24052 Bid Schedule.pdf

PDF 299 KB Posted

Attached to
Construct T-Hangars and Site 24052-W96
Solicitation number
IFB-120922
Issued by
New Kent County, Virginia

About this file

This is a bid schedule document for the Virginia construction project titled "Construct T-Hangars and Site 24052-W96." The project involves constructing a new 12-unit T-hangar complex with associated site work including grading, drainage, paving, and electrical installation. The bid schedule presents three alternates based on funding availability: the base bid for 12 units, Alternate One for 12 units with modified quantities, Alternate Two for 10 units, and Alternate Three for 8 units. The schedule lists 51 line items covering erosion control measures (silt fence, sediment traps, inlet protection), site preparation (clearing, grubbing, excavation), drainage infrastructure (pipes, culverts, drop inlets, manholes), electrical work (conduit, junction boxes, barricades), paving (milling, base course, asphalt surfaces), and T-hangar complex components (foundation, materials, erection, electrical). Quantities vary across the alternates, with notable differences in excavation volumes, subbase course requirements, bituminous material tonnages, and the number of T-hangar units, ranging from 8 to 12.

The bid schedule is formatted as a blank proposal form requiring contractors to enter unit prices in figures and written words for each line item, then calculate extended totals and provide an overall total bid amount. The document specifies unit measurements including linear feet (LF), each (EA), lump sum (LS), square yards (SY), cubic yards (CY), acres (AC), square feet (SF), and tons (TN). Each line item identifies the work code designation (such as C-102 for construction, P-152 for excavation, D-701 for drainage pipe, M-108 for hangar components, and R-315 for bituminous courses) and approximate quantity. The document provides no information regarding pricing terms, payment schedules, bid submission deadlines, award timelines, contract duration, or funding sources.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BID SCHEDULE

Date:

Bid Proposal Summary For All Work Depicted In The Plans And Specifications

UNIT PRICES EXTENDED

ITEM ITEM WITH UNIT PRICE IN FIGURES TOTAL

NO. WRITTEN IN WORDS --------------------- ---------------------

DOLLARS DOLLARS

CENTS CENTS

C-102 650 LF

PER LINEAR FOOT

C-102 450 LF

PER LINEAR FOOT

C-102 2 EA

PER EACH

C-102 1 EA

PER EACH

C-102 2 EA

PER EACH

C-102 3 EA

PER EACH

C-102 1 EA

PER EACH

C-102 950 LF

PER LINEAR FOOT

C-102 3 EA

PER EACH

C-105 1 LS

PER LUMP SUM

CULVERT INLET PROTECTION

TEMPORARY DIVERSION DIKE

ROCK FILTER

MOBILIZATION

INLET PROTECTION

BID ALTERNATE ONE (1)

APPROX.

QUANTITY

INSTALLATION AND REMOVAL OF SILT FENCE

INSTALLATION AND REMOVAL OF SUPER SILT FENCE

STONE CONSTRUCTION ENTRANCE

TEMPORARY SEDIMENT TRAP

CHECK DAM

Bid Form Construct T-Hangars and Site - Alternate 1 | 24052 - W96

BLANK

Bid Proposal Summary For All Work Depicted In The Plans And Specifications

UNIT PRICES EXTENDED

ITEM ITEM WITH UNIT PRICE IN FIGURES TOTAL

NO. WRITTEN IN WORDS --------------------- ---------------------

DOLLARS DOLLARS

CENTS CENTS

BID ALTERNATE ONE (1)

APPROX.

QUANTITY

P-101 875 SY

PER SQUARE YARD

P-151 1 LS

PER LUMP SUM

P-152 9,000 CY

PER CUBIC YARD

P-152 500 CY

PER CUBIC YARD

P-154 800 CY

PER CUBIC YARD

P-154 3,500 SY

PER SQUARE YARD

P-620 500 SF

PER SQUARE FOOT

P-620 500 SF

PER SQUARE FOOT

P-620 1,000 SF

PER SQUARE FOOT

P-620 1 LS

PER LUMP SUM

MARKING (PERMANENT BLACK)

REFLECTIVE MEDIA

MARKING (PERMANENT YELLOW)

COLD MILLING (1.5" NOMINAL DEPTH)

CLEARING AND GRUBBING

UNCLASSIFIED EXCAVATION

MUCK EXCAVATION

SUBBASE COURSE

SEPARATION GEOTEXTILE

MARKING (INITIAL YELLOW)

Bid Form Construct T-Hangars and Site - Alternate 1 | 24052 - W96

UNIT PRICES EXTENDED

ITEM ITEM WITH UNIT PRICE IN FIGURES TOTAL

NO. WRITTEN IN WORDS --------------------- ---------------------

DOLLARS DOLLARS

CENTS CENTS

BID ALTERNATE ONE (1)

APPROX.

QUANTITY

D-701 24 LF

PER LINEAR FOOT

D-701 376 LF

PER LINEAR FOOT

D-701 100 LF

PER LINEAR FOOT

D-702 135 LF

PER LINEAR FOOT

D-705 610 LF

PER LINEAR FOOT

D-751 1 EA

PER EACH

D-751 1 EA

PER EACH

D-751 1 EA

PER EACH

D-752 1 EA

PER EACH

D-752 1 EA

PER EACH

6" PVC UNDERDRAIN OR EDGE DRAIN PIPE (PERFORATED)

18" RCP, CLASS III

24" RCP, CLASS III

NON-ENCASED CONDUIT, 2 WAY - 4" SCHEDULE 40 PVC CONDUIT

TRENCH DRAIN

MANHOLE, VDOT STANDARD 60" (MH-2)

DROP INLET, VDOT STD. DI-1

DROP INLET, VDOT STD. DI-7

18" END SECTION, VDOT STD. ES-1

24" END SECTION, VDOT STD. ES-1

Bid Form Construct T-Hangars and Site - Alternate 1 | 24052 - W96

UNIT PRICES EXTENDED

ITEM ITEM WITH UNIT PRICE IN FIGURES TOTAL

NO. WRITTEN IN WORDS --------------------- ---------------------

DOLLARS DOLLARS

CENTS CENTS

BID ALTERNATE ONE (1)

APPROX.

QUANTITY

D-752 2 EA

PER EACH

D-752 1 LS

PER LUMP SUM

T-901 4 AC

PER ACRE

T-908 4 AC

PER ACRE

L-110 350 LF

PER LINEAR FOOT

L-110 55 LF

PER LINEAR FOOT

L-110 2 EA

PER EACH

M-107 320 LF

PER LINEAR FOOT

M-108 1 LS

PER LUMP SUM

M-108 1 LS

PER LUMP SUM

M-108 1 LS

PER LUMP SUM

6" UNDERDRAIN END WALL, VDOT STD EW-12

WEIR WALL

SEEDING

MULCHING

BORED ELECTRICAL CONDUIT, 1 WAY - 4" HDPE CONDUIT

T-HANGAR COMPLEX FOUNDATION (12 UNITS)

CONCRETE ENCASED ELECTRICAL CONDUIT, 1 WAY - 4" HDPE CONDUIT

ELECTRICAL JUNCTION BOX

AVIATION BARRICADES

T-HANGAR COMPLEX MATERIALS (12 UNITS)

T-HANGAR COMPLEX ERECTION (12 UNITS)

Bid Form Construct T-Hangars and Site - Alternate 1 | 24052 - W96

UNIT PRICES EXTENDED

ITEM ITEM WITH UNIT PRICE IN FIGURES TOTAL

NO. WRITTEN IN WORDS --------------------- ---------------------

DOLLARS DOLLARS

CENTS CENTS

BID ALTERNATE ONE (1)

APPROX.

QUANTITY

M-108 1 LS

PER LUMP SUM

M-150 1 LS

PER LUMP SUM

M-150 1 EA

PER EACH

M-150 1 EA

PER EACH

M-150 1 EA

PER EACH

R-315 650 TN

PER TON

R-315 450 TN

PER TON

R-316 60 SY

PER SQUARE YARD

R-414 150 SY

PER SQUARE YARD

R-606 15,000 SY

PER SQUARE YARD#N/A

Total Bid Amount $

T-HANGAR COMPLEX ELECTRICAL (12 UNITS)

REMOVE CONCRETE CHANNEL

REMOVE UNDERDRAIN END WALL

REMOVE FLARED END SECTION

SOIL STABILIZATION MAT (VDEQ TREATMENT-1)

REMOVE ELECTRICAL VAULT

BITUMINOUS INTERMEDIATE COURSE, TYPE IM-19.0

BITUMINOUS SURFACE COURSE, TYPE SM-9.5

CONCRETE SIDEWALK (DEPTH)

RIPRAP CLASS A1

Bid Form Construct T-Hangars and Site - Alternate 1 | 24052 - W96

Page Intentionally Blank

Bid Proposal Summary For All Work Depicted In The Plans And Specifications

UNIT PRICES EXTENDED

ITEM ITEM WITH UNIT PRICE IN FIGURES TOTAL

NO. WRITTEN IN WORDS --------------------- ---------------------

DOLLARS DOLLARS

CENTS CENTS

C-102 650 LF

PER LINEAR FOOT

C-102 450 LF

PER LINEAR FOOT

C-102 2 EA

PER EACH

C-102 1 EA

PER EACH

C-102 2 EA

PER EACH

C-102 3 EA

PER EACH

C-102 1 EA

PER EACH

C-102 950 LF

PER LINEAR FOOT

C-102 3 EA

PER EACH

C-105 1 LS

PER LUMP SUM

BID ALTERNATE TWO (2)

APPROX.

QUANTITY

STONE CONSTRUCTION ENTRANCE

TEMPORARY SEDIMENT TRAP

INSTALLATION AND REMOVAL OF SILT FENCE

INSTALLATION AND REMOVAL OF SUPER SILT FENCE

CULVERT INLET PROTECTION

TEMPORARY DIVERSION DIKE

CHECK DAM

INLET PROTECTION

ROCK FILTER

MOBILIZATION

Bid Form Construct T-Hangars and Site - Alternate 2 | 24052 - W96

UNIT PRICES EXTENDED

ITEM ITEM WITH UNIT PRICE IN FIGURES TOTAL

NO. WRITTEN IN WORDS --------------------- ---------------------

DOLLARS DOLLARS

CENTS CENTS

BID ALTERNATE TWO (2)

APPROX.

QUANTITY

P-101 875 SY

PER SQUARE YARD

P-151 1 LS

PER LUMP SUM

P-152 9,000 CY

PER CUBIC YARD

P-152 500 CY

PER CUBIC YARD

P-154 730 CY

PER CUBIC YARD

P-154 3,100 SY

PER SQUARE YARD

P-620 500 SF

PER SQUARE FOOT

P-620 500 SF

PER SQUARE FOOT

P-620 1,000 SF

PER SQUARE FOOT

P-620 1 LS

PER LUMP SUM

COLD MILLING (1.5" NOMINAL DEPTH)

CLEARING AND GRUBBING

SUBBASE COURSE

SEPARATION GEOTEXTILE

UNCLASSIFIED EXCAVATION

MUCK EXCAVATION

MARKING (PERMANENT BLACK)

REFLECTIVE MEDIA

MARKING (INITIAL YELLOW)

MARKING (PERMANENT YELLOW)

Bid Form Construct T-Hangars and Site - Alternate 2 | 24052 - W96

UNIT PRICES EXTENDED

ITEM ITEM WITH UNIT PRICE IN FIGURES TOTAL

NO. WRITTEN IN WORDS --------------------- ---------------------

DOLLARS DOLLARS

CENTS CENTS

BID ALTERNATE TWO (2)

APPROX.

QUANTITY

D-701 24 LF

PER LINEAR FOOT

D-701 376 LF

PER LINEAR FOOT

D-701 100 LF

PER LINEAR FOOT

D-702 135 LF

PER LINEAR FOOT

D-705 610 LF

PER LINEAR FOOT

D-751 1 EA

PER EACH

D-751 1 EA

PER EACH

D-751 1 EA

PER EACH

D-752 1 EA

PER EACH

D-752 1 EA

PER EACH

NON-ENCASED CONDUIT, 2 WAY - 4" SCHEDULE 40 PVC CONDUIT

TRENCH DRAIN

18" RCP, CLASS III

24" RCP, CLASS III

DROP INLET, VDOT STD. DI-1

DROP INLET, VDOT STD. DI-7

6" PVC UNDERDRAIN OR EDGE DRAIN PIPE (PERFORATED)

MANHOLE, VDOT STANDARD 60" (MH-2)

18" END SECTION, VDOT STD. ES-1

24" END SECTION, VDOT STD. ES-1

Bid Form Construct T-Hangars and Site - Alternate 2 | 24052 - W96

UNIT PRICES EXTENDED

ITEM ITEM WITH UNIT PRICE IN FIGURES TOTAL

NO. WRITTEN IN WORDS --------------------- ---------------------

DOLLARS DOLLARS

CENTS CENTS

BID ALTERNATE TWO (2)

APPROX.

QUANTITY

D-752 2 EA

PER EACH

D-752 1 LS

PER LUMP SUM

T-901 4 AC

PER ACRE

T-908 4 AC

PER ACRE

L-110 350 LF

PER LINEAR FOOT

L-110 55 LF

PER LINEAR FOOT

L-110 2 EA

PER EACH

M-107 320 LF

PER LINEAR FOOT

M-108 1 LS

PER LUMP SUM

M-108 1 LS

PER LUMP SUM

M-108 1 LS

PER LUMP SUM

6" UNDERDRAIN END WALL, VDOT STD EW-12

WEIR WALL

BORED ELECTRICAL CONDUIT, 1 WAY - 4" HDPE CONDUIT

CONCRETE ENCASED ELECTRICAL CONDUIT, 1 WAY - 4" HDPE CONDUIT

SEEDING

MULCHING

T-HANGAR COMPLEX MATERIALS (10 UNITS)

T-HANGAR COMPLEX ERECTION (10 UNITS)

ELECTRICAL JUNCTION BOX

AVIATION BARRICADES

T-HANGAR COMPLEX FOUNDATION (10 UNITS)

Bid Form Construct T-Hangars and Site - Alternate 2 | 24052 - W96

UNIT PRICES EXTENDED

ITEM ITEM WITH UNIT PRICE IN FIGURES TOTAL

NO. WRITTEN IN WORDS --------------------- ---------------------

DOLLARS DOLLARS

CENTS CENTS

BID ALTERNATE TWO (2)

APPROX.

QUANTITY

M-108 1 LS

PER LUMP SUM

M-150 1 LS

PER LUMP SUM

M-150 1 EA

PER EACH

M-150 1 EA

PER EACH

M-150 1 EA

PER EACH

R-315 610 TN

PER TON

R-315 425 TN

PER TON

R-316 60 SY

PER SQUARE YARD

R-414 150 SY

PER SQUARE YARD

R-606 15,000 SY

PER SQUARE YARD

Total Bid Amount $

REMOVE CONCRETE CHANNEL

REMOVE UNDERDRAIN END WALL

T-HANGAR COMPLEX ELECTRICAL (10 UNITS)

BITUMINOUS INTERMEDIATE COURSE, TYPE IM-19.0

BITUMINOUS SURFACE COURSE, TYPE SM-9.5

REMOVE FLARED END SECTION

REMOVE ELECTRICAL VAULT

SOIL STABILIZATION MAT (VDEQ TREATMENT-1)

CONCRETE SIDEWALK (DEPTH)

RIPRAP CLASS A1

Bid Form Construct T-Hangars and Site - Alternate 2 | 24052 - W96

Page Intentionally Blank

Bid Proposal Summary For All Work Depicted In The Plans And Specifications

UNIT PRICES EXTENDED

ITEM ITEM WITH UNIT PRICE IN FIGURES TOTAL

NO. WRITTEN IN WORDS --------------------- ---------------------

DOLLARS DOLLARS

CENTS CENTS

C-102 650 LF

PER LINEAR FOOT

C-102 450 LF

PER LINEAR FOOT

C-102 2 EA

PER EACH

C-102 1 EA

PER EACH

C-102 2 EA

PER EACH

C-102 3 EA

PER EACH

C-102 1 EA

PER EACH

C-102 950 LF

PER LINEAR FOOT

C-102 3 EA

PER EACH

C-105 1 LS

PER LUMP SUM

ROCK FILTER

MOBILIZATION

CULVERT INLET PROTECTION

TEMPORARY DIVERSION DIKE

CHECK DAM

INLET PROTECTION

TEMPORARY SEDIMENT TRAP

INSTALLATION AND REMOVAL OF SILT FENCE

INSTALLATION AND REMOVAL OF SUPER SILT FENCE

BID ALTERNATE THREE (3)

APPROX.

QUANTITY

STONE CONSTRUCTION ENTRANCE

Bid Form Construct T-Hangars and Site - Alternate 3 | 24052 - W96

UNIT PRICES EXTENDED

ITEM ITEM WITH UNIT PRICE IN FIGURES TOTAL

NO. WRITTEN IN WORDS --------------------- ---------------------

DOLLARS DOLLARS

CENTS CENTS

BID ALTERNATE THREE (3)

APPROX.

QUANTITY

P-101 875 SY

PER SQUARE YARD

P-151 1 LS

PER LUMP SUM

P-152 9,000 CY

PER CUBIC YARD

P-152 500 CY

PER CUBIC YARD

P-154 660 CY

PER CUBIC YARD

P-154 2,750 SY

PER SQUARE YARD

P-620 500 SF

PER SQUARE FOOT

P-620 500 SF

PER SQUARE FOOT

P-620 1,000 SF

PER SQUARE FOOT

P-620 1 LS

PER LUMP SUM

MARKING (PERMANENT BLACK)

REFLECTIVE MEDIA

MARKING (INITIAL YELLOW)

MARKING (PERMANENT YELLOW)

SUBBASE COURSE

SEPARATION GEOTEXTILE

UNCLASSIFIED EXCAVATION

MUCK EXCAVATION

COLD MILLING (1.5" NOMINAL DEPTH)

CLEARING AND GRUBBING

Bid Form Construct T-Hangars and Site - Alternate 3 | 24052 - W96

UNIT PRICES EXTENDED

ITEM ITEM WITH UNIT PRICE IN FIGURES TOTAL

NO. WRITTEN IN WORDS --------------------- ---------------------

DOLLARS DOLLARS

CENTS CENTS

BID ALTERNATE THREE (3)

APPROX.

QUANTITY

D-701 24 LF

PER LINEAR FOOT

D-701 376 LF

PER LINEAR FOOT

D-701 100 LF

PER LINEAR FOOT

D-702 135 LF

PER LINEAR FOOT

D-705 610 LF

PER LINEAR FOOT

D-751 1 EA

PER EACH

D-751 1 EA

PER EACH

D-751 1 EA

PER EACH

D-752 1 EA

PER EACH

D-752 1 EA

PER EACH

18" END SECTION, VDOT STD. ES-1

24" END SECTION, VDOT STD. ES-1

DROP INLET, VDOT STD. DI-1

DROP INLET, VDOT STD. DI-7

6" PVC UNDERDRAIN OR EDGE DRAIN PIPE (PERFORATED)

MANHOLE, VDOT STANDARD 60" (MH-2)

NON-ENCASED CONDUIT, 2 WAY - 4" SCHEDULE 40 PVC CONDUIT

TRENCH DRAIN

18" RCP, CLASS III

24" RCP, CLASS III

Bid Form Construct T-Hangars and Site - Alternate 3 | 24052 - W96

UNIT PRICES EXTENDED

ITEM ITEM WITH UNIT PRICE IN FIGURES TOTAL

NO. WRITTEN IN WORDS --------------------- ---------------------

DOLLARS DOLLARS

CENTS CENTS

BID ALTERNATE THREE (3)

APPROX.

QUANTITY

D-752 2 EA

PER EACH

D-752 1 LS

PER LUMP SUM

T-901 4 AC

PER ACRE

T-908 4 AC

PER ACRE

L-110 350 LF

PER LINEAR FOOT

L-110 55 LF

PER LINEAR FOOT

L-110 2 EA

PER EACH

M-107 320 LF

PER LINEAR FOOT

M-108 1 LS

PER LUMP SUM

M-108 1 LS

PER LUMP SUM

M-108 1 LS

PER LUMP SUM

T-HANGAR COMPLEX FOUNDATION (8 UNITS)

T-HANGAR COMPLEX MATERIALS (8 UNITS)

T-HANGAR COMPLEX ERECTION (8 UNITS)

ELECTRICAL JUNCTION BOX

AVIATION BARRICADES

BORED ELECTRICAL CONDUIT, 1 WAY - 4" HDPE CONDUIT

CONCRETE ENCASED ELECTRICAL CONDUIT, 1 WAY - 4" HDPE CONDUIT

SEEDING

MULCHING

6" UNDERDRAIN END WALL, VDOT STD EW-12

WEIR WALL

Bid Form Construct T-Hangars and Site - Alternate 3 | 24052 - W96

UNIT PRICES EXTENDED

ITEM ITEM WITH UNIT PRICE IN FIGURES TOTAL

NO. WRITTEN IN WORDS --------------------- ---------------------

DOLLARS DOLLARS

CENTS CENTS

BID ALTERNATE THREE (3)

APPROX.

QUANTITY

M-108 1 LS

PER LUMP SUM

M-150 1 LS

PER LUMP SUM

M-150 1 EA

PER EACH

M-150 1 EA

PER EACH

M-150 1 EA

PER EACH

R-315 570 TN

PER TON

R-315 400 TN

PER TON

R-316 60 SY

PER SQUARE YARD

R-414 150 SY

PER SQUARE YARD

R-606 15,000 SY

PER SQUARE YARD

Total Bid Amount $

SOIL STABILIZATION MAT (VDEQ TREATMENT-1)

CONCRETE SIDEWALK (DEPTH)

RIPRAP CLASS A1

BITUMINOUS INTERMEDIATE COURSE, TYPE IM-19.0

BITUMINOUS SURFACE COURSE, TYPE SM-9.5

REMOVE FLARED END SECTION

REMOVE ELECTRICAL VAULT

REMOVE CONCRETE CHANNEL

REMOVE UNDERDRAIN END WALL

T-HANGAR COMPLEX ELECTRICAL (8 UNITS)

Bid Form Construct T-Hangars and Site - Alternate 3 | 24052 - W96