Y1DA--CON NRM 580-18-111, Site Prep Cath Lab #2 and EP Lab
Solicitation number
36C25621R0114
Issued by

About this file

This document outlines the requirements for a federal construction contract opportunity to perform site preparation work for a cardiac catheterization laboratory and electrophysiology laboratory at the Michael E. DeBakey VA Medical Center in Houston, Texas. The contract is set aside solely for service-disabled veteran-owned small businesses and requires at least 15% of the contract costs for personnel to be spent on eligible SDVOSB employees. Interested parties are encouraged to register for notifications regarding the solicitation, which will be issued as a request for proposals on or around June 24, 2021. The solicitation documents will include specifications and drawings and be available electronically with no hard copies mailed. The construction work must be completed within 510 calendar days of the notice to proceed and bonding and insurance requirements apply. The estimated value of the construction is between $1,000,000 to $2,000,000.

View the file

Other files

File Type Posted
36C25621R0114 0002.pdf PDF
078100 Applied Fireproofing.docx DOCX document
36C25621R0114 0001.pdf PDF
2017 5YR After Backflow RnR.PDF PDF
014536 Schedule of Special Inspections.docx DOCX document
134900 RadiationProtection-R1.docx DOCX document
Clarifications dated 8-5-21.pdf PDF
Roof Pictures.pdf PDF
033053 (SF) CastPlace Concrete.docx DOCX document
2017 Annual Fire Pump.pdf PDF
580-18-111 Site Visit Instructions.docx DOCX document
36C25621R0114_1.docx DOCX document
580-18-111 Phase 1 EP Lab Specifications.pdf PDF
580-18-111 Phase 2 Cath Lab 2 Drawings.pdf PDF
580-18-111 Phase 2 Cath Lab 2 Specifications.pdf PDF
SF24 - BID BOND.pdf PDF
580-18-111 Phase 1 EP Lab Drawings.pdf PDF
DOL Wage Determinations TX20210253 dated 5-7-21.pdf PDF
36C25621R0114.docx DOCX document
Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Site Prep for Cath Lab #2 and EP Lab Project No: 580-18-111 Statement of Work 1 Foreword

1.1 Contractor shall provide all labor, materials, tools, equipment, expertise, administration, supervision and transportation as necessary to perform all work in accordance with provided construction specifications, drawings, all documents attached to this contract, all terms and conditions of this contract, and this statement of work.

1.2 This document does not relieve the contractor of their professional responsibility to comply with all local and federal construction and environmental codes and to perform and complete a fully coordinated job.

2 General Project Description

2.1 The project will perform site preparation for Cath Lab #2 and EP Lab to replace existing interventional x-ray equipment on the 3rd Floor of Building 100. All construction work must adhere to the latest JCAHO, NFPA, and life safety requirements. All construction work must be performed without affecting medical center’s operations.

2.2 Work includes construction labor and supervision for demolition, mechanical, electrical, plumbing, and interior finishes work as required by provided construction documents. This Scope of Work is not considered to be a comprehensive description of work details for this project. All work shall be completed per the plans/drawings and specifications.

3 General Construction Requirements

3.1 Prior to any mobilization and construction, the contractor shall request and have an approved Infection Control Construction Permit, Construction Safety Plan, and an Interim Life Safety Measures Certification from the VAMC. Also project/construction schedule, schedule of values/prices and construction phases have to be provided and approved by VA’s COR/Project Engineer and/or Contracting Officer.

3.2 Contractor shall completely prepare site, prior to the installation of the equipment, and furnish labor, equipment and materials to perform work for this specific project as required by construction documents.

3.3 The entire project’s associated construction and temporary works shall conform to the latest VA specifications, VA Standards, energy conservation methods, EPA, OSHA, NFPA, NEC, ASHRAE, LIFE SAFETY CODE, UBC, local, Federal and industry requirements and regulations.

3.4 Project Record Drawings: The Contractor will maintain a set of Record Drawings. The Contractor will maintain a set of construction documents (field as-built drawings) to record actual construction changes during the construction process. The project record drawings will be available for review by the VA Project Manager at all times.

3.5 The following milestone dates shall be incorporated into the contractor’s schedule.

3.5.1 Submittal Schedule and log shall be provided within ten (10) calendar days after Notice to Proceed. The contractor shall provide it to the Contracting Officer’s Representative (COR) for approval, and shall include the dates for submission of Shop Drawings, Product Data, and Samples.

3.5.2 All Shop Drawings, Product Data and Samples shall be submitted and approved by the VA within sixty (60) calendar days after Notice to Proceed. The VA will provide the Contractor with written comments within 15 business days after receiving each submittal.

3.5.3 The Contractor shall submit a construction schedule within ten (10) calendar days after Notice to Proceed. The construction schedule shall be prepared in terms of calendar days (not working days). Once the construction schedule is submitted by the Contractor and approved by the CO, no lateness in the schedule shall be tolerated without the CO’s approval.

3.5.4 A pre-construction meeting shall be held within ten (10) calendar days after award of Contract. During the construction, the Contractor shall attend all weekly construction progress meetings. The meeting schedule and place will be discussed in the pre-construction meeting.

3.6 The superintendent can act as the Site Safety and Health Officer (SSHO) and Quality Control (CP) provided they meet all the qualification requirements and it does not impact the project schedule.

3.7 The Test and Balance (TAB) and Low Voltage Controls contractors shall be a subcontractor to the General Contractor (prime contractor with the VA), and not a second-tier subcontractor. The General Contractor is responsible to hire these contractors directly.

3.8 The VA will work with the awardee to find a job trailer/laydown location after award. We have very limited space close to the main building, so there is no guarantee the specified area will be close to B100.

4 General Contract Requirement

4.1 VA’s Normal Working Hours are 7:00 am to 4:30 p.m., Monday through Friday. Contractor shall coordinate work with the COR in order to not disrupt the facility’s operations which may include work earlier or later in the day and on weekends or federal holidays with at no additional cost to the VA. Noise disturbances and utility shutdowns/tie-ins shall be coordinated with the COR and not interfere with VA daily operations.

4.2 Pursuant to clause 52.236-8 Other Contracts incorporated by reference under section 4.33 52.252-2 Clauses Incorporated by Reference, Contractor shall fully cooperate with the other contractors and with Government employees and shall carefully adapt scheduling and performing the work under this contract to accommodate the additional work, heeding any direction that may be provided by the Contracting Officer. If required by the Contracting Officer, Contractor shall, at no additional cost to the VA, coordinate with other VA’s activities including but not limited to construction activities near the job site to ensure the construction work under this project will be in harmony with those activities. This coordination shall include but not limited to the careful scheduling of work commencement, equipment mobilization etc.

4.3 The government’s tax exemption does not pass down to contractors per FAR 29.303. However, contractors can follow their state codes and may receive tax exemption per FAR 29.305.

4.4 The following and any other day the President of the United States declares as a federal holiday are legal holidays observed by this Government Agency:

New Year's DayJanuary 1st
Martin Luther King's BirthdayThird Monday in January
Presidents DayThird Monday in February
Memorial DayLast Monday in May
JuneteenthJune 19
Independence DayJuly 4th
Labor DayFirst Monday in September
Columbus DaySecond Monday in October
Veterans DayNovember 11th
Thanksgiving Day4th Thursday in November
Christmas DayDecember 25th

5 Project Meetings

5.1 At a minimum, every two weeks the contractor shall hold a progress meeting to review progress to date and to resolve all questions for the upcoming week. The progress meeting shall include at a minimum, the Project Manager and the Superintendent representing the Contractor, the COR and the CO representing the Government. Technical supervisor (foreman), sub-contractors, suppliers, etc. shall attend when requested by the Contracting Officer. The meeting shall be same day, time, and place each week.

5.2 Meeting Minutes - The contractor shall take minutes of all meetings held relative to this project. The format must be acceptable to the Contracting Officer (CO). Minutes must include the meeting date and time; agenda; meeting location; list of participants with their affiliations, and telephone numbers; be fully descriptive of issues, problems and decisions made; and action items with names of responsible parties and deadlines. In addition, the minutes must include, as attachments, all exhibits and references distributed as handout materials, unless the materials are part of a formal submission. The contractor shall provide, via e-mail, complete copies of all minutes to all attendees within 72 hours of the meeting. All challenges to the minutes will be reflected in a revised version prepared by the contractor and CO along with the contractor and COR shall sign/initial the minutes. In the event of any disputes or challenges that can’t be resolved, the Contracting Officer shall render a final decision. Copies of updated minutes shall be distributed to the all attendees within 48 hours after change notice.

6 Safety and Security

6.1 Contract workers under this project may require a VA issued identification card before the start of construction work at the Houston VAMC. There is no charge for the badges; however, multiple trips to MEDVAMC facility maybe required.

6.2 Contract employees, including all subcontractor employees, must be TB tested and receive a flu shot (each year under the contract performance) if they will work within the VA Hospital Building 100. A letter from the prime contractor shall be submitted to the CO prior to work commencing that all staff members are TB negative and the flu shot was received.

6.3 All contract personnel are subject to inspection of personal effects when entering or leaving the project site.

6.4 Parking is rigidly controlled throughout the Medical Center. Contractor parking is only allowed in authorized areas. Contractor shall abide by all police requirements. Parking in designated patient parking areas is strictly prohibited. Parking for unloading equipment necessary to perform the work will be authorized in advance by the COR prior to starting the project.

6.5 Contractor shall abide by MEDVAMC’s policy for measures to prevent the spread of COVID. Policies may change during contract performance. COR and/or CO will provide updates as they are issued by the Facility Director. Contractor shall follow the CDC guidelines for COVID found here:

https://www.cdc.gov/coronavirus/2019-ncov/community/organizations/businesses-employers.html The contractor shall provide the name and telephone number of any employee who tests positive that was on the VA campus. Contractor shall also identify the number of contractor and subcontractor employees who had contact with the positive COVID-19 person(s) and remove/replace the employee(s) for 14 days of when the positive employee(s) was last onsite.

--- End---