2027-07 Addendum 1.pdf

PDF 1 MB Posted

Attached to
HVAC Upgrades - DPW Garage
Solicitation number
BID 2027-07
Issued by
Fairfield County, Connecticut

About this file

This addendum to ITB 2027-07 modifies contract documents for HVAC system upgrades at the Town of Stratford Department of Public Works Garage located at 550 Patterson Avenue, Stratford, Connecticut. The project scope includes removal of the existing steam boiler and associated heating system; installation of new gas-fired rooftop makeup air units with associated gas piping; installation of new infrared heating units with associated gas piping; new electrical work for the heating system replacement; and roof framing modifications to support the new rooftop HVAC units. An alternate bid item covers removal of an existing underground oil tank. The pre-bid walk-through was held September 2, 2026 at 10:00 a.m., with bid opening scheduled for September 18, 2026 at 10:00 a.m. The project award is anticipated on or about October 16, 2026, with construction mobilization beginning December 1, 2026 and substantial completion targeted for January 29, 2027. Final contract close-out is required by February 26, 2027.

Addendum #1, issued September 3, 2026, includes revisions to the bid form to incorporate tank removal unit costs, an updated milestone schedule, and an asbestos testing report and abatement specification. Asbestos testing conducted in April 2020 identified asbestos-containing materials in the boiler packing (approximately 150 square feet), boiler gaskets (approximately 5 square feet), and boiler masonry. Connecticut regulations require that any work disturbing asbestos-containing materials be performed by a licensed asbestos abatement contractor. The bid form requires contractors to include a $10,000 allowance for unforeseen conditions, with unused portions credited back to the owner. Contractors must also provide unit pricing for removal of contaminated soil and soil testing. The existing roof is a built-up roof system under warranty by W.P. Hickman Systems, Inc., and any roofing subcontractor must maintain appropriate certifications. Connecticut Temperature Controls (CTC) serves as the town's controls vendor. State of Connecticut prevailing wages are required if the total bid exceeds $100,000.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

9/3/2026

Addendum 1 1 of 2

ADDENDUM #1

HVAC Upgrades:

DPW Maintenance Garage

550 Patterson Ave.

Stratford, CT 06614

TOWN PROJECT NUMBER: 2027-07

ISSUED: 9/3/2026

PROJECT TEAM

Architect / Project Manager Mechanical Engineer

Addendum 1 2 of 2

The work shall be carried out in accordance with the following supplemental instructions and in accordance with the Contract Documents.

PROJECT MANUAL CHANGES

1. Bid Form

• Bid Form revised to include Tank Removal related Unit Costs. See attached.

2. 01009 – Milestone Schedule

• Revised. See attached.

3. Asbestos Testing Report and Abatement/Removal Specification

• The existing boiler contains asbestos.

• See attached testing report and abatement specification.

MISCELLANEOUS CHANGES / CLARIFICATIONS

1. Requests For Information (RFI) Log

• See attached RFI Log.

2. HVAC Controls / Sequence of Operation

• See attached.

*** END OF ADDENDUM #1 ***

Bid Form

BID FORM

Bids must be submitted to the Town of Stratford Purchasing Office, attention Phillip Ryan, Purchasing Agent, on the following form signed by an authorized company officer. Bids will be opened on Friday, September 18, 2026, 10:00am.

Phillip Ryan, Purchasing Agent Town of Stratford 2725 Main Street Stratford, CT 06615

HVAC Upgrades:

DPW Maintenance Garage 550 Patterson Ave.

Stratford, CT

To Whom It May Concern:

(I, We) ______________________________________ the undersigned having visited the project site at the Stratford DPW and having familiarized ourselves with the local conditions affecting the cost of the work and with Contract Documents and all addenda thereto, hereby propose to furnish all labor, materials, tools, equipment, insurance to pay all applicable taxes, and to do and perform all things as provided in the drawings and specifications for the following sum(s):

BASE BID:

Refer to enclosed drawings and specifications.

Contractor shall include all monies and fees to complete documented project as indicated in bid documents. Contractor shall include a $10,000 allowance in base bid number for unforeseen conditions and changes to be used at Architect and Owners discretion. Any unused portion of allowance shall be credited back to owner.

Slab Repair Scope Only

*Written Form: __________________________________________________________

*Dollars: ($_________________)

*PLEASE NOTE THAT STATE OF CONNECTICUT PREVAILING WAGES MUST BE

USED IF TOTAL BID EXCEEDS $100,000.

Bid Form

ALTERNATE #1:

Remove underground oil tank. Refer to drawing MD-100 and spec section 026500.

*Written Form: ________________________________________________________

*Dollars: ($_________________) ADD ALTERNATE

UNIT PRICES:

Contractor must include unit prices for all items listed below, or bid could be rejected at client discretion. Shall include installed price.

1. Removal of Contaminated Soil $____________Per Cubic Yard

2. Soil Testing $____________Per Sample

ADDENDA

In submitting this proposal, I have received and included in this Proposal, the following Addenda:

Addendum No. Date

Signed:________________________________ ____________________________________

Signature Corporate Seal

Company Name : _________________________________________________________

Address : _________________________________________________________

City, St, Zip Code : _________________________________________________________

Phone : (__ __ __) - __ __ __ - __ __ __ __

Email : _________________________________________________________

Milestone Schedule

DPW Maintenance Garage 01009-1

SECTION 01009

MILESTONE SCHEDULE

PART 1 – GENERAL

1.01 MASTER SCHEDULE

The following milestone schedule serves as a basis for bidding. A Master Schedule shall be developed at a general meeting of the successful bidder within fourteen (14) days of Letter of Intent to Award the Contracts. This Master Schedule will incorporate the milestones listed below.

1.02 Milestone Dates:

A. Issue for Bid: 8/24/2026

B. Pre-Bid Walk-Through: 9/2/2026, 10:00am

C. Bid Opening: 9/18/2026, 10:00am

D. Award Project – on or about: 10/16/2026

E. Submittals & Shop Drawings: 10/30/2026

F. Start Construction/Mobilization: 12/1/2026

G. Substantial Completion: 1/29/2027

H. Final Close-out of Contract: 2/26/2027

• Final Milestone Schedule to be coordinated and approved by the Town of

Stratford and Stratford Public Schools

• Final close out of all contracts shall be by or prior to the date established above. All work including, but not limited to punch lists, project closeout, testing, balancing, owners operation, warranties, etc. shall be complete.

END OF MILESTONE SCHEDULE

AMC

Environmental,LLC

April22,2020

Mr.DanWakeling TownofStratford 1000EastBroadway StratfordCT06615

RE: AsbestosTestingatStratfordDPWGarage,Stratford,CT

DearMr.Wakeling:

INTRODUCTION

EnclosedaretheresultsofthebulksamplesobtainedonApril17,2020,todeterminethepresenceor absenceofasbestosintheboilerroomattheStratfordDPWGarage,550PatersonAve.,Stratford,CT.

Thetestingwaslimitedtothematerialslistedbelow.

RESULTS

Thesamplesinthetablebelowdocumentedlevelsofasbestosgreaterthan1% andthereforeare consideredasasbestoscontainingmaterials.

TABLE-1ASBESTOSCONTAININGMATERIALS

Sample# SampleLocation SampleDescription

B041701,02,03 BoilerRoom BoilerPacking

B041716,17 BoilerRoom BoilerGasket

Presumed BoilerRoom BoilerMasonry

TheRegulationsoftheStateofConnecticutrequirethatanyworkwhichmaydisturbasbestoscontaining materialsbeperformedbyaLicensedAsbestosAbatementContractor.

NON-ASBESTOSCONTAININGSAMPLES

Inaddition,thesamplesinTable2didnotdocumentthepresenceofasbestos,and thereforeareconsiderednon-asbestoscontainingmaterials.

AMC

Environmental, LLC

Phone:

203.378.5020

Fax:

203.375.7344

Email:

amc@amcenviro.com

P.O Box 423 Stratford, CT

06615

EnvironmentalMonitoring&consulting

TABLE-2NON-ASBESTOSCONTAININGMATERIALS

Sample# SampleLocation SampleDescription B041704,05,06 BoilerRoom Breeching24inch

B041707,08,09 BoilerRoom FiberGlass(papercovering)8inchLine

B041710,11,12 BoilerRoom InteriorBoilerDebris

B041713,14,15 BoilerRoom InteriorBoilerInsulation(door)

B041718,19 BoilerRoom FiberGlass(papercovering)5inchLine

B041820,21,22 BoilerRoom FiberGlass(papercovering)3inchLine

TheRegulationsoftheStateofConnecticutrequirethatanyworkwhichmaydisturb asbestoscontainingmaterialsbeperformedbyaLicensedAsbestosAbatementContractor.

Thankyoufortheopportunitytoprovideourservices.Ifyouhaveanyquestions,pleasedonothesitate tocall.

Verytrulyyours, JasonPringle Principal StateofCTAsbestosInsp./Mgmt.Planner#000269

Enclosure Note: ThedefinitionofAsbestosContainingMaterialasstatedintheStateofConnecticutStandardsforAsbestosAbatementismaterialcomposedof asbestosofanytypeandinanamountgreaterthan1%byweight,eitheraloneormixedwithotherfibrousornon-fibrousmaterial.

EMSL Analytical, Inc.

29 North Plains Highway, Unit # 4 Wallingford, CT 06492

Tel/Fax: (203) 284-5948 / (203) 284-5978 http://www.EMSL.com / wallingfordlab@emsl.com

242002435EMSL Order:

Customer ID: AMCT50

Customer PO:

Project ID:

Attention: Phone:Jason Pringle (203) 378-5020

Fax:AMC Environmental, LLC (203) 375-7344

Received Date:30 Hazel Terrace 04/20/2020 11:00 AM

Analysis Date:Suite 25 04/21/2020

Collected Date:Woodbridge, CT 06525 04/17/2020

Project: STRATFORD DPW-GARAGE

Test Report: Asbestos Analysis of Bulk Materials via EPA 600/R-93/116 Method using Polarized

Light Microscopy

Sample Description Appearance % Fibrous % Non-Fibrous

Non-Asbestos Asbestos

% Type

B041701

242002435-0001

None DetectedNon-fibrous (Other)60%Min. Wool40%Brown

Non-Fibrous

Homogeneous

BOILER RM -

BOILER PACKING

B041702

242002435-0002

2% ChrysotileNon-fibrous (Other)58%Min. Wool40%Brown

Non-Fibrous

Homogeneous

BOILER RM -

BOILER PACKING

B041703

242002435-0003

Positive Stop (Not Analyzed)BOILER RM -

BOILER PACKING

B041704

242002435-0004

None DetectedVermiculite

Non-fibrous (Other)

2%

67%

Cellulose

Min. Wool

Fibrous (Other)

6%

15%

10%

Brown

Non-Fibrous

Homogeneous

BOILER RM -

BREECHING 24

INCH

B041705

242002435-0005

None DetectedNon-fibrous (Other)72%Cellulose

Synthetic

Min. Wool

5%

8%

15%

Brown

Non-Fibrous

Homogeneous

BOILER RM -

BREECHING 24

INCH

B041706

242002435-0006

None DetectedNon-fibrous (Other)82%Synthetic

Min. Wool

3%

15%

Brown

Non-Fibrous

Homogeneous

BOILER RM -

BREECHING 24

INCH

B041707

242002435-0007

None DetectedNon-fibrous (Other)30%Cellulose

Glass

50%

20%

Tan/Silver

Fibrous

Homogeneous

BOILER RM -

FIBERGLASS

(PAPER COVERING)

8 INCH LINE

B041708

242002435-0008

None DetectedNon-fibrous (Other)30%Cellulose

Glass

50%

20%

Tan

Fibrous

Homogeneous

BOILER RM -

FIBERGLASS

(PAPER COVERING)

8 INCH LINE

B041709

242002435-0009

None DetectedNon-fibrous (Other)45%Cellulose

Glass

40%

15%

Tan

Non-Fibrous

Homogeneous

BOILER RM -

FIBERGLASS

(PAPER COVERING)

8 INCH LINE

B041710

242002435-0010

None DetectedNon-fibrous (Other)92%Fibrous (Other)8%Gray/Orange

Non-Fibrous

Homogeneous

BOILER RM -

INTERIOR BOILER

DEBRIS

B041711

242002435-0011

None DetectedNon-fibrous (Other)92%Fibrous (Other)8%Gray/Rust

Non-Fibrous

Homogeneous

BOILER RM -

INTERIOR BOILER

DEBRIS

B041712

242002435-0012

None DetectedNon-fibrous (Other)90%Fibrous (Other)10%Gray

Non-Fibrous

Homogeneous

BOILER RM -

INTERIOR BOILER

DEBRIS

B041713

242002435-0013

None DetectedNon-fibrous (Other)25%Min. Wool75%Brown/Tan

Fibrous

Homogeneous

BOILER RM -

INTERIOR BOILER

INSULATION (DOOR)

B041714

242002435-0014

None DetectedNon-fibrous (Other)25%Min. Wool75%Brown/Tan

Fibrous

Homogeneous

BOILER RM -

INTERIOR BOILER

INSULATION (DOOR)

B041715

242002435-0015

None DetectedNon-fibrous (Other)30%Min. Wool70%Brown/Tan

Non-Fibrous

Homogeneous

BOILER RM -

INTERIOR BOILER

INSULATION (DOOR)

Initial report from: 04/21/2020 11:27:30

Page 1 of 2ASB_PLM_0008_0001 - 1.78 Printed: 4/21/2020 11:27 AM

EMSL Analytical, Inc.

29 North Plains Highway, Unit # 4 Wallingford, CT 06492

Tel/Fax: (203) 284-5948 / (203) 284-5978 http://www.EMSL.com / wallingfordlab@emsl.com

242002435EMSL Order:

Customer ID: AMCT50

Customer PO:

Project ID:

Test Report: Asbestos Analysis of Bulk Materials via EPA 600/R-93/116 Method using Polarized

Light Microscopy

Sample Description Appearance % Fibrous % Non-Fibrous

Non-Asbestos Asbestos

% Type

B041716

242002435-0016

70% ChrysotileNon-fibrous (Other)30%Black

Fibrous

Homogeneous

BOILER RM -

BOILER HEAD

GASKET

B041717

242002435-0017

Positive Stop (Not Analyzed)BOILER RM -

BOILER HEAD

GASKET

B041718

242002435-0018

None DetectedNon-fibrous (Other)45%Cellulose

Glass

45%

10%

Tan/Silver

Fibrous

Homogeneous

BOILER RM -

FIBERGLASS

(PAPER COVERING)

5 INCH LINE

B041719

242002435-0019

None DetectedNon-fibrous (Other)40%Cellulose

Glass

50%

10%

Tan

Non-Fibrous

Homogeneous

BOILER RM -

FIBERGLASS

(PAPER COVERING)

5 INCH LINE

B041720

242002435-0020

None DetectedNon-fibrous (Other)40%Cellulose

Glass

50%

10%

Tan/Silver

Fibrous

Homogeneous

BOILER RM -

FIBERGLASS

(PAPER

COVERING)) 3 INCH

LINE

B041721

242002435-0021

None DetectedNon-fibrous (Other)45%Cellulose

Glass

45%

10%

Tan/Silver

Fibrous

Homogeneous

BOILER RM -

FIBERGLASS

(PAPER

COVERING)) 3 INCH

LINE

B041722

242002435-0022

None DetectedNon-fibrous (Other)45%Cellulose

Glass

40%

15%

Tan

Non-Fibrous

Homogeneous

BOILER RM -

FIBERGLASS

(PAPER

COVERING)) 3 INCH

LINE

Analyst(s)

Danny Sandhu (6)

Tara Svendsen (14)

Danny Sandhu, Asbestos Laboratory Manager or Other Approved Signatory

EMSL maintains liability limited to cost of analysis . The above analyses were performed in general compliance with Appendix E to Subpart E of 40 CFR (previously EPA 600/M4-82-020 "Interim

Method"), but augmented with procedures outlined in the 1993 ("final") version of the method. This report relates only to the samples reported above, and may not be reproduced, except in full, without written approval by EMSL. EMSL bears no responsibility for sample collection activities or analytical method limitations . Interpretation and use of test results are the responsibility of the client. All samples received in acceptable condition unless otherwise noted. This report must not be used by the client to claim product certification, approval, or endorsement by NVLAP, NIST or any agency of the federal government. EMSL recommends gravimetric reduction for all non -friable organically bound materials prior to analysis. Estimation of uncertainty is available on request.

Samples analyzed by EMSL Analytical, Inc. Wallingford, CT NVLAP Lab Code 200700-0, Initial report from: 04/21/2020 11:27:30

Page 2 of 2ASB_PLM_0008_0001 - 1.78 Printed: 4/21/2020 11:27 AM

ASBESTOSREMOVALPROJECTDESIGN

FOR:

TOWNOFSTRATFORD

STRATFORDDEPARTMENTOFPUBLICWORKSGARAGE

550PATERSONAVE.

STRATFORD,CT

PREPAREDFOR:

DANWAKELING

TOWNOFSTRATFORD

DEPARTMENTOFPUBLICWORKS

PREPAREDBY:

AMCENVIRONMENTAL,LLC

P.O.BOX423

STRATFORD,CT06615

(203)378-5020

April22,2020

AsbestosRemoval

AMCEnvironmental,LLC 550PatersonAve.

April22,2020 Stratford,CT

1.1 ProjectDescription

A. Theworkconsistsofalllabor,materials,equipmentandincidentalsrequired toremovetheasbestoscontainingcontaminatedmaterialsidentifiedin paragraph2.0.

B. Theworkconsistsoftheremovalanddisposalofapproximately200square feetofsheetrock/jointcompound.

1.2 ApplicableCodes

TheContractorshallbesolelyresponsibleforconductingthisprojectandsupervising allworkinamanner,whichwillbeinconformancewithallfederal,stateandlocal regulationsandguidelinespertainingtoasbestosabatement.Specifically,the Contractorshallcomplywiththerequirementsofthefollowing:

A. StateofConnecticutLicense&TrainingRequirements20-440-1 through20-440-9

B. NESHAPSRegulation(40CFR61,SubpartM);

C. OSHAAsbestosRegulations(29CFR1910.1001and1926.1101);

D. USEPAAHERARegulation(40CFR763FinalRuleandNotice) E. ConnecticutDEPRegulations(Section22a-209-8(I)andSection22a-220of theConnecticutGeneralStatutes);

F. Section19a-332a-1toSection19a-332a-16,inclusiveoftheRegulationsof

ConnecticutStateAgencies.

G. ConnecticutBasicBuildingCode;

H. ConnecticutFireSafetyCode;

I. Localhealthandsafetycodes,ordinancesorregulationspertainingto asbestosremediationandallnationalcodesandstandardsincluding ASTM/ANSIandUnderwriter’sLaboratories.

1.3 Exemptions

Anydeviationfromthesespecificationsrequiresthewrittenapprovalandauthorization fromtheOwnerandProjectDesigner.

1.4 Notifications,Postings,SubmittalsandPermits

TheContractorwillmakethefollowingnotificationsandprovidethesubmittalstothe followingagenciespriortothecommencementofremovalworkiftheamountof asbestoscontainingmaterialinvolvesmorethanten(10)linearfeetormorethan twentyfive(25)squarefeet.

A. ConnecticutDepartmentofEnvironmentalProtection SolidWasteManagementUnit 79ElmStreet Hartford,CT06106 (OnlyifdisposingofasbestoswasteinConnecticut)

B. Chief,EnvironmentalHealthServices DepartmentofPublicHealth EnvironmentalHealthSection 410CapitolAvenue,MS#51AIR P.O.Box340308 Hartford,CT06134-0308

April22,2020 Stratford,CT

Theminimuminformationincludedinthenotificationtotheseagenciesinclude:

1. Nameandaddressofbuildingowner/operator

2. Buildinglocation

3. Buildingsize,ageanduse

4. Amountoffriableasbestos

5. Workschedule,includingproposedstartandcompletiondate

6. Asbestosremovalprocedurestobeused

7. Nameandlocationofdisposalsiteforgeneratedasbestoswaste,residueand debris

1.5 WorkSiteSafetyPlan

TheContractorshallestablishasetofemergencyproceduresandshallpostthemina conspicuousplaceattheworksite.Thesafetyplanshouldincludeprovisionsforthe following:

A. Evacuationofinjuredworkers.

B. Emergencyandfireexitroutesfromallworkareas.

C. Emergencyfirstaidtreatment.

D. Localtelephonenumbersforemergencyservicesincludingambulance,fire andpolice.

E. Amethodtonotifyoccupantsofthebuildingintheeventofafireorother emergencyrequiringevacuationofthebuilding.

F. 24hoursitesecurityprogram.

TheContractorisresponsiblefortrainingallworkersintheseprocedures.

1.6 AlternateWorkPractices(AWP)

AnymodificationfromthestandardworkpracticesidentifiedintheStateof ConnecticutDepartmentofPublicHealth(DPH)StandardforAsbestosAbatement Section19a-332a-1to19a-332a-16mustberequestedinwritingfromtheDPH.Any suchrequestshallbepreparedbyalicensedProjectDesigner.

AWP’sarerequiredtoprovideanequivalentorgreaterlevelofcontrolofasbestos emissions.TheOwnerrequiresacopyofthewrittenapprovalbytheState DepartmentofPublicHealthforanyAlternateWorkPracticepriortoimplementation.

1.7 WorkSiteAbatementResponsibilities

A. TheContractorshallmaintaincontrolofandberesponsibleforaccesstoall workareastoensurethefollowingrequirements:

1. Non-essentialpersonnelareprohibitedfromenteringthearea;

2. Allauthorizedpersonnelenteringtheworkareashallreadthe“worker protectionprocedures”whicharepostedattheentrypointstothe enclosuresystem,andshallbeequippedwithproperlyfitted respiratorsandprotectiveclothing;

3. Allpersonnelwhoareexitingfromthedecontaminationenclosure systemshallbeproperlydecontaminated;

4. Asbestoswastethatistakenoutoftheworkareamustbeadequately wet,properlybaggedandlabeledinaccordancewiththisproject

April22,2020 Stratford,CT design.Thesurfaceofthebagsshallbedecontaminated.Asbestos leavingtheenclosuresystemmustbetransportedoffsiteor immediatelyplacedinlocked,postedtemporarystorageonsite.Any material,equipment,orsuppliesthatarebroughtoutofthe decontaminationenclosuresystemshallbecleanedand decontaminatedbywetcleaningand/orHighEfficiencyParticulateAir (HEPA)vacuumingallsurfaces.

5. Allpolyethylenesheetingshallbeflameretardantorsimilar.

B. Contractor’sResponsibilities

TheAsbestosAbatementContractorshallassumefullresponsibilityand liabilityforthecompliancewithallapplicableFederal,State,andlocal regulationspertainingtoworkpractices,haulinganddisposalofAsbestos ContainingMaterial(ACM),andprotectionofworkers,visitorstothesite,and personsoccupyingareasadjacenttothesite.Contractorisresponsiblefor providingmedicalexaminationsandmaintainingmedicalrecordsofpersonnel asrequiredbytheapplicableFederal,Stateandlocalrequirements.

ContractorshallholdtheProjectDesignerandOwner(‘s)Representative harmlessforfailuretocomplywithanyapplicablework,hauling,disposal, safety,healthorotheronthepartofhimself,hisemployees,orhis subcontractors.Contractorincursallsampling/analyticalcostsforsamplingto complywithOSHAregulations.TheContractorisresponsibleforrestoringall workareasandauxiliaryareasutilizedduringabatementtoconditionsequal toorbetterthanoriginal.Anydamagecausedduringtheperformanceof abatementactivitiesshallberepairedbytheContractor.TheContractorwill postappropriatesignageacceptabletotheOwnertodirectvisitorstoasign-in locationandwillbriefanysuchpersonnelonareasofabatementactivity.

1.8 Contractor’sAirSamplingResponsibility

A. TheContractorshallmonitorairborneasbestosconcentrationsintheworkers’ breathingzoneandtoestablishconditionsandworkproceduresfor maintainingcompliancewithOSHARegulations29CFR1910.1001and 1926.1001.

B. TheContractor’sairsamplingprofessionalshalldocumentallairsampling resultsandprovideallairsamplingreportstotheOwneratthecompletionof the project.

C. Allairsamplingshallbeconductedinaccordancewithmethodsdescribedin OSHAstandardsCFR1910.1001and1926.1101.

1.9 UponCompletionofAbatement,theContractorshallsubmitcopiesofalltransport manifests,tripticketsanddisposalreceiptsforallasbestoswastematerialsremoved fromtheworkareasduringtheabatementprocess.Submitaprojectreportthatshall includeacertificateofcompletion,datedandsignedbyanauthorizedrepresentative oftheContractorandthewasteshipmentrecordsignedbytheoperatorofthe licensedlandfill.

2.0 ScopeofWork

Theabatementincludestheremovalofapproximately150sq.ft.ofasbestos containingboilerpacking,approximately5sq.ft.ofboilergaskets,interiorboiler masonryandanyassociatedmaterialsfromtheboilerlocatedintheBoilerRoom.

Thematerialsshallberemovedinitsentiretyunderfullcontainmentthatisunder

April22,2020 Stratford,CT negativepressurewithacontiguousthree(3)stagedecontaminationunit.The negativeairexhaustshallbeexhaustedoutsideofthebuilding.Allwastematerials willberemovedusingwetmethodsandremovedfromcontainmentthroughthe decontaminationunit.

ProjectDesigner: JasonPringle LicenseNo. 000252

Maintenance Garage, Stratford Department of Public Works

Heating System Replacement Sequence of Operations

August 24, 2026

Sequence of Operation

1) Heating and Ventilation Units

a) Factory Controls

i) Each heating and ventilation unit shall be furnished with the manufacturer’s factory-installed, factory-wired, programmed, and tested microprocessor control system.

ii) The controller shall include a lighted local display and keypad for adjusting setpoints, schedules, and override periods and for reviewing operating status and alarms.

iii) Provide factory-installed outdoor-air and supply-discharge temperature sensors.

iv) Building management system communication is not required. All control, adjustment, status indication, and alarm review shall be available locally at the unit controller.

b) Unit Enable and Scheduling

i) Provide a permanent, factory-approved jumper between terminals R and G unless an external shutdown or enable contact is indicated.

ii) Occupied and unoccupied operation shall be controlled through the factory controller’s internal seven-day programmable time clock.

iii) The controller shall accommodate at least seven occupancy schedules.

iv) Provide a temporary occupied-mode override through the local keypad and a dry-contact input. The override period shall be adjustable and initially set at one hour.

v) Heating shall not be permitted until supply-fan operation and the manufacturer’s required minimum airflow have been proven.

c) Occupied Mode

i) Upon initiation of occupied mode, the controller shall complete its initialization sequence and energize the outdoor-air damper actuator.

ii) The controller shall prove that the outdoor-air damper is open before starting the supply fan.

iii) After an adjustable delay, start the supply fan.

iv) The factory-installed variable-frequency drive shall operate the supply fan at a constant speed established during testing and balancing. Fan speed shall not normally modulate.

d) Heating Control

i) The factory controller shall modulate the direct-fired gas burner to maintain an adjustable supply-discharge-air-temperature setpoint, initially 68°F.

ii) Heating shall be disabled when the outdoor-air temperature is above an adjustable heating-lockout setpoint, initially 60°F.

iii) The supply fan shall continue to operate during occupied periods when heating is locked out.

iv) When the heating requirement is below the burner’s minimum stable firing rate, the factory controller shall cycle the burner using an adjustable 5°F discharge-air-temperature deadband.

v) Following a temperature-controlled burner shutdown, the burner shall remain off for at least five minutes before being permitted to restart.

vi) Burner safety recycling, ignition, purge, shutdown, and lockout functions required by the equipment listing or manufacturer shall take precedence over the minimum off-time requirement.

e) Unoccupied Mode

i) During unoccupied periods, the supply fan shall be off, the outdoor-air damper shall be de-energized and spring-returned to its closed position, and the gas burner shall be disabled.

ii) Disable the unit’s unoccupied cycle-on-room-temperature function.

iii) Unoccupied space-temperature control shall be provided by the radiant tube heating system.

f) Preoccupancy Warm-Up

i) Disable the heating and ventilation unit’s factory morning warm-up and cooldown functions.

ii) Preoccupancy warm-up shall be provided by the radiant tube heaters.

iii) The heating and ventilation units shall remain off during preoccupancy warm-up and shall start at the scheduled occupied time.

g) Safeties and Interlocks

i) Burner operation shall be prohibited until supply-fan operation and minimum required airflow are proven.

ii) Loss of supply-fan status or airflow proof shall immediately disable the burner and initiate the applicable factory alarm.

iii) If supply-air temperature falls below an adjustable low-limit setpoint, initially 35°F, for an adjustable period, initially 300 seconds, the controller shall shut down the unit and initiate an alarm.

iv) Provide factory-installed manual-reset high-temperature limits, flame safeguard, ignition controls, gas-pressure switches, airflow switches, and other safety controls required by the equipment listing.

v) Burner ignition, flame failure, pre-purge, post-purge, safety shutdown, recycling, and manual-reset operation shall comply with the equipment manufacturer’s requirements and listing.

vi) Upon restoration of power, the unit shall automatically return to its scheduled operating mode, except where manual reset is required by a safety device.

vii) Where a fire-alarm shutdown signal is available, shut down the supply fan, disable the burner, and close the outdoor-air damper upon receipt of the signal.

h) Alarm Management

i) The factory controller shall record available alarm descriptions, dates, times, temperatures, and unit status for local review.

ii) Provide local indication for the following conditions:

(1) Global alarm.

(2) Outdoor-air temperature sensor failure.

(3) Supply-discharge temperature sensor failure.

(4) Low supply-air temperature.

(5) Dirty filter.

(6) Direct-fired gas-burner or flame failure.

(7) Supply-fan failure.

(8) High-temperature safety trip.

(9) Loss of airflow proof.

iii) Burner and high-temperature safety lockouts shall require manual reset where required by the manufacturer or equipment listing.

2) Radiant Tube Heaters

a) Each radiant tube heater or heating zone shall be controlled independently by a commercial programmable space thermostat.

b) During occupied periods, the radiant tube heaters shall maintain an adjustable space-temperature setpoint, initially 68°F.

c) During unoccupied periods, the radiant tube heaters shall maintain an adjustable setback temperature, initially 55°F.

d) The thermostats shall initiate preoccupancy warm-up sufficiently in advance of the occupied period to achieve the occupied space-temperature setpoint by the scheduled occupancy time.

e) Locate thermostats where they represent typical occupant conditions and are not directly exposed to the radiant tubes, exterior doors, direct sunlight, or supply-air discharge.

f) Provide each heater with the manufacturer’s flame safeguard, ignition controls, airflow or combustion-air proving, high-temperature limits, post-purge controls, and other safeties required by its listing.

g) Following restoration of power, the radiant heaters shall automatically return to their scheduled operating mode, except where manual reset is required by a safety device.

RFI LOG

DPW Maintenance Garage Date: 9/3/2026

Question Date Received

Directed To Response Response Date

1 Please provide information in case there is oil contamination in soil.

9/1/2026 Town See attached revised Bid Form that includes unit pricing to remove contaminated soil and soil testing.

9/1/2026

2 The boiler, flue, and related steam piping to be demolished may have ACM’s. This will need to be tested, with proper reports.

9/1/2026 Town See attached asbestos testing report from AMC Environmental and Abatement Specification.

9/1/2026

3 There will be roofing work to consider. Is there a bond on the roof?

9/1/2026 Town Existing roof is a built-up roof system under warranty by W.P.

Hickman Systems, Inc. Roofing sub-contractor must have appropriate certifications to maintain roof warranty.

9/1/2026

4 Please clarify site restoration scope of work in regards to tank removal?

9/1/2026 Snyder Site shall be restored to as-found condition and disturbed areas paved.

9/1/2026

5 Is there a BMS system currently in place at this location? If so, what vendor currently serves the system. If no BMS, is there a preferred vendor?

9/1/2026 Landmark The building does not currenty have a BMS system.

Connecticut Temperature Controls (CTC) is the town controls vendor.

9/3/2026

6 I did not see a sequence of operation for the new HVAC equipment temperature controls. Can this be provided, or clarified?

9/1/2026 Landmark Addendum #1: See attached controls information and Sequence of Operation.

9/3/2026

7 Please advise regarding building use and coordination during construction.

9/2/2026 Snyder/Town Vehicle repair operations much continue during construction so coordnation is needed between contractor and mechanics to phase work accordingly.

9/3/2026

8 Does the 4000 gallon underground fuel storage tank have an identification number? This info will be required by the State of Connecticut if it is to be removed.

9/3/2026 Snyder/Town Indentification number will be provided after project is awarded. 9/3/2026

9 Can the spacing of gas pipe roof supports be spaced at 8 ft. on center in lieu of 4 ft. on center? 8 ft. O/C will meet code for steel pipe supports.

9/3/2026 Landmark To be addressed in future Addendum.

10 Will the Town of Stratford waive local Permit Fees for this Town funded project?

9/3/2026 Snyder/Town Yes 9/3/2026

11 Oil tank is located below a concrete pad at grade. Can this area be covered with asphalt paving after tank removal in lieu of a concrete pad?

9/3/2026 Snyder/Town Yes 9/3/2026

12 How much fuel oil will be left in the tank at the time of tank removal? Or will this be a Unit Price to remove and dispose per gallon?

9/3/2026 Snyder/Town To be addressed in future Addendum.

13 Please confirm the gas pressure from the utility building meter for gas pressure regulators to be installed for new heating units.

9/3/2026 Landmark To be addressed in future Addendum.

PROJECT TEAM
*** END OF ADDENDUM #1 ***
02.1 BID FORM (Garage HVAC).pdf
BID FORM
02.2 01009 Milestone Schedule.pdf
END OF MILESTONE SCHEDULE
03 ASBESTOS REPORT & SPEC.pdf
01 RFI Log (DPW Garage)
Sheet1
02 Tank Location Sketch
ScreenHunter 610
03 Job Site Photos
04.1 2020-04-22 DPW Garage Asbestos Report
04.2 2020-04-22 DPW Garage Asbestos Spec
05 REVISED DRAWINGS
Stratford DPW - Mech-MD-100
Stratford DPW - Mech-MD-101
Stratford DPW - Mech-M-100
Stratford DPW - Mech-M-101
Stratford DPW - Mech-M-300
Stratford DPW - Mech-M-400
Stratford DPW - Mech-M-401
Stratford DPW - Fuel Gas-FG-200
ADPDDE.tmp
PROJECT TEAM
*** END OF ADDENDUM #2 ***

File details come from the government source that posted it. Updated .