24052 Instructions to Bidders.pdf
PDF 194 KB Posted
- Attached to
- Construct T-Hangars and Site 24052-W96
- Solicitation number
- IFB-120922
- Issued by
- New Kent County, Virginia
About this file
This is an Instructions to Bidders document for New Kent County Airport in Quinton, Virginia, related to the construction of T-Hangars and associated site work (Delta Project Number 24052-W96). The project scope includes construction of a new 12-unit T-Hangar building with alternate designs for 10-unit or 8-unit configurations based on available funding. The construction site work encompasses grading, drainage, paving, and installation of electrical infrastructure. A non-mandatory pre-bid conference is scheduled for June 4, 2026, at 10:00 AM at the New Kent County Airport Terminal Building (6901 Terminal Road, Quinton, Virginia 23141). Bidders may submit written questions regarding project requirements to John D. Borgie or Amy M. Ferrell via email (jborgie@deltaairport.com, aferrell@deltaairport.com) with a deadline of 5:00 PM local time on June 16, 2026. Bids must be submitted on prescribed forms and include evidence of bidder competency and financial responsibility as detailed in Section 20-02 of the Part 1 General Contract Provisions.
The bidding documents include the Invitation for Bids, Instructions to Bidders, Bid Forms, Bid Schedifications, Bid Certifications and Disclosures, Bid security, proposed Contract Documents, Plans, and any issued Addenda. Bidders must submit a Prime Contractor Data Collection Form and Subcontractor Data Collection Forms for all firms intended to subcontract work, as required by the U.S. Department of Transportation under 49 CFR Part 26 Subpart A. All federal contract provisions contained within the bidding and contract documents must flow down to subcontracts and sub-tier agreements, with the Contractor bearing responsibility for subcontractor compliance. The project is subject to federal assistance requirements, and bidders certify compliance with all Federal Contract Provisions by submitting their bids. Award of contract and contract execution procedures are governed by Section 30 of the Part 1 General Contract Provisions, with additional contract conditions and insurance requirements outlined in Sections 10 and 40-90 of the same document.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Instructions to Bidders 1
Construct T-Hangars and Site | 24052 - W96
Instructions to Bidders
DEFINITIONS
Bid – The Bidder’s formal offer, written and submitted on the prescribed forms, to perform the Work for the Project at a specified cost based on the terms and conditions outlined in the Bidding Documents.
Bidding Documents – The Bidding Documents include the Invitation for Bids (advertisement);
Instructions to Bidders; Bid Forms and Supplements (including but not limited to the Bid Form; Bid
Schedule(s); and all Bid Certifications and Disclosures); Bid bond or other accepted forms of Bid security; proposed Contract Documents; and issued Addenda.
Contract Documents – The Contract Documents include the Bid submitted by the awarded Contractor; the
Project Manual, other than the supplemental resource material included in the Appendices which provide geotechnical and existing conditions information; the Plans; and issued Addenda.
Project Manual – A comprehensive written manual consisting of the documents that define the technical, contractual, and administrative requirements for procuring and constructing the Project. Contents may be bound in one or more volumes.
BIDDING REQUIREMENTS
Refer to Section 20, Proposal Requirements and Conditions, as found in Part 1 – General Contract
Provisions.
PRE-BID CONFERENCE (NON-MANDATORY)
A pre-bid conference for the Construct T-Hangars and Site Project will be held to discuss the proposed construction, Project Manual, and Plans. All potential Bidders are strongly encouraged to attend. The pre-bid conference details are as follows:
Date: June 4, 2026
Time: 10:00 AM
Format: In-person meeting
Location: New Kent County Airport - Terminal Building
6901 Terminal Road
Quinton, Virginia 23141
BIDDER QUESTIONS
A Bidder that has questions regarding the correct meaning of a Project requirement may submit a written request for interpretation. Questions should be sent via email to the Owner's representative in the
"Attention" line listed below and include the Project name; Airport name and location; Delta Project number; and Bidder's name, contact information, and contact phone number.
Instructions to Bidders 2
Attention: John D. Borgie, Amy M. Ferrell
Via Email: jborgie@deltaairport.com, aferrell@deltaairport.com
Project Name: Construct T-Hangars and Site
Airport Name: New Kent County Airport
Airport Location: Quinton, Virginia
Delta Project Number: 24052 - W96
Questions received after 5:00 PM local time on June 16, 2026, may not be answered.
QUALIFICATION OF BIDDERS
The Bidder must provide evidence of its competency and financial responsibility to perform the Project
Work. Evidence must be submitted to the Owner with the Bid. Refer to Section 20, paragraph 20-02, Qualification of Bidders, as found in Part 1 – General Contract Provisions for a description of acceptable documentation.
The Owner is subject to public records laws and may be required to release Bid submissions in accordance with the law. Any document submitted as evidence of qualifications that the Bidder deems to be confidential must be clearly identified and marked as such; however, the material may still be subject to public release under applicable law. The Bidder may seek to invoke confidential information protection for submission of any data/material by (1) identifying the data/material in a written description included with the Bid submission, (2) clearly marking the data/material as confidential, and (3) providing a written statement included with the Bid submission detailing the reasons why protection is necessary. The Owner reserves the right to ask for additional clarification prior to establishing protection.
FEDERAL CONTRACT PROVISIONS AND SUBCONTRACTS
In order for the Owner to remain compliant with its Sponsor obligations, federal laws and regulations require the Owner as a recipient of federal assistance to include specific provisions in certain contracts, solicitations, or specifications regardless of whether the Project is federally funded. These clauses are listed in Contract Conditions.
Unless otherwise stated, the Federal Contract Provisions contained within the Bidding and Contract
Documents shall flow down to subcontracts and to sub-tier agreements, and the Contractor shall be responsible for compliance with the Federal Contract Provisions by any subcontractor, lower-tier subcontractor, or service provider.
By signing and submitting a Bid for the Project, the Bidder certifies that it has read, understands, and will comply with all Federal Contract Provisions.
PRIME CONTRACTOR AND SUBCONTRACTOR DATA COLLECTION
The U.S. Department of Transportation, under 49 CFR Part 26 Subpart A, requires the Owner to collect and report certain prime contractor and subcontractor data on its federally assisted projects. The Bidder must submit with its Bid a completed Prime Contractor Data Collection Form for itself and a completed
Subcontractor Data Collection Form for every firm with which it intends to subcontract to perform Work for the Project, regardless of its Disadvantaged Business Enterprise (DBE) status. Both forms are provided herein.
Instructions to Bidders 3
AWARD OF CONTRACT
Refer to Section 30, Award and Execution of Contract, as found in Part 1 – General Contract Provisions.
OTHER CONTRACT CONDITIONS, INCLUDING INSURANCE REQUIREMENTS
Refer to Section 10, Definition of Terms, and Sections 40 through 90 as found in Part 1 – General
Contract Provisions.
END OF INSTRUCTIONS TO BIDDERS