3-05A BID SCHEDULE.pdf

PDF 71 KB Posted

Attached to
IFB - MIDDLETON WASH TRAIL CONSTRUCTION
Solicitation number
26-255
Issued by
Washington County, Utah

About this file

This is a bid schedule document for the City of St. George, Utah, prepared by Alliance Consulting for the Middleton Wash Trail construction project. The project encompasses two separate segments: the base bid for Middleton Wash Trail South (Red Cliffs Drive to Arroyo Drive) and an alternate bid for Middleton Wash Trail North (Cottonwood Springs Road to Red Hills Parkway). The base bid includes general conditions, dust control, traffic control, clearing and grubbing of approximately 1.24 acres, storm drain installation with various pipe sizes and inlet configurations, 19,975 square feet of asphalt paving, concrete sidewalk flatwork, trail pavement markings, 415 linear feet of powder-coated safety rail, stacked rock walls totaling 1,000 square feet, an 80-foot pedestrian span bridge with concrete deck, and concrete abutment walls. The alternate bid scope includes similar general conditions and site preparation work for approximately 0.72 acres, earthwork and imported fill operations, storm drain components, 32,335 square feet of asphalt paving with milling of existing roadway, concrete sidewalk and curb/gutter installation, 1,095 linear feet of safety rail, and wall construction comprising both stacked concrete block and stacked rock walls totaling approximately 12,945 square feet.

Bidders are required to submit a bid bond equal to 5 percent of the total bid amount, issued by a surety company licensed in the State of Utah on a form acceptable to the City of St. George. A 100 percent performance bond covering labor and materials is mandated upon project award. The bid schedule format requires unit prices and extended prices for all line items, with separate totals for the base bid and alternate bid components. The City reserves the right to reject any or all submissions and waive any formality or technicality in the interest of the municipality. No specific bid opening date, award timeline, or contract term information is provided in this schedule document.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PREPARED BY: Alliance Consulting

PROJECT NO: 4669

LOCATION: St. George

DATE: 1/9/26

DRAWING: Middleton Wash Trail OPT3.dwg

ITEM DESCRIPTION QTY UNIT UNIT PRICE EXTENDED PRICE

GENERAL

1 General Condition/Mobilization

1 LS

2 Dust Control

1 LS

3 Traffic Control

1 LS

4 Clear & Grub (Approx 1.24 Acres)

1 LS

5 Pre-Construction Condition Documentation

1 LS

6 SWPPP Prep, Documentation & BMP Items

1 LS

7 Rock Trackout Pad (1 Location)

1 LS

8 Silt Fence

2,105 LF

9 Wattles (Size 12") 150 LF

EARTHWORK

10 Earthwork/Rework [Approx (3,540 CY)/Imported Fill(2,740 CY)]

1 LS

STORM DRAIN

11 3'X3' lnlet with Grate 5 Each

12 24" HDPE Storm Drain Pipe

205 LF

13 18" HDPE Storm Drain Pipe

40 LF

14 12" PVC SDR-35 Pipe with lnlet box (2 Beehive Grates)

55 LF

15 24" End Section with Rip-Rap & Filter Fabric 7 Each

16 18" End Section with Rip-Rap & Filter Fabric 2 Each

17 18" D50 Rip-Rap with Filter Fabric (Basalt Rock)

520 SF

18 12" D50 Rip-rap with Filter Fabric (Basalt Rock)

1,200 SF

PAVING

19 2.5" Thick Asphalt(Voidless Asphalt Mix)

19,975 SF

20 6" Thick Type II Gravel Roadbase

19,975 SF

21 4" Thick Concrete Sidewalk Flatwork with 4" Roadbase

565 SF

22 Remove Existing Concrete (Approx. 275 SF)

1 LS

23 Shoulder 1" Crushed Rock (Basalt)

10,250 SF

24 Trail Pavement Markings

1 LS

25 Trail Safety Rail (Powder-Coated)

415 LF

26 Sign Plaques and Wood Posts 7 Each

WALLS, BRIDGE

27 Install Stacked Rock Walls with Geo-Grid Fabric (Basalt Rock)

1,000 SF

28 Installation of 80 foot Pedestrian Span Bridge with Concrete Deck

1 LS

29 Concrete Abutment Walls & 6" Concrete Approaches

1 LS

Total

BID SCHEDULE - MIDDLETON WASH TRAIL

Middleton Wash Trail South (Red Cliffs Dr. to Arroyo Dr.)

(BASE BID)

ITEM DESCRIPTION QTY UNIT UNIT PRICE EXTENDED PRICE

Middleton Wash Trail North (Cottonwood Springs Rd to Red Hills Pkwy) (ALTERNATE BID)

ITEM DESCRIPTION QTY UNIT UNIT PRICE EXTENDED PRICE

GENERAL

30 General Condition/Mobilization

1 LS

31 Dust Control

1 LS

32 Traffic Control

1 LS

33 Clear & Grub (Approx 0.72 Acres)

1 LS

34 Pre-Construction Condition

1 LS

35 SWPPP Prep, Documentation & BMP Items

1 LS

36 Rock Trackout Pad (1 Location)

1 LS

37 Silt Fence

1,420 LF

EARTHWORK

38 Earthwork(1,635 CY)/Imported Fill(460 CY)

1 LS

STORM DRAIN

39 3'X3' lnlet Box (Cast In Place) 1 Each

40 12" PVC SDR-35 Pipe with lnlet box (5 Beehive Grates)

120 LF

41 12" D50 Rip-rap with Filter Fabric (Basalt Rock)

350 SF

42 8" D50 Rip-rap with Filter Fabric (Basalt Rock)

550 SF

POWER

43 Relocate Secondary/Communication Conduits (Cottonwood Springs Rd)

1 LS

PAVING

44 2.5" Thick Asphalt (Voidless Asphalt Mix)

32,335 SF

45 6" Thick Type II Gravel Roadbase

14,100 SF

46 Mill Existing Asphalt Roadway

38,400 SF

47 4" Thick Concrete Sidewalk Flatwork with 4" Roadbase

2,935 SF

48 30" High Back Curb & Gutter with Base

85 LF

49 ADA Ramp 1 Each

50 Remove Existing Concrete & ADA Ramp (Approx. 540 SF)

1 LS

51 Remove Existing Curb & Gutter (Approx 35 LF) (1700 E & Middleton Dr.)

1 LS

52 Shoulder 1" Crushed Rock (Basalt)

7,145 SF

53 Shoulder Milled Asphalt

9,155 SF

54 6" Thick Concrete (Driveway Approach) with 6" Base

70 SF

55 Trail Pavement Markings

1 LS

56 Trail Safety Rail (Powder-Coated)

1,095 LF

57 Sign Plaques and Wood Posts 10 Each

WALLS

58 Stacked Concrete Block Wall (Stone Look)

1,535 SF

59 Stacked Rock Walls with Geo-Grid Fabric (Basalt Rock)(Wall Drains

11,410 SF

60 Concrete Retaining Wall

1 LS

Total

GRAND TOTAL