About this file

This document is a Fee Sheet for a Construction Management At-Risk project (Project Number 26-08063-P-AW) for an Electrical Switchgear Bundle involving five facilities: Brandon Elementary School Main, Hollis Academy K8, Scott Elementary School, Whitefoord Early Learning Center, and Facilities Service Center Building. The project outlines pre-construction services with consistent milestones across all sites, including 80% Construction Documents (due 9/16/2025), Final Guaranteed Maximum Price (GMP) (due 11/24/2025), Notice to Proceed (due 2/4/2026), and Substantial Completion (due 12/12/2026).

The pre-construction services fee is structured identically for each facility, with $4,000 charged for each of the first three milestones and $0 for Substantial Completion, resulting in a total pre-construction fee of $12,000 per facility. The Construction Phase section is currently incomplete, with percentage fields for the Construction Manager's Fee and general conditions left blank. The document appears to be a template awaiting specific fee percentage negotiations, suggesting the final financial terms for the construction management services are yet to be determined.

View the file

Other files for this state and local contract opportunity

Show all 19

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Fee Sheet Construction Management At-Risk

PROJECT: 26-08063-P-AW Electrical Switchgear Bundle

FIRM NAME:

DATE:

PRE- CONSTRUCTION SERVICES

As compensation for pre-construction services, the CM shall receive a fee as negotiated below

Brandon Elementary School Main Hollis Academy K8 Scott Elementary School Whitefoord Early Learning Center Facilities Service Center Building

Completion Due

Dates

Lump Sum Fee

(Per Task)

Completion Due Dates Lump Sum Fee

(Per Task)

Completion Due Dates Lump Sum Fee

(Per Task)

Completion Due Dates Lump Sum Fee

(Per Task)

Completion Due Dates Lump Sum Fee

(Per Task)

1. 80% Construction Documents 9/16/2025 $4,000.00 9/16/2025 $4,000.00 9/16/2025 $4,000.00 9/16/2025 $4,000.00 9/16/2025 $4,000.00

2. Final GMP 11/24/2025 $4,000.00 11/24/2025 $4,000.00 11/24/2025 $4,000.00 11/24/2025 $4,000.00 11/24/2025 $4,000.00

3. Notice to Proceed 2/4/2026 $4,000.00 2/4/2026 $4,000.00 2/4/2026 $4,000.00 2/4/2026 $4,000.00 2/4/2026 $4,000.00

4. Substantial Completion 12/12/2026

$0

TOTAL PRE- CONSTRUCTION FEE

$12,000.00

CONSTRUCTION PHASE

5. Construction Manager’s Fee:

a.Percent of general conditions

b. Percent fee