This document is a Standard Form 30 Amendment of Solicitation/Modification of Contract for a Department of Veterans Affairs project at the Network Contracting Office (NCO) 10 in Cincinnati, OH. Amendment 0005 provides clarifications to multiple Requests for Information (RFIs) related to a construction project, including details about lead-based paint abatement, equipment installation, commissioning responsibilities, and demolition of headwall units. Key clarifications include: all existing doorframes requiring lead abatement, assumptions that OFCI equipment is plug-in type, confirmation that Levin Porter and Associates is contracted directly by the VA for commissioning, and specifications for demolishing second-floor wall-mounted patient headwalls while protecting third-floor ceiling-mounted booms.

The amendment also addresses technical questions about cable management for an EHRM project and potential cable pathway modifications. The contractor is instructed to bid according to the construction documents as presented, with the understanding that any significant deviations or additional costs may need to be addressed through change orders. Two attachments are included: a General Commissioning Specifications document (01 91 00) and a First Floor Plan for the ED Project. The bid opening date, time, and call-in information remain unchanged from previous amendments, and the document is signed by the Contracting Officer from the VA's Network Contracting Office.

View the file

Other files

Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE 7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO. 1. CONTRACT ID CODE

FACILITY CODE CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR

ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES

SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30 PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print) (Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

1 3

0005 01-13-2026

539-26-1-6905-0001

539-20-104

Department of Veterans Affairs

Network Contracting Office (NCO) 10

260 E. University Avenue

Cincinnati OH 45219

Department of Veterans Affairs

Network Contracting Office (NCO) 10

260 E. University Avenue

Cincinnati OH 45219

To all Offerors/Bidders

36C25026B0001

10-21-2025

X

X X

X 1

This amendment is issued to provide the following information:

-Post the clarifications to several RFI's (see page 2)

-Post 01 91 00 commissioning specification section (see attachment)

-Post the attachment for RFI #145 (First Floor Plan ED Project)

-Bid opening date, time and call-in information remain the same. (see amendments 0003 & 004)

Ronald T. Heidemann

Contracting Officer

NCO1015L3-0502

CONTINUATION PAGE

CLARIFICATIONS FOR RFIs

RFI #2 asked about LBP abatement. Response is to strip paint on the beige door frames in the MICU. Which frames are beige? The survey only identifies the one sampled as “North Doorway into Pharmacy Room in

MICU”. Plans do not identify a pharmacy. There is A277 Medication with a door to the North that goes to A298 Office. Even if we assume that door is the door mentioned, which other doors are beige? There are two other metal door frames identified in the survey (A299 and A389 (A389 is not in the project area)) and there is nothing distinguishing about any of these three types to be able to determine the other doors that match each type.

Perhaps for the sake of leveling bids, the COR could state a certain number for all bidders to include and any deviation may be addressed as a Change

Order.

Answer: All doorframes existing to remain in scope to require lead abatement.

RFI #15 asked for installation details for OFCI equipment. Response states to coordinate with COR. Without details, we cannot include the labor costs associated with installing any of this equipment. Please provide details or we will need owner to pay additional as change order.

Answer: Contractor should assume equipment is plug-in type only.

Several RFI ask who is responsible for Commissioning – meaning who pays for it. Is Levin Porter and Associates contracted and paid for directly by the VA under separate contract, or is the GC to include their cost in our bid? (RFI 32, 85, 129, and 163)

Answer: Refer to attachment for commissioning specification section.

Yes...Levin Porter and Associates are contracted and paid for directly by the VA under a separate contract. The phone number is 937-224-1931.

RFI #145 – asked about layout of the area indicated by Note 1.05 and A101-

N that states that area has a project underway. The response said to refer to RFI 13 which is about the laydown area. Please provide a response to this question.

Answer: Layout is provided in attachment. Project is currently under construction.

RFI #147 – asked about headwall units not shown on plans. Response stated we are to demo those. We cannot quantify the cost of this without knowing locations, quantity, etc. Please provide more information or this must be addressed as a change order as unforeseen.

Answer: Second floor wall mounted patient head walls shall be demoed.

Assume each patient room has (1) head wall each. Third floor ceiling mounted booms shall remain and contractor to protect in place and work around.

RFI #168 states that a separate EHRM project is underway and is providing racks and cable management and that the GC for this bid is responsible for terminating those cables. This is highly unusual to require a subsequent contractor to work another contractor’s system. We can’t know if they ran the correct wires, ran them properly, provided adequate labeling, etc. They should be responsible for all their own terminations. If this is to be on our contract, we need a detailed list of all drops, cable types, lengths, etc. as well as commitment that any errors introduced by them shall not negatively impact this GC for contract time or material expense.

Answer: Contractor to bid as shown in the construction documents.

RFI 169 asked if a different cable type could be used to address extended cable runs. Response asked us to provide new drawings proposing new pathways. We cannot ascertain the cost of that option not knowing if it will be approved. Please advise what we should include in our bid amount: 1 – use GameChanger for longer runs, 2 – bid as shown and owner will fund change order for either using GameChanger cables or developing designs and all costs associated with new pathways.

Answer: Contractor to bid as shown in the construction documents.

ATTACHMENTS:

01 91 00 General Commissioning Specifications.

First Floor Plan ED Project.