work progress so that traffic is minimized over completed roofing.
B. Protect installed products until completion of project.
END OF SECTION
ePM 45270 Miscellaneous Work at Coburn Gore LPOE and Residences 1,2,3, and 4 Page | 18
b. Residences 1,2,3,4 Window Replacement (Base Bid)
1. Scope of Work for this portion of the Project is for the replacement of existing windows at locations as indicated in Residences 1,2,3,4. The Scope will include the removal of exterior wood trim and stops or vinyl or metal cladding as necessary; ACM remediation that will involve the removal of interior wood trim and existing 1/2” gypsum behind the trim to the width of the wood trim (3-1/2” wide) at locations in Residences 1,2,3,4 as indicated within the appended Asbestos Survey (Appendix A); removal of existing storm and all wood windows; insulation of new FG batt insulation in the rough opening around the window perimeter; install ice and water membrane sill pan flashing; install new all wood window and existing storm window; install new 1/2” GWB; install new exterior wood trim primed and painted to match existing in-kind and apply sealant; install interior wood trim with finish and profile to match existing. **It is the intent of this work is to reuse the existing wood trim. This will involve careful removal of the trim to minimize damage, indentations to the wood surface, or delamination, and to reinstall the wood trim to include wood filler in all finish nail holes and finish painting.
2. Removal and Disposal: Removal and disposal of existing windows along with existing storm window components (if existing), wood trim and framing materials, ACM GWB. Dispose of any and all construction debris and removed materials in a proper manner. Dispose of any ACM in accordance with State regulations. All cost for ACM removal to be made part of the Contractor’s price.
3. Contractor will be responsible for verifying all existing window dimensioning, head-jamb-sill details, rough opening condition, as well as trim, rail, muntin, dimensioning and profiles for each window type as indicated on the drawings and in the window schedule below.
4. Protect window openings during construction. At the end of each day window openings where windows have been removed will be protected with a solid plywood sheet covering the opening completely with the plywood secured from the interior.
5. Replace deficient or rotted wood at the existing head-jamb-sill wood framing as required and when encountered with approval of GSA.
6. Install 25-mil thick bitumastic membrane on sill framing equal to Vycor Plus.
7. Install new historic wood windows equal to Jeld-Wen Custom Epic Wood Windows complete with exterior paint finish coating and simulated divided lites that macth the existing windows.
8. Install loose fiberglass batt insulation in the rough opening cavity around the window to the entire depth of the cavity.
9. Install new exterior wood trim to match existing, primed and painted.
10. Install new 1/2” GWB (anticipated to 3-1/2” wide) around the window perimeter.
11. **Install existing window trim (jamb extensions, 1-1/8”x sill, and 3-1/2” case moulding). Install wood trim in original locations. If wood trim is required to be replaced then the Contractor must match existing dimension and profile. Finish wood to match existing.
12. All existing paint may contain lead. The contractor shall take all precautions as required to ensure that the existing paint is captured and disposed of in accordance with the requirements of the Maine
Department of Environmental Protection.
13. The Contractor is to note asbestos containing materials (ACMs) in locations indicated in the schedule below as it pertains to existing trim and gypsum materials removal, window removal, and general scope intent of this Section. See Part 9 within this Statement of Work:
ACM - 1/2” GYPSUM WALLBOARD LOCATIONS FOR WINDOW REPLACEMENT
Per Federal Occupational Health Survey Report – Appendix A Residence Room Location ACM Material
1 All locations GWB and joint compound
2 Living Room GWB and joint compound
2 Bedroom 1 GWB and joint compound
2 Bedroom 2 GWB and joint compound
3 Living Room GWB and joint compound
3 Bedroom 2 GWB and joint compound
3 Bedroom 3 GWB and joint compound ePM 45270 Miscellaneous Work at Coburn Gore LPOE and Residences 1,2,3, and 4 Page | 19
4 Living Room GWB and joint compound
4 Master Bedroom GWB and joint compound
4 Bedroom 3 GWB and joint compound
14. Submittals:
a. For each window to be Replaced, measure each window opening and provide a table indicating the existing opening size and the size of the window to be installed. All of the measurements in this document are approximate.
b. Provide shop drawings indicating the materials to be installed including all windows, caulking, flashing and appurtenances. Details shall show how the window shall meet at the top, sides and bottom. Detail shall show the method of creating a water / air tight installation.
Detail shall allow for expansion and contraction.
c. Provide shop drawings for replacement style windows indicating the method of installation.
Detail shall indicate the manufacture’s recommended fastening method. Details shall show the method of securing the window in place while allowing movement do to temperature and moisture changes.
d. Detail shall indicate all required parts for a complete installation.
e. Detail shall indicate that all exterior surfaces are covered with vinyl or prefinished aluminum.
f. Detail shall include insulation requirements as required to seal the window into the rough opening while allowing for expansion and contraction.
g. Measure trim boards and document in submittal. New trim boards are to match existing. Paint color is to match the original paint color.
15. Design and Performance Requirements: Windows shall be in accordance with appended specification section 085213 Custom Epic Wood Windows. New window fenestration requirements will comply with State of Maine MUBEC, 2009 IECC, Section 401, Table 402.1.1.
16. BLINDS:
For all windows installed as part of this project, provide new mini blinds for windows. Mini blinds shall be off white and shall be sized to fill the opening. (width and length) Blinds shall be 1” horizontal louvered blinds. Slats: Aluminum; alloy and temper recommended by producer for type of use and finish indicated; with crowned profile and radius corners. Ionized Coating: Antistatic, dust-repellent, baked polyester finish. Provide with lift cord and tilt control cord. Install per manufacturer’s directions.
17. Existing Exterior window trim: Replace exterior trim around window. New trim to be in-kind and treated from core to surface with manufacturer’s preservation treatment system equal to Jeld-Wen’s
Auralast wood treatment. Work will include removal of the existing metal wrap covering from the exterior window trim components in addition to the existing exterior wood trim around the windows.
New wood trim should be properly fit to the vinyl J-trim around the window perimeter. The removed metal cladding will become the property of the Contractor and removed from the site.
18. Window Schedules: Residences 1 and 2 have like windows in number and size. Residences 3 and 4 have like windows in number and size. In addition Residences 1 and 2 have front porches with windows. Residences 3 and 4 have no front porches. Residences 1 and 2 have wood stud framing construction with exterior vinyl siding and metal cladding with rigid insulation installed over assumed original existing wood exterior siding and trim. Residences 3 and 4 have original brick masonry with wood stud back-up framing. The window schedules below indicate window types for each construction type: Residences 1 and 2 building type; and Residences 3 and 4 building type. The contractor must verify window type and size at each window location and at each Residence regardless of building type. Existing information has indicated that all windows are double-hung (DH) with the exception of the fixed Living Room unit in the Residence 3-4 building type, and the basement windows in both building types. **Existing storm windows that exist on Residences 1,2,3,4 will not be required to be reinstalled after new window installation and will become the property of the
Government.
ePM 45270 Miscellaneous Work at Coburn Gore LPOE and Residences 1,2,3, and 4 Page | 20
Residences 1 and 2 Building Type Window Schedule
Type Size Location / Remarks
A 3’-0”x 1’-2” Porch / Wood, DH, 8 Lites
B 4’-0”x 2’-4” Porch / Wood, DH, 16 Lites
C 4’-5”x 2’-5-1/2” Dining Room, Bedroom / Wood, DH, 16 Lites
D 2’-8”x 3’-1” Kitchen Sink Window / Wood, DH, 8 Lites
E 4’-5”x 2’-8-1/2” Kitchen / Wood, DH, 16 Lites
F 4’-5”x 1’-6” Back Entry / Wood, DH, 8 Lites
G 5’-0”x 2’-5-1/2” Bedroom / Wood, DH, 8 Lites
Residences 3 and 4 Building Type Window Schedule
Type Sash Size Location / Remarks
A (2)-2’-7”x 4’-6” Dining Room / Wood, DH, 12 Lites
B 3’-0”x 3’-6” Kitchen Sink Window / Wood, DH, 16 Lites
C 3’-0”x 4’-6” Living Room, Dining Room, Bathroom, Bedrooms / Wood, DH, 12 Lites
D 9’-6”x 4’-9” Living Room / Wood, Fixed, 15 Lites
E 3’-4”x 4’-6” Bedrooms / Wood, DH, 16 Lites
19. Historical Significance: It is the intent of this scope of work to have all windows comply in every detail with all aspects of the custom epic wood window specification in order to conform to the historical standards for this Project. It is also the intent of this Work to match the existing window detail at each location and in each building type (Residence 1-2, and
Residence 3-4 building types) with the Simulated Divided Lite pattern as indicated in the
Window Schedules above and on the Drawings for both Building types – Drawings A301 and
A302.
ePM 45270 Miscellaneous Work at Coburn Gore LPOE and Residences 1,2,3, and 4 Page | 21
SECTION 08 52 13
CUSTOM EPIC WOOD WINDOWS
PART 1 - GENERAL
1.1 SECTION INCLUDES
A. Double-Hung Replacement Windows
1.2 REFERENCES
A. American Architectural Manufacturer association (MMA)
1. ANSl/AAMNNWWDA 101/l.S.2/NAFS; Voluntary Specifications for Aluminum, Vinyl (PVC) and
Wood Windows and Gloss Doors
2. AAMA 506; Voluntary Specifications for Hurricane and Impact and Cycle Testing of F enestration
Products
3. AAMA 2605; Voluntary Specification, Performance Requirements and Test Procedures for Superior
Performing Organic Coatings an Aluminum Extrusions and Panels
B. ASTM International
C. National Fenestration Rating Council (NFRF)
1. NFRC 200; Procedure for Determining Fenestration Thermal Properties
2. NFRC 200; Solar Heat Gain Coefficient and Visible Transmittance
D. Manufacturer’s Association (WDMA)
1. WDMA l.S.4; Water Repellent Preservative Non-Pressure Treatment for Millwork
1.3 DESIGN REQUIREMENTS
A. NFRC Requirements - Provide windows capable of complying with the following indicated total window ratings:
1. U-Factor: .34 in accordance with NFRC 100.
2. Solar Heat Gain Coefficient (SHGC): .21 In accordance with NFRC 200.
3. Visible light Transmittance (VT): 34 in accordance with NFRC 200.
1.4 SUBMITTALS
A. Refer to Section
B. Prod uct Data: Submit window manufacturer current product literature, including installation instruction.
ePM 45270 Miscellaneous Work at Coburn Gore LPOE and Residences 1,2,3, and 4 Page | 22
C. Samples: Provide finish samples for all products.
D. Closeout Submittals
1. Refer to Section
1.5 QUALITY ASSURANCE
A. Certifications
B. Mock- ups
1. Window mock-up shall incorporate surrounding construction, including wall assembly fasteners, flashing, and other related accessories installed in accordance with window manufacturer’s approved Installation methods.
a. Mock-up size: as indicated on drawings.
b. Mock-up may remain as port of the work.
1.6 DELIVERY, STORAGE AND HANDLING
A. Deliver windows materials and components In manufacturer' s original, unopened, undamaged containers with identification labels intact.
B. Store windows as recommended by manufacturer.
1.7 WARRANTY
A. Manufacturer standard warranty indicating that the window unit will be free from material and workmanship defects from the date of substantial completion for the time periods indicated below.
1. Window Unit: 20 years.
2. Clad Finish: 20 years against peeling, checking, cracking caulk or color change.
3. Glazing:
a. Insulated Glass: 20 years against seal breakage
b. 7/8" Low-e : 5 years against delaminating
PART 2 - PRODUCTS, MANUFACTURER:
JELD-WEN Windows and Doors; 3250 Lakeport Blvd. P.O. Box 1329, Klamath Falls, OR 97601-0268, USA
PHONE: 541-885-7412, FAX 541-884-3331, TOLL FREE…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it.