Annex EV Chargers
Solicitation number
2026-MPW-162
Issued by
Pierce County, Washington

About this file

This is a construction specification document for Pierce County, Washington's Annex Electric Vehicle Infrastructure Project #24-00003, prepared by Hargis Engineers Inc. The project is located at Pierce County Annex, 2401 S 35th Street, Tacoma, WA 98409, and includes civil work (asphalt demolition, electrical conduit trench excavation, camera trench excavation, and repaving), electrical work (installation of an additional light pole, camera, electrical and communication conduit), and other work (EV signage and pavement markings). An additive alternate bid includes five security cameras, reach devices on both the Intermediate Distribution Frame (IDF) and camera sides, and cabling to connect cameras to an existing switch in the telecommunications room. The construction work shall be substantially complete and ready for occupancy by May 13, 2027, with an additional 14 calendar days for project closeout for final completion by May 27, 2027. Work is restricted to Monday through Friday, 7:00 AM to 5:00 PM, unless otherwise approved by the owner, with a requirement to provide seven days' notice for disruptive activities and 72 hours' notice for temporary traffic blockages. All contractor personnel require Pierce County background clearance and identification badges prior to commencing work, with moderate background checks required for exterior work and Criminal Justice Information System (CJIS) clearance required for interior access.

The contract is structured as a single prime contract based on a stipulated price with liquidated damages set at $700.00 per calendar day. A contingency allowance of $15,000.00 is included for miscellaneous or unforeseen items not accounted for in the base bid or alternates, to be used only with written owner approval. The contractor must submit a Schedule of Values within 15 days after the Notice to Proceed, with applications for progress payments due by the 15th of each month for work performed during the preceding month. Prevailing wage requirements apply, requiring contractors to submit Intent and Affidavit Forms with each invoice. The contractor is responsible for all costs associated with securing employee clearances and background checks, fingerprinting through South Sound 911 for CJIS clearances (up to eight weeks processing time), and badge issuance. A comprehensive Quality Control Plan must be submitted prior to the start of work, and the contractor must employ a full-time on-site superintendent during construction. Owner occupancy is anticipated upon substantial completion, and the contractor must coordinate all work to minimize disruption to county operations.

View the file

Other files

File Type Posted
Kempower_Satellite_Unit_datasheet.pdf PDF
Kempower_Unit_datasheet.pdf PDF
2026-MPW-162_-_DIV_00.pdf PDF
Hot_Work_Procedure.pdf PDF
Hazmat_Report.pdf PDF
Sample_ACM_Compliance.docx DOCX document
Background_Check_Form.pdf PDF
2026-MPW-162-20260518_DWG_PC_Annex_EV_Infrastructure_-_CD_Dwgs.pdf PDF
2026-MPW-162-DIV_27.pdf PDF
2026-MPW-162-DIV_31.pdf PDF
2026-MPW-162-DIV_28.pdf PDF
2026-MPW-162-DIV_32.pdf PDF
2026-MPW-162-DIV_02.pdf PDF
2026-MPW-162-DIV_26.pdf PDF
2026-MPW-162-DIV_03.pdf PDF
Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pierce County Annex Electric Vehicle Infrastructure Project # 24-00003

Summary 2026-MPW-162 01 10 00 - 1

SECTION 01 10 00

SUMMARY

PART 1 GENERAL

1.01 RELATED DOCUMENTS

A. Pierce County's General Conditions for Construction shall apply to all sections of the specifications and contract drawings.

1.02 PROJECT

A. Project Name: Annex Electric Vehicle Infrastructure 24-00003 B. Architect's Name: Hargis Engineers Inc.

C. General Description of the Project: The Project is located at Pierce County Annex 2401 S 35th

St. Tacoma, WA 98409. The Project consists of but not limited to the following elements:

1. Civil work to include: Asphalt demolition, excavating electrical conduit trench and Camera trench, repaving the trench locations..

2. Electrical work to include: Install additional light pole, camera, electrical and communication conduit..

3. Other work to include: Install EV signage, pavement markings.

4. Alternate Bid #1 to Include: 5 Security Cameras, One reach devices on both IDF and

Camera sides, cabling to connect cameras and existing switch in the telecommunications room

D. The construction work shall be substantially complete, ready for occupancy by May 13, 2027 with an additional 14 calendar days for project closeout for final completion by May 27, 2027.

1.03 CONTRACT DESCRIPTION

A. Contract Type: A single prime contract based on a Stipulated Price as described in Document

00 50 00 Public Works Agreement Form.

B. Liquidated Damages: The Liquidated Damages are set forth as $700.00 per calendar day. See

"Liquidated Damages Against Contractor" in Division 00.

1.04 PHASED WORK

A. The Contractor shall coordinate the progress of its Work with the established requirements for completion.

B. Work shall be conducted in a single phase.

1.05 DESCRIPTION OF ALTERATIONS WORK

A. Scope of demolition and removal work is indicated on drawings and specifications.

B. Scope of alterations work is indicated on drawings and specifications.

C. Hazardous materials abatement: Refer to Hazardous Material survey and report attached for reference.

D. Refinish or restore to existing condition all surface areas disturbed by the work or areas disturbed by installation of temporary walls or barriers.

E. Electrical Power and Lighting: Alter existing system and add new construction, keeping existing in operation.

F. Owner will remove the following items before start of renovation work:

1. Furnishings in the project area.

1.06 WORK RESTRICTIONS

A. Work Hours of the Day: Building Operating Hours are 7:00AM - 5:00PM, unless otherwise established. Work outside of normal business hours, can be requested and may be granted by

Summary 2026-MPW-162 01 10 00 - 2 the Owner. No work outside of the standard work hours shall be allowed without prior arrangement and written approval by Owner. Building operating hours are to be coordinated with owner.

B. Workdays of the Week: Monday-Friday. Work outside of normal workdays can be requested and may be granted by the Owner. No work outside of the standard workdays shall be allowed without prior arrangement and written approval by Owner.

C. Disruptions: The Contractor must plan the work so to avoid disrupting the County’s operations.

Disruptive activities include those which generate odor, vibration, dust, or noise which can be heard, smelled or felt on floors above, below and adjacent to construction activities. Unless specified elsewhere in the contract documents, disruptive work shall occur outside of normal business hours. The contractor will schedule the work with input of County project manager for least disruption. Contractor to provide 7-day notice for disruptive work.

1. Contractor requests to work on weekends and holidays will be accommodated at County’s discretion and permission not reasonably withheld. No work outside of the standard workdays shall be allowed without prior arrangement and written approval by Owner.

Building operating days and hours are: Monday - Friday 7:00AM - 5:00PM.

2. Work activities that are performed during normal business hours and later found to be disruptive, will have the remaining disruptive activities rescheduled to after hours.

D. Electrical work: Coordinate any shutdowns with Pierce County Project Manager with minimum 7 days notice unless specified elsewhere in the contract documents.

E. Utility Work: Coordinate any shutdowns with Pierce County Project Manager with minimum 7 days advance notice.

F. Building Access: Building access is by keys or by security badge. Contractor must maintain the secure perimeter of building at all times. Contractor may not prop doors open without providing Owner 24 hours advance notice of intent to do so and contractor to coordinate how security will be maintained during door usage. Security badge must be maintained during all phases of construction..

G. Security Requirements:

1. See Section 01 35 53 Security Procedures for additional information.

H. All work will be completed as to not impede regular vehicular traffic. If any area requires temporary blockage this will need to be coordinated with the owner no less than 72 hours prior to the event and alternate routes must be provided to allow traffic to flow.

1.07 WORK BY OWNER

A.

1.08 OWNER OCCUPANCY

A. General: Pierce County Buildings are occupied by County employees and visited by the

General Public. Additionally, the floors directly below and adjacent to the Area of Work in the Annex Building are occupied by County employees and subject to disturbance by the Project's construction activities. The Contractor will cooperate and coordinate with the Owner minimizing noise impacts and ensuring the Owner's operations continue throughout the duration of the Project. This includes construction activities during demolition and general construction.

1. If the Owner's operations are disrupted during construction activities, upon notification, the

Contractor shall cease construction activities immediately and reschedule the disrupting work with the Owner and in-writing. Disrupting work may require working outside of normal building hours or over a weekend.

B. Owner intends to continue to occupy adjacent portions of the site during the entire construction period.

C. Owner intends to occupy the Project upon Substantial Completion.

D. Cooperate with Owner to minimize conflict and to facilitate Owner's operations.

Summary 2026-MPW-162 01 10 00 - 3

E. Schedule the Work to accommodate Owner occupancy.

1.09 CONTRACTOR USE OF SITE

A. Construction Operations: The site and areas to be used solely for activities related to the construction of the project.

B. Locate and conduct construction activities in ways that will limit disturbance to site.

C. Arrange use of site and premises to allow:

1. Owner occupancy.

2. Work by Others.

3. Work by Owner.

4. Use of site and premises by the public.

D. Provide access to and from site as required by law and by Owner:

1. Emergency Building Exits During Construction: Keep all exits required by code open during construction period; provide temporary exit signs if exit routes are temporarily altered.

2. Do not obstruct roadways, sidewalks, or other public ways without permit.

E. Utility Outages and Shutdown:

1. Limit disruption of utility services to hours outside of building normal business hours.

2. Do not disrupt or shut down life safety systems, including but not limited to fire sprinklers and fire alarm system, without 7-days' notice to Owner and authorities having jurisdiction.

3. Prevent accidental disruption of utility services to other facilities.

1.10 WORK SEQUENCE

A. Coordinate construction schedule and operations with Architect/Owner.

1.11 SPECIFICATION LANGUAGE:

A. Abbreviated Language: Abbreviated words and shall be interpreted with standard meanings unless otherwise defined in the contract documents. Words implied, but not stated, shall be inferred. Singular words shall be interpreted as plural, and plural words shall be interpreted as singular where applicable as the context of the Contract Documents indicates.

B. Requirements expressed in the imperative mood shall be performed by Contractor.

1. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

a. The General Conditions for the Construction Contracts, General Requirements, technical specifications, and drawings are to be used together as one Construction Contract Document. When there is a discrepancy between the documents, the contractor shall bring the conflict to the architect in writing using the form of an RFI (Request for Information); use form 01 26 13 Request For Information. In general, the more stringent condition applies.

C. Days specified are in Calendar Days.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

END OF SECTION

Price and Payment Procedures 01 20 00 - 1

SECTION 01 20 00

PRICE AND PAYMENT PROCEDURES

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Procedures for preparation and submittal of applications for progress payments.

B. Documentation of changes in Contract Sum and Contract Time.

C. Change procedures.

D. Procedures for preparation and submittal of application for final payment.

1.02 RELATED REQUIREMENTS

A. Pierce County General Conditions for Construction Contracts and Special Conditions apply to this section.

1. Section 00 50 00 - Contracting Forms and Supplements: Forms to be used.

2. Section 00 72 00 - General Conditions for Construction Contracts.

3. Section 01 21 00 - Allowances: Payment procedures relating to allowances.

4. Section 01 35 53 - Security Procedures

B. Section 01 78 00 - Closeout Submittals: Project record documents.

1.03 SCHEDULE OF VALUES

A. Electronic media printout including equivalent information will be considered in lieu of standard form specified; submit draft for approval.

B. Forms filled out by hand will not be accepted.

C. Submit Schedule of Values in duplicate within 15 days after date established in Notice to

Proceed.

D. Format: Utilize the Table of Contents of this Project Manual. Identify each line item with number and title of the specification section. Identify site mobilization.

E. Revise schedule to list approved Change Orders, with each Application For Payment.

1.04 APPLICATIONS FOR PROGRESS PAYMENTS

A. Payment Period: To be established at pre-construction meeting

1. Invoices shall be received by the 15th of each month following the performance period starting on the 1st and ending on the last day of the preceding month, unless otherwise established at the pre-construction meeting.

2. Upon request, contractor may be required to provide a draft projected invoice for services rendered in the month of December, two days prior to the last business day in December for accounting purposes.

B. Use Form provided by Contractor. See Schedule of Values Section for requirements.

1. Contractor to submit with each application for payment an Intent and Affidavit Form, See

Section 01 26 15. Contractor to list all subcontractors who have performed work on the project, indicating subcontractors performing work during the pay period, including their approved Statement of Intent to Pay Prevailing Wage Number and approved Affidavit of Wages Paid if applicable (after all work on project has been completed by contractor or subcontractor).

C. Electronic media printout including equivalent information will be considered in lieu of standard form specified; submit sample for approval.

D. Forms filled out by hand will not be accepted.

E. For each item, provide a column for listing each of the following:

1. Item Number.

2. Description of work.

Price and Payment Procedures 01 20 00 - 2

3. Scheduled Values.

4. Previous Applications.

5. Work in Place under this Application.

6. Authorized Change Orders.

7. Total Completed to Date of Application.

8. Percentage of Completion.

9. Balance to Finish.

10. Retainage.

F. Execute certification by signature of authorized officer.

G. List each authorized Change Order as a separate line item, listing Change Order number and dollar amount as for an original item of work.

H. Submit one (1) electronic (PDF) of each Application for Payment.

I. Include the following with the application:

1. Invoices from sub-contractors.

2. Construction progress schedule: revised and current as specified in Section 01 32 16.

3. Current construction photographs specified in Section 01 30 00.

J. When Architect/Owner requires substantiating information, submit data justifying dollar amounts in question. Provide one copy of data with cover letter for each copy of submittal. Show application number and date, and line item by number and description.

1.05 MODIFICATION PROCEDURES

A. For minor changes not involving an adjustment to the Contract Sum or Contract Time, Architect/Owner will issue instructions directly to Contractor.

1. Documentation: Contractor to maintain detailed time and materials records.

B. For other required changes follow procedures described in the Division 00 Section 00 72 00 Pierce County General Conditions for Construction Contracts for Changes to the Contract.

1. Documentation: Contractor to maintain detailed time and materials records.

C. For other required changes, Architect/Owner will issue a document signed by Owner instructing Contractor to proceed with the change, for subsequent inclusion in a Change Order.

1. The document will describe the required changes and will designate method of determining any change in Contract Sum or Contract Time.

2. Promptly execute the change.

3. Documentation: Contractor to maintain detailed record of time, labor, and material, for change work directed by the Owner, to be submitted upon completion of the change for preparation of the Change Order.

D. Contractor may propose a change by submitting a request for change to Architect/Owner, describing the proposed change and its full effect on the work, with a statement describing the reason for the change, and the effect on the Contract Sum and Contract Time with full documentation.

E. Substantiation of Costs: Provide full information required for evaluation.

1. Provide the following data:

a. Quantities of products, labor, and equipment.

b. Taxes, insurance, and bonds.

c. Overhead and profit.

d. Justification for any change in Contract Time.

e. Credit for deletions from Contract, similarly documented.

2. Support each claim for additional costs with additional information:

a. Origin and date of claim.

b. Dates and times work was performed, and by whom.

c. Time records and wage rates paid.

Price and Payment Procedures 01 20 00 - 3

d. Invoices and receipts for products, equipment, and subcontracts, similarly documented.

3. For Time and Material work, submit itemized account and supporting data after completion of change, within time limits indicated in the Conditions of the Contract.

F. Execution of Change Orders: Owner will issue Change Orders for signatures of parties as provided in the Conditions of the Contract.

G. After execution of Change Order, promptly revise Schedule of Values and Application for Payment forms to record each authorized Change Order as a separate line item and adjust the Contract Sum.

H. Promptly revise progress schedules to reflect any change in Contract Time, revise sub-schedules to adjust times for other items of work affected by the change, and resubmit.

I. Promptly enter changes in Project Record Documents.

1.06 APPLICATION FOR FINAL PAYMENT

A. Prepare Application for Final Payment as specified for progress payments, identifying total adjusted Contract Sum, previous payments, and sum remaining due.

B. Application for Final Payment will not be considered until the following have been accomplished:

1. All closeout procedures specified in Section 01 70 00.

2. Evidence of completion of Project Closeout requirements.

3. Final Invoice.

4. Final meter readings for utilities, a measured record of stored fuel, and similar data relevant to project at date of Substantial Completion.

5. Liquidated Damages settlement.

PART 2 PRODUCTS - NOT USED

Pierce County Medical Examiner CT scanner and facility updates Construction Manager's Project Number

Allowances 01 21 00 - 1

SECTION 01 21 00

ALLOWANCES

A. PART 1 GENERAL

I. SECTION INCLUDES

1. Cash allowances.

2. Contingency allowance.

3. Inspecting and testing allowances.

4. Payment and modification procedures relating to allowances.

II. RELATED REQUIREMENTS

1. Section 01 20 00 - Price and Payment Procedures: Additional payment and modification procedures.

III. CASH ALLOWANCES

1. Contractor Responsibilities:

a. Assist Architect/Owner in selection of products, suppliers, and installers.

b. Obtain proposals from suppliers and installers and offer recommendations.

c. On notification of which products have been selected, execute purchase agreement with designated supplier and installer.

d. Arrange for and process shop drawings, product data, and samples. Arrange for delivery.

e. Promptly inspect products upon delivery for completeness, damage, and defects. Submit claims for transportation damage.

2. Differences in costs will be adjusted by Change Order.

IV. CONTINGENCY ALLOWANCE

1. Contractor's costs for products, delivery, installation, labor, insurance, payroll, taxes, bonding, equipment rental, overhead and profit will be included in Change Orders authorizing expenditure of funds from this Contingency Allowance.

2. Funds will be drawn from the Contingency Allowance only by Change Order.

3. At closeout of Contract, funds remaining in Contingency Allowance will be credited to Owner by Change Order.

V. INSPECTING AND TESTING ALLOWANCES

VI. ALLOWANCES SCHEDULE

1. Include the stipulated sum of $15,000.00 for use on miscellaneous/unforeseen items not accounted for in the base bid or alternates. This allowance will only be used with written approval from the owner/owner's representative.

B. PART 2 PRODUCTS - NOT USED

C. PART 3 EXECUTION - NOT USED

Pierce County Medical Examiner CT scanner and facility updates Construction Manager's Project Number

Allowances 01 23 00 - 1

SECTION 01 23 00

ALTERNATES

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Description of alternates.

B. Procedures for pricing alternates.

C. Documentation of changes to contract price and contract time.

1.023 ACCEPTANCE OF ALTERNATES

A. Alternates quoted on bid forms will be reviewed and accepted or rejected at owner's option. Accepted alternates will be identified in the owner-contractor agreement.

B. Coordinate related work and modify surrounding work to integrate the work of each alternate.

1.03 SCHEDULE OF ALTERNATES

A. Additive Alternate no. 1 - Project scope includes adding (5) security cameras, one-reach devices on both the IDF and camera sides, and all cabling to connect the cameras to the existing owner-provided switch in the telecommunications room. See Sheets E0.02, E1.03, E8.04, and E9.02 and project specifications for additional information.

PART 2 PRODUCTS - NOT USED

Substitution Procedures 01 25 00 - 1

SECTION 01 25 00

SUBSTITUTION PROCEDURES

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Procedural requirements for proposed substitutions.

1.02 RELATED REQUIREMENTS

A. Section 01 30 00 - Administrative Requirements: Submittal procedures, coordination.

B. Section 01 60 00 - Product Requirements: Fundamental product requirements, product options, delivery, storage, and handling.

C. Section 01 61 16 - Volatile Organic Compound (VOC) Content Restrictions: Restrictions on emissions of indoor substitute products.

1.03 DEFINITIONS

A. Substitutions: Changes from Contract Documents requirements proposed by Contractor to materials, products, assemblies, and equipment.

1. Substitutions for Cause: Proposed due to changed Project circumstances beyond

Contractor's control.

a. Unavailability.

b. Regulatory changes.

2. Substitutions for Convenience: Proposed due to possibility of offering substantial advantage to the Project.

a. Substitution requests offering advantages solely to the Contractor will not be considered.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

3.01 GENERAL REQUIREMENTS

A. A Substitution Request for products, assemblies, materials, and equipment constitutes a representation that the submitter:

1. Has investigated proposed product and determined that it meets or exceeds the quality level of the specified product, equipment, assembly, or system.

2. Agrees to provide the same warranty for the substitution as for the specified product.

3. Agrees to provide same or equivalent maintenance service and source of replacement parts, as applicable.

4. Agrees to coordinate installation and make changes to other work that may be required for the work to be complete, with no additional cost to Owner.

5. Waives claims for additional costs or time extension that may subsequently become apparent.

6. Agrees to reimburse Architect/Owner for review or redesign services associated with re-approval by authorities.

B. A Substitution Request for specified installer constitutes a representation that the submitter:

1. Has acted in good faith to obtain services of specified installer, but was unable to come to commercial, or other terms.

C. Document each request with complete data substantiating compliance of proposed substitution with Contract Documents. Burden of proof is on proposer.

1. Note explicitly any non-compliant characteristics.

D. Content: Include information necessary for tracking the status of each Substitution Request, and information necessary to provide an actionable response.

Substitution Procedures 01 25 00 - 2

a. Project Information:

1) Official project name and number, and any additional required identifiers established in Contract Documents.

2) Architect/Owner's, and Contractor's names.

b. Substitution Request Information:

1) Discrete and consecutive Substitution Request number, and descriptive subject/title.

2) Indication of whether the substitution is for cause or convenience.

3) Issue date.

4) Reference to particular Contract Document(s) specification section number, title, and article/paragraph(s).

5) Description of Substitution.

6) Reason why the specified item cannot be provided.

7) Differences between proposed substitution and specified item.

8) Description of how proposed substitution affects other parts of work.

c. Attached Comparative Data: Provide point-by-point, side-by-side comparison addressing essential attributes specified, as appropriate and relevant for the item:

1) Physical characteristics.

2) In-service performance.

3) Expected durability.

4) Visual effect.

5) Warranties.

6) Other salient features and requirements.

7) Include, as appropriate or requested, the following types of documentation:

(a) Product Data:

(b) Samples.

(c) Certificates, test, reports, or similar qualification data.

(d) Drawings, when required to show impact on adjacent construction elements.

d. Impact of Substitution:

1) Savings to Owner for accepting substitution.

2) Change to Contract Time due to accepting substitution.

E. Limit each request to a single proposed substitution item.

1. Submit an electronic document, combining the request form with supporting data into single document.

3.02 SUBSTITUTION PROCEDURES DURING PROCUREMENT

A. Invitation to Bid Details specifies time restrictions for submitting requests for substitutions during the bidding period, and the documents required.

B. Submittal Form (before award of contract):

1. Submit substitution requests by completing the form attached to this section. See this form for additional information and instructions. Use only this form; other forms of submission are unacceptable.

C. Owner will consider requests for substitutions only if submitted at least 10 days prior to the date for receipt of bids.

3.03 SUBSTITUTION PROCEDURES DURING CONSTRUCTION

A. Owner will consider requests for substitutions only within 15 days after date of Agreement.

B. Submit request for Substitution for Cause immediately upon discovery of need for substitution, but not later than 14 days prior to time required for review and approval by Architect/Owner, in order to stay on approved project schedule.

Substitution Procedures 01 25 00 - 3

C. Submit request for Substitution for Convenience immediately upon discovery of its potential advantage to the project, but not later than 14 days prior to time required for review and approval by Architect/Owner, in order to stay on approved project schedule.

1. In addition to meeting general documentation requirements, document how the requested substitution benefits the Owner through cost savings, time savings, greater energy conservation, or in other specific ways.

2. Document means of coordinating of substitution item with other portions of the work, including work by affected subcontractors.

3. Bear the costs engendered by proposed substitution of:

a. Owner's compensation to the Architect/Owner for any required redesign, time spent processing and evaluating the request.

b. Other construction by Owner.

c. Other unanticipated project considerations.

D. Substitutions will not be considered under one or more of the following circumstances:

1. When they are indicated or implied on shop drawing or product data submittals, without having received prior approval.

2. Without a separate written request.

3. When acceptance will require revisions to Contract Documents.

3.04 RESOLUTION

A. Architect/Owner or Owner may request additional information and documentation prior to rendering a decision. Provide this data in an expeditious manner.

B. Owner will notify Contractor in writing of decision to accept or reject request.

1. Owner's decision following review of proposed substitution will be noted on the submitted form.

3.05 ACCEPTANCE

A. Accepted substitutions change the work of the Project. They will be documented and incorporated into work of the project by Change Order, Construction Change Directive, Architectural Supplementary Instructions, or similar instruments provided for in the Conditions of the Contract.

3.06 CLOSEOUT ACTIVITIES

A. See Section 01 78 00 - Closeout Submittals, for closeout submittals.

B. Include completed Substitution Request Forms as part of the Project record.

3.07 ATTACHMENTS

A. A facsimile of the Substitution Request Form (During Construction) required to be used on the

Project is included after this section.

Substitution Request Form 01 26 10 - 1

SECTION 01 26 10

SUBSTITUTION REQUEST FORM

SUBSTITUTION REQUEST NUMBER: ______________

Project Name: Annex Electric Vehicle Infrastructure____Project Number: _24-00003_Date: ___________

From: _________________________________________ To: ________________________________________

Re: __________________________________ Contract For: ________________________________________

Proposed Substitution: _______________________________________________________________________

Manufacture: _________________________ Address: _________________ Phone: ___________________

Trade Name: __________________________________________ Model No.: ______________________

History: ___ New Product ___ 2-5 years old ___ 5-10 years old ___ more

Differences between proposed substitution and specified product: __________________________________

Reason for not providing specified item: ________________________________________________________

Proposed substitution affects other parts of work: _____ No Yes; explain ____________________

Savings to Owner for accepting substitution changes: __________________________($ _______________).

Proposed substitution changes Contract Time: ____ No ____ Yes ( Add ) ( Deduct ) _____days.

Supporting Data Attached: ___ Drawings ___ Product Data ___ Samples ___ Other

The Undersigned Certifies:

• Proposed substitution has been fully investigated and determined to be equal or superior in all aspects to the specified product.

• Same warranty will be furnished for proposed substitution as for the specified product.

Substitution Request Form 01 26 10 - 2

• Same maintenance service and source of replacement parts, as applicable, is available.

• Proposed substitution will have no adverse effect on other trades and will not affect or delay progress schedule.

• Cost data as stated above is complete. Claims for additional costs related to accepted substitution which may subsequently become apparent are to be waived.

• Proposed substitution does not affect dimensions and functional clearances.

• Payment will be made for changes to building design including A/E or Owner detailing and construction costs caused by the substitution.

• Coordination, installation, and changes in the Work as necessary for accepted substitution will be complete in all respects.

Submitted by: ________________________________________________________________________________________________

Signed by: ___________________________________________________________________________________________________

Firm: ________________________________________________________________________________________________________

Address: ______________________________________________________________________________________________________

Telephone: ___________________________________________________Fax: ______________________________________________

Owners Review and Action

______ Substitution approved.

______ Substitution approved as noted.

______ Substitution rejected- Use specified materials.

______ Substitution Request received to late - Use specified materials.

Project Manager: _________________________________________ Date: __________________________________

Additional Comments:

Request for Information Form 01 26 13 - 1

SECTION 01 26 13

REQUEST FOR INFORMATION FORM

Intent and Affidavit Form 01 26 15 - 1

SECTION 01 26 15

INTENT AND AFFIDAVIT FORM

Submit this form along with your invoice for prevailing wage projects.

STATEMENT OF CONTRACTORS ON PROJECT

Firm Name, Address, City, State & ZIP+4 Project Name and Number (Title) Contract No.

Current Invoice Amount:

Invoice #

Invoicing Period from: to

CONTRACTOR SUMMARY

I, the undersigned, do hereby certify on behalf of the firm name listed above that the prevailing wages for all work invoiced have been paid in accordance with the approved Statement(s) of Intent to Pay Prevailing Wages on file with the public agency. (RCW 39.12.040)

Printed Name: Signature:

Title: Date:

Contractor or

Subcontractor Name

Craft or Trade

Tiered Sub- Contractor?

Name of Company Contracted with

Intents Filed Affidavits Filed Services on Current Invoice

Intent # Dated approved

Affidavit

Dated approved

Schedule of Values 01 29 73 - 1

SECTION 01 29 73

SCHEDULE OF VALUES

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Requirements for the preparation, submission, and approval of the Schedule of Values (SOV) to support progress payments for the Work.

1.02 RELATED REQUIREMENTS

A. Drawings, Pierce County's General Conditions for Construction Contracts, and Division 1

Specifications Sections apply to this section.

B. Support values if requested. Use the Schedule of Values as a basis for developing the

Application for Payment, for developing Project Construction Schedule, and for developing estimated pay request amounts for each month during the course of the contract.

C. Application for payment will not be processed without an approved Schedule of Values.

D. Make sum of total scheduled costs equal to Contract Sum.

1.03 SUBMITTALS

A. Initial submission: Submit a draft Schedule of Values within seven (7) days after Notice to

Proceed or as directed by Owner.

B. Revisions: Revise and resubmit the Schedule of Values based on comments from the Owner or

Architect within 5 days of receiving feedback.

C. Final Approved SOV: Submit the final approved version prior to the first application for payment.

1.04 QUALITY ASSURANCE

A. The Owner or Architect may reject incomplete, inaccurate, or unbalanced SOV.

B. Submit a Schedule of Values in a format acceptable to the Owner/Architect; submit/review proposed format prior to submittal.

C. Identify each line item with number and title of respective Specification.

1. Under each line item show the value for the Specification Section of Work.

2. Mobilization and General Requirements costs can be a single line item. Overhead and

Profit costs can be a single line item. Include in each item a directly proportionate amount of contractor's overhead and profit. For each line item installed, show breakdown by major products or operation under each item.

PART 2 PRODUCTS

2.01 FORMAT

A. Use a standard format approved by the Owner. Form to include: project name, location, construction contract number, project number, Architect's name, Contractor's name, Contractor's address, and date of submittal.

B. Include the following columns:

1. Item Number

2. Description of Work (matching bid items, work breakdown structure, or specification sections).

3. Scheduled Value. Each line item shall be complete costs including overhead and profit.

4. Percent Complete.

5. Previously Billed Amounts.

6. Current Billing Amount.

C. Update the SOV to reflect all approved cost changes.

Schedule of Values 01 29 73 - 2

2.02 CONTENT

A. Break down the contract sum into logical components, such as:

1. Major work divisions or specification sections.

2. Mobilization.

3. Demobilization.

4. General conditions.

5. Overhead and Profit.

6. Subcontractor scopes of work broken out by labor, materials and equipment. Break down each stage of work.

a. Down-payment or prepayment requirements (if applicable).

7. General Contractors self-performed labor, materials, and equipment.

8. Badging and background checks.

9. Commissioning.

10. Closeout activities.

11. Punchlist items.

B. Ensure the total of all values equals the contract sum.

C. Change orders.

1. Provide a separate line item for each Change Order Proposal (COP) or Proposal Request

(PR).

2.03

Administrative Requirements 01 30 00 - 1

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

PART 1 GENERAL

1.01 SECTION INCLUDES

A. General administrative requirements.

B. Preconstruction meeting.

C. Site mobilization meeting.

D. Progress meetings.

E. Construction progress schedule.

F. Contractor's daily reports.

G. Record photographs existing conditions.

H. Progress photographs.

I. Coordination drawings.

J. Submittals for review, information, and project closeout.

K. Number of copies of submittals.

L. Requests for Interpretation (RFI) procedures.

M. Submittal procedures.

1.02 RELATED REQUIREMENTS

A. Pierce County General Conditions of the Contract apply to this section.

B. Section 01 60 00 - Product Requirements: General product requirements including Contractor affidavit certifying no Asbestos Containing Materials has been used on this project.

C. Section 01 70 00 - Execution and Closeout Requirements: Additional coordination requirements.

D. Section 01 78 00 - Closeout Submittals: Project record documents; operation and maintenance data; warranties and bonds.

E. Section 01 91 13 - General Commissioning Requirements: Additional procedures for submittals relating to commissioning.

1. Where submittals are indicated for review by both Architect/Owner and the

Commissioning Authority, submit one extra and route to Architect/Owner first, for forwarding to the Commissioning Authority.

2. Where submittals are not indicated to be reviewed by Architect/Owner, submit directly to the Commissioning Authority; otherwise, the procedures specified in this section apply to commissioning submittals.

1.03 GENERAL ADMINISTRATIVE REQUIREMENTS

A. Comply with requirements of Section 01 70 00 - Execution and Closeout Requirements for coordination of execution of administrative tasks with timing of construction activities.

B. Make the following types of submittals to Architect/Owner/Engineer:

1. Requests for Interpretation (RFI).

2. Requests for substitution.

3. Shop drawings, product data, and samples.

4. Test and inspection reports.

5. Design data.

6. Manufacturer's instructions and field reports.

7. Applications for payment and change order requests.

Administrative Requirements 01 30 00 - 2

8. Progress schedules.

9. Coordination drawings.

10. Correction Punch List and Final Correction Punch List for Substantial Completion.

11. Closeout submittals.

1.04 PROJECT COORDINATOR

A. Project Coordinator: Pierce County Facilities Management Construction Project Manager.

B. Cooperate with the Project Coordinator in allocation of mobilization areas of site, for field offices and sheds, for site access, traffic, and parking facilities.

C. During construction, coordinate use of site and facilities through the Project Coordinator.

D. Comply with Project Coordinator's procedures for intra-project communications; submittals, reports and records, schedules, coordination drawings, and recommendations; and resolution of ambiguities and conflicts.

E. Comply with instructions of the Project Coordinator for use of temporary utilities and construction facilities. Responsibility for providing temporary utilities and construction facilities is identified in Section 01 10 00 - Summary.

F. Coordinate field engineering and layout work under instructions of the Project Coordinator.

G. Make the following types of submittals to Architect/Owner through the Project Coordinator:

1. Requests for Interpretation.

2. Requests for substitution.

3. Shop drawings, product data, and samples.

4. Test and inspection reports.

5. Design data.

6. Manufacturer's instructions and field reports.

7. Applications for payment and change order requests.

8. Progress schedules.

9. Coordination drawings.

10. Correction Punch List and Final Correction Punch List for Substantial Completion.

11. Closeout submittals.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

3.01 PRECONSTRUCTION MEETING

A. Owner will schedule a meeting after Notice of Award.

B. Attendance Required:

1. Architect/Owner.

2. Contractor.

3. Major subcontractors.

C. Agenda:

1. Designation of personnel representing the parties to Contract.

2. Designation of NTP Date.

3. Procedures and processing of field decisions, submittals, substitutions, applications for payments, proposal request, Change Orders, and Contract closeout procedures.

4. Construction Management:

a. Use of Facilities.

b. Submittals.

c. Schedule.

d. Progress meetings.

e. Coordination.

f. Cleaning.

Administrative Requirements 01 30 00 - 3

g. Substantial Completion, Final Acceptance, and Closeout.

h. Safety, Security and Badging, and Sanitary Regulations.

i. Permitting and inspections.

5. Scheduling.

6. Scheduling activities of owner performed work.

D. Owner shall record minutes and distribute copies within 7 Calander days after meeting to participants, with copies to Architect/Owner, Owner, participants, and those affected by decisions made.

3.02 PREMIMINARY INFRASTRUCTURE VERIFICATION AND UTILITY ALIGNMENT

A. Mandatory Utility Alignment Meeting: Within seven (7) business days of NTP, the Contractor shall lead an on-site Utility Coordination Meeting.

1. Purpose: The meeting’s primary goal is to confirm the service point demarcation) to allow for immediate equipment procurement.

2. Site Verifiacation

3.03 SITE MOBILIZATION MEETING

A. Schedule meeting at the Project site prior to Contractor occupancy.

B. Attendance Required:

1. Contractor.

2. Architect/Owner.

3. Contractor's superintendent.

4. Major subcontractors.

C. Agenda:

1. Use of premises by Owner and Contractor.

2. Owner's requirements.

3. Temporary utilities provided by Owner.

4. Security and housekeeping procedures.

5. Schedules.

D. Owner will record minutes and distribute copies within two days after meeting to participants, with two copies to Architect/Owner, participants, and those affected by decisions made.

3.04 PROGRESS MEETINGS

A. Schedule and administer meetings throughout progress of the work. Frequency shall be determined during Pre-Construction Conference. It is anticipated that regular meetings to occur throughout progress of the work at maximum weekly intervals.

B. Contractor will provide a 3 week look ahead schedule with copies for all participants at meetings.

C. Contractor to submit electronic format of look ahead schedule to Owner 2 days prior to meeting date for Owner review.

D. Owner will make arrangements for meetings, prepare agenda with copies for participants, preside at meetings.

E. Attendance Required:

1. Contractor.

2. Architect/Owner/Engineer.

3. Special consultants.

4. Contractor's superintendent.

5. Major subcontractors.

Administrative Requirements 01 30 00 - 4

F. Architect or Owner shall record minutes and distribute copies within three days after meeting to participants, with copies to Architect/Owner, Owner, participants, and those affected by decisions made.

G. Agenda:

1. Review Minutes from previous meeting(s).

2. Safety.

3. Construction Progress Update.

a. Contractor's Schedule.

b. Three Week Look Ahead(s).

4. Risk.

5. Construction Coordination:

a. Current Action Items

b. Owner Action Items

6. Requests for Information (RFIs)

7. Field Authorizations/Change Order Proposal/Change Order Log and Status.

8. Submittal Review.

9. Quality Control / Quality Assurance.

10. Project Closeout.

11. Progress Payment.

12. New Business.

13. Discussion.

14. Vacations/Out of Office Schedule.

15. Next meeting Date and Time.

3.05 CONSTRUCTION PROGRESS SCHEDULE

A. If preliminary schedule requires revision after review, submit revised schedule within 10 days.

B. Within 20 days after review of preliminary schedule, submit draft of proposed complete schedule for review.

1. Include written certification that major contractors have reviewed and accepted proposed schedule.

C. Within 10 days after joint review, submit complete schedule.

D. Submit updated schedule with each Application for Payment.

3.06 DAILY CONSTRUCTION REPORTS

A. Include only factual information. Do not include personal remarks or opinions regarding operations and/or personnel.

B. Prior to mobilization, provide a weekly written status report to Owner including:

1. Date.

2. Tracking of long lead items.

3. Intents filed by subcontractors.

4. Background checks submitted including: name of person, subcontractor, approval status, badging appointment status, fingerprinting status, and identify date badge received (if applicable).

a. name of individual,

b. subcontractor name,

c. approval status,

d. badging appointment date,

e. fingerprinting status,

f. and identify date badge received (if applicable).

5. Permit status.

6. Directives and requests of Authority(s) Having Jurisdiction (AHJ).

Administrative Requirements 01 30 00 - 5

7. RFI's submitted.

8. Change Orders received and implemented.

9. List of verbal instruction given by Owner and/or Architect/Owner.

10. Signature of Contractor's authorized representative.

C. Prepare a daily construction report recording the following information concerning events at Project site and project progress:

1. Date.

2. High and low temperatures, and general weather conditions.

3. List of subcontractors at Project site.

4. List of separate contractors at Project site.

5. Approximate count of personnel at Project site.

a. Include a breakdown for supervisors, laborers, journeymen, equipment operators, and helpers.

6. Major equipment at Project site.

7. Material deliveries.

8. Safety, environmental, or industrial relations incidents.

9. Meetings and significant decisions.

10. Unusual events (submit a separate special report).

11. Stoppages, delays, shortages, and losses. Include comparison between scheduled work activities (in Contractor's most recently updated and published schedule) and actual activities. Explain differences, if any. Note days or periods when no work was in progress and explain the reasons why.

12. Meter readings and similar recordings.

13. Emergency procedures.

14. Directives and requests of Authority(s) Having Jurisdiction (AHJ).

15. Change Orders received and implemented.

16. Testing and/or inspections performed.

17. List of verbal instruction given by Owner and/or Architect/Owner.

18. Signature of Contractor's authorized representative.

3.07 RECORD PHOTOGRAPHS - EXISTING CONDITIONS

A. Contractor and subcontractors shall prior to starting work photo document all existing conditions shall be modified, augmented, or otherwise changed within the scope of work, including but necessarily limited to:

1. Existing wall, ceiling, and floor assemblies.

2. Existing electrical, mechanical, or plumbing equipment, fixtures, connections, or engineered systems.

3. Existing exterior envelope assemblies, components, joints, openings, or other elements modified in the scope of work.

4. Existing adjacent conditions including finishes, joints and existing damage, mars, or other defects not caused by activities within the scope of work.

5. Existing fencing and areas where fencing will be installed prior to any activities within the scope of work.

6. Existing parking stalls, walls, curbs, light poles, gates and any other components or adjacent area that could be affected prior to any activities within the scope of work.

3.08 PROGRESS PHOTOGRAPHS

A. Submit photographs with each application for payment, taken not more than 3 days prior to submission of application for payment.

B. Photography Type: Digital; electronic files.

Administrative Requirements 01 30 00 - 6

C. Provide photographs of site and construction throughout progress of work produced by an experienced photographer, acceptable to Architect/Owner.

D. In addition to periodic, recurring views, take photographs of each of the following events:

1. Completion of site clearing.

2. Excavations in progress.

3. Foundations in progress and upon completion.

4. Structural framing in progress and upon completion.

5. Enclosure of building, upon completion.

6. Final completion: minimum of ten (10) photos.

7. Conditions in concealed areas including in-ground trenches.

E. Views:

1. Provide non-aerial photographs from four cardinal views at each specified time, until date of Substantial Completion.

2. Consult with Architect/Owner for instructions on views required.

3. Provide factual presentation.

4. Provide correct exposure and focus, high resolution and sharpness, maximum depth of field, and minimum distortion.

F. Digital Photographs: 24-bit color, minimum resolution of 1024 by 768, in JPG format; provide files unaltered by photo editing software.

1. Delivery Medium: Via email.

2. File Naming: Include project identification, date and time of view, and view identification.

3. Point of View Sketch: Include digital copy of point of view sketch with each electronic submittal; include point of view identification in each photo file name.

4. PDF File: Assemble all photos into printable pages in PDF format, with 2 to 3 photos per page, each photo labeled with file name; one PDF file per submittal.

5. Photo CD(s): Provide 1 copy including all photos cumulative to date and PDF file(s), with files organized in separate folders by submittal date.

3.09 COORDINATION DRAWINGS

A. Provide information required by Project Coordinator for preparation of coordination drawings.

B. Review drawings prior to submission to Architect/Owner or Owner.

3.10 REQUESTS FOR INFORMATION (RFI)

A. Definition: A request seeking one of the following:

1. An interpretation, amplification, or clarification of some requirement of Contract Documents arising from inability to determine from them the exact material, process, or system to be installed; or when the elements of construction are required to occupy the same space (interference); or when an item of work is described differently at more than one place in Contract Documents.

2. A resolution to an issue which has arisen due to field conditions and affects design intent.

B. Whenever possible, request clarifications at the next appropriate project progress meeting, with response entered into meeting minutes, rendering unnecessary the issuance of a formal RFI.

C. Preparation: Prepare an RFI immediately upon discovery of a need for interpretation of

Contract Documents. Failure to submit a RFI in a timely manner is not a legitimate cause for claiming additional costs or delays in execution of the work.

1. Prepare a separate RFI for each specific item.

a. Review, coordinate, and comment on requests originating with subcontractors and/or materials suppliers.

b. Do not forward requests which solely require internal coordination between subcontractors.

2. Prepare using the form 01 26 13 Request For Information.

Administrative Requirements 01 30 00 - 7

3. Combine RFI and its attachments into a single electronic file. PDF format is preferred.

D. Reason for the RFI: Prior to initiation of an RFI, carefully study all Contract Documents to confirm that information sufficient for their interpretation is definitely not included.

1. Unacceptable Uses for RFIs: Do not use RFIs to request the following:

a. Approval of submittals (use procedures specified elsewhere in this section).

b. Approval of substitutions (see Section - 01 60 00 - Product Requirements)

c. Changes that entail change in Contract Time and Contract Sum (comply with provisions of the Pierce County General Conditions of the Contract).

d. Different methods of performing work than those indicated in the Contract Drawings and Specifications (comply with provisions of the Pierce County General Conditions of the Contract).

E. Content: Include identifiers necessary for tracking the status of each RFI, and information necessary to provide an actionable response.

1. Official Project name and number, and any additional required identifiers established in

Contract Documents.

2. Architect/Owner's, and Contractor's names.

3. Discrete and consecutive RFI number, and descriptive subject/title.

4. Issue date and requested reply date.

5. Reference to particular Contract Document(s) requiring additional information/interpretation. Identify pertinent drawing and detail number and/or specification section number, title, and paragraph(s).

6. Contractor's suggested resolution: A written and/or a graphic solution, to scale, is required in cases where clarification of coordination issues is involved, for example, routing, clearances, and/or specific locations of work shown diagrammatically in Contract Documents. If applicable, state the likely impact of the suggested resolution on Contract Time or the Contract Sum.

F. Attachments: Include sketches, coordination drawings, descriptions, photos, submittals, and other information necessary to substantiate the reason for the request.

G. RFI Log: Prepare and maintain a tabular log of RFIs for the duration of the project.

1. Indicate current status of every RFI. Update log promptly and on a regular basis.

2. Note dates of when each request is made, and when a response is received.

3. Highlight items requiring priority or expedited response.

4. Highlight items for which a timely response has not been received to date.

H. Review Time: Architect/Owner…