- Reconfiguration of the Vibration Environmental Chamber Box, Duct Work, and Support Structure
- Solicitation number
- 18-233-SOL-00167
About this file
Answers to Questions
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Q&A.docx | DOCX document | |
| Technical_Requirement_DRD_2637.docx | DOCX document | |
| Answers.pdf | ||
| InitialQuestions.pdf | ||
| UCF_-_Vibration_Chambers_(updated).pdf | ||
| Vibration_Environmental_Box.docx | DOCX document | |
| Vibration_Chamber_Air_Ducting_Verification.docx | DOCX document | |
| Return_Air-Vibration_Chamber.docx | DOCX document | |
| Vibration_Environmental_Box.docx | DOCX document | |
| Vibration_Chamber_Air_Ducting_Verification.docx | DOCX document | |
| Return_Air-Vibration_Chamber.docx | DOCX document | |
| Appendix_A-Doc1(Head_Expander).pdf | ||
| UCF_-_Vibration_Chambers_(Updated03-01-2018).pdf | ||
| Appendix_C-Doc2_(Over_View).pdf | ||
| Appendix_B-Doc1_(Layout_Horizontal).pdf | ||
| Appendix_B-Doc2_(Layout_Vertical).pdf | ||
| 18-233-SOL-00167_SF1449.pdf | ||
| UCF_-_Vibration_Chambers.pdf | ||
| Attachment_B_-_Picture.docx | DOCX document | |
| Attachment_A_-_Picture.docx | DOCX document |
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Maden Tech Consulting, Inc.
March 12, 2018
DPG Vibration Chamber RFP
Questions/Request for Clarifications
Solicitation No. 18-233-SOL-00167
Question Page
Section/
Paragraph
Number
Reference
Question/Comment
1 61 L.7 INQUIRES/SUBMISSION The RFP states that the “Offeror shall submit (1) original of the written technical, past performance and business proposals to the Government.
Additionally, the Offeror shall provide an electronic version of each proposal via email…” Is the Government requesting a hard copy be submitted of each proposal? If so, to what address?
2 63 L.10.1 BUSINESS PROPOSAL
INSTRUCTIONS
The RFP states the “Offerors must complete and include Standard Form
1449”. Please provide the Standard Form 1449.
3 63 L.10.3 BUSINESS PROPOSAL
INSTRUCTIONS
The RFP states the “Offerors shall include a completed copy of Section B of the solicitation in its proposal”. Is the Government referring to the chart in
Section B.5 for price by CLIN?
4 65 L.11 PAST PERFORMANCE
INFORMATION
Please provide the referenced Attachment J.1- Past Performance
Questionnaire
5 1 B.1 DESCRIPTION
The RFP states “It is all so an objective to ensure that the same air flow to the ECB is the same after
Re-configuration is completed as it is in the present configuration.”
What is the current air flow?
6 1 B.5 CONSIDERATION AND
PAYMENT
Does the Government require a separate Test Plan to be approved before the test? We recommend a separate test plan as a deliverable before the test is conducted.
7 3 C.1.5 PROGRAM
DESCRIPTION AND
BACKGROUND
Does the Government require the Contractor to submit their Quality Control
Plan to the Government PM/COR for approval? If so please clearly state the requirement and when the Quality Control Plan should be delivered.
8 12 C.2.8.1.3 SECURITY AND
SAFETY
Is the Accident Prevention Plan part of the Safety Plan required in the
Summary of Deliverables on page 10 of the RFP?
Maden Tech Consulting, Inc.
March 12, 2018
DPG Vibration Chamber RFP
Questions/Request for Clarifications
Solicitation No. 18-233-SOL-00167
Question 12: Can we install a diverting valve on the CO2 line after the control valve and use it to select either the old shaker or new shaker?
Answer - Yes they can add the valve.
9 12 C.2.8.1.5 SECURITY AND
SAFETY
Is the Fall Protection and Prevention Plan part of the Safety Plan required in the Summary of Deliverables on page 10 of the RFP?
10 12 C.2.8.2 SECURITY AND
SAFETY
What the security clearance level required for this work? Is the work restricted to US citizens only?
11 15 E.1.2 INSPECTION AND
ACCEPTANCE
What file format does the Government want used for diagrammatic files so that those files are editable by the Government?
17 G.3 ADVANCE
UNDERSTANDING
The paragraph states”Other provisions of this contract notwithstanding, the Contractor is hereby authorized to incur the following costs, within the limits set forth without further authorization.” Which costs is the Contractor authorized to incur without further authorization?