This is Addendum No. One to the construction contract documents for New Kent County Airport in Quinton, Virginia, issued by Delta Airport Consultants, Inc. on June 4, 2026. The project involves constructing a new 12-unit T-hangar facility with alternates available for 10-unit or 8-unit buildings depending on available funding. The scope includes site grading, drainage, paving, electrical installation, and associated site work. The County will award the project based on the alternate selected, with a Notice of Award executed upon bid evaluation and the signed contract to be received by the awarded contractor on or before October 20, 2026. Two separate Notices to Proceed will be issued: one for administrative startup and material procurement following final funding approval in October 2026, and a second for onsite construction anticipated to commence in Spring 2027. The total contract time is 165 calendar days, calculated only for onsite construction activities (tree clearing, earthwork, erosion and sediment control, drainage, foundation, building erection, paving, and electrical installation), with design, shop drawings, permitting, and material delivery excluded from this timeline. Liquidated damages are assessed at $3,000 per day for the overall contract and specifically for Phase A1, which affects access to the existing hangar.

The addendum clarifies that the contractor is responsible for final building, foundation, and electrical design to be signed and sealed by a professional engineer, with the minimum foundation depth of 5 inches of concrete over 6 inches of stone subbase serving as a planning reference only. The project specifies minimum internal ceiling height of 12 feet, minimum hangar door height of 12 feet, and LED interior and exterior lighting with minimum foot-candle requirements of 1 foot-candle in front of all doors and 50 foot-candles within the hangar. No building manufacturer is required to be pre-approved, though examples include Erect-a-Tube, Fulfab, Inc., and Kirk Airport Solutions, Inc. Electrical design must be based on single-phase power only, as three-phase power is unavailable at the airport. The Engineer will provide a Resident Project Representative for 90 calendar days to observe site work. No provisions for unit price indexing of asphalt or other materials are included in the contract documents, and the bifold doors may utilize either cable or strap lift systems.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM NO. ONE (1)

Addendum No. One (1) 1

CONSTRUCT T-HANGARS AND SITE

NEW KENT COUNTY AIRPORT

QUINTON, VA

AIP PROJECT NO. 3-51-0041-026-2025

DELTA PROJECT NO. 24052

JUNE 4, 2026

From: Delta Airport Consultants, Inc.

2700 Polo Parkway

Midlothian, VA 23113

To: All Bidders of Record

This Addendum is hereby made part of the contract documents and specifications of the above-referenced project. All other requirements of the original specification shall remain in effect in their respective order. Acknowledge receipt of this addendum by inserting its number and date in the proposal form.

PROPOSAL

1. NO CHANGES TO THE PROPOSAL

PROJECT MANUAL

2. NO CHANGES TO THE PROJECT MANUAL

PLANS

3. NO CHANGES TO THE PLANS

ATTACHMENTS

1. Questions and Answers

END OF ADDENDUM NO. ONE (1)

6/5/2026

ATTACHMENT NO. ONE (1)

Addendum No. One (1) 1 Attachment No. One (1)

CONSTRUCT T-HANGARS AND SITE

NEW KENT COUNTY AIRPORT

QUINTON, VA

AIP PROJECT NO. 3-51-0041-026-2025

DELTA PROJECT NO. 24052

QUESTIONS AND ANSWERS

1. QUESTION: If the bid is held until October, will the bid be awarded prior?

ANSWER: Yes. The County will award the project based on the Alternate selected. A

Notice of Award will be executed at that time. The awarded contractor will separately receive the signed contract on or before October 20, 2026.

Information regarding the bid bond is referenced in the Invitation to Bid.

2. QUESTION: When will the notice to proceed (NTP) be issued?

ANSWER: Two separate NTPs will be issued; one for the administrative start and procurement of materials and one for the start of onsite construction. The procurement NTP will be issued closely following final funding approval in October 2026.

3. QUESTION: What is the construction contract time and what are the liquidated damages?

ANSWER: The total contract time is 165 calendar days. Contract time will begin following the construction notice to proceed. The overall contract has

$3,000 per day of liquidated damages. The work phase that will affect access to the existing hangar (Phase A1) will have $3,000 per day of liquidated damages.

4. QUESTION: When is construction expected to start?

ANSWER: The County anticipates that administrative work will occur in Fall 2026 with construction in Spring 2027. The County’s intent is to allow flexibility for the Contractor to supply the building materials without impact to the construction. If the Contractor requests to start site work in Fall 2026, in anticipation of having the site prepared for the building materials delivery, the County will consider a full notice to proceed in Fall 2026. This will start the 165 Calendar Day Contract Time. A temporary stop work order would need to be issued to stop contract time for winter months. Any cost to temporarily stabilize the site during a stop work order would be at the

Contractor’s cost.

Addendum No. One (1) 2 Attachment No. One (1)

5. QUESTION: The building materials have a long lead time to approve and procure. What work may be completed prior to the start of construction time?

ANSWER: The 165 Calendar Day Contract Time is applicable only to on-site construction (tree clearing, earthwork, erosion and sediment control, drainage, foundation, building erection, paving, and electrical installation).

The final design, shop drawings, permitting, and material delivery period is

NOT included in the 165 Calendar Day period. The contractor may complete all shop drawings, and deliver materials to the project site, prior to construction.

6. QUESTION: What are the site work limits for Alternates 2 & 3?

ANSWER: Except for a portion of pavement on the plan-left side of the proposed building, the site work will end with the face of the selected building. In alternates 2 & 3, the areas not receiving full build out will be graded to final elevations and permanently stabilized. The limits of the alternates can be viewed on Sheet 8.

7. QUESTION: Are the hangar doors considered ADA?

ANSWER: No. Only the pedestrian doors will be considered accessible entrances.

8. QUESTION: Who designs the hangar foundation?

ANSWER: The Contractor will be responsible for final building, foundation, and electrical design, to be signed and sealed by a professional engineer.

9. QUESTION: What is the minimum foundation depth?

ANSWER: The depth shown on the plans should be considered the minimum foundation depth for planning purposes. 5” concrete over 6” stone subbase material. The final foundation depth is determined by the contractor’s final design of the foundation.

10. QUESTION: Is there a required building manufacturer?

ANSWER: No, several building manufacturers offer products that will meet the performance requirements of this project. Examples of manufacturers with recent Virginia T-hangars include but are not limited to Erect-a-Tube, Fulfab, Inc., and Kirk Airport Solutions, Inc. Manufacturers are not required to be pre-approved during bidding.

11. QUESTION: What is the standard bifold door height?

ANSWER: The minimum hangar door height is 12’.

Addendum No. One (1) 3 Attachment No. One (1)

12. QUESTION: What is the standard building height?

ANSWER: The minimum internal ceiling height is 12’.

13. QUESTION: Are the proposed electrical boxes to be traffic rated?

ANSWER: Yes.

14. QUESTION: Can a digital version of bid form be provided for bidders?

ANSWER: No. A digital bid for is not available. Please use the bid forms provided in the project manual.

15. QUESTION: Will the Engineer be providing an inspector?

ANSWER: The Engineer will be providing a Resident Project Representative (RPR) for

90 calendar days for the observation of site work.

16. QUESTION: Is the building sloped?

ANSWER: Yes, the building has a continuous slope along its longitudinal axis. See

Sheet 9.

17. QUESTION: Where do the spoils go?

ANSWER: Excess earthen materials will be placed to the north of the project site according to the information provided on the Grading and Drainage sheet, Sheet 9.

18. QUESTION: Will the building be fitted with high bay lights?

ANSWER: Yes.

19. QUESTION: What are the foot-candle requirements?

ANSWER: See Sheet 23 Hangar Details for Building Unit Electrical Notes – Contractor shall provide LED interior and exterior lighting sized in accordance with local code requirements but not less than 1 foot-candle of light in front of all doors and not less than 50 foot-candles of light within the hangar. Please note that exterior lights will require shielding to prevent direct light from reaching the runway and impacting pilots.

20. QUESTION: Can the contractor trim trees that inhibit access to the site?

ANSWER: Yes. The contractor can trim trees as needed with the permission of the airport manager.

Addendum No. One (1) 4 Attachment No. One (1)

21. QUESTION: Can the unit pricing for asphalt materials be tied to the VDOT AC Index?

ANSWER: No. No provision is included for indexing the unit price of asphalt or other materials.

22. QUESTION: Does the T-hangar require insulation of the roof and walls?

ANSWER: No. Insulation is not required for aircraft storage.

23. QUESTION: Does the trailer need to be onsite during site and earthwork construction?

ANSWER: Yes. The Engineer’s Field Office should be available during the 165

Calendar Day onsite construction period.

24. QUESTION: Is the electrical service on site single-phase or three-phase power?

ANSWER: Only single-phase power is available at the airport. All electrical design should be based on single phase.

25. QUESTION: Does the bifold doors require cable or strap lift doors?

ANSWER: Both cable and strap lift systems are acceptable.

2026-06-05T13:28:11-0400
John Borgie