This document is a Request for Proposals (RFP) issued by the Atlanta Independent School System for Construction Management at Risk Services for an Electrical Switchgear Bundle across five locations. The project involves providing professional engineering and design services to replace existing switchgear, design equipment pads, curbing, and switchgear room lighting at Brandon Elementary School, Hollis Innovation Academy, Scott Elementary School, Whitefoord Early Learning Center, and the Facilities Service Center. The RFP was released on September 22, 2025, with proposals due on October 21, 2025, at 11:00 a.m. ET. A pre-proposal conference and site visit are scheduled for September 29, 2025. The project timeline includes board approval and initial contract award in December 2025, with substantial completion targeted for December 12, 2026.
The total stated cost limitation for the project is $4,888,500.00, with individual location cost limitations ranging from $975,000 to $978,750. The RFP emphasizes minority and women-owned business enterprise (MWBE) participation, requiring the Construction Manager to make best efforts to involve qualified women, minority, and small business enterprises. The project will utilize the owner's project management software, and the Construction Manager must obtain a license and complete a training certification. The awarded Construction Manager must have a General Contractor's license and will be responsible for preparing detailed cost estimates, reviewing contract documents, and providing value engineering recommendations throughout the design and construction phases.
View the file
Other files for this state and local contract opportunity
Show all 19
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATLANTA PUBLIC SCHOOLS
Facilities Services
1631 LaFrance Street
Atlanta, Georgia 30307
Advertisement
Request for Proposals
For
Construction Management at Risk Services for Electrical Switchgear Bundle
September 22, 2025
RFP Number: 26-08063-P-AW
Due Date: October 21, 2025
Time Due: 11:00 a.m. ET
Atlanta Independent School System 26-08063-P-AW Electrical Switchgear Bundle (CM at Risk)
Page | 2
ADVERTISEMENT FOR REQUEST FOR PROPOSALS
The Atlanta Independent School System is seeking a Construction Manager to complete Electrical
Switchgear at five (5) locations. The successful Construction Manager will be expected to provide all the services included in the standard APS Construction Management at Risk Agreement for building improvements at the following location:
Five (5) Electrical Switchgear
Project
Number
School Name Address Stated Cost Limitations
2450.01 Brandon
Elementary
School Main
2741 Howell Mill Road N.W.
Atlanta, Georgia 30327
$978,250.00
2451.01 Hollis
Innovation
Academy
225 James P Brawley Dr NW, Atlanta, GA 30314
$978,750.00
2452.01 Scott
Elementary
School
1752 Hollywood Road, N.W.
Atlanta, Georgia 30318
$978,250.00
2453.01 Whitefoord
Early Learning Center
35 Whitefoord Avenue S.E.
Atlanta, Georgia 30317
$975,000.00
2455.01 Facilities
Service Center
1631 LaFrance Street
Atlanta, Georgia 30301
$978,250.00
Total $4,888,500.00
A Pre-Proposal conference will be held at the following address on Monday, September 29, 2025, at 1:00 p.m. ET, and the site visit will follow immediately at 1:30 p.m.
VDT Facilities Service Center
1631 LaFrance Street, NE
Atlanta, GA 30307
Attendance is not mandatory but is strongly encouraged.
The initial contract will be a lump sum contract for the provision of pre-construction services. The lump sum fee for the pre-construction services is set out in the Fee Sheet attached in Bonfire. The
Construction Management percentage of general conditions and the percent fee for the construction phase will also be set with the initial contract. During the pre-construction services stage, the
Construction Manager shall submit a Guaranteed Maximum Price (GMP) to APS for the Project in its entirety, and/or for phases or portions of the Project. If a GMP is accepted by APS, the contract shall be amended to add and incorporate the GMP into the contract (each a “GMP Amendment”).
Page | 3
APS shall have no obligation to accept any GMP.
All questions or requests for clarification must be sent via Bonfire under Message – Opportunity Q & A:
https://aps.bonfirehub.com/opportunities/202522.
All addendums related to this solicitation will be posted on the Bonfire website at https://aps.bonfirehub.com/opportunities/20252. The proposer’s responsibility is to check the Bonfire website for any addendums, responses to proposal questions, or other communications related to this
Request for Proposals.
Proposals shall be submitted online at https://aps.bonfirehub.com/opportunities/20252.
The Office of Procurement Services will only accept proposals submitted online.
Proposal submissions are due no later than Tuesday, October 21, 2025, at 11:00 a.m.
ET.
APS will only accept online submissions for this Request for Proposals. Proposals can be submitted online at: https://aps.bonfirehub.com/opportunities/20252.
Proposals submitted after the proposal submission close date will not be accepted. Note: Any proposal submitted in any other format (email, paper, fax, mail, etc.) will not be accepted for any reason.
If you cannot download these documents, contact the purchasing agent, Alicia White, at alicia.white@apsk12.org.
TENTATIVE TIMELINE
09/22/2025 Release RFP to the marketplace
09/29/2025 Pre-proposal conference, 1:00 p.m., ET
09/29/2025 Site Visit
10/02/2025 Deadline for written questions, 2 p.m. ET
10/07/2025 Response to questions to be posted to Bonfire.
10/21/2025 RFP due online at Bonfire by 11:00 a.m., ET
10/22/2025 Administrative Review
10/28/2025 10/30/2025
Initial Shortlist Evaluation Phase 2 Interview/Presentation (If applicable)
01/07/2026 Recommendation to the APS Board of Education https://aps.bonfirehub.com/opportunities/202522 https://aps.bonfirehub.com/opportunities/20252 https://aps.bonfirehub.com/opportunities/20252 https://aps.bonfirehub.com/opportunities/20252 mailto:alicia.white@apsk12.org
Page | 4
1. Purpose
The Atlanta Independent School System is seeking a Construction Manager to complete
Electrical Switchgear at five (5) location . The successful Construction Manager will be expected to provide all the services included in the standard APS Construction
Management at Risk Agreement for building improvements at the following location:
School Name Address Stated Cost Limitations
Brandon Elementary School Main 2741 Howell Mill Road N.W.
Atlanta Georgia 30327
$978,250.00
Hollis Innovation Academy 225 James P Brawley Dr
NW, Atlanta, GA 30314
$978,750.00
Scott Elementary School 1752 Hollywood Road, N.W.
Atlanta Georgia 30318
$978,250.00
Whitefoord Early Learning Center 35 Whitefoord Avenue S.E.
Atlanta, Georgia 30317
$975,000.00
Facilities Service Center 1631 LaFrance Street, Atlanta, Georgia 30301
$978,250.00
TOTAL $4,888,500.00
The basic program for the project to be responded to may include, but may not be limited to, the items listed below.
2. Project Information
2.1. The intent of this effort is to select a Construction Manager at Risk (CM) and enter into the standard APS Construction Management Agreement with the successful
Board-approved Construction Manager at Risk.
2.2. The planning and design for the project are underway. Currently, the construction documents are not yet complete. A project summary description, current facility inventory drawings, and proposed concept plans may be included for your use in this effort.
2.3. The APS Design Guidelines, APS Standard Specifications, APS Bulletins to
Design and Construction Professionals, APS Capital Project Expectations, and
APS standard Construction Management Agreement are located on the APS website at this address: https://www.atlantapublicschools.us/page/32597. The http://www.atlantapublicschools.us/page/32597
Page | 5 construction manger may obtain copies of these documents at your discretion and expense.
2.3.1. Construction Managers should familiarize themselves with the project description and the described and inferred project scope before submitting a proposal. The approach to the design management, construction, and schedule for this project should be established at your discretion, but must be constructed to expedite the start of the project by the estimated commencement and completion date shown in Section 2.6
2.4 Construction Manager’s proposal must be based on the existing site conditions, experience as a Construction Manager at Risk, knowledge of Georgia K-12 construction projects, APS construction projects, APS Design Guidelines, and the
APS Standard Specifications.
2.5 By submitting a proposal to this Request for Proposal, you acknowledge that the documents provided by APS and any documentation provided by you as part of your submittal to this RFP and accepted in writing by APS are applicable to this contract.
2.6 Project Tentative Timeline: This project is time sensitive. In order to complete the project on time, the vendor understands that the following schedule must be kept
CMAR Schedule
Release CMR RFP 09/22/2025
Responses Due /10/21/2025
Evaluate / Select 10/28/2025
Interviews (optional) 10/30/2025 –10/31//2025
Board Approval/Award Initial Contract
(Preconstruction Services)
12/03/2025
Contract execution – Initial Contract 01/02/2026
Notice To Proceed-Preconstruction 12/04/2025
80% Construction Documents + Arch. Cost Estimate 9/16/2025
100% Construction Documents + Arch. Cost
Estimate
10/17/2025
CMAR Anticipated 30-day Procurement Period 1/20/2025
Final GMP- Due to APS 2/20/2025
Month 2026 Board Meeting- GMP Approval 2/27/2026
Notice to Proceed (NTP)-Construction 3/02/2026
Substantial Completion 12/12/2026
Page | 6
2.7 This project requires a General Contractor's license for the firm
(Qualifying Agent, NOT Limited Tier).
3. Preconstruction Information and Services. The Construction Manager shall perform the pre-construction services set out in Article 3 of the Construction Management
Agreement, including but not limited to the following:
3.1 Preconstruction Services – General and Schematic Phase.
3.1.1 The Construction Manager shall review project requirements, educational specifications, on and off-site development, survey requirements, and preliminary budget, and make value engineering and constructability recommendations for revisions to APS in the form of a written report prior to final payment for this phase.
3.1.2 Where the project includes renovation or expansion of an existing Facility, the Construction Manager will assist the Construction Team in preparing an analysis package outlining the condition of the existing Facility, existing structure, existing finishes, existing equipment, code deficiencies, energy use, and life expectancy of other building systems by providing constructability, value engineering, and cost estimates recommendations.
The package should contain the Construction Manager’s recommendations, cost estimates, and preliminary schedules. Such information shall be provided to APS in the form of a written report prior to final payment for this phase.
3.2 Preconstruction Services – Design Phase
3.2.1 The Construction Manager will be required to attend all project-related meetings and include a summary of the meeting in its monthly report to the APS.
3.2.2 The Construction Manager will periodically review all contract documents for constructability and help ensure compliance with all applicable laws, rules, codes, design standards, and ordinances. The construction Manager shall immediately notify APS of any non-compliant contract document.
Such information shall be provided to the APS in the form of a written report in the format as noted herein prior to final payment for this phase.
Page | 7
3.3 Preconstruction Services – Construction Documents Phases
3.3.1 The Construction Manager shall prepare detailed cost estimates and recommendations for APS at the S.D. (Schematic Design), D.D. (Design
Development), and C.D. (80% and 100% Construction Documents) phases of the project. Such information shall be provided to APS in the form of a written report prior to final payment for each phase.
3.3.2 The Construction Manager shall review all contract documents for the new and existing buildings and/or building sites and provide value engineering recommendations to minimize APS’s capital outlay and maximize APS’s operational resources. Such information shall be provided to APS in the form of a written report prior to final payment for this phase.
3.3.3 The Construction Manager will review all contract documents, all new and existing buildings’ conditions, and the building site to ensure proper coordination, constructability, clarity, and completeness, and to minimize conflict, errors, omissions, and unforeseen conditions. The Construction
Manager shall strive to eliminate change orders due to errors, omissions, and unforeseen conditions. The Construction Manager agrees specifically that no change orders shall be requested by the Construction Manager or considered by APS for reasons that were or should have reasonably been known by the Construction Manager involving unforeseen conditions, conflicts, or questions of clarity in the contract documents, or between the contract documents and the existing conditions, utilities, and unforeseen underground conditions.
3.3.4 At the completion of the Construction Manager’s review of the plans and specifications, except only as to specific matters as may be identified by appropriate written comments pursuant to this section, the Construction
Manager, shall notify APS in writing that the plans and specifications are consistent, practical, feasible and constructible and that the work described in the plans and specifications for the various bidding packages is constructible within the scheduled construction time.
Page | 8
3.3.5 APS may select certain projects for expediting using fast-track construction.
When this option is exercised, in writing, by APS, it shall be implemented per the Construction Manager’s recommendation once approved by APS.
3.4 Preconstruction Services – Bidding and Award Phase
3.4.1 Upon obtaining all necessary approvals of the Construction Documents, including a Building Permit as required by the local governing authorities and APS approval of the latest Statement of Probable Construction Cost, the Construction Manager shall obtain bids and commence awarding construction contracts. The Construction Manager will have the drawings and specifications printed, or provided electronically for bidding purposes, through its open Agreements with printing firms.
3.4.2 The Construction Manager shall prepare and issue the bid packages to cover the scope of the Work for this contract.
3.4.3 The Construction Manager, in coordination with APS, shall schedule pre-bid conferences as required and issue a written summary of the conference(s).
3.4.4 The Construction Manager shall also make recommendations to APS for awards to the lowest, most responsive, and most responsible bidder on the respective construction contracts. A recommendation for award to other than the lowest bidder shall be justified in writing. The Construction
Manager will disclose any related party relationship with a bidding subcontractor in writing prior to the award of contracts. For the purposes of this agreement, a related party relationship shall constitute any instance of common ownership, common management, or an ownership stake in the bidding subcontractor. The Construction Manager is required to present the bid tabulation summary and all supporting bid day documentation to APS after the bid opening. The referenced documentation as well as the awarding of any subcontracts is subject to the written approval of APS. The
Construction Manager is not authorized to enter into any subcontract agreements without obtaining written approval for each subcontractor.
Page | 9
3.4.5 Guaranteed Maximum Price (GMP): Upon completion of the design phase
(e.g. when the construction documents are 80-100% complete) and bidding, the Construction Manager shall present to APS the GMP for APS’s review and approval.
3.5 Scope of Work / Construction Services (if amended later through Final GMP, Exhibit A)
Brandon Elementary School Main
Project #2450.01
Brandon ES Main Electrical Switch Gear Design scope:
1. Provide professional services:
1.1 Provide engineering and related services, including civil, structural, and electrical engineering design, to complete construction documents.
1.2 Provide the design for the replacement of the existing switchgear.
1.3 Provide the design of equipment pads, curbing, and switchgear room lighting.
Stated Cost Limitation $978,250.00
Hollis Academy K8
Project #2451.01
Hollis Academy K8 Electrical Switch Gear Design scope:
1. Provide professional services:
1.1 Provide engineering and related services, including civil, structural, and electrical engineering design, to complete construction documents.
1.2 Provide the design for the replacement of the existing switchgear.
1.3 Provide the design of equipment pads, curbing, and switch gear room lighting.
Stated Cost Limitation $978,750.00
Scott Elementary School
Project #2452.01
Scott ES Electrical Switch Gear Design scope:
1. Provide professional services:
1.1 Provide engineering and related services, including civil, structural, and electrical engineering design, to complete construction documents.
1.2 Provide the design for the replacement of the existing switchgear.
1.3 Provide the design of equipment pads, curbing, and switch gear room lighting.
Stated Cost Limitation $978,250.00
Page | 10
Whitefoord Early Learning Center
Project #2453.01
Whitefoord Early Learning Center Electrical Switch Gear Design scope:
1. Provide professional services:
1.1 Provide engineering and related services, including civil, structural, and electrical engineering design, to complete construction documents.
1.2 Provide the design for the replacement of the existing switchgear.
1.3 Provide the design of equipment pads, curbing, and switch gear room lighting.
Stated Cost Limitation $975,000.00
Facilities Service Center
Project #2455.01
Facilities Service Center Electrical Switchgear scope:
1. Provide professional services:
1.1. In addition to the fully defined work, it is the intent of this project to potentially identify and remedy, upgrade, or enhance building systems, structural components, fixtures, finishes, or site work at the project site if significant disruption can be avoided and costs saved.
1.2. The project consists of the replacement of the existing switch gear based on the design. The replacement may require the removal of walls, curbs, and existing conduit. Curbs may need to be modified, service lighting changed or modified for maintenance.
Stated Cost Limitation $978,250.00
Owner’s Project Management Software
4.1 The awarded Construction Manager shall be required to use the Owner’s project management software. One (1) license will be distributed to the
Construction Manager at a cost to the Owner, which will allow access to the project management software for the Project. Usage of this license will be provided throughout the duration of the Project. Based on availability, additional licenses may be provided as needed.
4.2 This Project will utilize a project management and collaboration system for all project documentation. Applicable team members of the
Construction Manager (to include subcontractors as determined by the
Owner) will be invited and are required to create a username (email) and password for the project management software if they do not already have one. The Construction Manager will be expected to obtain drawings, Page | 11 sketches, RFIs, meeting minutes, coordination drawings, change information, etc. via this application. The construction Manager will notify subcontractors as relevant items are added. It will be the responsibility of the Construction Manager to regularly check and review updated documents as they are added. Applicable team members of the
Construction Manager are required to complete a free, one-hour
Subcontractor training certification course for the project management software within two (2) weeks following the execution of this Agreement.
There will be no cost to the Construction Manager for the use of the
Owner’s project management software.
4.3 It is recommended that the Construction Manager provide mobile iOS or
Android devices with the project management software App installed to at least one individual on-site to provide real-time access to currently posted drawings, Specifications, RFIs, Submittals, project documents, as well as any deficient observations or Punch List items. Providing mobile access will improve communication, efficiency, and productivity for all parties.
5. General Requirements
5.1 All work conducted must be in accordance with all local, state, and federal guidelines.
5.2 Minority/Women-Owned Business Enterprises (MWBE) Outreach Efforts
It is the policy of the owner to promote the utilization of women, minorities, and small business enterprises in all phases of the design, development, construction, and maintenance of the Project. While the owner does not impose any quotas regarding their utilization, the awarded
Construction Manager shall take all steps established by the contract documents or otherwise reasonably requested by the owner to satisfy the
Owner that they have made their “best efforts” to be involved in the work as many companies or firms owned by women, minorities and small business enterprises as practicable, provided they are qualified to conduct the work.
When the Construction Managers are ready to begin the GMP process, they must work with the Owner’s Supplier Diversity office to provide an advertisement that will be made available via the Georgia Procurement
Registry for thirty (30) days.
Page | 12
The following organizations may provide relevant resources to the awarded Construction Manager:
National Association of Minority
Contractors, Georgia Minority
Development Council, National
Association of Women in Construction:
https://www.nawicatlanta.org/
For further information regarding the Owner’s policy, please click the following link: APS Supplier Diversity.
https://protect-us.mimecast.com/s/SjqJCBB80EfM16RGTjxmyP?domain=nam11.safelinks.protection.outlook.com https://protect-us.mimecast.com/s/SjqJCBB80EfM16RGTjxmyP?domain=nam11.safelinks.protection.outlook.com https://protect-us.mimecast.com/s/u5x4CDkYnEhn1vJ9ul7kxM?domain=nam11.safelinks.protection.outlook.com https://protect-us.mimecast.com/s/u5x4CDkYnEhn1vJ9ul7kxM?domain=nam11.safelinks.protection.outlook.com https://www.nawicatlanta.org/ https://protect-us.mimecast.com/s/wCBTCERZoQtgm907cQ2Yum?domain=nam11.safelinks.protection.outlook.com
File details come from the government source that posted it. Updated .