36C24419B0040-0002005.pdf

PDF 940 KB Posted

Attached to
Replace Mechanical Rooms, Project No. 542-18-105 Federal contract opportunity
Solicitation number
36C24419B0040
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 4

About this file

36C24419B0040 0002 MD102.pdf

View the file

Other files for this federal contract opportunity

Other files attached to Replace Mechanical Rooms, Project No. 542-18-105, newest first.
File Type Posted
36C24419C0185-000.docx DOCX document
36C24419B0040-0002004.pdf PDF
36C24419B0040-0002000.docx DOCX document
36C24419B0040-0002002.pdf PDF
36C24419B0040-0002003.pdf PDF
36C24419B0040-0002001.pdf PDF
36C24419B0040-0001000.docx DOCX document
36C24419B0040-0001001.pdf PDF
36C24419B0040-004.pdf PDF
36C24419B0040-005.pdf PDF
36C24419B0040-001.docx DOCX document
36C24419B0040-008.pdf PDF
36C24419B0040-006.pdf PDF
36C24419B0040-003.pdf PDF
36C24419B0040-007.pdf PDF
36C24419B0040-002.pdf PDF
36C24419B0040-000.docx DOCX document
Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ETR MEDIUM PRESSURE STEAM PIPING.

ENSURE INTEGRITY OF EXISTING INSULATION EFFECTED

BY INDICATED ICRA BARRIER. REPAIR ANY DAMAGED INSULATION.

REFER TO AE-101 FOR MORE INFORMATION.

M-102

MD102

M D

_____MD102

ENSURE INTEGRITY OF EXISTING INSULATION EFFECTED

BY INDICATED ICRA BARRIER. REPAIR ANY DAMAGED INSULATION.

REFER TO AE-101 FOR MORE INFORMATION.

## KEY NOTES:

Revisions: Date

Drawing Title:

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

Office of Construction and Facilities Management

CONSULTANTS: PROJECT MANAGER:

SHEET NOTES:

Date Checked Drawn

FULLY SPRINKLERED

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

7/

/2

3:

:2

P

M

MD102

BUILDING 4 DEMOLITION PLANS

4 23PLH SWR

RENOVATE MECHANICAL

ROOMS & EQUIPMENT

PHASE 1

1400 BLACKHORSE HILL RD

COATESVILLE, PA 19320

MAY 1, 2019

100% CONSTRUCTION DOCUMENTS

542-18-10517-251

N

AREA OF WORK

SCOPE OUTLINE

BUILDING 4 KEY PLAN

SCALE: NO SCALE

1 COORDINATE ALL WORK WITH THE GENERAL

CONTRACTOR, OTHER TRADES AND THE COR TO

MINIMIZE DISRUPTION OF AREAS OUTSIDE OF THE

PROJECT LIMITS OF WORK.

2 WORK SHALL BE CARRIED OUT SEASONALLY SUCH

THAT THE HOT WATER SYSTEM IS DOWN WHEN THE

BUILDING IS DEMANDING COOLING, AND THE CHILLED

WATER SYSTEM IS DOWN WHEN THE BUILDING IS

DEMANDING HEATING. SUBMIT A DETAILED PHASING

PLAN FOR APPROVAL.

3 THE DOMESTIC WATER SERVICE SHALL REMAIN

OPERATIONAL DURING OCCUPIED HOURS. MOST

BUILDINGS HAVE DOWNTIME DURING WEEKENDS AND

AFTER BUILDING HOURS. BUILDING 7 MUST MAINTAIN

DOMESTIC HOT AND COLD WATER SERVICE DUE TO

PATIENTS RESIDING IN THE BUILDING.

5 REPAIR OR REPLACE ALL DAMAGED DUCT AND PIPE

INSULATION DAMAGED DURING THE COURSE OF

WORK. INSULATE ALL UNINSULATED EXISTING PIPING

TO REMAIN PER SPECIFICATIONS.

6 FIELD VERIFY THE SIZES OF ALL EXISTING PIPING TO

REMAIN.

7 ABATE ALL ASBESTOS CONTAINING MATERIALS IN

THE WORK AREA. SUBMIT AN ABATEMENT PLAN FOR

APPROVAL.

8 THERE IS POTENTIAL FOR STERILE PROCESSING

SERVICE (SPS) REQUIRED ACCESS TO THE BUILDING

4 MECHANICAL ROOM DURING CONSTRUCTION.

ALLOW FOR COORDINATED ACCESS IF REQUIRED.

Scale: 1/2" = 1'-0"

BUILDING 4 MECHANICAL - DEMOLITION FROM 84" ABOVE

FLOOR TO DECK ABOVE

Scale: 1/2" = 1'-0"

BUILDING 4 MECHANICAL - DEMOLITION FROM FLOOR TO

84" ABOVE FLOOR

0 4 8 16

NORTH

TRUE

0 4 8 16

NORTH

TRUE

1 DEMOLISH PIPING TO WALL / CEILING AND

PREPARE FOR RECONNECTION PER NEW WORK.

2 CAP STEAM PIPING AT POINT SHOWN.

3 STERILIZERS SERVING SPS TO STAY

OPERATIONAL.

4 DEMOLISH EXPANSION TANK AND SUPPORTS

COMPLETE.

5 DEMOLISH SHELL AND TUBE HEAT EXCHANGERS

AND SUPPORTING STEEL DUNNAGE COMPLETE.

6 DEMOLISH HOT WATER PUMP COMPLETE.

7 DEMOLISH CHILLED WATER PUMP COMPLETE.

8 DEMOLISH SHELL AND TUBE DOMESTIC HOT

WATER HEAT EXCHANGER COMPLETE.

9 TEMPORARILY REMOVE THE STEAM GENERATOR

AND REINSTALL NEARBY, FOLLOWING

CONSTRUCTION. THE NEW LOCATION SHOULD BE

CLOSE TO THE EXISTING, BUT ADJUSTED TO

ALLOW FOR IMPROVED ACCESSIBILITY TO THE

STERILIZERS. COORDINATE WITH THE VA. EXTEND

CONNECTED PIPING ACCORDINGLY.

Scale: N.T.S.

3 BUILDING 4 ENTRY

Scale: N.T.S.

4 BUILDING 4 HOT WATER PUMPS

Scale: N.T.S.

5 BUILDING 4 STERILIZERS

4 Progress Issuance 4 Date 4

Sheets
M-102 - BUILDING 4 MECHANICAL ROOM NEW WORK PLANS
M-103 - BUILDING 4 MECHANICAL TEMPORARY CHILLED WATER PUMPS AND OVERALL BUILDING PLANS
M-107 - BUILDING 9 MECHANICAL ROOM NEW WORK PLANS
M-601 - MECHANICAL SCHEDULES
MD102 - BUILDING 4 DEMOLITION PLANS