Addendum 4 Updated Drawings.pdf
PDF 2 MB Posted
- Attached to
- Z2DA--Renovate MICU/SICU 539-20-104
- Solicitation number
- 36C25026B0001
About this file
These are architectural and engineering design documents for a U.S. Department of Veterans Affairs (VA) construction project located in Cincinnati, Ohio. The documents include detailed floor plans for the second and third floors, focusing on HVAC distribution, ductwork, and emergency exhaust system controls. Key technical specifications include:
The documents detail complex HVAC infrastructure with specific components like AHU-5 air handling unit, emergency exhaust fans, cooling coils, and air filter systems. The design incorporates redundant fan systems with N+1 arrangements, lead-lag control, and advanced safety features such as manual reset static pressure switches, automated damper controls, and emergency exhaust mode sequences. The project uses Variable Frequency Drives (VFDs), HEPA filtration, and includes precise control mechanisms for maintaining specific air pressure, temperature, and ventilation requirements across multiple hospital spaces including patient rooms, nursing stations, and support areas.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Accessory Not Included. Sold SeparatelyAccessory Not Included. Sold Separately
2"
2.5"
2" 2.5"
2"
2.5"
2.5"
2"
2"2.5"
P419
P419 P419
P419
P101
P419
P419
P101
P419
P419
P418
P419
P101
P418
P419
P101
P101
P419
P419
P101
P419
P419
P101
P419
P419
P101
P528 P505
4 4 4
3 3
3 3 3
3 3
1.25"1.25"1.25"
2" 2.5" 1.25"
1.25" 1.25"
1.25" 0.5"
2"2.5"
2"2.5"
P101
P419
P419
P419
P419
P418
P418
0.5"
0.5"
0.5"
0.5"0.5"
P809
P809
P809
P809
P809
P809
P809
P809
P809
P809
7 - 2 GPM
0.75"
1"
P101
P418
P701
P528
P418 P101
P502
P101
P418
P701
A292B
Soiled
Utility
C226B Passageway
A270A Staff Toilet
A269
Staff
Lounge
A271A
Staff
Bathroom
A272
Conference
Room
A273 Office
A275 Electrical
A274
HAC
A276 On-Call
A276A Bathroom
A268 Office
A267
RN
Manager
A293
Pharmacy
Office
A286A Toilet
A287A Toilet
A283
Negative
Pressure
Bariatric Patient
Room
A288A Toilet
A289 Grief/Consult
A285
Patient
Room
A278
Patient
Room
A279
Patient
Room
A280
Negative
Pressure
Patient Room
A281
Equipment
Storage
A282
Negative
Pressure
Bariatric Patient
Room
A283A Toilet
A284
Negative
Pressure
Patient Room
A277 Clean Linen
A290
HUC
Station
C226I
Patient
Circulation
A284B Ante Room
Elevator
A270
Male
Locker Room
A271
Female
Locker Room
P101
0.75" 0.75"
0.75"
AREA OF WORK
P: 937-224-0861 www.heapy.com
VA Project No.
JPA Project No.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
Office of Construction and Facilities Management
PROJECT NO. STATE COA FIRM NO.
3131 Newmark Drive, Suite 200 Miamisburg, Ohio 45342 |www.jpaarch.com| 937.461.3290
/6
/2
:5
:0
P M
Renovate MICU/SICU
10/17/2025
PARTIAL SECOND FLOOR PLAN -
DISTRIBUTION
PP102
SVHKMB
19018.00
539-20-104
Cincinnati, Ohio
100% CONSTRUCTION
DOCUMENTS
2019-05193 01528
N Scale:Scale: 1/8" = 1'-0"1/8" = 1'-0"
PARTIAL SECOND FLOOR PLAN - DISTRIBUTION
1. EXISTING TO REMAIN.
2. PROVIDE NEW REPLACEMENT FIXTURE (TYPE AS INDICATED) IN THE SAME
LOCATION AS EXISTING FIXTURE. EXTEND NEW PIPING FROM FIXTURE AND
CONNECT TO EXISTING DCW, DHW, AND SANITARY WASTE & VENT PIPING LOCATED
IN WALL AS REQUIRED TO ACCOMMODATE NEW FIXTURE AS INDICATED.
3. BOX MOUNTED TRANSFORMER LOCATED ABOVE THE CEILING TO CONTROL
SENSOR OPERATED FAUCET ON FIXTURE(S) BELOW. 120V-1PH POWER WILL BE
LOCATED IN A WIRING BOX ABOVE THE CEILING. REFER TO DIVISION 26 DRAWINGS.
A 0.75" CONDUIT (FOR LOW VOLTAGE WIRING) STUBBED ABOVE THE CEILING AND
EXTENDED DOWN TO AN ELECTRICAL WALL BOX LOCATED BELOW EACH
LAVATORY. REFER TO DIVISION 26 DRAWINGS. PROVIDE TRANSFORMER AND LOW
VOLTAGE WIRING. COORDINATE ALL WORK WITH DIVISION 26.
4. BOX MOUNTED TRANSFORMER LOCATED ABOVE CEILING TO CONTROL SENSOR
OPERATED FLUSH VALVE ON FIXTURE(S) BELOW. 120V-1PH POWER WILL BE
LOCATED IN A WIRING BOX ABOVE THE CEILING. REFER TO DIVISION 26 DRAWINGS.
A 0.75" CONDUIT (FOR LOW VOLTAGE WIRING) STUBBED ABOVE THE CEILING AND
EXTENDED DOWN TO AN ELECTRICAL WALL BOX LOCATED ABOVE EACH WATER
CLOSET. REFER TO DIVISION 26 DRAWINGS. PROVIDE TRANSFORMER AND LOW
VOLTAGE WIRING. COORDINATE ALL WORK WITH DIVISION 26.
5. UNDER BID ITEM 2, DELETE ALL LABOR AND MATERIALS ASSOCIATED WITH THE
CONSTRUCTION, ALTERATION, PLUMBING, MECHANICAL AND ELECTRICAL
MODIFICATIONS TO THE OFFICE/ CONFERENCE/ BREAK ROOM AREAS AS
INDICATED.
6. NEGATIVELY PRESSURIZED SPACE. SEAL ALL PENETRATIONS IN WALL AND/OR
CEILING AS REQUIRED TO MAINTAIN PRESSURIZATION.
7. FLOW CONTROLLER. REFER TO DETAIL 'D' / SHEET P601.
8. NEW DOMESTIC COLD WATER, DOMESTIC HOT WATER, AND DOMESTIC HOT WATER
RETURN RISERS FROM 1ST FLOOR.
A. REFER TO SHEET P001 FOR ABBREVIATIONS, SYMBOLS & INDEX OF DRAWINGS.
B. MAINTAIN AND RESTORE, IF INTERRUPTED, DOMESTIC WATER SUPPLY, MEDICAL
GAS & VACUUM SYSTEMS AND SANITARY & VENT SYSTEMS TO EXISTING
FIXTURES LOCATED IN AN UNDISTURBED AREA.
C. IN THE RENOVATION AREA, CORRECT ANY DOMESTIC WATER, MEDICAL GAS,
SANITARY & VENT PIPE LABELING ON EXISTING PIPING THAT IS MISLABELED/
MISSING LABELS AND/ OR FLOW ARROWS.
D. REFER TO SPECIFICATIONS 22 05 11 SECTION 1.3.B. ASME A13.1 SCHEME
FOR THE IDENTIFICATION OF PIPING SYSTEMS.
E. ALL SANITARY DRAIN, STORM AND DISTRIBUTION PIPING RUN OVER HVAC
EQUIPMENT, ELECTRICAL PANELS/ EQUIPMENT, OR MEDICAL EQUIPMENT
SHALL HAVE SPILL/ LEAK PROTECTION AND LEAK DETECTING SENSORS.
F COORDINATE ALL EXISTING PIPING AND NEW PIPING WITH NEW MEPT SYSTEMS
AND EQUIPMENT AND PATIENT LIFT SUPPORTS, RAILS, AND EQUIPMENT.
GENERAL NOTES
PLAN NOTES
KEYPLAN
A. REFER TO THE ARCHITECTURAL DOCUMENTS FOR A SEQUENCE OF CONSTRUCTION
PLAN, WHICH INCLUDES DETAILED NOTES REGARDING PROJECT PHASING. ALL
WORK SHALL BE COORDINATED AND SCHEDULED WITH THIS CONSTRUCTION
SEQUENCE. ALL REQUIRED SHUTDOWNS SHALL BE IDENTIFIED AT THE START OF
CONSTRUCTION AND SHALL BE COORDINATED AND SCHEDULED WITH THE VA.
PHASING NOTE
Revisions Date
6 Addendum #4 2026-01-06
UP DN36x14
UP36x14
DN14x12
DN16x10
DN18x10
UP & DN14x12
UP16x10
UP16x10
UP18x10
HAC
A380
Female Locker
A382C
M. Lock.
A382B
Lounge
A382
Tlt.
A382A Respiratory Therapy
A384
Clean Supply
A397
Pharm.
A386
Sig.
A396 Corridor
C*3*18
Elec.
A395
Soil Utility
A391
Linen Clos.
A389
Tlt.
A388
Equip. Stor.
A392
Nurse Off.
A390
Negative Pressure Patient Room
A387K
Patient Room
A387J
Patient Room
A387I
Shower
A387H
Patient Room
A387G
Patient Room
A387F
Patient Room
A387E
Patient Room
A387D
Patient Room
A387C
Patient Room
A387B
Negative Pressure Patient Room
A387A
Nurse Station
A387
Conference Room
A385
ICU Dir. Off.
C314
Soc. Wrk.
A383
Family Wtng.
C310
Grieve Consult
C313
Lactation
C312
18x10
16x10
UP14x12
DN20x8
UP14x14
14x8
10x6
8x14
?x?
UP?
8x
10ø
CD1
DN26x8
UP20x20
TO EF
TO 1-EF-25
TO EF-26
TO EF
TO EF
TO EF
DN10x10
TO EF-27
TO EF
8x
10ø
CD1
VAV-12
VAV-01
11/2" RS DOWN
1-1/8" RS DOWN
42x14
165 CFM
65 CFM
75 CFM 3
3 3
ACCU-396
1/2" RS UP
1-1/8" RL UP
AHU-5 AHU-4
UP14x8
UP14x8
TO EF
TO EF
OUTDOOR AIR
INTAKE
AHU4
CONDITIONED
VESTIBULE
BETWEEN
AHUs
OUTDOOR AIR
INTAKE
RELIEF AIR
AHU5
ROOF DRAIN
RELIEF AIR
CC-2
10x10 x1
12x10 10x10
UP19x19
7 335 CFM
DN16x10
AREA OF WORK
P: 937-224-0861 www.heapy.com
VA Project No.
JPA Project No.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
Office of Construction and Facilities Management
PROJECT NO. STATE COA FIRM NO.
3131 Newmark Drive, Suite 200 Miamisburg, Ohio 45342 |www.jpaarch.com| 937.461.3290
/6
/2
:4
:0
P M
Renovate MICU/SICU
10/17/2025
PARTIAL THIRD FLOOR PLAN -
DUCTWORK - NEW WORK
MH103
AJGBRB
19018.00
539-20-104
Cincinnati, Ohio
100% CONSTRUCTION
DOCUMENTS
2019-05193 01528
N Scale:Scale: 1/8" = 1'-0"1/8" = 1'-0"
PARTIAL THIRD FLOOR PLAN - DUCTWORK - NEW WORK
PLAN NOTES
1. EXISTING REFRIGERANT PIPING ASSOCIATED WITH THE ACCU-06 SYSTEM SHALL BE
RE-USED. COORDINATE NEW EQUIPMENT AND PIPING WITH THE MANUFACTURER OF
THE EXISTING VRF SYSTEM.
2. PROVIDE TYPE "A" FIRE DAMPER AT FLOOR PENETRATION TO LEVEL 2. SEE DETAIL.
PROVIDE DUCT ACCESS DOOR. COORDINATE WALL ACCESS PANEL LOCATION WITH
COR,
3. REBALANCE GRILLE TO INDICATED CFM.
4. PROVIDE NEW DX COOLING COIL IN SPARE SECTION OF AIR HANDLING UNIT. PROVIDE
INSULATED STAINLESS STEEL DRAIN PAN WITH COOLING COIL. CONNECT
REFRIGERANT PIPING TO COIL PER MANUFACTURER'S INSTRUCTIONS. DRAIN
CONDENSATE TRAP TO ROOF TO MATCH EXISTING COOLING CONDENSATE DRAIN.
5. PROVIDE BIPOLAR IONIZATION AIR PURIFICATION SYSTEM UPSTREAM OF FIRST
COOLING COIL. REFER TO SPECIFICATION SECTION 23 40 00.
6. PROVIDE 0.5"X0.5" WEATHER RESISTANT WIRE MESH BIRD SCREEN OVER OPENING.
PROVIDE WEATHER HOOD AT END OF DUCT.
7. BALALNCE DUCT TRAVERSE TO INDICATED CFM.
8. AUXILIARY RELIEF AIR DAMPER.
9. EMERGENCY EXHAUST AIR DAMPER.
10. THE EQUIPMENT MANUFACTURER SHALL PROVIDE ALL REFRIGERATION CONTROLS,
SAFETIES, AND LEAK DETECTION. THIS INCLUDES AN A2L REFRIGERANT LEAK
DETECTION SYSTEM COMPLETE WITH SENSORS AND A DEDICATED CONTROLLER.
THE A2L CONTROLLER SHALL PROVIDE AN ALARM CONTACT FOR BAS MONITORING
AND INTERFACE WITH THE REFRIGERATION SYSTEM DDC CONTROLLER. THE
MANUFACTURER SHALL DETERMINE THE QUANTITY OF SENSORS AND PROVIDE ON-
SITE ASSISTANCE FOR INSTALLATION AND PROPER PLACEMENT OF A2L SENSORS
INSIDE THE EXISTING AIR HANDLER CASING. THE REFRIGERATION SYSTEM SHALL
INCLUDE A DDC CONTROLLER THAT MONITORS THE A2L CONTROLLER VIA MODBUS
INTERFACE. THE DDC CONTROLLER SHALL ACCEPT AN INPUT FROM THE BAS FOR
REFRIGERATION CAPACITY CONTROL AND PROVIDE AN OUTPUT TO ENERGIZE OR
DE-ENERGIZE THE FAN DURING A LEAK DETECTION EVENT. THE REFRIGERATION
SYSTEM DDC CONTROLLER SHALL ALSO ACCEPT FAN STATUS FEEDBACK IF
REQUIRED FOR PROPER LEAK DETECTION LOGIC.
KEYPLAN
GENERAL NOTES
1. LABEL ALL MECHANICAL EQUIPMENT PER SPECIFICATION, INCLUDING EXHAUST FANS,
VALVES, VAV BOXES, AND AIR VALVES. ANY OUTDOOR LABELING SHALL BE
WEATHER- RESISTANT. COORDINATE ALL LABELING WITH THE VA PRIOR TO
ORDERING THE LABELING.
PHASING NOTE:
A. REFER TO THE ARCHITECTURAL DOCUMENTS FOR A SEQUENCE OF
CONSTRUCTION PLAN, WHICH INCLUDES DETAILED NOTES REGARDING THE
REQUIRED PROJECT PHASING. ALL WORK SHALL BE COORDINATED AND
SCHEDULED WITH THIS CONSTRUCTION SEQUENCE. ALL REQUIRED SHUTDOWNS
SHALL BE IDENTIFIED AT THE START OF CONSTRUCTION AND SHALL BE
COORDINATED AND SCHEDULED WITH THE VA.
Revisions Date
7 Addendum #4 2026-01-06
FILTER TAG CFM SYSTEM
MERV
RATING
EFFICIENCY
MAX. S.P. DROP (1)
INITIAL FINAL
HOUSING TYPE
MAX.
FACE
VELOCITY
SEE
NOTE
HEPA-3 18,000
EF-3 EMERGENCY
EXHAUST
35%
99.97%
0.38"
0.8"
0.76"
2.0"
WEATHER PROOF SIDE
ACCESS HOUSING
450 1,2,3
NOTES:
1. STATIC PRESSURE REQUIREMENTS BASED ON 500 FPM FACE VELOCITY. FINAL PRESSURE DROP BASED ON VA'S RECOMMENDED CHANGE OVER PRESSURE DROP.
2. BAG-IN/BAG-OUT HEPA FILTER MODULE WITH REDUNDANT PAIR AND BUBBLE TIGHT DAMPERS AT EACH PAIR. CAMFIL MODEL NO. CF-3X4-212P-4GB-SS
3. PREFILTER SIZE 24"X24"X2" (NOM.) - QTY 12. HEPA FILTER SIZE 24"X24"X12" (NOM.) - QTY 12.
AIR FILTER SCHEDULE
P: 937-224-0861 www.heapy.com
VA Project No.
JPA Project No.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
Office of Construction and Facilities Management
PROJECT NO. STATE COA FIRM NO.
3131 Newmark Drive, Suite 200 Miamisburg, Ohio 45342 |www.jpaarch.com| 937.461.3290
/6
/2
:4
:0
P M
Renovate MICU/SICU
10/17/2025
SCHEDULES
M602
AJGBRB
19018.00
539-20-104
Cincinnati, Ohio
100% CONSTRUCTION
DOCUMENTS
2019-05193 01528
M A
R K
DESCRIPTION LOCATION A
IR
F L
O W
C
F M
DX COOLING APPROX. DIMENSIONS
SEISMIC
RESTRAINTS
T O
T A
L C
A P
A C
IT
Y
M
B H
S E
N S
IB
L E
C A
P A
C
IT
Y
M B
H
E N
T E
R
IN
G A
IR
T
E M
P E
R A
T U
R E
D B
/W B
°F
L E
A V
IN
G
A
IR
T E
M P
E R
A T
U R
E D
B
°F
L E
N G
T H
W
ID
T H
H E
IG
H
T
R E
Q U
IR
E
D
I M
P O
R T
A N
C E
F A
C T
O R
CC-2 DX COOLING COIL AHU-5 20,000 872.8 592.2 80.0 / 67.0 53.0 / 52.6 120" 10" 86" ● 1.5
NOTES:
1. FACE VELOCITY TO BE BASED ON SUPPLY FAN CFM.
GENERAL NOTES:
A. CONDENSING UNITS SHALL INCLUDE LOW AMBIENT CONTROLS AND
ACCESSORIES, OPERATIONAL TO 20°F.
B. CONDENSING UNIT COOLING CAPACITY SHALL BE BASED ON 95°F AMBIENT
CONDITIONS.
2. REFRIGERANT PIPE SIZES SHALL BE PER MANUFACTURER'S
RECOMMENDATIONS.
SPLIT SYSTEM COOLING COILS
OUTDOOR CONDENSING UNIT - AIR COOLED
REFRIGERANT
CONN. SIZE
H O
T G
A S
B Y
P A
S S
S E
E N
O T
E
M A
R K
DESCRIPTION N
O
M
IN
A L
T O
N S
S
IZ
E
D T
O M
A T
C H
C O
IL
V A
R
IA
B L
E S
P E
E D
C O
M P
R E
S S
O R
(S
ELECTRICAL SERVICE
SEISMIC
RESTRAINTS
L
IQ
U
ID
L
IN
E
S U
C T
IO
N
L
IN
E
V O
L T
A G
E
P H
A S
E
F U
L L
L O
A D
A M
P S
F
L A
M
IN
C
IR
C U
IT
A
M P
S
M C
A
M A
X O
V E
R C
U R
R E
N T
P R
O T
E C
T
IO
N
M O
C P
M
IN
IM
U
M S
C C
R
A M
P S
R E
Q U
IR
E
D
I M
P O
R T
A N
C E
F A
C T
O R
CU-2 AIR-COOLED CONDENSING UNIT 80 - 480 - 3 175 200 200 35KAIC ● 1.5 1.125 2.125 - 1,2,3
E. ELECTRIC SERVICES FOR OUTDOOR UNIT AND INDOOR UNIT - SINGLE POINT
POWER SERVICE CONNECTIONS TO EACH UNIT. UNLESS NOTED OTHERWISE,
ADEQUACY OF LISTED CIRCUIT SIZES MUST BE VERIFIED BY H.C. AND UNIT
SUPPLIER. COST FOR INCREASE OR CHANGE OF ELECTRIC SERVICE FOR
EQUIPMENT SELECTED SHALL BE BORNE BY H.C.
C. WHEN APPLICABLE, REFER TO SPECIFICATIONS FOR VIBRATION ISOLATOR
TYPES AND SEISMIC RESTRAINT REQUIREMENTS.
D. REFRIGERANT PIPING - SIZES LISTED ARE APPROX. CIRCUITING, SIZING,
NUMBER OF PIPES AND CIRCUITS, ARRANGEMENT, ETC. SHALL BE IN
ACCORDANCE WITH MANUFACTURER'S RECOMMENDATIONS.
DX COOLING COIL
NOTES:
1. FAN HORSEPOWER LISTED IS FOR ONE FAN. FANS SYSTEM
SHALL CONTAIN TWO FANS WITH 100% REDUNDANCY.
2. FAN NOISE SHALL NOT EXCEED 62 DB'A' AT 10 FT WHILE
OPERATING AT 60 HZ.
GENERAL NOTES:
A. ALL FANS SHALL BE A.M.C.A. 211 AND 311 PERFORMANCE
CERTIFIED AND SHALL BEAR THE A.M.C.A. LABEL.
B. SONES VALUES BASED ON A.M.C.A. 301 MEASURED AT 5 FT.
C. MOTOR HORSEPOWERS LISTED SHALL BE CONSIDERED MINIMUM.
E. ROOF & WALL OPENINGS ARE APPROX. VERIFY SIZE &
COORDINATE.
F. COORDINATE STEEL FRAMING AROUND ROOF OPENING WHERE
REQUIRED FOR DECK SUPPORT, AND WALL LINTELS FOR WALL
OPENINGS.
G. WHEN APPLICABLE, REFER TO SPECIFICATIONS FOR VIBRATION
ISOLATOR TYPES AND SEISMIC RESTRAINT REQUIREMENTS.
H. VFD'S SHALL BE CONSTRUCTED AND LABELED FOR REQUIRED
SCCR (SHORT CIRCUIT CURRENT RATING). COORDINATE WITH
DIVISION 26.
I. IF EC MOTORS ARE INDICATED OR SPECIFIED, EACH MOTOR SHALL
BE PROVIDED WITH FACTORY DISCONNECTING MEANS, INTERNAL
OVERLOAD PROTECTION, FIELD ADJUSTABLE SPEED CONTROL,
AND REMOTE ANALOGUE SPEED CONTROL INPUT WHEN REMOTE
CONTROL IS SPECIFIED, COORDINATED WITH THE BUILDING
AUTOMATION SYSTEM.
FANS
M A
R K
DESCRIPTION SERVICE C
O
N N
E C
T E
D C
F M
F A
N C
F M
S T
A T
IC
P
R E
S S
U R
E
IN
W
.C
A P
P R
O X
W
H E
E L D
IA
M
E T
E R
M A
X
IM
U M
S O
N E
S
MOTOR
A P
P R
O X
R
O O
F /W
A L L
O P
E N
IN
G
A P
P R
O X
W
E
IG
H T
L
B S
V
IB
R A
T
IO
N I S
O L A
T O
R T
Y
E
SEISMIC
RESTRAINTS
S E
E N
O T
E
H O
R S
E P
O W
E R
H
P
V O
L T
A G
E
P H
A S
E
E L
E C
T R
O N
IC
A
L L Y
C O
M M
U T
A T
D
V A
R
IA
B L E
F R
E Q
U E
N C
Y D
R
IV
E
R E
Q U
IR
D
I M
P O
R T
A N
C E
F A
C T
O R
EF-3 HIGH PLUME EXHAUST FAN ISOLATION EXHAUST 18,000 19,390 3.4 - NOTE 2 25 460-3 - ● - 6,445 ● 1.5 1
Revisions Date
7 Addendum #4 2026-01-06
3. MAX. REFRIGERANT CHARGE PER CIRCUIT, 150 LBS
EXHAUST FAN
START/STOP
SAFETY SHUTDOWN RELAY
EXHAUST FAN
EA-5DRIVE SPEED
NC
H DP
EAP-LL-6
L
LOW STATIC CUTOUT
SAFETY SHUTDOWN
H
HEPA FILTER
LDP
H
PRE-FILTER
DP-PRE-FLTR-3
LDP
FAN VFD
EXHAUST FAN
START/STOP
SAFETY SHUTDOWN RELAY
EXHAUST FAN
DRIVE SPEED
NC
H
HEPA FILTER
LDP
H
PRE-FILTER
LDP
FAN VFD
STAT-EF-2
FAN
STATUS
STAT-EF-2FAN
STATUS
EAF-SS-1
EAF-SS-1DP-FNL-FLTR-4
MANUAL
DAMPER
MANUAL
DAMPER
DP
EASP-7
L
(DOWNSTREAM OF AIR HANDLING
UNIT, MULTIPLE SENSORS)
H
MANUAL
DAMPER
EXHAUST AIR
EMERGENCY
HMANUAL
DAMPER
EXHAUST AIR
STATIC PRESSURE
EXHAUST FAN CONTROL SEQUENCES
1. EMERGENCY EXHAUST MODE TO BE STARTED MANUALLY, AND INITIATED BY USER
THROUGH THE BUILDING AUTOMATION SYSTEM.
2. INTEGRATE EXHAUST FAN STARTUP WITH AHU-5 SEQUENCE. WHEN EMERGENCY
EXHAUST SYSTEM IS ACTIVATED, AHU-5 RETURN AIR DAMPER SHALL BE FULLY CLOSED,
AND ITS OUTSIDE AIR AND RELIEF AIR DAMPERS SHALL BE FULLY OPEN. AHU-5 SHALL
OPERATE AT 100% OUTSIDE AIR.
3. WHEN OPERATING IN EMERGENCY EXHAUST MODE, AUXILIARY RELIEF AIR DAMPER SHALL
BE FULLY CLOSED AND EMERGENCY EXHAUST AIR DAMPER SHALL BE FULLY OPEN.
REFER TO AHU-5 SECTION ON SHEET MH103.
4. WHEN OPERATING IN EMERGENCY EXHAUST MODE, FANS SHALL OPERATE
CONTINUOUSLY, 24/7/365, IN AN N+1 ARRANGEMENT, LEAD-LAG CONTROL, WITH LEAD
SWITCHING WEEKLY.
5. ON A COMMAND TO START, THE ISOLATION DAMPER SHALL OPEN WITH END-SWITCH
PROVED OPEN.
6. WHEN THE DAMPER IS OPEN, THE FAN SHALL START VIA THE END SWITCH WIRED IN
SERIES WITH THE MOTOR VFD SAFETY CIRCUIT. FANS WITH A DISCONNECT NEAR THE
MOTOR SHALL HAVE AN EARLY BREAK CONTACT INSTALLED AT THE DISCONNECT, SO
THAT IF THE MOTOR IS SHUTDOWON AT THE DISCONNECT, THE VFD IS OPENED (TURNED
OFF) AND THE ISOLATION DAMPERS CLOSE.
7. SYSTEM CONTROL - FAN SYSTEM SHALL MAINTAIN DUCT STATIC PRESSURE, WITH BYPASS
DAMPER MODULATING TO MAINTAIN DUCT STATIC. THE BYPASS DAMPERS SHALL BE
MODULATED TO A DUCT STATIC PRESSURE SENSOR LOCATED AS SHOWN ON THE
DRAWINGS. A PROPORTIONAL PLUS INTEGRAL CONTROL SHALL PROVIDE A COMMON
CONTROL SIGNAL TO THE SYSTEM TO PROVIDE A STATIC PRESSURE OF -0.5” W.G. (ADJ.)
AT THAT POINT.
8. FAN SOFT START – WHEN COMMANDED TO RUN, THE VARIABLE-SPEED DRIVES SHALL BE
BROUGHT UP TO FULL SPEED OVER A 90 SECOND PERIOD.
9. FAN SPEED TO MAINTAIN SCHEDULED PLUME HEIGHT, AS SET BY BALANCING
CONTRACTOR AT TIME OF INITIAL FAN BALANCE BY MEASURING OUTLET VELOCITY AT
NOZZLE.
10. SAFETIES – THE FOLLOWING SHALL BE PROVIDED TO STOP THE EXHAUST FANS AND
POSITION THE CONTROL DEVICES TO THEIR “FAIL SAFE” POSITION. SAFETIES SHALL BE
WIRED INTO THE FAN STARTER CIRCUIT SUCH THAT THE SAFETY SHALL FUNCTION
WHETHER THE START SELECTOR SWITCH IS IN THE “HAND”, “ON” OR AUTOMATIC
POSITION.
A. EXHAUST AIR DUCT HIGH NEGATIVE PRESSURE CUTOUT – PROVIDE A MANUAL RESET
TYPE DUCT STATIC PRESSURE SWITCH, SET AT THE MAXIMUM NEGATIVE WORKING
PRESSURE OF THE DUCTWORK, TO STOP THE FAN SYSTEM ON AN INCREASE OF
DUCT STATIC ABOVE SETPOINT.
B. EXHAUST AIR LOW STATIC CUTOUT SAFETY SHUTDOWN - PROVIDE A MANUAL RESET
TYPE DUCT STATIC PRESSURE SWITCH, SET AT THE MAXIMUM NEGATIVE WORKING
PRESSURE OF THE DUCTWORK, TO STOP THE FAN SYSTEM ON A DECREASE OF DUCT
STATIC ABOVE -4” WG (ADJ.).
C. AHU-5 RETURN AIR DUCT STATIC PRESSURE - PROVIDE A MANUAL RESET TYPE DUCT
STATIC PRESSURE SWITCH, SET AT THE MAXIMUM NEGATIVE WORKING PRESSURE
OF THE DUCTWORK, TO STOP INCREASING THE FAN SPEED ON AN INCREASE OF
DUCT STATIC ABOVE SETPOINT DURING SWITCHOVER.
11. ALARMS:
A. CURRENT SENSING – ALARM BAS UPON LOSS OF CURRENT.
B. PRESSURE DIFFERENTIAL ACROSS FAN – ALARM BAS UPON DROP IN DIFFERENTIAL
PRESSURE ACROSS FAN.
C. AHU-5 RETURN AIR DUCT STATIC PRESSURE - ALARM BAS UPON INCREASE OF DUCT
STATIC ABOVE STATIC SETPOINT.
12. TESTING:
A. WEEKLY TESTING SHALL BE PERFORMED WITH FAN OPERATING AT 75% CAPACITY
(ADJ.), HEPA FILTER MANUAL DAMPERS CLOSED, AND BYPASS OPEN TO MAXIMUM
WITHOUT REGARD TO PLUME HEIGHT. FANS SHALL OPERATE IN LEAD-LAG, IN AN N+1
ARRANGEMENT, WITH LEAD SWITCHING AFTER FOUR (4) HOUR (ADJ.) RUNTIME, AND
SECOND LEAD OPERATING FOR ANOTHER FOUR (4) HOURS (ADJ.)
B. MONTHLY TESTING SHALL BE PERFORMED IN CONJUNCTION WITH SHUTDOWN AND
ISOLATION OF ASSOCIATED RETURN FAN OF AHU-5. FAN SYSTEM OPERATION SHALL
BE AS DESCRIBED IN ABOVE SEQUENCE OF OPERATION. FAN SYSTEM SHALL
OPERATE FOR ONE (1) DAY (ADJ.) WITH EACH FAN RUNNING FOR TWELVE (12) HOURS
EACH (ADJ.).
E X
H A
U S
T F
A N
S
T A
R T
/S T
O P
EAF-SS-1POINTS NO.
POINT
NAME
DOTYPE
NOTES
EMERGENCY EXHAUST FANS
E
X H
A U
S T
F A
N S
T A
T U
S
STAT-EF-2
DI
A
IR
F
IIL
T E
R P
R E
S S
U R
E D
R O
(P R
E -F
IL
T
E R
DP-PRE-
FILTER-3
AI
A
IR
F
IIL
T E
R P
R E
S S
U R
E D
R
(H
P A
-F
IL
T E
R
DP-FNL-
FLTR-4
AI
V F
D D
R
IV
E S
P E
E D
EA-5
AO
E X
H A
U S
T F
A N
L O
W S
T A
T
IC
C
U T
O U
T
EAP-LL-6
E X
H A
U S
T A
IR
S
T A
T
IC
P R
E S
S U
R E
EASP-7
DI AI
EA-5
DP-PRE-FLTR-3 DP-FNL-FLTR-4
HF-EF-8
M
MOTORIZED ISOLATION
DAMPER STATUS
DAMPER
OPEN/CLOSED
HF-EF-9
M
HF-EF-8
MOTORIZED ISOLATION
DAMPER STATUS
DAMPER
OPEN/CLOSED
HF-EF-9
M O
T O
R
IZ
E D
IS
O
LA
T
IO
N
D A
M P
S
T A
T U
S
HF-EF-8
HF-EF-8
M
MOTORIZED ISOLATION
DAMPER STATUS
DAMPER
OPEN/CLOSED
HF-EF-9
NO
HF-EF-8
M
MOTORIZED ISOLATION
DAMPER STATUS
DAMPER
OPEN/CLOSED
HF-EF-9 NC
DI
M O
T O
R
IZ
E D
IS
O
LA
T
IO
N
D A
M P
S
IT
IO
N
HF-EF-9
DO
P: 937-224-0861 www.heapy.com
VA Project No.
JPA Project No.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
Office of Construction and Facilities Management
PROJECT NO. STATE COA FIRM NO.
3131 Newmark Drive, Suite 200 Miamisburg, Ohio 45342 |www.jpaarch.com| 937.461.3290
/6
/2
:4
:0
P M
Renovate MICU/SICU
10/17/2025
CONTROLS
M902
AJGBRB
19018.00
539-20-104
Cincinnati, Ohio
100% CONSTRUCTION
DOCUMENTS
2019-05193 01528
SCALE: NONE
EMERGENCY EXHAUST SYSTEM CONTROLS
Revisions Date
7 Addendum #4 2026-01-06
AHU SEQUENCE
1. THE UNIT SHALL BE PROVIDED WITH FACTORY MOUNTED UL LISTED A2L MITIGATION
CONTROLLER. THE A2L MITIGATION CONTROLLER IS PART OF THE REFRIGERANT
DETECTION SYSTEM AND IS DESIGNED TO DETECT A2L REFRIGERANT LEAKS IN THE
AIRSTREAM AND/OR CABINET.
A. AN ALARM IS TRIGGERED BY ANY ONE OR MORE OF THE ATTACHED SENSORS
DETECTING A A2L REFRIGERANT LEAK OR BY THE CONTROLLER NOT DETECTING A
SENSOR CONNECTION THE ALARM STATE, THE CONTROLLER WILL ENABLE THE
SUPPLY FAN, DISABLE THE COMPRESSORS, ENABLE THE ALARM, AND ALARM TO THE
BAS THRU AN ALARM RELAY CONTACT.
B. IF THE CONTROLLER DOES NOT RECEIVE PROOF OF FLOW WITHIN 2.5 MINUTES AFTER
ENABLING THE FAN IN THE ALARM STATE, OTHERWISE THE FAN WILL BE DE-
ENERGIZED AND REINITIATE MITIGATION MODE.
C. THE A2L CONTROLLER WILL REMAIN IN THE ALARM STATE FOR FIVE MINUTES AFTER
THE SENSOR IS CLEARED BEFORE RETURNING TO NORMAL OPERATION.
D. IF A CABINET SENSOR DETECTS A A2L REFRIGERANT LEAK THE CONTROLLER WILL
DISABLE THE COMPRESSORS, AND ALARM TO THE BAS THRU AN ALARM RELAY
CONTACT.
2. UPON AN ALARM OF THE AIR HANDLER A2L MITIGATION CONTROLLER REFRIGERANT LEAK
DETECTION IN THE AIRSTREAM (MONITORED BY THE BAS THRU THE MITIGATION
CONTROLLER ALARM RELAY CONTACT AND ALSO THRU BACNET COMMUNICATION). THE
BAS SHALL DRIVE ALL VAV DAMPER POSITION TO FULL AIRFLOW SETPOINT.
File details come from the government source that posted it. Updated .